0 evaluări0% au considerat acest document util (0 voturi)
293 vizualizări24 pagini
This document provides an agenda and summary of a presentation on FPSO projects challenges and lessons learned from the Dalia FPSO project in Angola. The presentation discusses the major challenges of FPSO projects including engineering interfaces between different contractors, meeting a fast track schedule for long lead items, and ensuring safety and weight requirements are met. It provides examples of both areas of improvement and success on the Dalia project, such as establishing common engineering standards between contractors and dedicating resources to weight control. The conclusion emphasizes continued focus on contractor coordination, early engineering anticipation of issues, and multi-center project communication.
This document provides an agenda and summary of a presentation on FPSO projects challenges and lessons learned from the Dalia FPSO project in Angola. The presentation discusses the major challenges of FPSO projects including engineering interfaces between different contractors, meeting a fast track schedule for long lead items, and ensuring safety and weight requirements are met. It provides examples of both areas of improvement and success on the Dalia project, such as establishing common engineering standards between contractors and dedicating resources to weight control. The conclusion emphasizes continued focus on contractor coordination, early engineering anticipation of issues, and multi-center project communication.
This document provides an agenda and summary of a presentation on FPSO projects challenges and lessons learned from the Dalia FPSO project in Angola. The presentation discusses the major challenges of FPSO projects including engineering interfaces between different contractors, meeting a fast track schedule for long lead items, and ensuring safety and weight requirements are met. It provides examples of both areas of improvement and success on the Dalia project, such as establishing common engineering standards between contractors and dedicating resources to weight control. The conclusion emphasizes continued focus on contractor coordination, early engineering anticipation of issues, and multi-center project communication.
November 8 t h , 2006 Franck Rogez 2 AGENDA 1. I nt r oduc t i on 2. FPSO pr oj ec t s c hal l enges 3. DALI A FPSO Feed bac k - Ar eas of i mpr ovement - Ar eas of suc c ess 4. Conc l usi on 3 1 - I nt r oduc t i on 4 Tec hni p i n a snapshot A leading provider of engineering, technologies and construction services for the oil & gas, petrochemical and other industries Listed on Euronext Paris and NYSE Share of 2005 Revenues OFFSHORE FACILITIES Shallow water facilities Deepwater platforms (Spar, FPSO, semi) INDUSTRIES Life science / Chemicals Metal & Mining Power Plant / Infrastructures OFFSHORE SURF Subsea: umbilicals risers flowlines ONSHORE DOWNSTREAM Refining / Hydrogen Petrochemicals Gas, LNG, GTL Onshore Pipelines 5 % 5 % 19 % 19 % 43 % 43 % 33 % 33 % 5 A w or l dw i de pr esenc e 6 DALI A FPSO Mai n par amet er s Water depth: 1,400 m Prod. capacity: 240,000 bpd Gas production: 280 MMSCFD Water injection: 405 000 bpd Storage capacity: 2 MMb Dimensions: 300mx59mx32m Modules: 12+2+1 Topsides dry wt 28,000 t Dalia FPSO Dalia Angola Cont r ac t det ai l s Client: TOTAL Contractor: DMP consortium (TSS JV, Daewoo,Samsung) Contract Value: about 800 MMUS$ Schedule: 40 months 7 2 FPSO pr oj ec t s c hal l enges 8 How t o per f or m f r om a basi c engi neer i ng 9 t he det ai l ed desi gn and pr oc ur ement 10 t o del i ver a FPSO on t i me ?? Tow out 34 mont hs af t er c ont r ac t aw ar d as pl anned 11 FPSO c hal l enges FPSOs are offshore mega-projects Large team to be managed Construction requires world class yards Engineering shall fit with an efficient construction (constructability) Endorsment of FEED is critical Very short review period at bid stage for a large installation with many interfaces FEED contractor are generally not EPC contractor : no smooth transfer Endorsement includes usually numerous bid bulletins ( FEED concurrent to bid phase) Numerous interfaces between hull, risers and topsides Different contractual entities Different priorities The managing entity (usually topsides Contractor) has no contractual relationship with the two others Long Lead Items equipment Fast track schedule for major equipment Early start of LLI requires an early mobilisation of the contractor Safety and environment design constraints to be right the first time Safety studies are long lead studies compared to the engineering schedule Noise studies are based on vendor data arriving late in the execution Late impact on IFC design to be avoided Weight control is always of essence Modules weight not to exceed lifting capacity Weight increase and COG elevation could affect FPSO stability 12 3 - DALI A FPSO Feed bac k - Ar eas of i mpr ovement - Ar eas of suc c ess 13 FPSOs ar e of f shor e mega-pr oj ec t s Large team to be managed Task force organisation High value engineering centers involved to cope with large mobilisation request Quick mobilisation needed in Paris Multi cultural team requires mutual understanding Reliable communication systems settled at early stage and spread on all sites One management system, one 3D model for two centers Construction requires