Sunteți pe pagina 1din 30

Aux Boiler Steam Blow Procedure

Document No. 2012111272-SB-PROC Rev. 0



Vung Ang 1 Project Steam Blow
Ha Tinh, Viet Nam


Viet Nam Machinery Installation Corporation Approval
Print Name:
Signature:
Date:






0 04/16/2013 Issued for review R. Emery J. Haldane
Revision Date Reason for Issue Originator Approved by
B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 2 of 30
TABLE OF CONTENTS

Section
1 Scope of work
2 Safety and risk assessment
3 Preparations prior to steam blowing
4 Steam blow sequence and procedure

Appendix A Steam Blow Marked up P&IDs
Appendix B Pre-Blow Safety Checklist
Appendix C Continuous Blow MCR Data
Appendix D Construction Activities
Appendix E B&W temporary piping isometrics
Appendix F Reference Materials

REVISION HISTORY


Revision 0 Issued April 16, 2013 Issued for review.





















B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 3 of 30
1 SCOPE

1.0 General Information

1.0.1 The steam cleaning method of choice for the Boiler Feed Pump Turbines, Aux steam
to CRH, AUX back-blow will be a continuous steam blow. Firing rates will control the
steam production of the Aux boiler to provide the steam for these blows. Aux Boiler
must have minimum pressure of 0.8 MPag. An Orifice plate will be utilized to
maintain boiler pressure and control the mass rate.

1.0.2 This document is intended to define the activities required to complete the steam
blow program and to define the parties responsible for completion of those activities.

1.0.3 Target blowing continues until a polished brass target plate is withdrawn from the
system that meets the acceptance criteria.

1.0.4 Piping systems to be blown include:

1.0.4.1 Target Blows:

1.0.4.1.1 Boiler Feed Pump Turbine supply from Aux steam supply.
(Continuous Blow 1)

1.0.4.1.2 Boiler Feed Pump Turbine supply from Aux steam through
CRH. (Continuous Blow 2)

1.0.4.1.3 Gland Seal Steam - HP A, HP B, IP, LP A and LP B.
(Continuous blow 3)

1.0.4.2 Service Blows:

1.0.4.2.1 Deaerator from aux boiler through BFPT header.

1.0.4.2.2 Deaerator from aux boiler.

1.0.4.2.3 #2 HP heater header from CRH back blow.

1.0.4.2.4 Boiler bottoms header from aux boiler.

1.0.4.3 Piping not blown should be cleaned by other methods (aqua lazing).
Typically on previous power projects, lines that cannot be blown with steam
have been cleaned with high pressure (100 bar) water. To accomplish this
type of cleaning, access points need to be planned. Typically they are either
left out sections of pipe, cut out driplegs, etc. See Appendix F.

1.0.4.3.1 #1 Extraction Steam

1.0.4.3.2 #3 Extraction Steam

1.0.4.3.3 #4 Extraction Steam upstream of deaerator connection

1.0.4.3.4 HFO Atomizing

1.0.4.3.5 HFO Preheating

B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 4 of 30
1.0.4.3.6 Firefighting of coal pulverizing system

1.0.4.3.7 Air preheat soot blowers

1.0.4.3.8 CRH to Aux Steam Header

1.0.4.3.9 HP Cylinder Preheating

1.0.4.3.10 Portion of #2 Extraction Steam, upstream of tie in with aux
steam.

1.0.5 Steam blowing occurs until the cleanliness criteria described in section 4 of this
document is reached. No water injection thermal cycling is planned for any of the
piping systems.

1.0.6 The steam will be quenched prior to venting to atmosphere for the continuous blows
to reduce velocity and temperature.






































B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 5 of 30
1.1 B&W Fluid Dynamics Scope of Supply

1.1.1 Engineering package consisting of detailed step-by step procedure addressing blow
sequence, process flow diagrams, required mass flow rates, thermal cycle process,
CFR calculations, velocities, exit points, cleanliness criteria, safety, bill of materials
and isometric drawings for Client and BWFD supplied temporary piping and
equipment. Note: common package will be issued for both Units, with some minor
variance to temporary piping arrangement and equipment numbers

1.1.2 Aux steam blow piping and equipment on-site for 45 days for Aux System Blows (for
both Units). Note: Aux Blow Equipment can remain onsite for use during Main Boiler
Steam Blows at no additional cost to Client. This equipment includes:

