Sunteți pe pagina 1din 21

Levelling

Principle
operation required in the determination of
heights of points on the surface of the Earth

Elementary Land Surveying

ELS_Levelling05_06: 1

Equipment
1. Level with tripod (device
to gives a truly
horizontal line)
2. Levelling staff (a suitably
graduated staff for
reading vertical heights)
3. Chain/Tape (to enable
the points leveled to be
located relative to each
other on a map)
4. Change plate (staff base
plate)
5. Staff bubble
Elementary Land Surveying

ELS_Levelling05_06: 2

Elements of Surveyors Level


1. Telescope
 Diaphragm plane glass on
which a series of line is
etched (cross-hairs)
 Parallax in focusing the real
image formed by the
objective lens is made to lie in
the same plane as diaphragm
Procedure of focusing:
a) Adjusting eyepiece to bring
diaphragm into sharp focus
b) Adjust focusing screw until no
parallax

Elementary Land Surveying

ELS_Levelling05_06: 3

Elements of Surveyors Level


2. Compensating Device in
Automatic Level
 The telescope need only
be approximately
levelled and then a
compensating device
corrects for the residual
mislevelment

Elementary Land Surveying

ELS_Levelling05_06: 4

Levelling Staff
1. Sectional and assembled
by slotting onto one
another vertically
2. Made of aluminium alloy
3. E-shaped graduation
(reading to 1mm for
ordinary levelling)

Elementary Land Surveying

ELS_Levelling05_06: 5

Precision Levelling Staff


1. Used for more
accurate work
(accuracy to 0.1mm in
use with precise level)
2. Spring-mounted at the
top
3. Made of invar alloy
(iron + nickel) which
has a lower coefficient
of expansion
unaffected by
temperature effects

Elementary Land Surveying

ELS_Levelling05_06: 6

Levelling Terminology
1. Level line is a surface
which is at a constant
height relative to Mean
Sea Level (MSL) and is a
curved line
2. Horizontal line is
tangential to the level
line at any particular
point and is
perpendicular to the
direction of gravity.
Over short distance, the 2
lines are taken to
coincide

Elementary Land Surveying

ELS_Levelling05_06: 7

Levelling Terminology (cont)


3. Datum
 A level line is chosen in which the elevation of
all points is referred
a) Mean Sea Level (MSL) is the mean of tidal
height over a period of time (> 19 years)
b) Principal Datum Hong Kong (PDHK) most of
the works in HK refer to this. It is 1.230m
below MSL (revised in June 1984)
c) Chart Datum (CD) is a tidal datum for marine
works and navigation

Elementary Land Surveying

ELS_Levelling05_06: 8

Relationship among different datums


(Source: Lands Department, No Date)

Elementary Land Surveying

ELS_Levelling05_06: 9

Levelling Terminology (cont)


4) Bench Marks
 Points of known
elevation above PDHK
a) Bench Mark (BM)
established on vertical
surfaces such as walls
of buildings or
substantial structures

Elementary Land Surveying

ELS_Levelling05_06: 10

Levelling Terminology (cont)


4. Bench Marks (cont)
b) Temporary Bench Marks
(TBM) constructed at
locations on site or off
site, where the level of
the mark is calculated
from PDHK
5. Reduced Level (RL)
the height of a point
relative to PDHK
6. Height of Collimation is
the height of collimation
above PDHK

+5.00

TBM
+10.00

Elementary Land Surveying

ELS_Levelling05_06: 11

Levelling Terminology (cont)


7. Backsight (BS) 1st sight taken after the level has been set up. It is
also a sight taken to a point whose height above HKPD is known
8. Foresight (FS) last sight taken before moving the level. It is also a
sight taken to a point whose height is required to carry on the line
of levels
9. Intermediate Sight (IS) other staff readings taken between BS and
FS
10. Change Point (CP) the staff position at which a FS and then a BS
readings are taken

BS

FS

IS

CP
Elementary Land Surveying

ELS_Levelling05_06: 12

Levelling Terminology (cont)

FS
BS
FS
IS

IS

BS

Elementary Land Surveying

ELS_Levelling05_06: 13

Field Procedure

1. The level is set up at P where BM may be observed and


readings taken at points A, B, C and D
a) The 1st reading (BS) made with the staff on a point of known
RL
b) The staff is now held at points A, B and C (ISs) in turn, and
record the readings
c) A change point (CP) is chosen at D, owing to the nature of the
ground and take the reading (FS)
Elementary Land Surveying

