Sunteți pe pagina 1din 9

CONTROLLING TEMPERATURES IN MASS CONCRETE

Saeed Ahmad*, University Engineering & Technology Taxila, Pakistan


Safdar Iqbal, University Engineering & Technology Taxila, Pakistan
Imran A Bukhari, University Engineering & Technology Taxila, Pakistan
34th Conference on OUR WORLD IN CONCRETE & STRUCTURES: 16 - 18 August 2009, Singapore

Article Online Id: 100034005

The online version of this article can be found at:


http://cipremier.com/100034005

Thisarticleisbroughttoyouwiththesupportof
SingaporeConcreteInstitute
www.scinst.org.sg

AllRightsreservedforCIPremierPTELTD
YouarenotAllowedtoredistributeorresalethearticleinanyformatwithoutwrittenapprovalof
CIPremierPTELTD
VisitOurWebsiteformoreinformation
www.cipremier.com

34th Conference on OUR WORLD IN CONCRETE & STRUCTURES: 16 18 August 2009, Singapore

CONTROLLING TEMPERATURES IN MASS CONCRETE


Saeed Ahmad*, University Engineering & Technology Taxila, Pakistan
Safdar Iqbal, University Engineering & Technology Taxila, Pakistan
Imran A Bukhari, University Engineering & Technology Taxila, Pakistan

Abstract
Concrete generates heat as the cementitious material hydrate and for thin sections, heat dissipates
almost as quickly as is generated. In case of massive structures, temperature increases due to
generation of more heat of hydration therefore management of concrete temperatures is necessary
to prevent damages, minimize delays and meet specifications.
This study was carried out at Dubai International Airport(DIA) project during expansion
phase2. During the study different Trial Mixes were used and their suitability was ascertained
through temperature monitoring data. Three Trial Mixes of ratio 1 : 1.40 : 2.86 were made with
constant workability and varied percentage of Cement and GGBFS as follows:
One Heat Block Cube of plain concrete (3x3x3 m) and one Scaled Model of dimensions
3x3x2.8 m, having actual Rebar of Raft were made for each trial Mix. Temperature monitoring was
carried out for both blocks. In addition, some more experimental work was carried out to study the
effects of cement and slag combinations on temperature as well as on strength. This work was
studied under two cases:
Case-1: Effect of increasing the quantity of cementitious contents (cement and slag) on temperature
and strength of mass concrete.
Case-2: Effect of GGBFS on temperature and strength of mass concrete.
Results indicated that increasing the quantity of cementitious contents results in increase of
the concrete temperature as well as strength. It was also concluded that GGBFS is a useful material
to control the temperature in mass concrete although it reduces the 28 days cylinders strength of
concrete.
INTRODUCTION
Mass concrete is extensively being used in the construction industry all over the world. A lot of research
work has been done on behavior of mass concrete all over the world however there is still a need of
further evaluation especially in hot climates. According to ACI 116R,1 any volume of concrete with
dimensions large enough to require that measures be taken to cope with generation of heat from
hydration of the cement and attendant volume changes, to minimize cracking is categorized as mass
concrete. Traditionally mass concrete has been associated with dams and other extremely large
placements but this is no longer the case. Use of concrete with high cement contents for durability and
rapid strength gain demands to treat increasing number of placements as a Mass Concrete.
A successful completion of mass concrete pour demands special attention to the logistical and
technical considerations like Concrete supply, Casting sequence, Cold joints, Plastic settlement and Heat
of Hydration. One of the major benefits of mass concreting is cost effective as it reduces stop ends and
speed up construction. Moreover the elimination of potential cracks at construction joints results in a
monolithic unit. Continuous casting also takes advantage of the ability of ready-mixed concrete
companies to supply concrete at high delivery rates.
All concretes generate heat as the cementitious materials hydrate and an exothermic reaction
occurs. Most of this heat generation occurs in the first few days after placement. For thin items such as