1.1.3 Up to 200 feet of standard inventory pipe for installation downstream of the
temporary Blow Valve. This includes standard length 19 ft flanged Class 150
temporary steam blow pipe spools as supplied by BWFD up to 24 in diameter

1.1.3.1 One (1) Lg standard wet noise suppressor, capable of venting up to 500,000
lbs/hr of steam.

1.1.3.2 Adequate number of integrated quenching systems for use with standard
suppressor

1.1.3.3 Studs, nuts, gaskets for all BWFD temporary equipment

1.1.3.4 Fifty (50) polished brass targets

1.1.3.5 Two (2) Pneumatic Target Inserter Devices for use with supplied targets

1.1.3.6 Design of two (2) Orifice Plates

1.1.4 One (1) round trip mobilization / freight for BWFD supplied equipment to Hai Phong
Port. It is estimated that six (6) containers are required for mobilizing all required
steam blow equipment above one (1) container for Aux System Blows and five (5)
containers for Main Boiler Steam Blows

1.1.5 Manpower (Onsite Representation) during Steam Blows of Unit 1 Auxiliary System:

1.1.5.1 Rig-Up: One (1) Field Technical Advisor, day shift only, for seven (7) days

1.1.5.2 SB Service: Two (2) Field Technical Advisors, 1 per 12 hr shift, for ten (10)
days

1.1.5.3 Rig Down: One (1) Field Technical Advisor, day shift only, for two (2) days

1.1.6 Manpower (Onsite Representation during Steam Blows of Unit 2 Auxiliary System:

1.1.6.1 Rig-Up: One (1) Field Technical Advisor, day shift only, for seven (7) days

1.1.6.2 SB Service: Two (2) Field Technical Advisors, 1 per 12 hr shift, for ten (10)
days

1.1.6.3 Rig Down: One (1) Field Technical Advisor, day shift only, for two (2) days

1.1.7 Two (2) separate mobilizations of two (2) BWFD Field Technical Advisors to site for
Aux System Blows, one (1) mobilization for each Unit

B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 6 of 30
1.2 Lilama Scope of Supply

1.2.1 Pre-commissioning cleaning director, or coordinator, to serve as single point of
contact for the steam blow activities

1.2.2 Master commissioning (project) schedule including steam blow activities

1.2.3 Temporary pipe, hose and fittings not included in 1.1.3 above

1.2.4 Design, material and fabrication of any spools required for control valves, flow
meters, or any device within the permanent system which would require removal for
steam blowing

1.2.5 Design, material and fabrication of any custom spools required to connect the
permanent system to the temporary (standard) steam blow piping provided by
BWFD

1.2.6 Design, material and fabrication of any temporary lines required for injection of
thermal cycle water for target blowing (if required)

1.2.7 Blind flanges, if required, to isolate steam flow during the steam blow program

1.2.8 Material and fabrication of pipe supports/ restraints for temporary piping as specified
by BWFD engineering package

1.2.9 Utilities including water, air, and electricity

1.2.9.1 Water (service water, fire water or equivalent) for temporary
equipment desuperheating/silencing, including delivery hoses. Connection
to BFWD supplied desuperheating devices is 2 NPT. Max required quench
water required is 0.1237 m
3
/hr.

1.2.9.2 Air supply of 690kPag (~100 psig) for target insertion device. Intermittent
use only

1.2.9.3 Air supply 850kPag (~125 psig) or nitrogen bottle(s) with regulator to clear
drip legs of accumulated debris. This air supply must be oil-free, so as not to
contaminate the steam system

1.2.9.4 Suitable drain location for un-evaporated quench water from the temporary
steam blow equipment. This water temperature may be up to 93 deg C

1.2.10 Transportation of BWFD steam blow equipment from Hai Phong Port to Vung Ang 1
Project Site, including customs clearance, taxes, and permits (if any)

1.2.11 All supervision, labor, and equipment to unload and reload all temporary steam
blowing equipment to/from delivery trucks. The temporary piping is supplied in
flanged spools

1.2.12 All supervision, labor, and equipment required to erect, break down, and relocate all
temporary steam blowing equipment as per the erection isometrics and equipment
utilization plan

1.2.13 Any modifications and restoration required to the permanent plant systems to
accommodate the cleaning per B&W Fluid Dynamics engineering
B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 7 of 30

