0 evaluări0% au considerat acest document util (0 voturi)
146 vizualizări42 pagini
This course covers process plant design and economics. It focuses on (1) economic analysis to determine project profitability through estimating costs and revenues, and (2) detailed design of process equipment like columns and heat exchangers. Assessment includes assignments, a test, and an open-book final exam. Topics include column design, heat exchanger design, and process plant economics including capital cost estimation methods like using historical data, the factorial method, and bare module factor method. The textbook and other references provide guidance on these design and economic analysis techniques.
This course covers process plant design and economics. It focuses on (1) economic analysis to determine project profitability through estimating costs and revenues, and (2) detailed design of process equipment like columns and heat exchangers. Assessment includes assignments, a test, and an open-book final exam. Topics include column design, heat exchanger design, and process plant economics including capital cost estimation methods like using historical data, the factorial method, and bare module factor method. The textbook and other references provide guidance on these design and economic analysis techniques.
This course covers process plant design and economics. It focuses on (1) economic analysis to determine project profitability through estimating costs and revenues, and (2) detailed design of process equipment like columns and heat exchangers. Assessment includes assignments, a test, and an open-book final exam. Topics include column design, heat exchanger design, and process plant economics including capital cost estimation methods like using historical data, the factorial method, and bare module factor method. The textbook and other references provide guidance on these design and economic analysis techniques.
What is this course about? (Objectives) 1. Process Plant Economics Economic analysis Helps to determine whether a project is profitable or not Estimation of fixed and operating costs (expenses) Estimation of revenue (income) Estimation of profits (=income expenses) for many years Overall profitability 2. Design (Process equipment design) Column design Plate column design Detailed design of columns with plates More than diameter and height calculations (which is known as sizing) Plate design Packed column design Detailed design of column with packing materials Diameter and height calculations Height is calculated using empirical correlations ( not using theoretical or graphical methods) Easy for computer (spreadsheet calculations) Heat exchanger design More than heat exchanger surface area calculation Shell and tube heat exchangers Shell and tube diameters are calculated Number of tubes are calculated Number of tube passes are calculated Assessment Assessment Components % of Overall Marks 1. Individual assignment 1 ( Week 4 - Economic analysis using spreadsheet calculations) 7.5% 2. Week-in-industry (Week 7 whole week) 10% 3. Test (Week 8 Closed-book) 15% 4. Individual assignment 2 ( Week 9 Plate column design using Hysys simulation and spreadsheet calculations) 7.5% 5. Final examination ( 2 hours, all topics in the course are included, open-book examination) 60% Prescribed text book Sinnott, R. K. and Towler, G., Chemical Engineering Design, 2009, Butterworth- Heinemann. Copies available in RMIT Bookshop Required definitely for the open-book final examination Useful for your future courses and career as a design reference book Other useful references: 1. Brennan, D., (1998), Process Industry Economics - An international perspective, IChemE. 2. Turton, R., Bailie, R.C., Whiting, W.B. and Shaeiwitz, J .A., Analysis , Synthesis, and Design of Chemical Processes, 2009, Prentice Hall. N.J ., U.S.A. 3. Peters, M.S., Timmerhaus, K.D., and West, R.E., (2003), Plant Design and Economics for Chemical Engineers, McGraw Hill. Process Plant Economics (Weeks 1 to 3) Topics to be covered: 1) Fixed capital estimation- (Week 1) 2) Time value of money- (Week 1) 3) Operating cost and working capital estimation- (Week 2) 4) Depreciation - (Week 2) 5) Cash flow analysis - (Week 3) Estimation of fixed capital cost Source: The Australian, Dec 2011 Capital investment in process industries is required for new projects sustaining existing plants during their operating life modifying an existing plant to accommodate changes in feedstocks, product quality, specifications, available technology and operating cost structure Purposes of detailed capital cost estimate to decide whether or not to proceed with a new plant or plant modification to support the allocation of funds to an approved project and then to control their subsequent disbursement Sources of capital Equity funds - Funds owned by the company derived from shareholders or retained earnings Loan funds - Funds borrowed from financial institutions such as banks and insurance companies Whatever be the source of capital, these funds have a cost (such as interest) which is known as cost of capital . Capital requirements for process plants Land costs Fixed and capital investment into plant and buildings Start-up capital Working capital Total investment = Land cost + Fixed capital + Start-up capital + Working capital Land costs Depends on whether the land is an existing site or a new site For existing site, no cash flow For a new site, land cost is a function of size and location New sites are also termed as greenfield sites Existing sites are known as brownfield sites Land cost is usually negligible when compared with fixed capital costs of plant and buildings Fixed Capital Total cost of the plant before start-up Cost paid to