Sunteți pe pagina 1din 71

INSTALLATION

OPERATION &
MAINTENANCE

DA SLV/KTB

DA PUMP I/B
SLV/KTB CONFIGURATION

READ THIS BEFORE PROCEEDING

It should be understood that the information contained in this manual does not relieve operating and maintenance
personnel from the responsibility of exercising normal good judgement in the installation, operation, and maintenance of the pump and its components.
Only qualified personnel should work on this equipment, and only after reading this manual and becoming familiar
with all of the safety notices and procedures contained herein. Safe and successful operation of this equipment is
dependent upon its proper handling, installation, operation, and maintenance as described in this manual.
It should be understood that the contents of this manual do not add to or modify any prior or existing warranty,
agreement, commitment, and/or relationship between Flowserve and the purchaser. The sales contract between
the parties contains the sole warranty for this equipment.
During initial start-up of this equipment, it is recommended that the service of a Flowserve service supervisor be
obtained to assure trouble-free operation. In some cases, the presence of a Flowserve service supervisor may be
a contractual requirement for continuation of warranty. Check your contract.

DA SLV/KTB

To schedule a service supervisor, contact Flowserve Corporation, Customer Service Department (1-800-5478671 or 908-859-7372), or contact the nearest Flowserve sales office.

Table Of Contents
Section 1
Introduction
Pump Data Sheet

1-1

Approximate Weights

1-1

Introduction

1-2

Safety

1-2

Description

1-2

DA SLV/KTB MS

CASING
IMPELLERS
CASING RINGS
CHANNEL RINGS
CENTER SLEEVE
CENTER BUSHING
THROTTLING SLEEVE
THROTTLING BUSHING
SHAFT
SHAFT SLEEVES
BEARINGS
STUFFING BOXES
RECEIPT INSPECTION
UNPACKING

1-2
1-3
1-3
1-3
1-3
1-3
1-3
1-3
1-3
1-3
1-3
1-4
1-4
1-4

Care During Storage

1-4

Painting/Rust Preventive

1-4

Lifting Equipment

1-5

TO LIFT UNIT
TO LIFT DRIVER
TO LIFT PUMP
TO LIFT UPPER HALF CASING
TO LIFT PUMP ROTOR

1-5
1-5
1-5
1-5
1-5

Table Of Contents
Extended Storage Requirements

1-5

GENERAL
INSPECTION UPON ARRIVAL
STORAGE AREA
STORAGE PREFERRED (DRY)
GENERAL
ROTOR STORAGE
INSPECTION AND MAINTENANCE
STORAGE NON-PREFERRED (WET)

1-5
1-6
1-6
1-6
1-6
1-6
1-6
1-8

Painting And Preservation

1-8

Start-Up

1-8

Drivers

1-8

Section 2
Installation
Location

2-2

Foundation

2-2

Installation Check List

2-2

Level The Bedplate

2-3

DA SLV/KTB MS

PRELIMINARY ALIGNMENT

2-3

Grouting

2-4

Shaft/Coupling Alignment

2-4

TYPES OF MISALIGNMENT
ALIGNMENT
HORIZONTAL MOVE
VERTICAL MOVE
CHECK COUPLING ALIGNMENT
ASSEMBLE AND LUBRICATE COUPLING
DOWEL PUMP AND DRIVER
HOT ALIGNMENT CHECK
ALIGNMENT DATA SHEET SHEET 1 OF 2
ALIGNMENT DATA SHEET SHEET 2 OF 2
ALIGNMENT DATA EXAMPLE

2-5
2-5
2-7
2-8
2-8
2-8
2-8
2-9
2-10
2-11
2-12

Table Of Contents
Piping

2-13

SUCTION AND DISCHARGE PIPING


BY-PASS LINE
SUCTION STRAINER

2-13
2-13
2-14

Coupling Alignment Check

2-15

Gib Block Installation

2-15

Inspection Of Oil Rings Before Start-Up

2-16

Commissioning Of Equipment

2-16

Section 3
Operation
Technical Data

3-1

SPECIFIC GRAVITY
VISCOSITY
CHANGING PUMP SPEED
NET POSITIVE SUCTION HEAD (NPSH)

3-1
3-1
3-1
3-1

Operating Precautions

3-1

Pre-Operational Checks

3-2

PUMP INSTRUMENTATION SET POINTS

3-2
3-3

Operating Checks

3-3

Normal Start-Up

3-4

Securing The Pump

3-4

DA SLV/KTB MS

Initial Start-Up Procedure

Section 4
Troubleshooting
Troubleshooting

4-1

Flowserve Corporation Pump Service Centers

4-4

Table Of Contents
Section 5
Lubrication
Lubricating Oil

5-1

Oil Specifications

5-1

Oil Temperature

5-2

Cleaning The Lubrication System Prior To Operation

5-2

Trico Oiler Setting

5-2

Section 6
Shaft Sealing
Mechanical Seal

6-1

MECHANICAL SEAL REMOVAL

6-1

Section 7

DA SLV/KTB MS

Maintenance
General

7-1

Preventive Maintenance Schedule

7-2

Torque Values

7-3

Coupling Removal

7-3

Dismantling Procedure

7-3

THRUST BEARING REMOVAL


PLAIN BEARING REMOVAL
REMOVAL OF STUFFING BOX PARTS
ROTOR REMOVAL
DISMANTLING THE ROTOR
HEATING IMPELLERS FOR REMOVAL

7-3
7-4
7-4
7-4
7-5
7-5

Inspection And Renewal Of Parts

7-6

Parting Flange Gasket

7-7

Parting Flange Torque Procedure

7-8

Table Of Contents
Bearing Handling Information

7-8

BEARING HANDLING
BEARING INSTALLATION
BEARING REMOVAL
BEARING CLEANING

7-8
7-9
7-9
7-9

Reassembly Of Pump

7-10

REBUILDING ROTOR
INDICATE AND DYNAMIC-BALANCE ROTOR
INSTALLING ROTOR IN CASING
ASSEMBLE STUFFING BOX EXTENSION
CHECK ROTOR VERTICAL LIFT
CHECK ROTOR AXIAL FLOAT
HORIZONTAL AND VERTICAL SHAFT ALIGNMENT
CENTRALIZE ROTOR AXIALLY
SET THRUST BEARING END PLAY
INITIAL THRUST BEARING ASSEMBLY
FINAL THRUST BEARING ASSEMBLY
FINAL ASSEMBLY

7-10
7-11
7-11
7-12
7-12
7-12
7-13
7-14
7-14
7-15
7-15
7-16

Section 8

DA SLV/KTB MS

Parts Information
Service Instructions

8-1

Ordering Instructions

8-1

Recommended Spare Parts

8-2

Exploded View No. 1 Typical Rotor Assembly

8-3

Exploded View No. 2 Lower Half Bushings, Rotor & Casing Assembly

8-4

Exploded View No. 3 Upper Half Bushings & Casing Assembly

8-5

Exploded View No. 4 Shaft Sealing

8-6

Exploded View No. 5 Plain Bearing End

8-7

Exploded View No. 6 Thrust Bearing End

8-8

Table Of Contents

DA SLV/KTB MS

Flowserve Corporation Pump Service Centers

8-9

Flowserve Corporation Domestic Sales Facilities

8-10

Flowserve Corporation International Sales Facilities

8-12

Introduction

INTRODUCTION

SAFETY

This manual contains instructions for installation,


operation and maintenance of your Flowserve Centrifugal pump. It has been designed to provide safe
and reliable service. However, it is both a pressure
vessel and a piece of rotating machinery. Therefore
the operator(s) must exercise good judgement and
proper safety practices to avoid damage to the
equipment and surroundings and prevent personal
injury.

It is assumed that your safety department has established a safety program based upon a thorough
analysis of industrial hazards. Before installing and
operating or performing maintenance on the pump
and associated components described in this manual, the safety program must be reviewed to ensure
that it covers the hazards arising from high- speed
rotating machinery.
It is important that due consideration be given to
those hazards which arise from the presence of
electrical power, hot oil, high-pressure and high-temperature liquids, toxic liquids and gases and flammable liquids and gases. Proper installation and care
of protective guards, shutdown devices and overpressure protection equipment should also be considered a mandatory part of any safety program.

The instructions in this manual are intended for the


guidance of personnel with a general training in operation and maintenance of Centrifugal Pumps. It is
our hope that you will become acquainted with its
content as an aid to better pump performance. This
manual should be read in its entirety before installing
and/or operating the equipment. The Assembly
Drawings (included in Appendix) and General Arrangement Drawing (included in Appendix) should
be consulted for accurate details and determination
of specific optional features that are furnished with
your pump. All numbers in parentheses ( ) following
part names correspond with Exploded View Noun
Codes. EXAMPLE. (1-003A) Exploded View #1,
Noun Code #003A Impeller Assembly. Exploded
Views are included in Section 8.

Also essential are special precautionary measures


to prevent the possibility of applying power to the
equipment at any time when maintenance work is in
progress. The prevention of rotation due to reverse
flow should not be overlooked.
In general, all personnel should be guided by all the
basic rules of safety associated with the equipment
and the process.

NOTE

DA SLV/KTB

DESCRIPTION
The installation/commissioning of this equipment
must be conducted in accordance with API Recommended Practices 686/PIP REIE 686 First Edition.
Refer to API 610 Eighth Edition Appendix `L for
baseplate grouting requirements.

The DA pump is a multistage, single suction opposed impeller, horizontally split volute pump.

Copies of API Recommended `Practices 686/PIP


REIE 686 First Edition may be obtained from
America Petroleum Institute, 1220 L Street, N.W.,
Washington, DC 20005. Telephone (202) 6828000.

Rotating parts are accessible by removing the upper-half casing which can be removed without
breaking suction and discharge piping.

The suction and discharge nozzles are cast integral


with the lower half casing.

CASING
The casing provides for immediate containment of
the liquid being pumped, while directing the flow of
liquid from the suction nozzle to the impellers and
subsequently through the volute to the discharge
nozzle.

1-2

Introduction

THROTTLING SLEEVE

The casing halves are sealed by the use of a gasket


and are joined together by studs, which are installed
in the lower half casing and fastened with washers
and cap nuts.

Renewable type throttling sleeve is used under the


throttling bushing. The throttling sleeve is tubular,
keyed, has a shrink fit to the shaft, and is held in
position by a split ring.

IMPELLERS

THROTTLING BUSHING

The impellers are single suction, enclosed type, onepiece construction and are dynamically balanced.

Renewable type throttling bushing is used. It is held


in position by the annular ring of the bushing engaging the annular groove in the casing.

They are fitted with renewable impeller rings (front


and back) which are held in place by headless setscrews.

The throttling bushing, in conjunction with the throttling sleeve, allows pressure to be bled off thru the
balance lines, so that pressure on the stuffing boxes
is balanced. The throttling bushing also balances
the axial thrust of the pump rotor.

The impellers are keyed, have a shrink fit to the


pump shaft and are held in axial position by a split
ring.
CASING RINGS

SHAFT
Casing rings are positioned over the impeller front
rings. These rings are tubular and renewable.