1.2.14 Operating and craft personnel as required to operate plant and temporary equipment
as needed during the blows. At least two (2) operators and four (4) craft personnel
(two fitters and two helpers) per shift are required

1.2.15 Laydown area for B&W Fluid Dynamics Equipment, including security for equipment

1.2.16 Office space for B&W Fluid Dynamics personnel for the duration of the Steam Blows

1.2.17 Steam at the specified conditions

1.2.18 Safety signs and barriers and temporary insulation as required

1.2.19 Scaffolding as required for accessing valves and targeting devices







































B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 8 of 30

2 SAFETY AND RISK ASSESSMENT

2.1 This procedure is designed so pressures in the steam blow temporary piping downstream of the
temporary blow valve will not exceed their working pressure. Any valve downstream of a low-
pressure temporary spool is to be tagged for open position only.

2.2 Check for the following personnel protection from hot piping:

2.2.1 Piping from the tie-in points to the target insertion locations and near valves that will
be operated are to be wrapped with temporary insulation, such as a single layer of
fiberglass or mineral wool, for personnel protection. Temporary flanges are to be left
uninsulated so that leaks can be readily detected and repaired.

2.2.2 All hot piping is to be barricaded and labeled as hazard. Also barricade areas at
grade around all drip leg drain valves. These will be opened during the steam blow
process.

2.2.3 All flammable material will be moved away from hot piping or shielded by insulation.

2.2.4 All heat sensitive or exposed instrumentation cabling, etc. must be moved away from
hot piping or shielded by insulation.

2.3 Hearing protection will be required near all steam piping during the blow.

2.4 The B&W Fluid Dynamics technical representative and the Lilama steam blow coordinator must
have radio communication with the control room (operations personnel) during the steam
blowing execution.

2.5 The Lilama steam blow coordinator will be responsible for overall control of the steam blow
program.

2.6 All scaffolding used for access to drip leg valves, target insertion devices, etc. will be erected to
Lilama standards.

2.7 The B&W Fluid Dynamics technical representative will conduct a safety meeting for all personnel
who are working in the vicinity of the steam blow.

2.8 All Lilama and Boiler OEM recommended warm up/operating procedures are to be followed
during the steam blow.

2.9 Review hazards associated with the installation and disassembly of the temporary piping:

2.9.1 Working on elevated platform.

2.9.2 Working below platform.

2.9.3 Pinch points involved with assembling large bore flanged joints.

2.9.4 Rigging, lifting, moving large diameter pipe spools.

2.9.5 Rigging, lifting, assembling/disassembling large steam silencer vessel.

B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 9 of 30
3 PREPARATIONS PRIOR TO STEAM BLOWING

3.1 General Notes

3.1.1 Pressure gauges and temperature probes must be functioning on the steam
headers. It may be necessary to install additional pressure gauges near the header
inlets to be able to verify proper conditions during the steam blow.

3.1.2 It is recommended that all steam headers be completely insulated before steam
blowing begins. Inadequate insulation may lead to prolonged blowing times.

3.2 All drip legs will need to be fully opened during initial warm-up. Drip legs from the bottom of the
mud boot are piped to blow down tanks. Subsequently, each location will need to be blown down
during the steam blow prior to target insertion. A man-lift, scaffolding or temporary piping will be
required at any drip leg not accessible at grade. Drip leg drain steam trap isolation valves shall
remain closed until the piping is proven clean. Temperature readings will need to be taken either
with an IR heat gun or inline thermal wells to verify open to the blow down tanks. Should a drip
leg become plugged, the drip leg will need to be unplugged. Steam will need to be isolated at
the source. The drip leg line will need to be cut for inspection and locating the plug. The line will
need to be clear either mechanically or with air prior to proceeding with the exhaustive blows.
Upon completion of the blows, the blow down tanks will need to be cleaned. Upon completion of
the low pressure proving blows on the drip legs, the drip legs can be isolated during the higher
pressure blows. However, the drip legs should be cycled open and closed prior to targeting.