ELS_Levelling05_06: 14

Field Procedure (cont)

2. The staff remains at point D. The level is moved to Q, set up and


levelled
a) Taking the reading on the staff at the change point D (BS)
b) Followed by IS with the staff on E, F and G until a further change
becomes necessary

3. This procedure is repeated until all the required levels have been
obtained
4. The final staff position is at a point of known RL
Elementary Land Surveying

ELS_Levelling05_06: 15

Procedure in Levelling

1. Height of Collimation Method


1st find the height of the line of collimation above the datum
Height of collimation (HC) = 128.480 + 3.222 = 131.702m PD
a) level at B (rise from A to B)
= height of collimation reading at B = 131.702 1.414
= 130.288m PD
b) level at B (rise from A to B)
= height of collimation reading at B = 131.702 3.484
= 128.218m PD
Elementary Land Surveying

ELS_Levelling05_06: 16

Procedure in Levelling

2. Rise and Fall Method


Rise 2nd reading < 1st reading
Fall - 2nd reading > 1st reading
b) from A to B
a) from A to B
1st reading 2nd reading
= 3.222 1.414 = 1.808 (rise)
level at B (rise from A to B)
= level at A + rise
= 128.480 + 1.808
= 130.288mPD

1st reading 2nd reading


= 3.222 3.484 = -0.262 (fall)
level at B (fall from A to B)
= level at A - fall
= 128.480 + 0.262
= 128.218mPD

Elementary Land Surveying

ELS_Levelling05_06: 17

Booking and Calculation


1) Rise and Fall Method each reading is entered on a different line in the
appropriate column, except at a change point, where a FS and BS occupy the
same line. To check, BS - FS = Rise - Fall = Last RL First RL

BS

IS

FS

Rise

Fall

RL

Remarks

98.760

BM

1.283

97.477

98.415

0.145

98.270

0.432

97.838

D (CP)

0.663
1.946
1.008

0.938

1.153
2.787

1.585
2.270

0.517

98.355

1.218

1.052

99.407

0.646

0.572

99.979

2.231

3.079

3.450

1.860

99.979

2.231

1.860

98.760

1.219

1.219

1.219

Elementary Land Surveying

ELS_Levelling05_06: 18

Booking and Calculation (cont)


2) Height of Collimation Method the collimation height is obtained by
adding the staff reading, which must be a BS, to the known RL of the point on
which the staff stands. To check, BS - FS = Last RL First RL
BS

IS

FS

Collimation

RL

Remarks

99.423

98.760

BM

1.946

97.477

1.008

98.415

1.153

98.270

97.838

D (CP)

98.355

0.663

2.787

1.585

100.625

2.270
1.218
3.450

99.407

0.646

99.979

2.231

99.979

2.231

98.760

1.219

1.219

Elementary Land Surveying

ELS_Levelling05_06: 19

Comparison
Rise and Fall Method
More accurate
More calculation
Intermediate RLs are known

Height of Collimation Method


Quicker
Good for a lot of ISs

Elementary Land Surveying

ELS_Levelling05_06: 20

10

Accuracy in Levelling
For normal engineering works and site surveys
Allowable misclosure = 5 n mm
where n = no. of instrument positions

OR
Allowable misclosure = 12 k mm
where k = length of levelling circuit in km

If actual misclosure > allowable misclosure,


levelling should be repeated
If actual misclosure < allowable misclosure,
misclosure should be equally distributed equally
between the instrument positions
Elementary Land Surveying

ELS_Levelling05_06: 21

Summary of Levelling Fieldwork


 For levelling fieldwork, the following practice should be
adhered to in order to improve the accuracy of the
levelling works.
1. Levelling should always start and finish at points of
known RL so that misclosure can be detected
2. Where possible, all sight lengths should be below 60 m
3. The staff must be held vertically by suitable use of a
bracket bubble
4. BS FS Lengths
5. Reading should be booked immediately after they
are observed. Important readings, particularly readings
at change points, should be checked
6. The rise and fall method of reduction should be used if
possible, especially for control works
Elementary Land Surveying

ELS_Levelling05_06: 22

11

Collimation Error
if level is set up, levelled and the line of sight or
collimation is not truly horizontal, it will sweep out a
cone as it is rotated.
this cone will be either above or below the horizontal
plane
Staff
Horizontal Line