The high-strength shaft is ground over its entire


length to close tolerances. The shaft is designed to
transmit the required power without vibration and is
stepped at each impeller fit for ease of assembly
and disassembly.

CHANNEL RINGS
Renewable channel rings are positioned over the
impeller back rings. They divide the casing into
stages. These rings are horizontally split and are
held together by shoulder screws.

SHAFT SLEEVES
Renewable shaft sleeves are provided with pumps
equipped with packed stuffing boxes to protect the
shaft at the stuffing box areas. The sleeves are tubular type, keyed to the shaft, and held in position by
the retaining rings.

CENTER SLEEVE
A renewable type center sleeve is used under the
center bushing. The center sleeve is tubular and
keyed to the shaft (via the impeller key).

BEARING LINING
CENTER BUSHING
The bearings are carbon steel backed, babbitt lined,
sleeve-type insert bearings. The bearing inserts are
mounted in the bearing bodies and kept from rotating by means of stop pins. The bearing inserts are
renewable.

DA SLV/KTB

The renewable center bushing is horizontally split,


the two halves are held together by socket-head
capscrews and taper dowel pins. It is held in position by the raised annular ring of the bushing engaging the annular groove in the casing.
MS

THRUST BEARING (Refer to Kingsbury Drawing)


The center bushing, in conjunction with center
sleeve, divides the casing at the center (back-toback) impellers.

The Kingsbury thrust bearing is of the equalizing


type, having six thrust shoes on each side of the
thrust collar, and is consequently capable of transmitting the thrust load in either direction. The thrust
is transmitted through the thrust collar to the shoes,
by the shoes to the shoe supporting elements, and
thence to the bearing body and the foundation.

1-3

Introduction

STUFFING BOXES

CARE DURING STORAGE

The stuffing boxes are cast integral with the casing.


The suction and discharge end stuffing boxes can
be equipped with a cartridge type mechanical seal or
stuffing box packing.

(see Extended Storage Requirements)


If it is necessary to store the unit any length of time
before installation, find a vibration-free location that
is protected from unfavorable weather.

RECEIPT INSPECTION

The nozzle covers provided with the unit should be


left in place during storage.

NOTE
The following information regarding receiving is only
offered as a general guideline to the customer.
Flowserve Corp. requires that all receiving be conducted in accordance with specifications set forth in
Chapter 3 -`Jobsite Receiving and Protection from
API Recommended Practices 686/PIP REIE 686,
First Edition.

Electric motors (pump driver) should not be stored in


damp places without special protection (refer to motor manufacturers instructions).

PAINTING/RUST PREVENTIVE
Internal parts of the pump and bearing housings are
protected prior to shipment with a thin-film polar-type
rust preventive [pump internals (Ferrocote 5684),
bearing housings (MIL-C-16173 Grade 3)]. This can
be removed by flushing with natural citrus solvent.

The pump and its associated equipment were carefully inspected at the factory prior to shipment to ensure compliance with the purchase requirements
and job specification. It is suggested that the pump
be inspected upon arrival and that any irregularities
or damage be reported to the carrier immediately.

External machined surfaces are protected with durable drying-type rust preventive (MIL-C-16173 Grade
1). This can be removed with kerosene or safety
solvent (Tower No. 392).

The condition of the skid and covering is indicative


of the way the shipment was handled. Broken skids,
torn coverings, bent hold-down bolts, broken straps,
etc. indicate rough handling.

External non-machined surfaces are painted with


one coat of gray enamel followed by a coat of multicolor speckle lacquer.

The protective covers on the pump nozzles should


be in place and undamaged. The shipping papers
should be checked to determine satisfactory arrival
of any special tools, loose parts, and/or spare parts,
etc., which are usually preserved and packed in a
separate box attached to the skid.

Exception: External non-machined surfaces of the


o
pump [if operating at a temperature above 200 F.
o
(94 C)] are painted with a high-temperature aluminum base paint.
Parts ordered separately are protected with a thinfilm polar-type rust preventive. This can be removed
with petroleum solvents.

DA SLV/KTB

If any damage is discovered and/or parts are missing, notify the carrier or nearest Flowserve office
immediately.

MS

UNPACKING
The pump should arrive already mounted on the
bedplate and it is therefore suggested that the unpacking of the equipment should proceed per instruction as outlined in this manual.
In general, care is to be taken when removing crating, coverings, and strapping in order not to damage
any auxiliary equipment and/or the paint finish.
1-4

Introduction

TO LIFT UPPER HALF CASING

LIFTING EQUIPMENT

Rig to overhead hoist from cast lifting lugs provided.

NOTE

TO LIFT PUMP ROTOR

The following information regarding lifting is only


offered as a general guideline to the customer.
Flowserve Corp. requires that all lifting and rigging
be performed in accordance with specifications set
forth in Chapter 2 - `Lifting and Rigging from API
Recommended Practices 686/PIP REIE 686, First
Edition.

Using slings that will not damage shaft, rig around


shaft close to the impellers and to overhead hoist.
Carefully lift rotor from lower half casing.

EXTENDED STORAGE REQUIREMENTS


NOTE

WARNING

The following information regarding receiving is only


offered as a general guideline to the customer.
Flowserve Corp. requires that all receiving be conducted in accordance with specifications set forth in
Chapter 3 `Jobsite Receiving and Protection from
API recommended Practices 686/PIP REIE 686,
First Edition.

MAKE SURE THAT ANY EQUIPMENT USED TO


LIFT THE PUMP OR ANY OF ITS COMPONENTS
IS CAPABLE OF SUPPORTING THE TOTAL
WEIGHT ENCOUNTERED. MAKE SURE THAT
ALL PARTS ARE PROPERLY RIGGED BEFORE
ATTEMPTING TO LIFT.
TO LIFT UNIT

GENERAL

Pump, driver and bedplate can NOT be lifted as a


unit. Driver must be removed from bedplate before
lifting.

During extended periods of storage prior to installation and from the time of installation until commercial
operation, precautions must be taken to protect the
pump from deterioration. The various parts of the
pump are protected prior to shipment by applying
varying grades of preservatives and paint. However,
during shipment and handling, the preservatives are
subjected to conditions that can cause their removal.
Also, during extended periods of time, the preservative may deteriorate. The following procedures
should be followed to prevent deterioration of the
pump during the extended storage period. These
procedures may also be supplemented by the experience of the person(s) performing the tasks.

To lift pump and bedplate or just bedplate, sling bedplate from all lifting eyes. Failure to do this may result in permanent deformation of bedplate.
TO LIFT DRIVER
Refer to driver manufacturers instructions.

DA SLV/KTB

TO LIFT PUMP
Install sling from overhead hoist and under bearing
housing mounting brackets (cast portion of casing
where bearing housings attach).

It should be noted, that unless otherwise agreed to,


full responsibility and costs associated with the storage and inspection of this equipment rests with the
customer.

WARNING
DO NOT LIFT ENTIRE PUMP FROM CAST LIFTING LUGS ON UPPER HALF CASING. THESE
LUGS ARE FOR LIFTING UPPER HALF CASING
ONLY.

1-5

Introduction

STORAGE PREFERRED (DRY)

CAUTION
IF PUMP IS EQUIPPED WITH A MECHANICAL
SEAL AND IS STORED OR HAS NOT BEEN RUN
FOR 1 YEAR OR MORE, THE MECHANICAL
SEAL MUST BE REMOVED BEFORE START-UP
AND FACES RE-LAPPED TO GUARD AGAINST
THE POSSIBILITY OF SEAL LEAKAGE. WHEN
RE-INSTALLING THE SEAL, NEW "O RINGS
AND GASKETS MUST BE USED.

GENERAL
If at all possible, the pump and its components
should be stored indoors where they will be protected from the elements. If it is not possible to store
the pump and its components indoors, precautions
must be taken to protect them from the elements.
Regardless of whether storage is inside or outside,
the storage area should be vibration-free. All boxes
that are marked for inside storage must be stored
indoors. The pump and its components, when
stored outdoors, should be protected from dirt, dust,
rain, snow or other unfavorable conditions by coverings of heavy-gauge plastic sheets, canvas, waterproof burlap or other suitable coverings.

INSPECTION UPON ARRIVAL


When the pump is received, it should be inspected
for damage or other signs of rough handling. Any
damage found should be reported to the carrier immediately.
Inspect the preservative coating on the various
parts. If necessary, renew the preservative in areas
where it has been rubbed off or scraped.

All equipment must be placed upon skids or blocks


to prevent contact with the ground and surface contaminants. Equipment must be adequately supported to prevent distortion and bending.

Inspect all painted surfaces. If necessary, touch up


the areas where paint has been chipped or scraped.

ROTOR STORAGE
It is recommended that pump rotor be stored in the
pump. Multistage diffusor-type pump rotors that
cannot be stored in the pump must be supported at
the channel rings so that rotor weight is evenly distributed. Single-stage and volute-type pump rotors not
stored in pump must be supported close to im- peller(s) to eliminate sag that may cause rotor to take a
permanent set.

Inspect all covers over pump openings and piping


connections. If covers or seals for the covers are
damaged or loose, they are to be removed, and a
visual inspection made of the accessible interior areas for accumulation of foreign materials or water. If
necessary, clean and recoat the interior parts with
preservative to restore the parts to the as shipped
condition. Install or replace covers and fasten securely.

LUBE OIL SYSTEM

STORAGE AREA

NOTE

DA SLV/KTB

When selecting a storage area, the following should


be taken into consideration:

The following information regarding lubrication is


only offered as a general guideline to the customer.
Flowserve Corp. requires that the receiving, protection, and installation of the lubrication system be
conducted in accordance with specifications set forth
in Chapter 8 - `Lubrication Systems from API Recommended Practices 686/PIP REIE 686, First Edition.

1. The deterioration of the equipment will be proportionate to the class/type of storage provided.
2. The expenses involved in restoring the equipment at time of operation will be proportionate to the
class/type of storage provided.

1-6

Introduction

1. The lube oil reservoir shall be filled with a rust-inhibiting, turbine-type, lube oil with a viscosity of approximately 150 to 160 Saybolt Universal Seconds
o
at a temperature of 100 F. The oil shall be examined periodically and replaced if it loses its effectiveness or if it has dissipated the rust inhibitor.

(d) Pump covers are periodically removed from


openings and interior accessible areas inspected. If
moisture has accumulated or surface rusting has
occurred, clean and repaint or recoat with preservative.
(e) Loosen casing drain plugs to allow seepage of
any accumulated moisture.

2. The lube oil pipes to pump and driver bearings (if


furnished) shall be capped and the auxiliary oil pump
wired to allow manual operation.

(f) If rusting occurs on exterior surfaces, clean and


repaint or recoat with preservative.

3. Auxiliary oil pump and reservoir heater (if furnished) shall be operated each month, long enough
to heat the lube oil in the pump reservoir to approxio
mately 110 F.