3.3 Remove/modify the following:

3.3.1 See Construction Activities in Appendix D.

3.4 The following exit point(s) will be used:

3.4.1 Removed Valves at Boiler Feed Water Pumps

3.4.2 Spread Pipe of HP Heater #2

3.4.3 Elbow at Aux Steam to Deaerator

3.4.4 Cut and rotate elbow at Deaerator

3.4.5 Removed valve at boiler warming

3.5 Install temporary vent piping and supports per BWFD erection isometric drawings (Appendix E).

3.6 Install drain lines from the noise suppressors to the desired drain location.

3.7 Install air supply to the target insertion device. Test for proper operation prior to admitting steam
into header.

3.8 Install scaffolding as required to access the target insertion location, and each drip leg valve.

3.9 Spring can stops need to be addressed.





B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 10 of 30
4 STEAM BLOW SEQUENCE AND PROCEDURE

4.1 Follow and review all steps in section 1 through 3 of this document before any steam blowing
begins.

4.2 Steam blow sequence:

4.2.1 Target Blows:

4.2.1.1 Blow 1 - Boiler Feed Pump Turbine supply from Aux steam supply.

4.2.1.2 Blow 2 - Boiler Feed Pump Turbine supply from Aux steam through CRH.

4.2.1.3 Blow 5 - Gland Seal Steam - HP A, HP B, IP, LP A and LP B.

4.2.2 Service Blows:

4.2.2.1 Blow 3 - Deaerator from aux boiler through BFPT header.

4.2.2.2 Blow 4 - Deaerator from aux boiler.

4.2.2.3 Blow 6 - #2 HP heater header from CRH back blow.

4.2.2.4 Blow 7 - Boiler bottoms header from aux boiler.

4.3 Each individual blow is covered in the following sections. The following target criteria applies:

4.3.1 The targets to be exposed shall be made of brass with a finish as close to mirror
quality as possible.

4.3.2 The disturbance factor or cleaning force ratio (CFR) shall be greater than 1.05 in all
areas of the line being targeted.

4.3.3 The target shall be exposed to 20 minutes of a steady flow of steam at the mass flow
rates and temperatures specified in this section.

4.3.4 No impacts larger than (0.016) 0.4 mm are allowed on the target plate.

4.3.5 No more than 10 impacts (0.008) 0.2mm to (0.016) 0.4 mm size are allowed on
100 cm^2 target plate surface.

4.3.6 Target plates will span at least 90% of the diameter of the piping being targeted.

4.3.7 Two acceptable consecutive targets are required.

4.4 Prior to any target being inserted into the steam flow, the following steps must be taken:

4.4.1 Blow down all drip legs and dead legs in the steam flow path.

4.5 For service blows, the individual blow circuit cleaning is complete when the set minimum
duration has elapsed and there are no visible contaminants in the exhausting steam plume or
waste effluent exiting the silencer.



B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 11 of 30
4.6 After proper notification has been given to the control room and work area, open the warm up
line bypassing the steam blow valve. Follow all recommended start-up and warm-up procedures
of Lilama, Boiler OEM and any other governing plant procedures.

4.7 Check for steam leaks and expansion problems in the temporary piping and system piping.
During the warm up for steam blow operation, repair leaking flanges on temporary vent pipe as
necessary. Monitor spring can support settings on permanent piping.

4.8 Closely monitor all drip legs in the steam blow flow path during warm up procedures to ensure
flow. If any blockage is detected, immediately utilize a compressed air or nitrogen source to
back blow the drip leg.

4.8.1 During the warm up process all drip legs should be clear and dry steam exiting.

4.9 Once the system is warm:

4.9.1 For Continuous Blows 1 through 8, slowly open system valve to increase flow as
needed.

4.10 Orifice change is required between blow 4 and blow 5.

4.11 Preliminary valve lineup in aux system:

Note: Valves that are listed are aligned for Blow 1.

B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 12 of 30



Item Position B&W Signoff Lilama Signoff
Blow 1 Boiler Feed Pump Turbine supply from Aux steam supply
Aux Boiler


00QHB01AA816
Closed

00QHB01AA815
Closed

00QHE30AA851
Closed

00QHE30AA852
Closed

00QLA17AA504
Closed

00QLA18AA501
Closed

00QHE30AA853
Closed

00QHE30AA854
Closed

00QLA17AA505
Closed

00QLA18AA502
Closed

00QHE30AA855
Closed

00QHE30AA856
Closed

00QHE30AA857
Closed

00QHE30AA858
Closed

00QHB14AA601
Closed

00QHB13AA501
Closed

00QUB20AA501
Closed

00QHB01AA912
Closed

00QHB01AA913
Closed

00QHB01AA914
Closed

00QHB01AA915
Closed

00QHB01AA916
Closed

00QHB01AA917
Closed

00QHB01AA818
Closed

00QLA19AA501
Closed

00QHB10AA501
Closed

00QHB10AA901
Closed

00QHB10AA902
Closed

00QHB10AA903
Closed

00QHB10AA904
Closed

B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 13 of 30


Item Position B&W Signoff Lilama Signoff
Blow 1 Boiler Feed Pump Turbine supply from Aux steam supply
Aux Header