as pavements, thin slabs and walls, heat dissipates almost as quickly as it is generated. However for
thicker concrete sections (mass concrete), heat dissipates more slowly than it is generated and the
temperature of the mass concrete increases.
Significant Tensile stresses in mass concrete are developed from volume changes associated
with Heat of Hydration. If proper measures are not taken, cracking due to thermal behavior may occur
in mass concrete which may cause:
1. Loss of structural integrity and monolithic action,
2. Excessive seepage
3. Shortening of the service life of the structure,
4. Esthetically objectionable
5. Worst effect can occur in Dams and other Hydraulic Structures where cracks are more
objectionable.
There are various factors which effect Heat of Hydration like cement content, cement type, size of
concrete pour, type of formwork, concrete temperature, thermal coefficeient of aggregates and
ambient temperature. Generally higher the cement content, the more will be heat of hydration. To
predict concrete temperature, a simplest method (described in a PCA document.3) can be used
according to which every 45 kg of cement increase the temperature of concrete 70 C. Using this
method, the maximum concrete temperature of a concrete element that contains 365 kg/m3 of
concrete (as in case of Raft at a Case Study project) and is cast at 300C, is approximately 860C which
is above the safe limit (650C). There are some other methods like Fitz Gibbon method, Schmidts
method etc and software has also been developed for more accuracy and precision which can be
used for 1, 2, and 3 dimensional analyses to predict maximum concrete temperatures and
temperature differences. Similarly there are various methods of controlling temperatures in mass
concrete like use of low-heat Materials (replacement of cement with Pozzolanic Materials or Slag),
pre-cooling of concrete ingredients, cooling arrangements during pouring, post-cooling of concrete,
concrete surface insulation and using aggregates with low thermal expansion-e.g Limestone.
This research work was carried out to evaluate the behavior of mass concrete with respect to
temperature effects and as a case study, Phase II of Dubai International Airport was selected.
Overview of Dubai International Airport Expansion project- Phase II:The major structural details
about the project are given in Table 1.
Terminal Building: The Terminal Building is a totally underground Structure comprising of 6 Levels,
and accommodates passengers processes, Air Line and governmental service offices, Food Courts,
Duty Free Areas and all special airport systems, baggage handling systems (BHS), flight/baggage
information display (FIDS/BIDS). The Roof of the Terminal Building forms a part of the air side Apron.
The Terminal Building is connected to the public Levels of Concourse 2. It is also connected to
Concourse 3 building via an Automated People Mover (APM).
Car Park: The Car Park is totally underground Structure on 3 Levels and connected to Terminal 3
Arrival and Departure levels . Capacity is about 3000 cars. The LRT related facilities are located
above the Car Park. This consists of two elliptical structures. The one closer to the Terminal is the
Ticketing Hall and the other is the actual station / platform.
CONCOURSE 2: The Concourse 2, which is directly linked to Terminal 3, is dedicated to the Emirates
Airlines passengers. (26 contact gates of which five for A380 aircraft stands). This Concourse
accommodates ground operation and immigration services, Gates /Holding Lounges, Duty Free Area
and electromechanical equipments. The Hotel levels are also situated in C2. These consist of 5-star
(46 keys) and 4-star (207 keys) rooms along with a business centre and a health club.
CONCOURSE 3: Concourse 3 (C3) is an extension and continued development of Concourses 1
(C1) and 2 (C2). C3 is partially an underground structure comprising the APM stations (both arriving
and departing) and extends above ground under a metal shell to accommodate 20 aircraft stands, out
of which 18 are for A-380. Similar to C2, the lower and upper levels of C3 are connected by means of
a special vertical transportation system (sky train) that acts as a focal point feature in a central atrium.
EXPERIMENTAL PROGRAM
Three trial mixes of concrete were prepared with varying ratios of cement and GGBS to study various
properties. Following requirements for mass concrete were specified:
1. Use of OPC Type-1 with max heat of Hydration 325 Kj/kg, when tested as per ASTM C186.
2. Use of Ground Granular Blast Furnace Slag(GGBS) which complies with ASTM C989,Grade
100 or 120.
3. Max size of coarse aggregates was 20 mm

