Managing Multiple Projects with Project Groups with Project Groups Developed By Carol Bolstad Scheduling and Information Services, Inc. January 2005 Please Do Not Distribute without written permission from SIS Scheduling and Information Services, Inc. 2 Tracking Multiple Schedules Tracking Multiple Schedules Independently plan, schedule, and control multiple Independently plan, schedule, and control multiple projects projects Combine for overall corporate reporting and planning, Combine for overall corporate reporting and planning, and company and company- -wide decision making at higher levels of wide decision making at higher levels of management. management. Manage limited resources across multiple projects Manage limited resources across multiple projects simultaneously. simultaneously. Manage relationships between different projects Manage relationships between different projects activities. activities. Divide a large, complex project into smaller projects, Divide a large, complex project into smaller projects, making each one more manageable for individual project making each one more manageable for individual project managers. managers. Scheduling and Information Services, Inc. 3 Benefits of Project Groups Benefits of Project Groups Project 1 Project 2 Project 3 Project 4 Project 5 Business Development Management and Reporting Staffing Subcontractors Labor Cash Flow Equipment Project Group Centralized Procurement Scheduling and Information Services, Inc. 4 Check In / Check Out of Projects to the Check In / Check Out of Projects to the Group Project Group Project Create Project Group. Create Sub- Projects Check Out Sub Projects for Development by Project Managers Check In Sub Project Link activities for Resource availability from Group Project if necessary Check Out Sub Project to field Define activity coding structure, resource codes, and calendars Scheduling and Information Services, Inc. 5 10 Projects Grouped 10 Projects Grouped Scenario: Scenario: Arrow Kitchen & Bath is a general contractor specializing Arrow Kitchen & Bath is a general contractor specializing in kitchen and bath remodels, and deck construction. in kitchen and bath remodels, and deck construction. Self perform carpentry Self perform carpentry Procure cabinetry, countertops, appliances, specialty items Procure cabinetry, countertops, appliances, specialty items Obtain all permits Obtain all permits Coordinate inspections. Coordinate inspections. Subcontract Subcontract - - electrical, plumbing, concrete/masonry, electrical, plumbing, concrete/masonry, tile/flooring, drywall/paint, cabinetry, HVAC, insulation, tile/flooring, drywall/paint, cabinetry, HVAC, insulation, landscaping, appliance installation, and cleaning. landscaping, appliance installation, and cleaning. Scheduling and Information Services, Inc. 6 10 Projects Grouped 10 Projects Grouped They have the following projects either in progress or They have the following projects either in progress or starting within the next 30 days: starting within the next 30 days: 5 Kitchen Remodels 5 Kitchen Remodels: : Attleboro, Cumberland, Rumford, Hillside, and West Lincoln Attleboro, Cumberland, Rumford, Hillside, and West Lincoln 3 Bath Remodels 3 Bath Remodels: : Hood River, Riverside, and Stevenson Hood River, Riverside, and Stevenson 2 Decks 2 Decks with with Tiki Tiki Bar and hot tubs: Bar and hot tubs: Carson and Bend Carson and Bend Scheduling and Information Services, Inc. 7 Staffing Staffing They have the following staff: They have the following staff: Tony Osborne, President Tony Osborne, President John Johnson, Purchaser John Johnson, Purchaser 5 Superintendents each can manage 2 concurrent 5 Superintendents each can manage 2 concurrent projects: projects: Andy Henson Andy Henson Frank Church Frank Church Greg Smith Greg Smith Howard Miller Howard Miller Judy Prince Judy Prince Scheduling and Information Services, Inc. 8 Summary of all projects Summary of all projects Current and Upcoming Procurement Items Current and Upcoming Procurement Items Upcoming Permits and Inspections Upcoming Permits and Inspections Labor requirements Labor requirements Critical activities Critical activities Staff members requirements Staff members requirements When can I take on a new project and who will I assign it to? When can I take on a new project and who will I assign it to? Subcontractor requirements Subcontractor requirements Owner and Superintendent want only their schedule sorted by: Owner and Superintendent want only their schedule sorted by: Early start Early start Responsibility Responsibility At the weekly meeting, they would like to review At the weekly meeting, they would like to review the following information about their projects. the following information about their projects. Scheduling and Information Services, Inc. 9 Summary of all projects Summary of all projects Scheduling and Information Services, Inc. 10 Procurement Items for Next 3 Weeks Procurement Items for Next 3 Weeks Scheduling and Information Services, Inc. 11 Permits and Inspections Permits and Inspections Scheduling and Information Services, Inc. 12 Carpenter and Laborer Requirements Carpenter and Laborer Requirements Scheduling and Information Services, Inc. 13 Carpenter and Laborer Requirements Carpenter and Laborer Requirements By Day By Day Scheduling and Information Services, Inc. 14 Critical Activities for the Next 3 weeks Critical Activities for the Next 3 weeks Scheduling and Information Services, Inc. 15 Summary of Jobs By Staff Summary of Jobs By Staff Scheduling and Information Services, Inc. 16 Activities by Staff Member Activities by Staff Member Scheduling and Information Services, Inc. 17 3 Week Look ahead By Subcontractor 3 Week Look ahead By Subcontractor Scheduling and Information Services, Inc. 18 Single Project for Owner and Single Project for Owner and Superintendent Superintendent Scheduling and Information Services, Inc. 19 Single Project Organized By Responsibility Single Project Organized By Responsibility Scheduling and Information Services, Inc. 20