00LBG10CP003 Closed

00LBG10AA201 Open

20LBG13AA701 Closed

10LBG13AA520 Closed

20LBG13AA504 Closed

20LBG13AA502 Closed

20LBG13AA503 Closed

10LBG13AA521 Closed

00LBG93AA202 Closed

00LBG43AA201 Closed

10LBG13AA520 Closed

10LBG13AA507 Closed

10LBG13AA508 Closed

10LBG13AA506 Closed

10LBG13AA701 Open

10LBG13AA201 Open

10LBG13AA503 Open

10LBG13AA502 Closed

10LBG13AA504 Closed

10LBG14AA601 Closed

10LBG92AA201 Closed

10LBG15AA601 Closed

10LBG10AA901 Closed

10LBG10AA902 Closed

10LBG30AA201 Closed

10LBG80AA201 Closed

10LBG80AA530 Closed

10LBG70AA512 Closed

10LBG70AA518 Closed

10LBG70AA515 Closed

10LBG80AA001 Closed

B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 14 of 30


Item Position B&W Signoff Lilama Signoff
Blow 1 Boiler Feed Pump Turbine supply from Aux steam supply
Aux Header

10LBG80AA202 Closed

10LBG40AA201 Closed

10LBG91AA201 Open

10LBG42AA201 Closed

10LBG70AA501 Closed

10LBG70AA512 Closed

10LBG70AA514 Closed

10LBG70AA513 Closed

10LBG70AA520 Closed

10LBG90AA202 Closed

10LBG90AA201 Closed

10LBG16AA501 Closed

BFPT

10LBG60AA861 Closed

10LBG60AA862 Closed

10LBG60AA801 Closed

10LBG60AA802 Closed

10LBG60AA201 Open

10LBR10AA802 Closed

10LBR12AA201 Open

10LBR14AA801 Closed

10LBR22AA502 Closed

10LBR22AA801 Closed

10LBR22AA802 Closed

10LBR22AA901 Closed

10LBR22AA902 Closed

10LBR22AA801 Closed

10LBR22AA501 Closed

10LBR12AA901 Closed

10LBR12AA902 Closed

10LBR12AA801 Closed

B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 15 of 30

Item Position B&W Signoff Lilama Signoff
Blow 1 Boiler Feed Pump Turbine supply from Aux steam supply
BFPT

10LBR12AA905 Closed

10LBR12AA906 Closed

10LBR12AA907 Closed

10LBR12AA908 Closed

10LBR12AA909 Closed

10LBR12AA910 Closed

10LBR12AA903 Closed

10LBR12AA904 Closed

10XAL42AA801 Closed

10LBR10AA201 Closed

10LBR10AA801 Closed

10LBR11AA201 Open

10LBR13AA801 Closed

10LBR21AA502 Closed

10LBR21AA801 Closed

10LBR21AA802 Closed

10LBR21AA801 Closed

10LBR21AA901 Closed

10LBR21AA902 Closed

10LBR21AA501 Closed

10LBR11AA902 Closed

10LBR11AA901 Closed

10LBR11AA903 Closed

10LBR11AA904 Closed

10LBR11AA801 Closed

10LBR11AA905 Closed

10LBR11AA906 Closed

10LBR11AA907 Closed

10LBR11AA908 Closed

10LBR11AA909 Closed

10LBR11AA910 Closed

B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 16 of 30

Item Position B&W Signoff Lilama Signoff
Blow 1 Boiler Feed Pump Turbine supply from Aux steam supply
Gland Seal Steam