4. Water Cement ratio of 0.4


5. High Range water-Reducing Admixture (Super plasticizer) complying with ASTM C494
To be in line with the specification for massive cast in place concrete at Dubai International Airport,
following design criteria for the temperature control was established.
1. Concrete Temperature at time of placement should be maintained below 300 C.
2. Concrete Temperature at core of the structural elements shall not exceed 650 C.
3. Temperature Differential within the concrete body shall not exceed 250 C.
Tests were carried out on different materials to confirm their compliance with the specified
requirements for Trial Mix Design. For the temperature monitoring, three Heat Blocks of 3m*3m*3 m
each was casted. In addition, Casting of prototype section of raft 3m*3m*2.8 m with actual
reinforcement was also done for each of the concrete trial mix. Two probes were installed at center of
the mass concrete i.e. Center Middle-1 and Center Middle -2 positions to find the accurate value of
core temperature and temperature was noted using a data logger as shown in Figure 1.
In addition to the trial mixes, 4xconcrete blocks with 500mmx500mmx500mm were cast at
Dubai International Airport Site Concourse 3. Each block was cast using different concrete mix
designs. Due to smaller size of the block, only one transducer/ probe was placed at the center of the
block and activated just after the completion of pouring of each block. Temperature monitoring was
recorded for minimum fourteen days of each block.
RESULTS AND DISCUSSION
Results of Trial Mix-1 indicate that both probes at central location have very consistent results, with a
core temperature of 67 degree Celsius while specification allow only 65 degree Celsius. A steep rise
observed (especially in core temperature) during the first three days after concrete pouring. Trial mix
was rejected due to high core temperature and ingredients of mix were revised. The details are given
in Table 2 and temperature monitoring data for the heat block and prototype raft are given in Figures
2 and 3 respectively.
Results of Trial Mix-2 show that both probes at central location have very consistent results,
with a core temperature of 63 degree Celsius which is in acceptable limits. Again a steep rise was
observed during the first three days after concrete pouring. However, concrete temperature at poring
time, always kept less than 30 degree Celsius which is as per the specification requirement. Although
core temperature noted (63 degree) is meeting the specified requirement which is 65 degree
maximum, however keeping in view the worst weather conditions in Gulf region, high importance of
the project ie Dubai International Air port Airport Project and expected improper handling of concrete
at site, it was decided that Peak temperature to be further reduced. Since cement contents were
already reduced to 30% , another suitable option was selected for the next Trial and that was use of
slag (GGBFS) with Reducing Blaine (fineness). The details are given in Table 2 and temperature
monitoring data for the heat block and prototype raft are given in Figures 4 and 5 respectively.
In Trial Mix-3, again only two probed were installed at center of the mass concrete i.e. Center
Middle-1 and Center Middle-2 positions to find the accurate value of core temperature with higher
degree of certainty. Probes at other points were not installed to save time and cost. Results indicate
that both probes at central location have very consistent results, with a core temperature of 60 degree
Celsius which is within safe acceptable limits. As the Trial Mix no-3 meets the core temperature
requirement it was decided that this mix design should be further studied in actual site condition.
Hence first Raft with actual size (28m*28m*2.80 m) was poured with Mix Design no-3 and results
were recorded. The details are given in Table 2 and temperature monitoring data for the heat block
and prototype raft are given in Figures 6 and 7 respectively.
Eight probes were installed to monitor the temperature in the massive structure of an actual size
raft. The core temperature peak was observed 58 degree Celsius (Well below specified limit of 65
degree Celsius) as recorded by probes (Center Middle -1 & 2). Core temperature reached at its peak,
about 68 hours after completion of casting of Raft and remained at peak around 62 hours (until 5.5
days from completion of casting). Temperature within the mass of raft (excluding reading of corner top
and corner bottom) remained within the specified limit of 25 degree Celsius. Core to surface
temperature differentials average was less than 10 degree Celsius for the first four days and then
gradually increased. A max differential of 21 degree was recorded at approx 08 days after casting.
The temperature differentials between the mass of raft and extreme outer corners peaked at 31
degree. However this was not replicated within the body of raft or between core and surfaces and no
detrimental effects (e.g. cracking) were observed on removal of insulation. The Temperature
Monitoring Data of the raft is shown in Figure 8.