world class yards Korean partners are leaders on New built Specific training sessions organized (how to work with Koreans) Lack of understanding of the blockfabrication (production line approach) Engineering shall fit with an efficient construction (constructability) Early mobilisation in Paris of Daewoo and Samsung rep. Achieved Standards applied are yard ones, whichever fits the best to both Poor input from Yard rep. during design reviews in Paris, good input at yard with people in charge of integration Late design of pipe supports incompatible with yards execution plan MTOs definition and early bulk procurement incompatible with yards culture 14 15 Numer ous i nt er f ac es bet w een hul l -H, r i ser s-U, SPS-S and t opsi des-T Different contractual entities Contracting strategy, reducing the number of contract concentrates the risks. One common entity for all contracts : the Client. Involved in the resolution of limits of scope Different priorities H wants the modules loads when T is optimising them H wants riser loads when U is focusing on flowlines installation program Each one focus on its own scope But alternative solution has been used to compromise between late engineering information and construction schedule (pipe supports avoiding hull roof, glueing procedure,) The managing entity (usually topsides Contractor) has no contractual relationship with the other ones Interface matrix settled at Contract stage Vendor Documents dataBase (VDB) has been applied to Interface document management to be customized and improved. Interface documents dispatch settled quickly 16 Numer ous i nt er f ac es bet w een hul l -H, r i ser s-U, SPS-S and t opsi des-T 17 Long Lead I t ems equi pment Fast track schedule for major equipment LLI strong and dedicated management follow-up One project engineer mobilized on the crude oil separation when problems occured Monitoring of progress with permanent inspector in major LLI plant: slippage can be accepted but delivery after ROS date not permitted Early start of LLI impose a corresponding early contractor mobilisation VDB System quickly in operation Requisition engineers, inspection coordinators early mobilisation Other disciplines not sufficiently mobilized to cover vendor input review Major Vendors are organized in a multi-center way. Slow reactivity and comments late or unclear are time-consuming 18 NUOVO-PIGNONE TURBO-GENERATEUR NUOVO PIGNONE MOTO-COMPRESSEUR Long Lead I t ems equi pment 19 Saf et y and envi r onment desi gn c onst r ai nt s t o be r i ght t he f i r st t i me Safety studies are long lead studies compared to the engineering schedule Anticipation required, define assumptions and validate them a posteriori Involvement of blast expertise early in the project Lengthy discussion with client on hypothesis selection Noise studies are based on vendor data arriving late in the execution Vendor inquiries with specific strategy on noise ( low noise value requested as an option with commercial impact quantified for management decision) Issue of piping design guidelines versus noise aspects Late impact on IFC design to be avoided Iterations avoided on Dalia Many calculations performed at the end of engineering to validate the IFC design were not anticipated Conventional design tools not adequate to treat dynamic problem (CAESAR for piping stress) 20 Wei ght c ont r ol i s al w ays of essenc e Modules weight not to exceed lifting capacity Dedicated weight control engineer mobilized early in the project Focus of the project management and participation in weight optimisation Powerful in-house weight control tool interface with Equipment List database and 3D model/MMS Weight increase and COG elevation could affect FPSO stability Design of hull and design of topsides are concurrent: reserve of stability carefully monitored and remedial actions launched Realistic contingencies and validated layout at proposal stage are keys of success for execution. 21 Wei ght c ont r ol i s al w ays of essenc e Tot al Topsi des Dry Wei ght Excl udi ng Fut ure (Phase 3) 29 816 28 630 28 590 28 127 27 409 27 502 27 408 27 493 27 618 27 180 27 285 27 373 27 475 27 469 29 442 29 577 30 323 30 711 30 917 31 237 31 405 30 845 29 790 29 671 29 411 29 327 26 000 27 000 28 000 29 000 30 000 31 000 32 000 Rev A Rev B Rev C Rev D Rev E Rev F Rev G Rev H Rev J Rev K Rev M Rev N Rev P Rev ision T o n n e s Nett Wt Gross Wt Original Design 22 4 - Conc l usi on 23 Conc l usi ons interfaces H, U, T, S Interface managers should work as a team Dedicated communication system between interface managers Incentive on milestones achieved shared between contractors ? FEED Endorsement Endorsement after contract award by project mobilized personnel Bad surprise or excessive contingencies to be avoided Anticipation Engineering iterations not permitted Sponsoring of expert at the beginning of the project Deterministic approach could increase the price but reduce risks ? Additional and dedicated mobilisation to focus on a raising problem Multi-centres projects Learn from and understand each others Good communication systems does not mean good communication Training/information sessions to be organised Weight control Good start at proposal stage by a realistic weight and layout Weight Statistics/information to be shared among basic engineering and EPC contractors ? 24 Thank You f or Your At t ent i on