(g) Periodically remove bearing covers and inspect


for accumulation of moisture, rust and foreign material. As required, clean bearings and bearing housing and represerve. Install bearing cover and secure
to assure maximum protection. Bearings removed
for storage should be coated with pre- servative,
wrapped in oil/wax paper, and stored in a warm dry
area.

CAUTION
THE LUBE OIL SYSTEM SHALL BE DRAINED,
FLUSHED AND FILLED WITH THE PROPER
LUBE OIL JUST PRIOR TO START-UP.

(h) Check individually wrapped parts for signs of deterioration. If necessary, renew preservative and
wrapping.

INSPECTION AND MAINTENANCE


1. Customer Inspection And Maintenance

2. Six Months Prior To Installation

The stored equipment is to be placed on a periodic


inspection schedule by the customer.

Six months prior to the scheduled installation date, a


Flowserve Corporation representative is to be employed to conduct an inspection. All costs involved
during inspection, dismantling, restoration, replacement of parts, and reassembly will be the responsibility of the customer. All necessary labor, tools, and
cranes will be supplied by the customer. This inspection will include (not necessarily in its entirety)
but not be limited to, the following:

NOTE

DA SLV/KTB

The responsibility for setting up an inspection and


maintenance schedule rests with the customer and
will be dependent upon the class/type of storage
provided. It would be expected that initially in- spection would occur weekly, then depending upon the
inspection reports being favorable or unfavorable,
inspection would continue weekly, monthly, or quarterly, as may be determined. Inspection reports
must be kept on file.

(a) An inspection of all periodic inspection records


as kept on file by the customer, and all inspection
reports that have been compiled during the storage
period.

Each inspection should consist of a general surface


inspection.

(b) An inspection of the storage area to determine


the as stored condition of the equipment prior to
any protection covers being removed.

(a) Pump supports are firmly in place.

(c) An inspection of the equipment with protection


covers and flange covers removed.

(b) Pump covers over openings are firmly in place.


(c) Pump covering, plastic or tarps, is firmly in place.
Any holes or tears must be repaired to prevent entrance of dirt or water.

1-7

Introduction

Fill pump with a 1% solution of Immunol 1809 and


water, (or owner-approved preservative). Immunol
is a water-phase corrosion inhibitor for ferrous and
mixed-metal couples and is composed of 5% sodium
nitrate with polyglycols, copper corrosion inhibitor,
and other organic materials. The pump should be
filled to highest level possible, affording the greatest
protection possible to all internal parts of the pump.
This solution, when drained, will result in a thin residual oil film (less than .0005 in.(.0127 mm) on all
internals after the water has evaporated. This residue provides added corrosion protection until pump
is again filled with liquid or put into service.

(d) Depending upon the length of time the equipment was stored, the class/type of storage provided,
(i.e.: indoor, heated, unheated, ground floor, concrete floor, out-of-doors, under roof, no roof, waterproof covering, on concrete, on ground) and as a
result of the inspection of a, b and c above, the
Flowserve representative may require a partial or
complete dismantling of the equipment.
(e)
Dismantling may necessitate restoration of
painted or preserved surfaces, and/or replacement
of gaskets, O rings, packing, and/or mechanical
seal and bearings. Use only Flowserve recommended replacement materials.

(b) Non-Corrosive Pumpage.


Upon completion of the inspection, the Flowserve
Corporation representative shall submit a report to
the customer, and to the Manager of Customer Service, stating in detail the results of the inspection.

Fill pump with pumpage to the highest level possible. Periodically open drain connection to drain off
any moisture that may have accumulated. Refill to
high- est level possible. Drain and inspect pump
prior to start-up.

3. One Month Prior To Installation

3. Lube Oil System

One month prior to installation of the equipment, a


Flowserve Corporation representative is to be employed to conduct a final inspection. This final inspection will be made to assure that the requirements of the six-month inspection report were satisfactorily completed and that the equipment is ready
for installation.

NOTE
The following information regarding lubrication is
only offered as a general guideline to the customer.
Flowserve Corp. requires that the receiving, protection, and installation of the lubrication system be
conducted in accordance with specifications set forth
in Chapter 8 - `Lubrication Systems from API Recommended Practices 686/PIP REIE 686, First Edition.

Upon completion of this inspection, the Flowserve


Corporation representative shall submit a final report
to the customer, and to the Manager of Customer
Service, advising the results of the final inspection.

DA SLV/KTB

STORAGE NON-PREFERRED (WET)

(a) The lube oil reservoir shall be filled with a rustinhibiting, turbine-type, lube oil with a viscosity of
approximately 150 to 160 Saybolt Universal Seco
onds at a temperature of 100 F. The oil shall be
examined periodically and replaced if it loses its effectiveness or if it has dissipated the rust inhibitor.

It is not recommended that the rotor be subjected to


extended periods of submergence or wetting prior to
start-up. However, it is recognized that in some
cases, a long period of time may lapse from installation until commercial operation.

(b) The auxiliary oil pump and reservoir heater (if


furnished) shall be wired to allow manual operation.
They shall be operated each month, long enough to
o
heat the oil in the reservoir to approximately 110 F.

If the pump must be stored after being installed and


wetted, the following inspection and maintenance
procedures should be performed.
1. Isolate pump with valving tag (seal) all valves.

CAUTION

2. Preserve the pump internals.

THE LUBE OIL SYSTEM SHALL BE DRAINED,


FLUSHED AND FILLED WITH THE PROPER
LUBE OIL JUST PRIOR TO START-UP.

(a) Corrosive Pumpage.


1-8

Introduction

4. Rotate pump rotor 1-1/4 revolutions at least once


a week.

START-UP
Prior to and during start-up, any requirement for the
services of a Flowserve Corporation representative
will revert to the original contract agreement for the
equipment purchased.

NOTE
Auxiliary oil pump shall be operated during any shaft
rotation.

DRIVERS

PAINTING AND PRESERVATION

Generally storage must be indoors and dry. See the


specific manufacturers storage requirements.

DA SLV/KTB

Paints and preservatives used are either Flowserve


Corporation standard or special as required by the
contract specification. Refer to RUST PREVENTIVE for the description of paints and preservatives
used on this order or contact the branch office
through which the order was placed.

1-9

Installation

NOTE
The installation/commissioning of this equipment must be conducted in accordance with API Recommended Practices 686/PIP REIE 686 - First Edition. Refer to API 610 - Eighth Edition - Appendix `L` for baseplate grouting requirements.
Copies of API Recommended Practices 686/PIP REIE 686 - First Edition may be obtained from - America Petroleum Institute, 1220 L Street, N.W., Washington, D.C. 20005. Telephone: (202) 682-8000.
The following ASTM Specifications are furnished as references for test methods used in conjunction with installation of grouting materials and should be used to obtain proper results.
ASTM C 78-84

Test Method for Flexural Strength for Concrete.

ASTM C 109-90

Test Method for Compressive Strength of Hydraulic Cement Mortars - Modified.

ASTM C 469-87a

Test Method for Static Modulus of Elasticity and Poissons Ratio of Concrete in Compression.

ASTM C 496-90

Test Method for Splitting Tensile Strength of Cylindrical Concrete Specimens.

ASTM C 531-85

Test Method for Linear Shrinkage and Coefficient of Thermal Expansion of Chemical Resistant Grouts and Monolithic Surfacings - (Modified).

ASTM C 666-90

Test Method for Resistance of Concrete to Rapid Freezing and Thawing.

ASTM C 939-87

Test Method for Flow of Grout for Preplaced Aggregate Concrete (Flow Cone Method).

ASTM C 942-86

Test Method for Compressive Strength of Grouts for Preplaced Aggregate Concrete in the
Laboratory.

ASTM C 1090-88
lic Cement Grout.

Test Method for Measuring Changes in Height of Cylindrical Specimens from

ASTM C 1107-91

Standard Specification for Packaged Hydraulic-Cement Grout (Non-Shrink).

(CRD-C 621-92)
ACI 351
24 Hour Test

Grouting for Support of Equipment and Machinery.


MBT Test Method for Grout Performance.

DA SLV/KTB

MINIMUM REQUIREMENTS FOR EPOXY GROUT


o
o
[TYPICAL PROPERTIES AT 73 F.(23 C.)]
ASTM D-635

Fire Resistant

ASTM C-579B

Minimum Compressive Strength 12000 psi

ASTM C-827

Height Change @ 90 F.(38 C.) Positive Effective Bearing Area 95%

ASTM C-1181

Maximum Creep in 1 Year 1.6X10 in/in at 140 F., 400 psi

ASTM C-307

Minimum Tensile Strength 1800 psi (12.4 MPa)

ASTM C-580

Minimum Flexural Strength 3800 psi (26.2 MPa)

ASTM C-580

Minimum Flexural Secant Modulus 1.8X10 psi (1.2X10 MPa)

ASTM C-531

Maximum Coefficient of Expansion 17X10 in/in/ F.


o
o
Maximum Peak Exotherm 1000 gm insulated 95 F.(35 C.)
Full Aggregate Must Be Used.

-3

-6

2-1

Hydrau-

Installation

LOCATION
Install the unit close to the source of the liquid to be
pumped.
When selecting the location, be sure to allow adequate space for operation as well as for mainteance operations involving dismantling and inspection
of parts.
Head room is an important consideration, as an
overhead lift of some type is required.

FOUNDATION

Template For Hanging Foundation Bolts


NOTE

The sketch illustrates a recommended foundation


bolt arrangement. Notice the large washer with lugs
at the bottom. It should be welded to the bolt and
pipe sleeve to prevent turning.

The following information regarding foundation is


only offered as a general guideline to the customer.
Flowserve Corp. requires that all foundations be designed/installed in accordance with specifications set
forth in Chapter 4 - `Foundations from API Recommended Practices 686/PIP REIE 686, First Edition.

Allow a little more than the specified threaded bolt


length above the rail of the baseplate. The excess
can always be cut off it not needed.

The design of foundations, is not the responsibility of


Flowserve Corp. It is therefore recommended that
the customer consult a competent specialist skilled
in the field of foundations, to insure proper design/
installation of the foundation.

A rough finish top surface is best when applying


grout.

The foundation should be sufficiently rigid and substantial to prevent any pump vibration and to permanently support the bedplate at all points.
The most satisfactory foundations are made of reinforced concrete. These should be poured well in
advance of the installation to allow proper time for
drying and curing.

DA SLV/KTB

The General Arrangement Drawing will furnish anchor bolt locations, size of bolts, etc.

INSTALLATION CHECK LIST


1. Level Bedplate
2. Preliminary Alignment
3. Grout Bedplate
2-2

Installation

4. Align Shaft/Coupling
5. Piping
6. Check Coupling Alignment

LEVEL THE BEDPLATE


NOTE
The following information regarding leveling of
equipment is only offered as a general guideline to
the customer. Flowserve Corp. requires that all leveling of equipment be performed in ac- cordance
with specifications set forth in Chapter 5 - `Mounting
Plate Grouting from API Recommended Practices
686/PIP REIE 686, First Edition.