Four concrete blocks (500mmx500mmx500mm) of different concrete mix designated as Mix


Design A, B, C and D were cast and temperature was monitored using one transducer/ probe placed
at the center of each block for minimum fourteen days. Cement content of the concrete mixes was
kept 115, 122,125 and 390 kg/m3. GGBS was also used in varying quantities in three concrete mixes
A,B and C whereas it was not used in mix D. The details of the mix designs are given in Table 3.
The compressive strength of the mix D (with no cement replacement) was found higher than
the other mix designs as shown in Figure 9. Increase in the peak temperature was also observed with
the increase in quantities of cementitious materials as shown in Figure 10.
1.
2.
3.
4.
5.
6.
7.

[1]
[2]
[3]
[4]
[5]
[6]
[7]
[8]
[9]
[10]
[11]

CONCLUSIONS
Replacement of cement with GGBFS is an effective remedial measure to control the HOH in
mass concrete at design stage and upto 70% replacement of cement can be made.
Rate of exothermic reaction in mass concrete can be controlled by using GGBFS with reduced
Blaine(fineness)
For temperature monitoring in mass concrete, center point was found critical and gives maximum
temperature.
Peak temperature in mass concrete can be achieved in first 3 to 4 days of pouring of concrete.
Increasing the cementitious material results in increased peak temperature and compressive
strength.
GGBFS slows down the strength gaining process of concrete.
Test results indicate that mix design no-3 fulfils the specified requirements and hence
recommended for Mass Concrete in raft for any project especially in Gulf region where weather
conditions are very hot and humid.
REFERENCES
ACI Committee 116, Cement and Concrete Terminology (ACI 116R-00).
ACI Committee 207, Mass Concrete (ACI 207.1R-96).
ACI Committee 207, Effect of Restraint, Volume Change and Reinforcement on Cracking of
Mass Concrete (ACI 207.2R-95).
Portland Cement Association, Design and Control of Concrete Mixtures 13th Edition, Stokie,
III., 1988, pp212.
The CIRIA Guide to concrete construction in the Gulf Region, Special Publication 31.
Springenschmd, R.editor, Prevention of thermal cracking in concrete at early ages London:
Spon, 1988(RILEM Report 15).
ACI 207.4R-93, Cooling and insulating systems for mass concrete Farmington Hills,
Michigan: American Concrete Institute, 1998, p207.4R-7.
Campbell-Allen, D and Thorne, C.P The thermal conductivity of concrete, Magazine of
Concrete Research, vol.15, No.43. March1963,pp 39-48.
Gibbon, G.J and Ballim,Y. Laboratory test procedures to predict the thermal behavior of
concrete Journal of SAICE, Vol 38, No 3,1996, pp21-23.
Koenders, E.A.B. and Van Breugel, K. Numerical and experimental adiabatic hydration cure
determination, Proceedings of the International RILEM Symposium: Thermal Cracking in
Concrete at early ages, Munich, 1994, pp 3-10.
Taylor, H.F.W Cement Chemistry, 2nd Edition, London: Thomas Telford, 1997, pp212.

KEY ELEMENTS
Piles

C2-T3 & CP

C3

8700 Nos.

4560 Nos.

10 million m

4 million m3

57,600 m2

35,000 m2

Concrete

2.4 million m3

1.2 million m3

Reinforcement

450,000 tons

220,000 tons

Structural Steel

29,000 tons

Approx. 16,000 tons

Excavation
Diaphragm Walls

Table 1: Major Civil Structural Statistics

Weight Kg/m3

Materials

Specified limits

Cement (Kg/m3)

ASTM C 150 -Type -1

GGBS Replacement (Kg/m3) ASTM C 989 -Grade 100/120

Trial Mix 1

Trial Mix 2 Trial Mix 3

135 (35%)

110 (30%) 110 (30 %)

245 (65%)

255 (70%) 255 (70%)

Blaine Fineness of GGBS

420

420

380

Total Cementations Content

Min = 350 kg/m3

380

365

365

Max Water Cement Ratio

Max 0.4

0.36

0.37

0.37

585

510

510

- 20 mm lime stone

690

690

690

- 10 mm lime stone

345

355

355

2.79

2.79

2.79

Admixture (Lit/m3)

Fiber reinforcement

0.6

0.6

0.6

Fine Aggregate:(kg/m3)
Course Agg :(kg/m3)