Level

Line of Sight

Elementary Land Surveying

ELS_Levelling05_06: 23

Permanent Adjustment Two Peg Test


1. On fairly level ground, set 2 points A and B, a maximum of 60m
apart. Let this distance be L metres
2. Set up the level exactly midway between the points at point C and
level carefully
3. Place a levelling staff at each peg in turn and obtain readings S1
and S2

S1 S2 = (S1 + x ) (S2 + x) = S1 S2
= true difference on height between A and B
X is the error due to collimation error (inclination of the collimation line by
angle

Elementary Land Surveying

ELS_Levelling05_06: 24

12

Permanent Adjustment Two Peg Test


4. Move the level so that it is L/10 metres from point B at
D. Take readings S3 and S4
Apparent difference in height between A and B = S3 S4
If there is any difference between the apparent and true value,
e = (S1 S2) (S3 S4) m per L metres
(e should be less than 0.5mm per 10 m for average precision)

Elementary Land Surveying

ELS_Levelling05_06: 25

Permanent Adjustment Two Peg Test


5. Any error e of the level should be adjusted using the
adjusting screw with the collimation line altered to the
correct staff reading
For example, to adjust the level with instrument at D
and staff at A,
S4 = S4 e(L/10 + L) / L
6. The test should be repeated to ensure that the
adjustment has been successful

Elementary Land Surveying

ELS_Levelling05_06: 26

13

Two Peg Test - Example


 The reading obtained from a two-peg test
carried out on an automatic level with a single
levelling staff set up alternately at 2 pegs A and
B placed 60m apart are as follows:
1. With the level midway between A and B
Staff reading at A = 1.283m
Staff reading at B = 0.860m

2. With the level positioned 5 m from peg B on


the line produced from AB
Staff reading at A = 1.612m
Staff reading at B = 1.219m

Find the collimation error (e) and corrected


staff reading (S4)?
Elementary Land Surveying

ELS_Levelling05_06: 27

Errors in Levelling
 Errors in Equipment
1. Collimation Error

Keep sight distance roughly equal


Check by two peg test regularly

2. Parallax Error

Move eye with respect to eyepiece, see if any relative movement


between target & cross-hairs, if so adjust eyepiece

3. Defects of Staff

Zero error, check by tape, does not affect height difference if one
staff is used
3-section staff should be properly extended

4. Tripod

Robust, properly tightened


On soft ground, force it firmly into the ground

Elementary Land Surveying

ELS_Levelling05_06: 28

14

Errors in Levelling (cont)


 Field Errors
1. Staff not vertical

Staff is held vertical with aid of a bracket bubble

2. Unstable ground

A change plate should be used

3. Instrument not level

Ensure that the circular bubble is centered before and after a


reading is taken

4. Weather condition

Avoid windy condition


Avoid line of collimation close to the ground in hot weather

5. Checking

Start and finish at points of known height


Run a loop

Elementary Land Surveying

ELS_Levelling05_06: 29

Errors in Levelling (cont)


 Reading and Booking Errors
1. Misreading of the staff graduation

Keep sight distance < 60 m, otherwise it becomes


impossible to take accurate readings

2. Erroneous Booking

Carefully entered the reading into the fieldbook


always read the staff, book the observation and then
check that the recorded entry agrees with a second
reading through the telescope.