the contractors Unrecoverable Fixed capital investment is estimated for 1. Battery limits 2. Offsites Battery Limits: Geographical boundary, real or imaginary, around the processing plant which converts raw material into finished products Inside battery limits (IBL) - processing plant Outside battery limits (OBL) - also known as offsites, includes storage, utilities, effluent treatment facilities, service facilities IBL and OBL Ref: Wilson, B. (2008),Detail Engineering and Lay-out of Piping Systems, 1 st edition Inside battery limits Outside battery limits or offsites Start-up capital Includes all nonrecurring costs between the completion of plant and commencement Within 1% to 10% of fixed capital Higher costs, if technology is new Working capital Additional investment needed over and above the fixed capital Capital required to start the plant and operate it until income is earned IBL Plant Cost Estimate Types and classification of capital cost estimates 1. Order of magnitude estimate 2. Study estimate 3. Preliminary estimate 4. Definitive estimate 5. Detailed estimate Classification of capital cost estimates Nomenclature Probable range of accuracy Cost as % of project expenditure Detailed estimate 2 to 5% 5 to 10% Definitive estimate 5 to 15% 1 to 3% Preliminary estimate 10 to 25% 0.4 to 0.8% Study estimate 20 to 30% 0.1 to 0.2% Order of magnitude estimate 30 to 50% 0 to 0.1% What you do in your University courses Capital cost estimating methods 1. Using historical costs (order-of -magnitude estimate or exponential method) Involves extrapolation from known plant cost data and has a potential accuracy of 30 to 50% 2. Factorial method (study estimate) Involves applying factors to PEC (Purchased Equipment Cost) Accuracy 20 to 30% - Bare module factor method Capital cost estimation using historical costs (Order-of-magnitude estimate) Performed at the preliminary stage No flowsheet is required Exponential method (Capital cost estimation by extrapolation from known plant cost data) Order-of-magnitude estimate, approximate and applicable over a limited range where I P = investment for a proposed plant I R = investment for a reference plant Q P , Q R = capacities of proposed and reference plants, respectively b = exponent, usually 0.5 to 0.6 F p , F R = cost inflation index values for the proposed and reference years, respectively L = Location factor I I = Q Q F F L P R P R b P R
Cost indices (or) Inflation indices (F
p and F R ) Published in the journal Chemical Engineering Published by McGraw-Hill www.che.com Chemical Engineering Plant Cost Index (CEPCI): Weighs numerous components of plant, equipment and constructions costs Includes engineering costs as well as those for materials, manufacturing and installation There are two chemical engineering indices i) plant ii) purchased equipment CEPCI can be found Using RMIT libraraydatabase Proquest (choosing Proquest science journals) Using Google search bythe key word Chemical Engineering Plant Cost Index Chemical Engineering Plant Cost Index (CEPCI) Ref: Chemical Engineering, J anuary, 2012 Ref: Chemical Engineering, J anuary 2012 Marshall & Swift cost index values are another popular cost indices used widely in the US Influence of location on capital cost estimate L = location factor Note that both costs are expressed in the same currency L values vary from 0.8 to 1.8 L values vary with time country reference in plant of Cost country proposed in plant of Cost L = Location factors Sinnott, R.K. and Towler, G., (2012), Chemical Engineering Design, Page 338 Tutorial question on Fixed capital cost estimation using exponential method Bare module cost method (Reference: Turton, R., Bailie, R.C., Whiting, W.B. and Shaeiwitz, J .A., Analysis , Synthesis, and Design of Chemical Processes, 2009, Prentice Hall. N.J ., U.S.A.) Bare module cost = direct costs + indirect costs involved in purchasing and installing equipment (or) Bare module cost = Purchased equipment cost + installation cost Base conditions for bare module cost for equipment: 1. Unit is fabricated fromcarbon steel 2. Unit is operated at near ambient pressure (i.e., P =1 bar) Bare module cost method Bare module cost (installed cost) for each piece of equipment C BM : C BM = C p o F BM where C BM = Bare module equipment cost (= direct + indirect costs) C P o = Purchased cost for base conditions F BM = Bare module cost factor (= multiplication factor to account for the installation etc. (or) installation cost) Total module cost C TM (or ) Fixed capital cost C 18 . 1 C 1 i BM, TM
= = n i where n = total number of process equipment C TM includes 15% contingency and 3% contractors fee Grass roots cost C GR C 35 . 0 C C 1 i BM, TM GR
+ = = n i C GR is for greenfield project It includes costs for land, site development, auxiliary buildings, and off-sites and utilities Example: Estimate the bare module cost for a heat exchanger with the following specifications: - Horizontal shell and tube heat exchanger - Area = 20 m 2 - Design pressure < 10 bar - Carbon steel - Two-pass, internally bolted, floating head Solution: C BM = C o P F BM = C o P (B 1 + B 2 F M F p ) where F M = material factor F p = pressure factor B 1 and B 2 = constants Estimation of purchase cost (C p ) for heat exchangers These graphs give purchase cost based on heat exchanger surface area But they are for carbon steel heat exchangers operating at 1 bar Determination of installation factor C BM Material factor, F M Material factor F M Pressure factor F p where P = pressure, barg C 1 , C 2 , and C 3 = constants. Feed preheater Area =20 m 2 P =10 bar MOC =Carbon Steel Floating head type Bare module factor method Tutorial question Tutorial question on Fixed capital cost estimation using exponential method