PART I, EXHIBIT ONE

Appendix 2
Client Name: SMCV
Project Name: CVPUE
Project Location: AREQUIPA, PERU
TYPE OF WORK UNIT
Receive &
Shakeout Fabricate Erect
Supports,
Weldout &
Punchout
Hydro-test
Signoff
Flush &
Re-Instate
Final
Acceptance
A/G Pipe Fab & Erection LF 5% 15% 40% 15% 10% 10% 5% 100%
(painting see below)
Excavate &
Preparation
Erect Pipe
/conduit
Hydro
Test &
Signoff
Backfill /
concrete
Flush & Re-
Instate
Final
Acceptance
U/G Pipe Installation LF 10% 55% 10% 15% 5% 5% 100%
U/G Conduit / Ductbanks LF 10% 45% 40% 5% 100%
U/G 34.5 KV Cable Trench LF 35% 50% 15% 100%
Excavate &
Preparation
Form &
Rebar Pour
Strip &
Finish
Back fill &
Compact
Clear
Punchlist
Final
Acceptance
Typical Foundations CY 10% 40% 15% 10% 15% 5% 5% 100%
Area Paving CY 10% 55% 15% 10% 5% 5% 100%
Receive &
Shakeout Erect
Plumb,
Bolt &
Torque
Clear
Punchlist
Final
Acceptance
Structural Steel Erection TON 10% 50% 25% 10% 5% 100%
Ladders & Platforms LF, SF 10% 50% 25% 10% 5% 100%
Pipe Supports TON 10% 50% 25% 10% 5% 100%
Misc. Steel EA,LF,SF 10% 50% 25% 10% 5% 100%
Receive
Rough Set &
Prelim Align
Level &
Grout Final Align Run-In
Clear
Punchlist
Final
Acceptance
Static Equipment EA 5% 65% 15% 10% 5% 100%
Vessel Internals EA 5% 80% 10% 5% 100%
Rotating Equipment EA 5% 40% 10% 25% 10% 5% 5% 100%
Install Units Conduit
Wire
/Cable
Terminate /
Test
Clear
Punchlist
Final
Acceptance
Cable Tray LF 90% 5% 5% 100%
Grounding LF 40% 30% 20% 5% 5% 100%
Electrical Equipment EA 70% 20% 5% 5% 100%
Home Run Cable LF 70% 20% 5% 5% 100%
Instrument Wire LF 50% 40% 5% 5% 100%
Power Cable LF 20% 40% 30% 5% 5% 100%
34.5 KV Cable LF 75% 15% 5% 5% 100%
Lighting (Devices or wiring) EA,LF 10% 40% 20% 20% 5% 5% 100%
Receive Calibrate
Install &
Support Loop Check
Clear
Punchlist
Final
Acceptance
Tagged Instruments EA 5% 10% 50% 25% 5% 5% 100%
Insulation Metal Trim
Clear
Punchlist
Final
Acceptance
Equipment Insulation EA,SF 40% 40% 10% 5% 5% 100%
Pipe Insulation LF,SF 40% 40% 10% 5% 5% 100%
Blast &
Prime Finish Coat
Clear
Punchlist
Final
Acceptance
Painting LF,SM 20% 70% 5% 5% 100%
Contract No.:
Rev. No.:
Progress Assessment Increments
FORM 000.430.F0188 (Revision Date: June 8, 2005)
Contact Management
Page 1 of 3
PART I, EXHIBIT ONE
Appendix 2
Client Name: SMCV
Project Name: CV2
Project Location: AREQUIPA, PERU
TYPE OF WORK UNIT
Final
Acceptance
Final
Acceptance
Final
Acceptance
Final
Acceptance
Final
Acceptance
Final
Acceptance
Final
Acceptance
Final
Acceptance
Final
Acceptance
Contract No.:
Rev. No.:
Progress Assessment Increments
(THE CONTRACT ADMINISTRATOR SHALL COMPLETE THE "TYPE OF WORK" COLUMN BASED ON THE BREAKDOWN OF THE CONTRACT
FORM 000.430.F0188 (Revision Date: June 8, 2005)
Contact Management
Page 2 of 3
PART I, EXHIBIT ONE
Appendix 2
PRICE SET FORTH IN PART II OF THE RFP.)
AND AGREED IN THE FINAL CONTRACT.)
(BIDDERS SHALL PROVIDE PERCENTAGES AS A PART OF THEIR PROPOSAL WHICH SHALL BE REVIEWED AS A PART OF BID CONDITIONING