Level the bedplate by using a machinists level on


the machined surfaces of the pump and driver pads.
When the bedplate is leveled, pull down the foundation bolts so they are snug. The bedplate may have
been disturbed by tightening the foundation bolts;
therefore, recheck with level and make necessary
adjustments by wedges or shimming.

Before putting the unit on the foundation, thoroughly


clean the top of the foundation. Break off any loose
pieces of cement and roughen the top with a chisel
to afford a good hold for grout.

As a final bedplate alignment check on spacer type


couplings, install a mounting bracket for dial indicator on driver hub. Fasten or clamp indicator on
mounting bracket, so that dial indicator button is
con- tacting the face of the pump half coupling, and
zero the dial indicator. (Non-spacer type coupling
should be check with tapered wedge or feeler
gages.)

NOTE
Coupling bolting and spacer piece (when used) must
be removed from between pump/driver half couplings
before lifting baseplate with pump element.

Rotate the driver half coupling (in direction of pump


o
rotation) 90 . Record this reading.

NOTE
Repeat this procedure until readings have been
o
taken at four 90 positions.

DA SLV/KTB

When lifting bedplate with pumping element, sling


bedplate from all lifting eyes provided. Failure to do
this may result in permanent deformation of bedplate.

PRELIMINARY ALIGNMENT
Using the previous procedure, shim and/or wedge
bedplate until pump and driver are within .003 in.
(.076 mm).

Prepare enough iron wedges or shims to be placed


on each side of each foundation bolt.
These
wedges should be about 4 in.(102 mm) to 6 in.(152
mm) long by 2 in.(51 mm) to 3 in.(76 mm) wide and
thick enough to allow for 1-1/4 in.(32 mm) of grout
under the edge of the bedplate. Place wedges as
shown in sketch.

2-3

Installation

Holes are provided in the bedplate to permit pouring the


grout and stirring. They also act as air vents. Fill under
the bedplate completely, stirring to assure proper distribution of the grout. Check to see that the grout flows
under the edges of the bedplate evenly.

GROUTING
NOTE
The following information regarding grouting is only
offered as a general guideline to the customer.
Flowserve Corp. requires that all grouting be installed in accordance with specifications set forth in
Chapter 5 - `Mounting Plate Grouting from API Recommended Practices 686/PIP REIE 686, First Edition.

NOTE
Do not vibrate bedplate when grouting; make sure bedplate is vented properly and all areas indicated on General Arrangement drawing are thoroughly puddled to
prevent any resonant problems.

It is recommended that the customer consult a competent specialist skilled in the field of grouting, to
insure the proper installation of all grouting.

When the grout is thoroughly hardened, remove the


dam and wedges, if desired, filling in the holes they
leave with grout.

Build a dam around the foundation. It is a matter of


personal preference whether the leveling wedges under the bedplate should be removed after grouting. If
you do want to remove the wedges, carefully mark
their locations before pouring grout.

SHAFT/COUPLING ALIGNMENT
NOTE
The following information regarding shaft alignment
is only offered as a general guideline to the customer. Flowserve Corp. requires that all shaft alignment
be performed in accordance with specifications set
forth in Chapter 7 - `Shaft Alignment from API Recommended Practices 686/PIP REIE 686, First Edition.

CAUTION
SHAFT ALIGNMENT MUST BE CORRECT FOR
SUCCESSFUL OPERATION. RAPID WEAR, NOISE,
VIBRATION AND ACTUAL DAMAGE TO THE
EQUIPMENT MAY BE CAUSED BY SHAFT MISALIGNMENT. THE SHAFTS MUST BE ALIGNED
WITHIN THE LIMITS GIVEN WITHIN THIS SECTION.
NOTE
DA SLV/KTB

Build Dam Around Foundation Before Pouring Grout


Adjustments to correct the alignment in one direction
may alter the alignment in another direction. Always
check in all directions after making any adjustments.

Use a quality, high strength, non-shrink epoxy grout


- mix and install per manufacturers instructions.

2-4

Installation

Coupled equipment must be aligned to minimize unnecessary stresses in shafts, bearings and coupling.
Flexible couplings will not compensate for appreciable misalignment. Foundation settling, thermal expansion or nozzle loads resulting in baseplate/foundation deflection and vibration during operation may
require the full coupling misalignment capability.
Combination Offset
And
Angular Misalignment

TYPES OF MISALIGNMENT
There are two types of shaft misalignment: Angular
and offset. Therefore, two sets of measurements
and corrections are required. Both types of misalignment can occur in horizontal and vertical planes
and are present in most applications.
A.

ALIGNMENT
A. Measure Gap

Angular Misalignment

The first step in shaft/coupling alignment is to bring


the pump and driver shafts into their proper axial
position. The shaft gap, or distance between coupling hubs, must be in accordance with the certified
General Arrangement Drawing and must be measured with pump and driver shafts in the center of
their axial end float. Motor with sleeve bearings is to
be aligned with rotor at magnetic center.

In angular misalignment, the centerline of the shafts


intersect, but are not on the same axis.

Move driver to insure proper gap distance.


NOTE

B. Offset Misalignment

It is recommended that the pump hold-down bolting be


torqued and the pump be dowelled before taking any
alignment measurements. This makes the pump the
fixed machine and the driver the movable machine. In
certain cases, however, it may be impractical to move
the driver; therefore, the pump may have to be moved.
When this case exists, the pump should not be dowelled until after final alignment.

In offset misalignment, the shaft centerline are parallel but do not intersect.

B. Measure Angular Misalignment


Refer to ALIGNMENT DATA SHEET and examples.

DA SLV/KTB

Offset Misalignment

2-5

Installation

CAUTION

4. Repeat Step 3 until measurements have been


o
o
o
o
taken at the four positions (0 ,90 ,180 ,270 ).

PUMP SHAFT SHOULD NOT BE ROTATED MORE


THAN NECESSARY WHEN ALIGNING SHAFTS.
DAMAGE COULD OCCUR TO INTERNAL WEARING
PARTS WHICH ARE LUBRICATED BY THE PUMP
LIQUID.

5. Rotate both shafts to the starting position (12


oclock markings at top center) and recheck dimension recorded in Step 2.
o

6. For 0 ,90 ,180 ,270 Columns, subtract the bottom from the top and left from right. Record in their
respective blocks on Data Sheet. Watch sign notations.

The angular misalignment can best be determined


by the use of a hand-held inside micrometer, marked
B on sketch. All measurements should be taken at
the same radial distance from the shaft centerline,
as close as possible to the hub outside diameter.
The location of these measurements is defined as
the D dimension on the ALIGNMENT DATA
SHEET. Do not move the shafts axially while rotating the shafts and taking measurements. Both hubs
must be rotated together to cancel possible hub face
runout. The relative measurement (top minus bottom, right minus left) is the important number.

7. Total the different numbers (reading across), divide by 4 and record the average_____. Record in
Open At _____ the shaft relative angular position.
NOTE
The inside faces of the driver and pump half hubs
must be parallel within .001 in.(.0254 mm).
C. Measure Offset Misalignment

1. Mark both coupling hubs at 3,6,9 and 12 oclock


o
positions so they can be rotated together and at 90
intervals.

Offset misalignment is measured using a dial indicator on the outside diameter of the coupling hubs
and rotating the hubs together to cancel rim surface
inaccuracies.
1. Starting with the 12 oclock markings of both
hubs on top center, fasten or clamp an indicator on
driver hub, marked A on sketch, with dial indicator
button contacting alignment surface on the pump
hub.
2. Zero the dial indicator.
3. Rotate both coupling hubs (in the direction of
pump rotation) 90o and take a reading. Record on
ALIGNMENT DATA SHEET-Sheet 1, Part 2 in the
proper right side or left side blank (right or left sides
are determined when viewing the driver half coupling
from the pump).

DA SLV/KTB

2. Starting with the 12 oclock markings of both


hubs in the top center position, measure the gap at
top, bottom, right and left side. Record these dimensions on ALIGNMENT DATA SHEET Sheet 1,
o
Part 1 in the 0 Column.
NOTE

4. Repeat Step 3 until readings have been taken at


o
the four 90 positions (top center, right, bottom and
left).

Right side and left side are determined when viewing


the driver coupling from the pump.

5. Rotate both shafts to the starting position (12


oclock markings at top center) and verify indicator
returns to zero.

3. Rotate both shafts 90 in the direction of pump


rotation. Measure gap dimensions at the four locations as in Step 2. Record on ALIGNMENT DATA
o
SHEET-Sheet 1, Part 1 in the 90 Column.

2-6

Installation

NOTE
The sum of the top and bottom readings should always equal the sum of the left and right readings. If
the sums are not equal, check for indicator bracket
deflection, hub surface irregularity or loose radial
bearings.

GH =

Gap difference (right minus left) taken from


Sheet 1, Part 1.

LI =

Distance from driver coupling hub to centerline of driver inboard hold-down bolt.

LO =

Distance from driver coupling hub to centerline of driver outboard hold-down bolt.

6.
Using the formula on ALIGNMENT DATA
SHEET-Sheet 1, Part 2, subtract the top from the
bottom indicator reading, divide by 2. This will yield
the vertical misalignment.
7.
Using the formula on ALIGNMENT DATA
SHEET-Sheet 1, Part 2, subtract the left from the
right indicator reading, divide by 2. This is the horizontal misalignment.
8. Circle the proper high or low and left or right position of the driver hub, using the rules given on the
Data Sheet.

3. Record vertical offset from Sheet 1, Part 2 and


vertical move obtained from calculations in the INBOARD, and OUTBOARD DRIVER PEDESTAL
SHIFT columns. Also record the required direction
of shift (raise or lower).

NOTE
The outside diameters of pump and driver coupling
hubs must be aligned within .003 in.(.0762 mm) TIR.

4. Record horizontal offset from Sheet 1, Part 2 and


horizontal move obtained from calculations in the
INBOARD, and OUTBOARD DRIVER PEDESTAL
SHIFT columns. Also record the required direction
of shft (right or left).

D. Movement Calculations (ALIGNMENT DATA


SHEET-Sheet 2).
1. Sketch the relative driver shaft position in the
side and top views. These sketches will assist visualizing the required equipment move.

5. Total the move requirements (watch move direction). This will yield the required horizontal move
(right or left) and the vertical move (raise or lower)
required at each mounting foot.

2. Alignment depends upon the relationship between D, LI and Lo.

HORIZONTAL MOVE
Use the formula G X L to determine the required
move.
D

The dial indicators shown below are required to accurately measure the move in the horizontal direction. Move the driver by bumping with soft hammer/mallet or using the jackscrews (if provided).
The amount of horizontal relocation required is the
total of the horizontal move calculation (bottom of
Sheet 2).

DA SLV/KTB

NOTE
D =

Diameter of the circle at which angular


misalignment readings were taken (not
coupling diameter).

Gy =

Gap difference (top minus bottom) taken


from sheet 1, Part 1.

