Documente Academic
Documente Profesional
Documente Cultură
Introduction
Magnitude of
Settlement
Exposed Pile
(b)
(a)
(b)
Foundation System =
9m length of 150mm x
150mm reinforced
concrete (RC) square
piles interconnected
with 350mm x 600mm
strips and 150mm thick
raft.
Page 2 of 7
Stiff layer
MALAYSIA
Site
SUMATRA
Page 3 of 7
A 120 ton per hour palm oil mill has been constructed over
the sand filled platform with an area of about 83,000m2 on
soft swampy ground. Figure 7 shows the location of the
proposed site, which is about 50km away from Sg.
Guntung of the Province of Riau, Sumatra, Indonesia
At the proposed site, there are seven numbers of heavy
steel tank structures for the storage of processing water
and processed palm oil. The site is underlain by recent
alluvium and coral reefs of Quaternary age. The original
and the surrounding ground conditions of the site are
generally flat with reduced level of RL+8.3m. The water
level is almost at the original ground surface.
Adopted
(a)
(b)
Figure 9. Comparison of
(a) Conventional Piled-to-Set Foundation
(b) Floating piled-raft foundation
The steel tanks are seated on 0.5m sand bed coated with
bitumen strips in order to have uniform seating between
the coned-down tank base and the reinforced concrete raft
of 500mm thick. Piled rafts with different pile lengths
have also been used as more cost effective foundation
replacing the conventional piles to set foundaion system as
the support for 2500Ton oil storage tanks on very soft and
compressible alluvial clayey soil of about 34m thick as
shown in Figure 9. The storage tanks sit on a 20m
diameter and 500mm thick reinforced concrete (RC)
circular raft. The pile points have been strategically
located beneath the RC raft. Varying pile penetration
lengths have been designed to minimize the angular
distortion of the thin RC raft and the out-of-plane
deflection at the tank edge. A total number of 137 of
350mm diameter hollow circular prestressed concrete (PC)
spun piles with concrete strength of 60MPa have been
designed and installed to support the tank through the RC
raft. (Liew, et al. 2002).
In order to monitor and validate the actual performance of
the piled raft during water-loading test, strain gauges and
horizontal inclinometer and settlement markers have been
installed in the piles and also the raft. Seven working piles
were instrumented with strain gauge at the pile top. Figure
10 shows the details of the piled raft for the instrumented
tank structures. These tanks have performed better than
our prediction in terms of total and differential measured
settlement.
Page 4 of 7
between
(a)
(b)
(a)
(b)
(a)
(c)
(b)
(d)
(e)
(f)
Fig 16. (a) Milling works up to 300mm deep in progress (b) After milling (c) Laying of
steel reinforcement (d) Concreting (e) Completed RC Raft (f) Pavement
completed, traffic re-opened.
In summary, results of FEM analyses have shown that the
mushroom problems arise due to the ineffective arching
mechanism influenced by the following factors:
a) Unsuitable fill materials
b) Large pile spacing to the height of fill
The occurrence of the mushroom problems has
necessitated regular repaving works to ensure the riding
comfort and safety of the highway. However, repaving
works are only a short-term solution as the embankment
continues to settle due to additional loads from the
pavement. Therefore, an effective remedial design for the
mushroom problems must satisfy the following criteria:
a)
Conclusion
Innovative designs are the outcomes of exploring various
options or alternatives to conventional solutions. The
various options need to be explored in terms of technical
suitability, cost, time and ease of construction or
installation as well as minimal long term maintenance.
These should not be compromised on the quality, safety
and good engineering practice. This tall order is possible
if we invest in giving your best resources where the value
engineering works are needed most. Commitment to in
house research and development is also a contributing
factor.
References
1. Gue, S. S., Tan, Y. C. Liew, S. S. (2002), Cost
Effective Solutions for Roads and Factories Over Soft
Marine Deposits, CAFEO2002, Cambodia, 2-5
September, 2002.
2. Liew, S. S., Gue, S.S. & Tan, Y.C. (2002), Design and
Instrumentation Results of A Reinforcement Concrete
Piled Raft Supporting 2500 Ton Oil Storage Tank On
Very Soft Alluvium Deposits, Ninth International
Conference on Piling and Deep Foundations, Nice, 3rd
5th June, 2002
3. Randolph, M.F. (1994) Design Methods for Piled
Rafts,: State-of-the Art Report, Proc. 13th Int. Conf.
Soil Mech. Found. Engng, New Delhi Vol. 4, pp 61-82.
4. Tan, Y.C. Gue, S.S., Ng, H.B. & Lee, P.T. (2004a),
Some Geotechnical Properties of Klang Clay, Proc.
of Malaysian Geotechnical Conference 2004, Selangor,
pp.179-186.
5. Tan, Y. C., Chow, C.M. & Gue, S.S.(2004b), A
Design Approach for Piled Raft with Short Friction
Piles for Low Rise Buildings on Very Soft Clay, 15th
SEAGC, Bangkok, Thailand.
6. Tan, Y.C., Chow, C.M. & Gue, S.S. (2005), Piled raft
with Different Pile Length for Medium-Rise Buildings
on Very Soft Clay, (to be published) Proc. 16th Int.
Conf. on Soil Mechanics & Geotechnical Engineering,
Osaka, Japan.
Page 7 of 7