0MAW01AA205 Open

OMAW01AA005 Closed

0MAW01AA010 Open

0MAM03AA705 Closed

0MAM13AA705 Closed

0MAW02AA601 Closed

0MAW02AA901 Closed

0MAW02AA902 Closed

0MAW02AA005 Closed

0MAW02AA205 Closed

0MAM15AA005 Closed

Deaerator

10LBD10AA807 Closed

10LBD10AA201 Closed

10LBD10AA803 Closed

10LBD10AA861 Closed

10LBD10AA862 Closed

10LBD10AA804 Closed

10LBD10AA202 Closed

10LBD10AA805 Closed

10LBD10AA905 Closed

10LBD10AA906 Closed

10LBG51AA201 Closed

10LBD10AA865 Closed

10LBD10AA866 Closed

10LBG50AA203 Closed

10LBG50AA803 Closed

10LBG50AA202 Closed

10LBG50AA201 Closed

10LBG50AA203 Closed

10LBG50AA802 Closed

B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 17 of 30
















Item Position B&W Signoff Lilama Signoff
Blow 1 Boiler Feed Pump Turbine supply from Aux steam supply
Deaerator

10LBG50AA863 Closed

10LBG50AA864 Closed

10LBG50AA801 Closed

10LBG50AA861 Closed

10LBG50AA862 Closed

HP No.2 Heater

10LBQ20AA901 Closed

10LBQ20AA902 Closed

10LBQ20AA903 Closed

10LBQ20AA904 Closed

10LBQ20AA801 Closed

10LBQ20AA802 Closed

10LBQ20AA201 Closed

10LBQ20AA202 Closed

10LBQ20AA861 Closed

10LBQ20AA862 Closed

10LBQ20AA803 Closed

Warming Steam

10LBG11AA501 Closed

10LBG12AA501 Closed

10LBG23AA501 Closed

10LBG23AA503 Closed

B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 18 of 30
4.12 Blow 1. This blow will clean the aux steam header from the aux boiler, through the aux header
and to the boiler feedwater pumps. Exiting at removed BFW pump turbine valves.

Type of Blow: Continuous Targeted Blow

Reference: Marked up flow path for Blow 1 in Appendix A

Preliminary preparations: Verify communication with control room.
Verify all drip leg drain valves are fully open.
Verify proper target insertion device operation.
Valve lineup

Steam Source: Aux boiler

Mass Flow Rate: 50,000 kgs/hr

Temperature: 300 deg C

CFR 39.46 in line from aux header to BFPT
2.51 upstream of valve 10LBR12-AA201
2.05 upstream of valve 10LBR11-AA201

Blow duration: 12 to 24 hours

The above piping system meets the acceptable cleanliness criteria.


________________________________________________________________
B&W Fluid Dynamics Representative Date


________________________________________________________________
Lilama Representative Date


________________________________________________________________
Viet Nam Oil and Gas Group Representative Date


Upon Completion of Blow 1 Manipulate the following valves.

Open Valves Close Valves
10LBG70AA701 10LBG91AA201
10LBG70AA201 10LBR11AA201
10LBR22AA501 10LBR12AA201
10LBR21AA501
10LBR21AA502
10LBR22AA502





B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 19 of 30
4.13 Blow 2. This blow is designed to clean the alternate pipe path from the extraction steam to the
BFW pump turbines. To accomplish this blow, the steam must pass through part of the cold
reheat piping. During this blow, the piping to the reheater must be completed and available for
blowing. Steam will exit at same point as blow 1.

Type of Blow: Continuous Targeted Blow

Reference: Marked up flow path for Blow 2 in Appendix A

Preliminary preparations: Verify communication with control room.
Verify all drip leg drain valves are fully open.
Verify proper target insertion device operation.
Valve lineup

Steam Source: Aux boiler

Mass Flow Rate: 50,000 kgs/hr

Temperature: 300 deg C

CFR 0.58 in line from CRH to Aux header
1.10 in line from CRH to HP Heater No. 2
2.52 in line from HP No.2 Heater to BFPT
1.84 upstream of valve 10LBR12-AA501
1.61 upstream of valve 10LBR11-AA501

Blow duration: 12 to 24 hours

The above piping system meets the acceptable cleanliness criteria.


________________________________________________________________
B&W Fluid Dynamics Representative Date


________________________________________________________________
Lilama Representative Date


________________________________________________________________
Viet Nam Oil and Gas Group Representative Date


Upon Completion of Blow 1 manipulate the following valves.