2-7

Installation

CHECK COUPLING ALIGNMENT


The angular and offset coupling alignment must be
rechecked.
1. Coupling faces are to be parallel within .001
in.(.0254 mm) TIR.
VERTICAL MOVE

2. Coupling outside diameters are to be aligned


within .003 in.(.0762 mm) TIR.

Before moving the equipment vertically, it is important that the vertical thermal expansion be taken
into consideration. The preceding vertical move calculations are based on pump and driver shafts being
set on the same plane. Refer to General Arrangement Notes and/ or driver instructions for recommended cold vertical setting (if thermal expansion is
a factor).

3A. Motor-Driven: Bump the motor and check motor rotation (see Troubleshooting).
3B. Turbine-Driven: Check turbine rotation.
wrong, consult turbine manufacturer.)

(If

ASSEMBLE AND LUBRICATE COUPLING

The shims between the equipment feet and mounting surface should be clean and dry. This is especially critical for pumps that have been in service for
some time and need to be realigned. Water, dirt and
rust may change the height of the shim pack over a
period of time. Shims should be made large enough
to support the weight of the equipment on its mounting foot. Do not use many thin shims, as this may
result in a spongy mounting.

1. Assemble and lubricate coupling per the manufactur- ers instructions included in Appendix of this
manual.
2. Install coupling guard.
DOWEL PUMP AND DRIVER
o

A. Cold Pumps [temperature below 200 F.(94 C.)]


Pump hold-down bolts are to be torqued to the
proper value and dowel pins put in two diagonally
opposite feet.
B. Hot Pumps
o

Pumps handling liquids at temperatures of 200 F.


o
(94 C.) and over are designed to permit the casing
to expand with temperature away from coupling end
of pump. The units that come under this classification must have the pump supports or feet dowelled
to the baseplate at the coupling end. This maintains
the coupling gap at the desired amount.

DA SLV/KTB

Recommended Shim Design


Move the equipment vertically by adding or removing the calculated thickness of shims. Torque equipment hold-down bolting to required values.

The pump feet at the opposite end are held from


moving vertically by the use of a self locking nut.
The clearance between the base of the nut and the
top of the pump foot should be .002 in.(.051 mm).

NOTE
It is recommended, the completed ALIGNMENT
DATA SHEET be retained as part of your permanent maintenance file.

2-8

Installation

C. Pump Driver

The horizontal movement is controlled by a Gib


block running parallel to the length of the pump at
each of the outboard feet. The Gib Blocks are
bolted and dowelled to the baseplate at the time of
mounting at the factory. A .010 in.(.254 mm) gap is
maintained between the Gib Block and pump foot.

Refer to driver outline drawing and/or driver


instructions for dowelling information.

HOT ALIGNMENT CHECK

IMPORTANT

A hot check can only be made after the unit has


been in operation a sufficient length of time to
assume its NORMAL operating temperature and
conditions. If the unit has been properly cold set,
the offset misalignment will be within .003 in.(.076
mm) TIR and the angular misalignment will be within
.001 in.(.0254 mm) TIR when in operation. If not,
make adjustments.

The self locking nuts which hold the pump from


moving in a vertical motion are clamped tight to the
pump foot at time of shipment. The .002 in.(.051
mm) clearance must be established at time of installation.

WARNING

DA SLV/KTB

DO NOT ATTEMPT ANY MAINTENANCE, INSPECTION, REPAIR OR CLEANING IN THE


VICINITY OF ROTATING ELEMENT.
SUCH
ACTION COULD RESULT IN INJURY TO
OPERATING PERSONNEL.

2-9

ALIGNMENT DATA SHEET


HORIZONTAL PUMPS
NAME

SHEET 1 OF 2

DATE

TIME

ALIGNMENT DATA FOR

SERIAL NUMBER

PUMP TEMPERATURE
PART 1

ANGULAR ALIGNMENT CHECK


o

POSITION

90

180

270

TOTALS

TOP

Open At

BOTTOM

Average

DIFF. (T-B)
*RIGHT SIDE

Open At

*LEFT SIDE

Average

DIFF. (R-L)
* Right and Left side are determined when viewing the driver hub from the pump.
PART 2

OFFSET ALIGNMENT CHECK

TOTAL INDICATOR READINGS


INDICATE
BY ARROW
DIRECTION
OF ROTATION

RULES TO APPLY TO THE RESULTS BELOW:


When Indicator Mounted On The Driver Reads

.000

TOP
Negative = Driver Coupling Is High & Left
Positive = Driver Coupling Is Low & Right

OFFSET
ALIGNMENT
CHECK
RIGHT
SIDE

DA SLV/KTB

LEFT
SIDE

BOTTOM
Driver Coupling Is (Circle Correct One):
High Or Low And Right Or Left
VIEW OF DRIVER HALF COUPLING
HUB VIEWED FROM PUMP
Vertical Offset
Misalignment

Bottom - Top
2

Horizontal Offset
Misalignment

Right - Left
2

2-10

ALIGNMENT DATA SHEET


HORIZONTAL PUMPS

SHEET 2 OF 2

TOP
PUMP
AXIS

LEFT

RIGHT

(FIXED)

PUMP
AXIS
(FIXED)

BOTTOM

SIDE VIEW (VERTICAL MOVE)

TOP VIEW (HORIZONTAL MOVE)

VERTICAL ANGULAR MOVE CALCULATION


Driver Inboard Pedestal Shift

MOVE DRIVER TO CORRECT ALIGNMENT


GV X LI

Driver Outboard Pedestal Shift

G V X LO
D

INBOARD DRIVER PEDESTAL SHIFT


MILS

OUTBOARD DRIVER PEDESTAL SHIFT

DIRECTION

MILS

DIRECTION

OFFSET MOVE
ANGULAR MOVE
TOTAL

HORIZONTAL ANGULAR MOVE CALCULATION


Driver Inboard Pedestal Shift

MOVE DRIVER TO CORRECT ALIGNMENT

GHX L I

D
Driver Outboard Pedestal Shift

G XL
H
O
D

DA SLV/KTB

INBOARD DRIVER PEDESTAL SHIFT


MILS

DIRECTION

OFFSET MOVE
ANGULAR MOVE
TOTAL

2-11

OUTBOARD DRIVER PEDESTAL SHIFT


MILS

DIRECTION

2-12

DA SLV/KTB

Installation
Install a check valve and a gate valve in the discharge pipe on the pump. When the pump is
stopped, the check valve will protect the pump
against excessive pressure and will prevent the
pump from running backward. The check valve
should be installed between the gate valve and the
pump nozzle in order to permit its inspection. The
gate valve is also useful in priming and starting the
pump.

WARNING
BEFORE ATTEMPTING ANY INSPECTION OR
REPAIR ON THE PUMP, THE DRIVER CONTROLS
MUST BE IN THE OFF POSITION, LOCKED
AND TAGGED TO PREVENT INJURY TO PERSONNEL PERFORMING SERVICE ON THE PUMP.
PIPING

Keep the suction pipe short and direct. Use a suction pipe at least one size larger than the pump suction nozzle. Keep the suction pipe free of all air
pockets.

NOTE
The following information regarding piping is only
offered as a general guideline to the customer.
Flowserve Corp. requires that all piping and related
systems be designed/installed in accordance with
specifications set forth in Chapter 6 -`Piping from
API recommended practices 686/PIP REIE 686, First
Edition.

IMPORTANT
A spool piece should be installed in suction line so
that the suction screen may be installed and removed.

The design of piping, and related systems, is not the


responsibility of Flowserve Corp. It is therefore recommended that the customer consult a competent
specialist skilled in the field of piping, to insure
proper design/installation of all piping.

BY-PASS LINE

CAUTION
OPERATION AT LOW FLOWS RESULTS IN
PUMP HORSEPOWER HEATING THE LIQUID. A
BYPASS MAY BE REQUIRED TO PREVENT VAPORIZATION AND SUBSEQUENT PUMP DAMAGE. MECHANICAL DAMAGE MAY RESULT
FROM CONTINUOUS OPERATION AT FLOWS
LESS THAN 25% OF DESIGN OPERATING POINT
(see General Arrangement drawing & nameplate).

SUCTION AND DISCHARGE PIPING


These units are furnished for a particular service
condition. Changes in the hydraulic system may
affect performance adversely. This is especially true
if the changes reduce the pressure at the suction
flange.
In case of doubt, contact the nearest
Flowserve Office.
Suction and discharge piping should be of ample
size, be installed in direct runs, and have a minimum
of bends.

WARNING
WHEN PUMP IS EQUIPPED WITH MANIFOLDED
VENT AND DRAIN LINES, EACH LINE MUST BE
EQUIPPED WITH AN INDIVIDUAL VALVE TO
PREVENT ANY LIQUID FROM A HIGH PRESSURE LINE FLOWING INTO A LOW PRESSURE
LINE. THESE VALVES MUST BE KEPT IN THE
CLOSED POSITION DURING PUMP OPERATION.

DA SLV/KTB

NOTE
Provision must be made to support piping external to
the pump to prevent excessive nozzle loads and
maintain pump-driver alignment.

2-13

Installation
SUCTION STRAINER

CAUTION

In a new installation, great care should be taken to


prevent dirt, scale and welding beads from entering
the pump. Even when piping has been previously
flushed, it is difficult to break loose the oxides and
mill scale which will become free when the pipe
heats and cools several times. Numerous close
running clearances are vulnerable to abrasive matter
present in new piping. Foreign material may be
large enough, or of sufficient volume, to jam a pump,
with probable damage to both pump and drive
equipment. Smaller size material passing through
the pump can cause rapid pump wear and premature pump failure.

EXCESSIVE FORCE USED TO TRY TO FREE A


BOUND ROTOR MAY CAUSE DAMAGE BEYOND
MINOR CLEAN-UP AND REPAIR OF ROTOR
PARTS.
Generally, a pump should not be installed without
start-up strainer protection.
The suction piping
should be thoroughly flushed before installing the
suction strainer and connecting the suction piping to
the pump. The strainer should be installed in the
inlet piping near the pump, making certain that it is
located where it may be readily serviced (cleaned).
Be sure, however, that the installed strainer will not
distort the flow to the pump suction nozzle.

This pump is provided with the exception that it will


be pumping clean liquids (unless otherwise stated in
the order and addressed in the proposal).
Flowserve pumps are provided with running clearances ranging typically from 0.005 inch(0.12 mm) to
0.030 inch(0.80 mm), depending on the service. It is
impractical to install a suction strainer to remove particulate of this size. Such particles will normally pass
through the pump without causing damage, providing the concentrations are minor.

Do not install the strainer directly on the pump suction nozzle. For a cone-type strainer, the downstream end of the cone should be no closer than four
(4) pipe diameters from the pump suction nozzle.
Basket-type strainers typically introduce greater flow
disturbances and should be installed at least six (6)
pipe diameters from the pump suction nozzle.
The Flowserve standard for suction strainers consists of conical-shaped steel plate with 1/8 perforations. The open area of the strainer should be a
minimum of three times the area of the pump suction.