Specific Gravity

Min=2.6

Core Temperature

Max=65 C
Table 2: Trial Mix Designs for mass concrete

Figure 1: Thermocouple affixed to steel reinforcement


cen-top
cen-middle-2
cor-top
edge-top

Pour Temperature Profile


Heat Block-1 (Trial mix-1)

cen-middle-1
cen-bottom
cor-bottom
edge-middle

80
70

Temperature (C)

60
50
40
30
20
10
0
0

25

50

75

100

125

150

175

Time in Hours

200

225

250

275

300

Figure 2: Temperature Monitoring Data (Trial Mix 1- Heat Block)


cen-top
cen-m iddle-2
cor-top
edge-top

Pour Temperature Profile of


Prototype Raft (Trial mix-1)

cen-m iddle-1
cen-bottom
cor-bottom
edge-m iddle

80

70

60

Tem
perature(C)

50

40

30

20

10

0
0

25

50

75

100

125

150

175

200

225

250

275

300

Time in Hours

Figure 3: Temperature Monitoring Data (Trial Mix 1- Prototype raft)

70

cen-top
cen-bottom
edge-top

Pour Temperature Profile


Heat Block (Trial Mix-2)

cen-middle-1
cor-top
edge-middle

cen-middle-2
cor-bottom

60

Temperature (C)

50
40
30
20
10
0
0

25

50

75 100 125 150 175 200 225 250 275 300 325 350 375 400 425
Time in Hours

Figure 4: Temperature Monitoring Data (Trial Mix 2- Heat Block)


Pour Temperature Profile
Prototype Raft (Trial Mix-2)

cen-top
cen-middle-2
cor-top
edge-top

cen-middle-1
cen-bottom
cor-bottom
edge-middle

70
60

Temperature (C)

50
40
30
20
10
0
0

25

50

75

100 125 150 175 200 225 250 275 300 325 350 375 400 425
Time in Hours

Figure 5: Temperature Monitoring Data (Trial Mix 2- Prototype raft)


Pour Temperature Profile
Heat Block (Trial Mix-3)

cen-top
cen-middle-2
cor-top
edge-top

cen-middle-1
cen-bottom
cor-bottom
edge-middle

70
60

Temperature (C)

50
40
30
20
10
0
0

25

50

75 100 125 150 175 200 225 250 275 300 325 350 375 400 425
Time in Hours

Figure 6: Temperature Monitoring Data (Trial Mix 3- Heat Block)


cen-top
cen-middle-2
#REF!
cor-bottom
edge-middle

Pour Temperature Profile


Prototype Raft (Trial Mix-3)

cen-middle-1
cen-bottom
cor-top
edge-top

70

60

Temperature (C)

50

40

30

20

10

0
0

25

50

75

100 125 150 175 200 225 250 275 300 325 350 375 400 425

Time in Hours

Figure 7: Temperature Monitoring Data (Trial Mix 3- Prototype raft)


Pour Temperature Profile
Actual Raft -Trial Mix-3
cen-top
cen-middle-2
cor-top

cen-middle-1
cen-bottom
cor-bottom

70
60

Temperature (C)

50
40
30
20
10
0
0

25

50

75 100 125 150 175 200 225 250 275 300 325 350 375 400 425
Time in Hours

Figure 8: Temperature Monitoring Data (Trial Mix 3- Actual raft)


Mix Design-Weight Kg/m3

Specified
Materials

limits

A(Block 1)

B(Block 2)

C(Block 3) D(Block 4)

115

122

125

390

245

258

265

380

380

380

ASTM C 150
-Type -1

Cement (Kg/m3)

ASTM C 989
GGBS Replacement (Kg/m3)

-Grade 100

Blaine ( Fineness) of GGBS)


Total Cementitous Content kg/m3

Min = 350

360

380

390

390

Max Water Cement Ratio

Max 0.4

0.37

0.37

0.37

0.36

0-5mm crushed sand

744

662

655

675

Dune sand

227

198

195

202

Microsilica(Kg/m3)

12

12

- 20 mm lime stone

687

721

720

730

- 10 mm lime stone

318

329

325

333

Admixture Reobuild 858 (Lit/m3)

5.5

5.5

5.5

Fine Aggregate:(Kg/m3)

Course Aggregate:

Table 3: Mix Design

Figure 9: Compressive Strength gain


with time

Figure 10: Peak temperature and Cementatious


Material

S-ar putea să vă placă și