Elementary Land Surveying

ELS_Levelling05_06: 30

15

Error adjustments in levelling calculations

Elementary Land Surveying

ELS_Levelling05_06: 31

Error adjustments in levelling calculations


1. Rise and Fall Method
BS

IS

FS

Rise

Provisional
RL

Correction

Corrected
RL

Remarks

32.640

32.640

BM

32.893

0.003

32.896

CH0

0.318

32.575

0.003

32.578

CH20

Fall

1.944
1.691

0.253

2.009
0.367

2.114

4.425

0.833

31.742

0.003

31.745

CH40

1.223

2.842

0.856

30.886

0.005

30.891

CH60

1.347

0.124

30.762

0.005

30.767

CH80

0.775

0.572

31.334

0.005

31.339

CH100

0.816

1.298

32.632

0.008

32.640

BM

4.433

2.123

2.131

32.632

4.433

2.131

32.640

-0.008

-0.008

-0.008

Elementary Land Surveying

ELS_Levelling05_06: 32

16

Error adjustments in levelling calculations


2. Height of Collimation Method
BS

Collimation

Provisional RL

Correction

Corrected
RL

Remarks

34.584

32.640

32.640

BM

32.893

0.003

32.896

CH0

32.575

0.003

32.578

CH20

31.742

0.003

31.745

CH40

1.223

30.886

0.005

30.891

CH60

1.347

30.762

0.005

30.767

CH80

31.334

0.005

31.339

CH100

0.816

32.632

0.008

32.640

BM

4.433

32.632

IS

FS

1.944
1.691
2.009
0.367

2.842

2.114

4.425

0.775

32.109

33.448

4.433

32.640

-0.008

-0.008

Elementary Land Surveying

ELS_Levelling05_06: 33

Error adjustments in levelling calculations


Note:
Misclosures = -0.008m
No. of instrument station = 3
Correction is +0.0027m and is added to the RL found
from each instrument station
No adjustment is applied to the initial BM, since this
level cannot be altered.

Elementary Land Surveying

ELS_Levelling05_06: 34

17

Additional Levelling Methods


1. Inverted Staff
Used to determine the RL of
points, such as the soffit of a
bridge, underpass or canopy
The inverted staff reading is
booked with a negative sign
BS

IS

FS

Rise

Fall

1.750
-3.100

4.850

1.490

4.590

-4.210

-2.560
1.640

8.900

Remarks
BM

77.150

A) Frame (lift-shaft)

72.560

B) Floor Level

76.610

C) Canopy

8.410

68.200

D) Kerb

13.000

68.200

4.050

4.200
-2.460

RL
72.300

1.640

13.000

72.300

-4.100

-4.100

-4.100

Elementary Land Surveying

ELS_Levelling05_06: 35

Example
BS

IS

FS

1.432
-0.874

-1.235

Collimation

RL

31.432

30.000

TBM A

31.793

32.667

Top of wall

-1.107

0.558

32.900

Arch soffit

1.383

30.410

0.148

30.410

0.148

30.000

0.410
BS

Remarks

0.410
IS

FS

Rise

Fall

1.432
-0.874

-1.235
-1.107

2.667
0.233

1.383
0.558

0.148

2.900

RL

Remarks

30.000

TBM A

32.667

Top of wall

32.900

Arch soffit

2.490

30.410

2.490

30.410

0.148

2.490

30.000

0.410

0.410

0.410

Elementary Land Surveying

ELS_Levelling05_06: 36

18

Additional Levelling Methods


2. Reciprocal Levelling

By means of reciprocal levelling, the need for applying


curvature and refraction corrections may be avoided
2 similar instruments in correct adjustment are required
H = ((a1 b1) + (a2 b2)) / 2

Elementary Land Surveying

ELS_Levelling05_06: 37

Example
In levelling across a river, reciprocal levelling
observations gave the following results for staffs
held vertically at X and Y from level stations A
and B on each bank respectively:
Staff
Staff
Staff
Staff

reading
reading
reading
reading

of
of
of
of

X
X
Y
Y

from
from
from
from

A
B
A
B

=
=
=
=

1.753m
2.080m
2.550m
2.895m

If the RL of X is 90.370m PD, calculate the RL of


station Y.
(note: Y is lower than X)
Elementary Land Surveying

ELS_Levelling05_06: 38

19

Effects of Earths Curvature and Atmospheric Refraction


A. Earths Curvature
In ,
L2 + R2 = (R + c)2
L2 = (R + c)2 - R2
L2 = 2cR + c2
L2 2cR
c L2 / 2R (km)
= 0.0785 L2 (m)
where
radius of the Earth,
R 6370 km
and L in km

Elementary Land Surveying

ELS_Levelling05_06: 39

Effects of Earths Curvature and Atmospheric Refraction

Refraction
Line of sight is not really horizontal and bent
downwards towards the Earth
Value not constant, affected by pressure, temperature,
latitude, humidity etc.
Usually taken as 1/7 and opposite of the correction of
curvature
Combined correction
= 0.0785 L2 * (6/7) = 0.0673 L2 (m)
where L in km
If L = 120m, c = -0.00097m 0.001m 1mm
The effect is negligible for ordinary levelling
Elementary Land Surveying

ELS_Levelling05_06: 40

20

Example
A staff is held at a distance of 200m from a level
and a reading of 2.758m obtained. Calculate the
reading corrected for curvature and refraction.

Elementary Land Surveying

ELS_Levelling05_06: 41

21

S-ar putea să vă placă și