DA SLV/KTB

The possibility exists that, on shutdown of the pump,


such particles can become trapped in the close running clearances during coastdown, causing binding.
Flowserve cannot recommend a procedure that will
totally prevent such binding; however, we strongly
suggest that systems be cleaned and thoroughly
flushed prior to connecting the pump to the piping to
minimize particles entering the pump. Starting and
stopping of the pump should be MINIMIZED as
pumps are most susceptible to dirt during starts and
stops.
In the event that binding on coastdown occurs, it is
unlikely that the binding can be remedied by hand
rolling the rotor, and partial disassembly may be required to clean the affected parts. It should be noted
that increased particle concentrations increase the
probability of coastdown binding and seizures, as
well as erosion damage.

2-14

Installation
When dirt and scale have been removed from the
system, as indicated by no further change in pressure drop across the strainer with time, the start-up
strainer may be removed or the screen may be replaced with one having larger openings. If a permanent strainer will be used during normal operation,
the pressure differential needs to be monitored on a
continuous basis.

DA SLV/KTB

At all times when using suction strainers, it is critical


that the pressure drop across the strainer be constantly monitored to ensure that the pump suction
pressure does not fall below that required to prevent
pump cavitation. Pressure (or vacuum) gauges
should be installed on both sides of the strainer so
that the pressure drop across the strainer can be
monitored.
During start-up of the system, the
gauges should be monitored continuously. Consult
the plant engineer or system designer for the allowable pressure differential across the strainer prior to
operating the pump. Pressure differential across the
strainer and/or screen is typically no more than 2 3
psig. An increase in the differential pressure between the two gauges indicates that the strainer or
screen is becoming clogged with dirt and scale. Before the pressure drop becomes so severe that cavitation occurs, the pump should be shut down and
the strainer cleaned. Alarm settings to protect the
pump from damaging cavitation and loss of suction
need to be supplied by the plant engineer or system
designer prior to operating the pump. Typical alarm
settings to protect the pump from damaging cavitation and loss of suction would be 5 psig differential
pressure across the strainer (screen). The suction
piping should be arranged such that the ultimate
strainer configuration (location) allows ready access
for cleaning.

If a permanent strainer is not used, the start-up


strainer needs to be temporarily reinstalled whenever the system is opened up for repair or routine
maintenance. As long as a suction strainer or
screen remains in place, the differential pressure
should be monitored on a regular basis.

CAUTION
THE PRESSURE DROP ACROSS THE STRAINER
IS A DIRECT REDUCTION IN THE NPSH AVAILABLE TO THE PUMP. NPSH AVAILABLE MUST
ALWAYS EXCEED THE NPSH REQUIRED BY THE
PUMP. THIS REQUIREMENT MAY LIMIT THE
PUMP FLOW RATE, PARTICULARLY DURING
START-UP OPERATION. ALARMS OR AUTOMATIC PUMP SHUT-DOWN DEVICES SHOULD
BE INSTALLED TO MINIMIZE THE POSSIBILITY
OF PUMP DAMAGE. IT IS THE RESPONSBILITY
OF THE PUMP OPERATOR TO OBTAIN THE ALLOWABLE PRESSURE DROP ACROSS THE
STRAINER FOR SAFE PUMP OPERATION FROM
THE PLANT ENGINEER OR SYSTEM DESIGNER
PRIOR TO OPERATION OF THE PUMP.

The strainer may be fitted with a finer screen to filter


the inlet flow. When this is done, 40 mesh screen is
typically used for start-up operation, at reduced flow
rates. For final operation in a closed system, the
suction strainers are normally removed after the system is cleaned. For critical pump applications,
where continuous screening of suction flow is desirable, and in open systems, 20 mesh screening is
typically used for permanent strainers. At all times,
when using screens and suction strainers, it is critical that pressure drop across the screen and/or
strainer be constantly monitored to ensure that the
pump suction pressure does not fall below that required to prevent cavitation.

COUPLING ALIGNMENT CHECK


Refer to the section entitled SHAFT/COUPLING
ALIGNMENT and perform a coupling alignment
check as outlined. This check is recommended to
insure the alignment has not been disturbed during
the grouting of the bedplate or while installing suction and discharge piping.

2-15

Installation
GIB BLOCK INSTALLATION

Step 4

Gib blocks are installed to control the direction of


thermal growth while maintaining pump-motor coupling alignment. They are installed after baseplate
has been leveled and grouted, suction and discharge piping connected, and final shaft coupling
alignment is completed.

Tighten the hold-down bolts for the gib blocks.

Gib blocks are shipped loose and field installed at


the site. The following procedure must be followed
for correct installation of gib blocks.

Step 6

Step 5
Install the dowel pin in the gib blocks by reaming the
block and baseplate for the tapered dowel provided.

Tighten the hold-down locknuts on the non-drive end


pump feed to establish a 0.002 inch(.05 mm) gap
between the locknut and the pump foot.

Step 1

LUBRICATION SYSTEM INSTALLATION

Fully torque the hold-down bolts in the drive-end of


pump feet to torque values listed in the instruction
manual (refer to Pump Sectional Assembly Drawing
in Appendix).

The receiving, protection, and installation of the lubrication system must be performed in accordance
with specifications set forth in Chapter 8 - `Lubrication Systems from API Recommended Practices
686/PIP REIE 686, First Edition.

Step 2
Install the dowel pins in the pump drive-end feet by
reaming the foot and baseplate for the tapered
dowel provided.

COMMISSIONING OF EQUIPMENT
Commissioning of all equipment must be performed
in accordance with specifications set forth in Chapter
9 -`Commissioning from API Recommended Practices 686/PIP REIE 686, First Edition.

Step 3

DA SLV/KTB

Position the gib blocks to obtain a 0.010 inch(.25


mm) clearance between the gib block and the side of
the non-drive end pump foot as noted on the attached figure. Drill and tap the capscrew holes for
the gib blocks.

Gib Block Installation Sketch

2-16

Operation
The head of liquid necessary to push the required
flow into the pump is called the Net Positive Suction
Head. This value, more commonly called NPSH, is
measured above the vapor pressure of the liquid at
the pumping temperature.

TECHNICAL DATA
These pumps are furnished for a particular service
condition. Changes in the hydraulic system may
affect the pumps performance adversely. This is
especially true if the changes reduce the pressure at
the suction flange or if the liquid temperature is increased. In case of doubt, contact the nearest
Flowserve Office.

There are two kinds of NPSH. The NPSH required


by the pump, as shown on the pump curve, is the
head needed to cover the losses in the pump suction. The second NPSH is that available in the system, taking into account friction loss in suction piping, valves, fittings, etc. In all cases, the NPSH
Available (measured above vapor pressure) must
exceed the NPSH Required in order to push the liquid into the pump.

SPECIFIC GRAVITY
The capacity and total head of liquid developed by a
centrifugal pump are fixed for every point on the
curve and are always the same for the same speed.
Neither capacity nor total head will be affected by a
change in the specific gravity of the liquid pumped.
However, since the developed pressure and the
brake horsepower to drive the pump are a function
of the specific gravity of the liquid, both will be affected in direct proportion by any change in specific
gravity. Therefore, a change in specific gravity will
affect the discharge gage pressure. Any changes
should be noted, in that they may overload the
pumps driver.

OPERATING PRECAUTIONS

WARNING
DO NOT WIPE DOWN IN THE VICINITY OF ROTATING PARTS. IF UNUSUAL NOISE OR VIBRATIONS OCCUR, SECURE THE PUMP AS
SOON AS POSSIBLE.

VISCOSITY

WARNING

The pump is designed to deliver rated capacity at


rated head for a liquid with a particular viscosity.

THE UNIT MUST NOT BE OPERATED UNLESS


COUPLING GUARD IS BOLTED IN PLACE.
FAILURE TO OBSERVE THIS COULD RESULT IN
INJURY TO OPERATING PERSONNEL.

When contemplating operation at some viscosity


other than that for which the pump was originally
designed, the changed conditions should be referred
to Flowserve Corp. for our recommendations.

CAUTION

DA SLV/KTB

CHANGING PUMP SPEED

LUBRICATION SYSTEM MUST BE IN OPERATION BEFORE STARTING THE UNIT.

Changing the speed of a centrifugal pump changes


the capacity, total head and brake horsepower. The
capacity will vary in a direct ratio with the speed,
whereas the total head will vary as the ratio of the
speed squared. The brake horsepower will vary as
the ratio of the speed cubed, except in cases where
the speed change also reduces the efficiency of the
pump.

WARNING
WHEN PUMP IS EQUIPPED WITH MANIFOLDED
VENT AND DRAIN LINES, EACH LINE MUST BE
EQUIPPED WITH AN INDIVIDUAL VALVE TO
PREVENT ANY LIQUID FROM A HIGH PRESSURE LINE FLOWING INTO A LOW PRESSURE
LINE. THESE VALVES MUST BE KEPT IN THE
CLOSED POSITION DURING PUMP OPERATION.

NET POSITIVE SUCTION HEAD (NPSH)


Any liquid, hot or cold, must be pushed into the impeller of the pump by some absolute pressure, such
as the atmosphere or the pressure of the vessel
from which the pump takes its suction.

3- 1

Operation
A. If pump is equipped with a mechanical seal, ensure it is properly assembled and tightened (refer to
STUFFING BOX section).

WARNING
OBSERVE EXTREME CAUTION WHEN VENTING
AND/OR DRAINING HAZARDOUS LIQUIDS.
WEAR PROTECTIVE CLOTHING IN THE PRESENCE OF CAUSTIC, CORROSIVE, VOLATILE,
FLAMMABLE, OR HOT LIQUIDS.
DO NOT
BREATHE TOXIC VAPORS. DO NOT ALLOW
SPARKING, FLAMES, OR HOT SURFACES IN VICINITY OF THE EQUIPMENT.

CAUTION
MOST CARTRIDGE SEALS ARE EQUIPPED WITH
A SPACER BETWEEN THE GLAND PLATE AND
DRIVE COLLAR. THIS SPACER MUST BE REMOVED BEFORE STARTING UNIT.
B. If pump is equipped with a packed box, insure
box is properly packed (refer to STUFFING BOX
section).

CAUTION
TO MAINTAIN CLOSE RUNNING CLEARANCES
AND BEARING LUBRICATION, THE PUMP
SHOULD NOT BE OPERATED BELOW THE
SPEED OF 1800 RPMS.

6. Ensure coupling is properly aligned and lubricated, and pump and driver are properly dowelled
(refer to SHAFT/COUPLING ALIGNMENT procedure).

1. Never operate the pump with suction valve


closed.

7. Ensure coupling guard is in place.

2. Never operate pump unless it is filled with liquid


and vented.

8. Check torque of all bolting and plugs for tightness.

3. Never operate the pump unless a liquid source is


available.

PUMP INSTRUMENTATION SET POINTS

PRE-OPERATIONAL CHECKS

The following set points apply to these DA Pumps


which use a Sleeve/KTB (Kingsbury Thrust Bearing)
arrangement.

At initial start-up and after the equipment has been


overhauled.