Open Valves Close Valves
10LBG91AA201 10LBG70AA701
10LBR10AA201 10LBG70AA201
10LBD10AA202 10LBR22AA501
10LBR21AA501
10LBR21AA502
10LBR22AA502

B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 20 of 30
4.14 Blow 3. This blow is designed to backblow the line from the BFPT header to the No. 4 extraction
header. Steam must pass through the No. 4 extraction header to reach the deaerator. The exit
point is a cut and rotated elbow before the deaerator.

Type of Blow: Continuous Service Blow

Reference: Marked up flow path for Blow 4 in Appendix A

Preliminary preparations: Verify communication with control room.
Verify all drip leg drain valves are fully open.
Valve lineup

Steam Source: Aux boiler

Mass Flow Rate: 50,000 kgs/hr

Temperature: 300 deg C

Blow duration: 15 minutes

The above piping system meets the acceptable cleanliness criteria.


________________________________________________________________
B&W Fluid Dynamics Representative Date


________________________________________________________________
Lilama Representative Date


________________________________________________________________
Viet Nam Oil and Gas Group Representative Date


Upon Completion of Blow 1 manipulate the following valves.

Open Valves Close Valves
10LBG30AA201 10LBG91AA201
10LBG80AA201














B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 21 of 30
4.15 Blow 4. This blow is designed to clean the steam line from the aux header to the deaerator tank.
The exit point is an elbow installed in place of removed check valve 10LBG50AA701.

Type of Blow: Continuous Service Blow

Reference: Marked up flow path for Blow 5 in Appendix A

Preliminary preparations: Verify communication with control room.
Verify all drip leg drain valves are fully open.
Valve lineup.

Steam Source: Aux boiler

Mass Flow Rate: 50,000 kgs/hr

Temperature: 300 deg C

Blow duration: 15 minutes


The above piping system meets the acceptable cleanliness criteria.


________________________________________________________________
B&W Fluid Dynamics Representative Date


________________________________________________________________
Lilama Representative Date


________________________________________________________________
Viet Nam Oil and Gas Group Representative Date


Upon Completion of Blow 1 manipulate the following valves.

Open Valves Close Valves
10LBG80AA201 10LBG30AA201
10LBG80AA202














B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 22 of 30
4.16 Blow 5. This bow is designed to clean the steam line from the aux header to the gland seal
steam system. The lines to HP A, HP B, IP, LP A, and LP B glands will be blown. Cycle through
temporary valves to blow each gland individually.

Type of Blow: Continuous Targeted Blow

Reference: Marked up flow path for Blow 3 in Appendix A

Preliminary preparations: Verify communication with control room.
Verify all drip leg drain valves are fully open.
Verify proper target insertion device operation.
Valve lineup for other seal steam temp valves closed

Steam Source: Aux boiler

Mass Flow Rate: 10,000 kgs/hr

Temperature: 300 deg C

CFR 7.34 in line from aux header to gland seals

Blow duration: 12 - 24 hours

The above piping system meets the acceptable cleanliness criteria.


________________________________________________________________
B&W Fluid Dynamics Representative Date


________________________________________________________________
Lilama Representative Date


________________________________________________________________
Viet Nam Oil and Gas Group Representative Date

Note: Waiting on Toshiba to provide information on connections for LP steam glands inside turbine
shell for blows 3D and 3E.

Upon Completion of Blow 1 manipulate the following valves.

Open Valves Close Valves
10LBG70AA501 10LBG80AA201
10LBG70AA201 10LBG80AA202
10LBQ20AA201 10LBR22AA501
10LBQ20AA202 10LBR21AA501







B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 23 of 30
4.17 Blow 6. This blow is designed to clean the steam line from CRH piping to HP heater No.2. Steam
will flow through the aux header and backflow through the CRH to aux steam line and CRH
piping. The exit point is at the left out weld at HP Heater No. 2 (currently blinded for hydrotest
purposes). Install fire blanket on top portion of HP Heater No. 2 to protect insulation.

Type of Blow: Continuous Service Blow

Reference: Marked up flow path for Blow 8 in Appendix A

Preliminary preparations: Verify communication with control room.
Verify all drip leg drain valves are fully open.
Valve lineup

Steam Source: Aux boiler

Mass Flow Rate: 10,000 kgs/hr

Temperature: 300 deg C

Blow duration: 15 minutes


The above piping system meets the acceptable cleanliness criteria.


