GUESE, Aris H. Arch. Dennis C.

de Villa
AR51FC1 Construction Management
Activity: Footing and Column
Duration: 49 Days
CODE ACTIVITY DURATION (days) 1 2 3 4 5 6 7 8 9 10 12 13 14 15
A Clearing 2
B Layout 1
C Order of materials 1
D Excavation 11
E Installation of rebars and tie wires for footing 8
F Installation of formworks for footing 3
G Concrete pouring for footing 3
H Installation of rebars and tie wires for column 8
I Installation of fromworks for column 5
J Conrete pouring for column 3
K Laying of Masonry for wall footing 3
L Backfilling of foundation 1
CODE ACTIVITY DURATION (days) 16 17 18 19 20 21 22 23 24 25 26 27 28 29
A Clearing 2
B Layout 1
C Order of materials 1
D Excavation 11
E Installation of rebars and tie wires for footing 8
F Installation of formworks for footing 3
G Concrete pouring for footing 3
H Installation of rebars and tie wires for column 8
I Installation of fromworks for column 5
J Conrete pouring for column 3
K Laying of Masonry for wall footing 3
L Backfilling of foundation 1
CODE ACTIVITY DURATION (days) 30 31 32 33 34 35 36 37 38 39 40 41 42
A Clearing 2
B Layout 1
C Order of materials 1
D Excavation 11
E Installation of rebars and tie wires for footing 8
F Installation of formworks for footing 3
G Concrete pouring for footing 3
H Installation of rebars and tie wires for column 8
I Installation of fromworks for column 5
J Conrete pouring for column 3
K Laying of Masonry for wall footing 3
L Backfilling of foundation 1
CODE ACTIVITY DURATION (days) 43 44 45 46 47 48 49
A Clearing 2
B Layout 1
C Order of materials 1
D Excavation 11
E Installation of rebars and tie wires for footing 8
F Installation of formworks for footing 3
G Concrete pouring for footing 3
H Installation of rebars and tie wires for column 8
I Installation of fromworks for column 5
J Conrete pouring for column 3
K Laying of Masonry for wall footing 3
L Backfilling of foundation 1