Bearing metal temperature


o
o
o
o
Normal
140 to 180 F.(60 to 82 C.)
o
o
Alarm
190 F.(88 C.)
o
o
Shutdown
200 F.(93 C.)

1. Ensure pump and piping are clean. Before putting the pump into operation, it should be thoroughly
flushed to remove the rust preventive as well as any
foreign matter which may have accumulated during
installation.

Bearing housing vibration


Normal
.1 to .3in/sec(2.5 to 7.6 mm/sec)
Alarm
.4 in/sec(10.2 mm/sec)
Shutdown
.5 in/sec(12.7 mm/sec)

DA SLV/KTB

Take all possible care not to contaminate your system.

Radial Shaft Vibration


Normal
1 to 2 mils (.0254 - .051 mm)
Alarm
3 mils (.0762 mm)
Shutdown
4 mils (.1016 mm)

2. Clean and flush bearing housings. Fill reservoir


with oil to the proper level (see LUBRICATION).
3. Ensure rotor is aligned within casing (see MAINTENANCE).

INITIAL START-UP PROCEDURE

4. Turn rotor by hand or with strap to make sure it


turns freely.

1. Close discharge valve if valve is not already


closed.

5. Check stuffing box.

2A. Prepare the driver for start-up in accordance


with the manufacturers instructions.
3- 2

Operation
2B. Refer to lube oil system instructions and drawings to prepare system for start-up.

CAUTION
IF PUMP STOPS ABRUPTLY WHEN DRIVER IS
SHUT DOWN, INVESTIGATE FOR PUMP BINDING. TAKE NECESSARY REMEDIAL ACTION BEFORE RESUMING OPERATION.

3. Warm-Up Pump.
Avoid severe thermal shocks to the pump as a result
of sudden liquid temperature changes. The pump
must be preheated prior to start-up. Unless otherwise specified, the external temperature of the caso
o
ing must be within 100 F.(55.6 C.) of the temperature of the liquid to be pumped at time of start-up.
Due to the heavy metal sections, the casing will lag
the liquid temperature during such changes, and
severe temperature stresses and subsequent misalignment of machined fits may result. Pre-heating
is accomplished by circulating a small amount of hot
fluid through the casing by utilizing vents, drains or
bypass from discharge. Preheat pump slowly at a
o
o
rate not to exceed 100 F.(55.6 C.) per hour.

10A. Starting the driver (motor driven).


Prepare the driver for start-up in accordance with the
manufacturers instructions.
Start the driver.
10B. Starting the driver (turbine driven).
Prepare the turbine for start-up in accordance with
the manufacturers instructions.
Start the turbine and bring it up to speed quickly.

4. Prime pump and ensure pump suction valve is


open.

11. As soon as pump is up to rated speed, slowly


open discharge valve.
This will avoid abrupt
changes in velocity and prevent surging in the suction line.

CAUTION
BEFORE STARTING OR WHILE OPERATING THE
PUMP, THE CASING AND SUCTION LINE MUST
BE COMPLETELY FILLED WITH THE LIQUID BEING PUMPED. THE ROTATING PARTS DE-PEND
ON THIS LIQUID FOR LUBRICATION, AND THE
PUMP MAY SEIZE IF OPERATED WITHOUT LIQUID.

12. Check to see that auxiliary oil pump (when supplied) has shut down.

OPERATING CHECKS

WARNING

DA SLV/KTB

5. Ensure pump recirculating line (if required) is


open and free of obstructions.
6. Check that pump is vented by observing leakage
from casing vent and seal piping vent. Close vent
when liquid is emitted.

IN THE INTEREST OF OPERATOR SAFETY, THE


UNIT MUST NOT BE OPERATED ABOVE THE
NAMEPLATE CONDITIONS. SUCH OPERATION
COULD RESULT IN UNIT FAILURE CAUSING INJURY TO OPERATING PERSONNEL.

7A. If pump is equipped with a mechanical seal,


make sure seal piping is turned on.

CAUTION
OPERATION AT LOW FLOWS RESULTS IN PUMP
HORSEPOWER HEATING THE LIQUID. A BYPASS MAY BE REQUIRED TO PREVENT VAPORIZATION AND SUBSEQUENT PUMP DAMAGE.
MECHANICAL DAMAGE MAY RESULT
FROM CONTINUOUS OPERATION AT FLOWS
LESS THAN 25% OF DESIGN OPERATING POINT
(see General Arrangement drawing notes).

7B. If pump is equipped with a packed box, turn on


cooling liquid.
8. Start auxiliary oil pump (when supplied).
9. Check pump rotating by starting unit momentarily.
The direction of rotation is shown on PUMP DATA
SHEET (1-1). Note the pump coasts to a gradual
stop.

3- 3

Operation
Immediately after start-up, and frequently during
running, check the following:

NORMAL START-UP

1. Check suction and discharge pressure gauges.

The starting procedure to be followed for normal


start-up is the same as that for initial starting.

2. Check pressure gauges on each side of suction


strainer.

SECURING THE PUMP


1A. Motor Driven.

3. Check for excessive leakage at stuffing box gland


area.

De-energize driver circuit.

A. If pump is equipped with a mechanical seal, there


should be no visible leakage to the naked eye.

1B. Turbine Driven.


Stop turbine-driven pumps by manually tripping the
overspeed trip.

B. If pump is equipped with stuffing box packing,


leakage should be 1 oz. 2 oz./min.(30 ml 59
ml/min.)

2. The pump should be shut down rapidly to protect


the internal wearing parts which are lubricated by the
liquid being pumped.

4. Check for unusual noises.


5. Check oil pressure of bearing inlets and sight flow
indicator.

Lubrication is reduced when a pump is stopped


slowly, and seizure could result.

6. Check oil rings to ensure they are rotating (eye


protection required optional construction).

NOTE
If pump stops abruptly when driver is shut down, investigate for pump binding. Take necessary remedial action before restarting pump.

7. Check for adequate flow of cooling liquids.


8. After unit has been operated a sufficient length of
time to reach normal operating temperature and condition, the unit is to be shut down and a HOT coupling alignment check must be made (refer to
SHAFT/COUPLING ALIGNMENT procedure).

3. Close the pump suction and discharge valve.


4. Close valve in bypass line.
5. Turn off auxiliary oil pump and cooling liquid
(when supplied).

WARNING
OPERATION OF THE UNIT WITHOUT PROPER
LUBRICATION CAN RESULT IN OVERHEATING
OF THE BEARINGS, BEARING FAILURES, PUMP
SEIZURES AND ACTUAL BREAKUP OF THE
EQUIPMENT EXPOSING OPERATING PERSONNEL TO INJURY.
DA SLV/KTB

6. If pump is subjected to freezing temperatures, the


pump must be drained of liquid to prevent damage to
pump.

3- 4

Troubleshooting
The following chart presents information that is useful in the analysis of some typical pump performance problems. The Pump Data Sheet, assembly drawings, parts list, and performance curve provided with each unit
should be available when investigating performance problems. Assembly and disassembly procedures are included in the MAINTENANCE section.
FOR 24-HOUR EMERGENCY REPAIR SERVICE, CALL 1-800-547-8671.
A listing of the Flowserve Pump Repair Centers is included at the end of this section.
TROUBLESHOOTING CHART
Trouble
Insufficient capacity and/or pressure

Possible Cause
Suction Pressure or speed too low

Corrective Action
Open suction valve wide. Check
power supply for correct voltage.

Incorrect direction of rotation.

MS

DA SLV/KTB

Pump loses prime after starting

Pump Vibration

A. If pump is motor driven:

Refer to motor instruction manual


and reconnect motor leads.

B. If pump is turbine driven:

Contact turbine manufacturer.

Excessive amount of air or vapors


in the fluid

Check suction system for air leakage and correct.


Vent air.
Tighten flange bolts.

Foreign material in suction line

Dismantle suction line and remove


foreign material.

Mechanical Defects:
Impeller damaged.
Sheared impeller keys.
Broken or damaged coupling.

Dismantle pump and correct.

Insufficient liquid supply

Ensure that suction valve is wide


open. Check for proper liquid level.

Excessive amount of air or vapor in


the liquid

Check suction system for air leakage and correct.

Clogged impeller

Dismantle pump and correct.

Suction pipe clogged.

Remove foreign material.

Loose Mounting or coupling bolts.

Tighten bolts.

Coupling

Check alignment and correct.

4- 1

Troubleshooting

Trouble

Possible Cause

(Contd)
Pump vibration

Pump overloads driver

DA SLV/KTB

Mechanical seal
used) overheats

Vent air and check suction for leaks.


Tighten flange bolts.

Foreign material in impeller causing


unbalance

Dismantle pump and remove any


foreign material.

Mechanical Defects:
Shaft bent.
Bearings worn.

Dismantle pump and replace part or


parts causing vibration.

bearing

(when

A. If pump is motor driven:

Refer to motor instruction manual


and check power supply for correct
frequency.

B. If pump is turbine driven:

Check steam pressure to turbine.

Pump bearings seize or rotating


element binds

Dismantle pump and replace part or


parts causing seizures, or binding.

Pump binding at running fits

Dismantle pump and realign rotor in


casing.

Improper lubrication

Replenish oil with proper grade lubricant.

Rotor not centered in volutes

Check rotor centralization.

Insufficient oil.
Contaminated oil.

Add oil.
Drain and clean reservoir.
Refill with clean oil.

High Oil Temperature

Connect cooling liquid to lube oil


cooler.

Insufficient cooling water to seal

Obstruction in seal water piping.


Remove and clean.

Mechanical seal not properly set.


(Check for cracked stationary face/
rotating face)

Refer to SHAFT SEALING pages.

Cavitation

Check that pump is primed, check


for high suction temperature, increase static head, check for obstruction in suction line.

MS

Pump is noisy

gland

Air or gas in liquid

Speed too high

Pump stops abruptly


High
pump
thrust
temperature rise

Corrective Action

4- 2

Troubleshooting

Trouble

Possible Cause

Corrective Action

(Contd)
Pump is noisy

Loose Parts

Tighten or replace defective part.

Noise in driver

Check driver with stethoscope.

MS

DA SLV/KTB

Check driver instruction book for troubleshooting instructions.