________________________________________________________________
B&W Fluid Dynamics Representative Date


________________________________________________________________
Lilama Representative Date


________________________________________________________________
Viet Nam Oil and Gas Group Representative Date


Upon Completion of Blow 1 manipulate the following valves.

Open Valves Close Valves
10LBG90AA202 10LBG70AA501
10LBG70AA201











B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 24 of 30
4.18 Blow 7. This Blow is designed to clean the steam lines from the aux header to the boiler
headers. The exit points will be either removed valves or left out welds.

Type of Blow: Continuous Service Blow

Reference: Marked up flow path for Blow 7 in Appendix A

Preliminary preparations: Verify communication with control room.
Verify all drip leg drain valves are fully open.
Valve lineup

Steam Source: Aux boiler

Mass Flow Rate: 10,000 kgs/hr

Temperature: 300 deg C

Blow duration: 15 minutes


The above piping system meets the acceptable cleanliness criteria.


________________________________________________________________
B&W Fluid Dynamics Representative Date


________________________________________________________________
Lilama Representative Date


________________________________________________________________
Viet Nam Oil and Gas Group Representative Date





















B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 25 of 30
Appendix A

Drawing attachments

1. Blow 1 Steam Blow Flow Diagrams Rev 0
2. Blow 2 Steam Blow Flow Diagrams Rev 0
3. Blow 3 Steam Blow Flow Diagrams Rev 0
4. Blow 4 Steam Blow Flow Diagrams Rev 0
5. Blow 5
a. Blow 5A Steam Blow Flow Diagrams Rev 0
b. Blow 5B Steam Blow Flow Diagrams Rev 0
c. Blow 5C Steam Blow Flow Diagrams Rev 0
d. Blow 5D Steam Blow Flow Diagrams Rev 0
e. Blow 5E Steam Blow Flow Diagrams Rev 0
6. Blow 6 Steam Blow Flow Diagrams Rev 0
7. Blow 7 Steam Blow Flow Diagrams Rev 0

B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 26 of 30
Appendix B


Pre-Blow Safety Checklist



Item No. Description YES NO N/A
1. Walkdown of permanent system piping has been performed by
execution team;
There is no combustible material in contact with piping.
Spring can stops are removed at all locations.
Piping is not restricted to grow by any items (scaffold, etc.)
Uninsulated sections have been wrapped or barricaded.
Isolation list is complete and all tags are in place.


2. Walkdown of temporary vent piping has been performed by execution
team;
There is no combustible material in contact with piping.
Temporary pipe supports are in place and are adequate.
Temporary insulation is installed at inserter and quench points.
Air delivery hose is connected and charged.
Silencer location is adequate and drain hose is installed.


3. Fire extinguishers are available and ready for use.
4. Communication with the control room (steam source) has been
established and review of shutdown procedure has taken place.

5. High noise areas are identified and ear protection is readily available.
6. Safety barricade tape has been erected around silencer (s) and signs
are in place.

7. All road closure permits related to the steam blow are in place.
8. Projected steam plume direction will not cause any harm or reduce
visibility for adjacent work.

9. All scaffolding installed for access to valves, target insertion devices,
etc. is complete and green tag(s) are in place.

10. Notification of all site personnel and adjacent units has taken place.
11. Notification of surrounding community has taken place per site policy.
12. JHA is signed by all personnel involved.









B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 27 of 30
Appendix C

Continuous Blows MCR Data*



Aux steam
Outlet
BFP Turbine
aux supplied
Aux Steam to
CRH

Design Flow [kg/hr] 50000 35423** 120000

Pressure [kPag] 1300 1032 1300

Pressure [kPa] 1400 1132 1400

Temperature [deg C] 350 350 335

Specific Volume [cu-
m/kg] 0.2003 0.2489 0.1950


* 105% load heat balance was used for MCR data
** Flow rate is for each of the BFP turbines

B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 28 of 30
Appendix D

Construction Activities


B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 29 of 30
Appendix E

B&W Temporary Piping Isometrics and Bill of Materials

2012111272-SB-ISO-001 Rev 0 Blow 1








































B&W Fluid Dynamics
Steam Blow Procedure
Vung Ang 1 Project Steam Blow

Issue Date: April 16, 2013
Revision: 0

Page 30 of 30

Appendix F

Reference Materials

Marked up P&IDs showing lines not steam blown, to be cleaned by other means.

S-ar putea să vă placă și