Sunteți pe pagina 1din 2

METHOD STATEMENT FOR INSTALLATION OF FAN COIL UNIT

1.0 SCOPE OF WORK


The Method Statement is applicable to installation of Fan Coil Units at all designated levels.
2.0 RESPONSIBILITY
Before commencement of any installation activity, the following procedures are reuired to be carried out.
!." #ll materials used must have an approved material submittal.
!.! Chec$ that FCUs are in compliance with approved submittal.
!.% Chec$ for any physical damages upon receipt of the same at site.
!.& Before
!.' installations ensure that the location of FCU is as per the approved shop drawing.
!.( Chec$ Base Frame and #nti )ibration mounts are in place as per approved submittal.
!.* +etain the shipping crates and protection covers until the unit is at its final location.
3.0 DESCRIPTION OF WORK
Installat!n P"!#$%&"$
%." ,rovide supervision and labor to assist in the rigging operation.
%.! Maneuver the euipment from loading points to the proper locations as shown in approved drawing in a
reasonably timely manner.
%.% Select the correct si-e . model FCU and install the unit in the location as configured in the shop drawing.
%.& /rill 0 fi1 the hanging brac$ets 0 lift and hang the FCU2s.
%.' #fter completing the installation remove the shipping spacers between the fan.motor base frame and the
unit. 3Manufacturer to secure the fan assembly during shipment normally uses shipping spacers.4
%.( Connect drainpipe through a 5U5 trap to open drain. The trap shall have minimum water seal euivalent to
negative suction pressure at the fan plus "6mm.
%.* Connection of supply and return chilled water to be done as per with supply at the bottom and return at the
top and ensure counter flow connection.
%.7 Complete electrical connection to the unit recommended by the manufacturer. Motor up to &89 with
/.:.;. Starter and above star<delta starter.
%.= >nstallation to be as per approved shop drawing.
%."6 Ta$e the reuired action to protect the interior of the FCU during construction.
%."" Complete electrical connection to the unit recommended by the manufacturer.
'.0 LABOUR( PLANT ) MATERIAL RE*UIREMENTS
&." The material shall be of approved Manufacturer as per the material submittal.
&.! S$illed technicians, in sufficient numbers, shall carry out the installation.
&.% The wor$manship shall be maintained at all times.
+.0 SUPER,ISION ARRAN-EMENTS
'." # constant supervision by the foreman and supervisor shall be carried out in order to control the wor$ and
the wor$manship.
'.! ?1perienced supervisors shall be appointed to carry out the wor$ smoothly and to have the full control of
the labour.
..0 R$/$"$n#$ D!#&0$nts
(." /rawings
(.! Specification@ "'7%6
1.0 E2&30$nt R$2&"$%
*." #ll necessary rigging euipment i.e. slings, chains, deshac$les, spreader bars etc.
*.! Chain bloc$s, e1tra chains.slings, rollers etc for maneuvering within plant rooms.
4.0 EN,IRONMENTAL RE*UIREMENTS
7." # Safety officer shall ensure that the labor has a good wor$ing environment, a ha-ard free environment.
5.0 TEMPORARY WORKS TO BE DESI-NATED AND INSTALLED
A.#
10.0 HEALTH ) SAFETY RE*UIREMENTS
"6." ?nsure wor$ area is clean and tidy.
"6.! ?nsure the wor$ #rea is well ventilated.
"6.% #ll employees shall adopt safe wor$ing practices.
"6.& Safety euipment 3e1ample Bard Bats, Safety Shoes, Coveralls, Cloves, Coggles when necessary etc.4 to
be worn at all times.
P"$3a"$% 678 K. Ln9anna R$:$;$% 678 Can$" T!na< A33"!:$% 678 Can$" T!na<

S9nat&"$8 S9nat&"$8 S9nat&"$8

S-ar putea să vă placă și