4- 3

Troubleshooting

MS

DA SLV/KTB

FLOWSERVE CORPORATION PUMP SERVICE CENTERS


Baton Rouge SC
4152 Rhoda Drive
Baton Rouge, LA 70816
Phone: 225-293-5780
Fax: 225-281-8134

Beaumont SC
2920 West Cardinal Drive
Beaumont, TX 77705
Phone: 409-842-5594
Fax: 409-842-5958

Benecia SC
6077 Egret Court
Benecia, CA 94510
Phone: 707-745-3773
Fax: 707-746-1568

Boothwyn SC
11 Creek Parkway
Boothwyn, PA 19061
Phone: 610-859-0700
Fax: 610-859-0711

Carson SC
24351 S. Wilmington
Carson, CA 94510
Phone: 310-522-0925
Fax: 310-522-0758

Charlotte SC
4816 Worth Place
Charlotte, NC 28216
Phone: 704-399-0446
Fax: 704-393-7296

Cleveland SC
6250 Halle Drive
Cleveland, OH 44125
Phone: 216-524-6155
Fax: 216-642-5741

Customer Field Service


942 Memorial Parkway
Phillipsburg, NJ 08865
Phone: 908-859-7066
Fax: 908-859-7836

Elgin SC
695 Church Road
Elgin, IL 60123
Phone: 847-742-9510
Fax: 847-742-9593

Fairfield SC
142 Clinton Road
Fairfield, NJ 07004
Phone: 973-227-4565
Fax: 973-227-6615

Greer SC
2431 S. Highway #14
Greer, SC 29650-8201
Phone: 864-879-7276
Fax: 864-879-0997

Houston SC
6832 Wynnwood Lane
Houston, TX 77008
Phone: 713-868-6666
Fax: 713-868-6630

Leduc/Edmonton SC
4405 70th Avenue
Leduc, Alberta
Canada T9E 7E6
Phone: 780-986-7100
Fax: 403-986-4854

Parts Distr. Center (Moosic)


Rocky Glen Road
Rocky Glen Industrial Park
Moosic, PA 18507
Phone: 717-451-2200

Pittsburgh Parts
1885 Mayview Road
Bridgeville, PA 15017
Phone: 412-257-4600
Fax: 412-257-3162

Sarnia SC
235 Henry Drive RR No. 4
Sarnia, Ontario
Canada N0N 1T0
Phone: 519-336-3614
Fax: 519-336-7410

Scranton Parts
942 Griffin Pond Road
Clark Summit, PA 18411
Phone: 570-586-8800
Fax: 570-587-5006

Tampa SC
6405 Badger Drive
Tampa, FL 33610
Phone: 813-621-8865
Fax: 813-626-1274

Texas City SC
146 FM 519 Building 4C
Texas City, TX 77568
Phone: 409-935-1977
Fax: 409-935-2269

Vancouver SC
10400 N.E. 13th Street
Vancouver, WA 98686
Phone: 360-573-5211
Fax: 360-574-7656

Wasilla SC
2051 Foundry Way
Wasilla, AK 99654
Phone: 907-376-0550
Fax: 907-376-0659

Woodbridge SC
120 Vinyl Court
Woodbridge, Ontario
Canada L4L 4A3
Phone: 905-856-1140
Fax: 905-856-2010

4- 4

Lubrication
A check valve is mounted in the auxiliary oil pump
discharge line to prevent oil from returning to the oil
reservoir when the main oil pump is running and the
auxiliary oil pump is shut down.

LUBRICATION SYSTEM

WARNING
OPERATION OF THE UNIT WITHOUT PROPER
LUBRICATION CAN RESULT IN OVERHEATING
OF THE BEARINGS, BEARING FAILURES, PUMP
SEIZURES AND ACTUAL BREAKUP OF THE
EQUIPMENT, EXPOSING OPERATING PERSONNEL TO INJURY. REFER TO LUBE OIL PIPING/CONSOLE DRAWING.

Normal lube oil pressure is 15 20 psig (103 137


Kpa).

LUBRICATING OIL
Remember that oil requires frequent replenishment
at normal operating temperatures and very frequent
replenishment at elevated operating temperatures.
Oil is always subject to gradual deterioration from
use and contamination from dirt and moisture. This
deterioration and contamination will, in time, be
harmful to the bearings and can cause premature
wear. For these reasons, oil should be checked for
contamination and deterioration regularly.

MS

DA SLV/KTB

Oil is supplied to the pressure lubrication system by


one of the two oil pumps. The main oil pump is
mounted on a support head (6-172) which is bolted
to the thrust end bearing body and cap (6-021/023)
and is driven by the main pump shaft via a Lovejoy
coupling (6-185).
A motor-driven auxiliary oil pump is furnished to
supply oil to the pressure lubrication system during
starting and stopping periods. At time of start-up,
the auxiliary oil pump must be started manually.
When the main oil pump supplies the required oil
pressure, the auxiliary oil pump will automatically
stop by action of an auxiliary oil pump pressure
switch mounted in the lubrication system. Can also
be manually shutdown. The auxiliary oil pump will
remain in the standby state, until such time as the
lubricating oil pressure falls to a pre-determined
value, at which time the auxiliary oil pump pressure
switch will automatically start the auxiliary oil pump.

The frequency of oil change depends on the operating conditions and the quality of the lubricant. Oil
should be checked for deterioration and contamination weekly during periods of operation. Mineral oils
oxidize and should be replaced at no more than
three month intervals when operated continuously in
o
o
o
o
the 160 -180 F.(71 -82 C.) range. Longer intervals
between replacement may be possible at lower operating temperatures, but three month intervals are
recommended to protect against normal oxidation,
contamination and deterioration.

During operation, oil is taken from the oil reservoir by


the oil pump and is directed to the oil cooler. From
the oil cooler, the oil is directed through the oil filter
and is then supplied to the pump/driver bearings. A
back-pressure relief valve mounted in the lubrication
system maintains the required system oil pressure of
15 psi. The system is additionally equipped with a
low pressure, pressure switch which trips the unit
when the oil pressure in the lubrication system decreases to a pre-determined value or prevents the
starting of the unit until adequate oil pressure is established. A gravity assisted, sloped oil-return line
conducts the oil from the pump/driver bearings back
to the system reservoir.

Straight mineral oil without additives are generally


preferred for bearing lubrication. It should preferably
be of the turbine type and not contain free acid, chlorine, sulfur or more than a trace of free alkali. Quality
mineral oils with a minimum Viscosity Index (VI) of
95 are recommended. Lubricating oils are identified
by an ISO Viscosity Grade (VG) Number. The VG
o
o
Number is the viscosity of the oil at 40 C.(104 F.) in
centistokes. In the majority of instances, a turbine
oil with a VG Number of 32 (nominally equivalent to
SAE 10) will meet bearing lubrication requirements
(see OIL TEMPERATURE).

OIL SPECIFICATIONS

5- 1

Lubrication

ASTM STANDARDS
for mineral oils

Oil Characteristics
Saybolt Viscosity (SSU)
o
o
100 F.(38 C.)

158 Seconds

Pour Point

20 F.(-7 C.)

Flash Point

400 F.(204 C.)

Recommended ISO Viscosity


Grade (VG) Number

32

In a majority of instances, ISO 32 (nominally equivalent to SAE 10 turbine type oil) will meet the above specifications.
LUBRICANT MUST BE COMPATIBLE WITH ALL PARTS REQUIRING LUBRICATION.
Refer to lube, seal, and lube oil console piping drawings and notes for information pertaining to your system.

OIL TEMPERATURE

2. Heat the bearing housing(s) using heat tape (or


other suitable means).

Oil temperature entering the plain/thrust end bearo


o
ings should be maintained between 60 F.(15.6 C.)
o
o
and 160 F.(71 C.).

3. Circulate warm liquid through the cooling jacket


or immersion cooler (if supplied).

4. Utilize oil with a lower viscosity, or VG number.

Alarm temperature is 175 F.(80 C.) with shut down


o
o
temperature set at 185 F.(85 C.).

NOTE
If bearing oil temperature exceeds the above mentioned limits, cooling liquid to the lube oil cooler will
have to be increased.

ISO 32 is recommended for continuous operating oil


o
o
o
temperatures between 60 F.(16 C.) and 120 F.
o
(49 C.), with a minimum startup temperature of
o
o
40 F.(4 C.). For startup when oil temperature is beo
o
low 40 F.(4 C.), oil preheating is recommended.

IMPORTANT
o

MS

DA SLV/KTB

The minimum bearing oil temperature is 60 F.


o
(16 C.). If necessary, prior to startup, one of the following procedures should be employed:

CLEANING THE LUBRICATION SYSTEM


PRIOR TO OPERATION

1. Drain the oil in the bearing housing(s) and replace with warm oil.

Before operating the pump, the lubrication system


should be thoroughly cleaned to remove any foreign
matter that may have accumulated during shipment,
storage or installation.

5- 2

Lubrication
8. Fill oil reservoir with oil that is proper grade and
viscosity in accordance with lubrication recommendations.

To clean the lubrication system, proceed as follows:


1. Remove the bearing caps, bearing linings, thrust
shoes and drain plugs. (Refer to MAINTENANCE
section.)

9. Flush through lube oil system filters for a period


of 4 hours. After 4 hour period, shut-down and inspect temporary strainers.

2. Flush out the bearing housings with kerosene or


other suitable solvent.

NOTE
3. Wash the bearing lings/thrust shoes with a suitable solvent.
During flushing operation, examine the piping for
leaks and correct as necessary. Also check for any
obstructions that will interfere with free flow of oil to
bearings.

4. Flush the entire lubrication system following the


procedure below. (Also refer to Flowserve P&I diagram in Appendix of this manual.
5. Break open bearing supply pipe flanges and install 100 mesh screens in the supply line.

10. If screens are not clean, replace with new,


clean screens and repeat Steps 9.

6. Remove main journal bearings (shell type) from


bearing housing bearings can be rolled-out.
Check for anti-rotation pin.

11. If the screens are clean, clean lube oil reservoir


tank, install new, clean filter cartridges, and wipe out
bearing housings.

NOTE
12. Replce drain plugs, piping and install bearing
close system and refill with oil that is proper grade
and viscosity in accordance with lubrication recommendations.

If temperature probes are supplied, remove them


prior to rolling-out bearings.

13. Lubrication system is now ready for routine


start-up operation.

7. Remove shoes from KTB bearing (refer to KTB


drawing in Appendix of this manual.

WARNING

NOTE

OPERATION OF THE UNIT WITH INCORRECT


OIL LEVEL SETTING CAN RESULT IN OVERHEATING OF THE BEARINGS, LACK OF LUBRICATION TO THE BEARINGS, BEARING FAILURES,
PUMP
SEIZURES
AND
ACTUAL
BREAKUP OF THE EQUIPMENT, EXPOSING OPERATING PERSONNEL TO INJURY.

Observe position of shoes as they must be reassembled in the same position and orientation.
NOTE

MS

DA SLV/KTB

Remove temperature probes and proximity probes (if


supplied) prior to removing shoes.

5- 3

Shaft Sealing
MECHANICAL SEAL

MECHANICAL SEAL REMOVAL

Your pump is typically shipped with the mechanical


seal already installed. All mechanical seals are of
the cartridge type design. The mechanical seal is
designed to suit each application. This creates the
correct seal loading face when seal gland is bolted
in place.

To remove mechanical seal from pump:


1. Install setting plates/eccentric washer in place.*
2. Loosen drive collar.
3. Remove gland bolting.

Cartridge type mechanical seals are preset at the


seal manufacturers facility and require no field settings. The seal installation should be checked before startup.

4. Slide sleeve with mechanical seal from shaft.


Seal may be disassembled/inspected/reassembled
per seal manufacturers drawing and instructions in
Appendix of this manual.

Refer to the mechanical seal manufacturers drawing


and instructions found in the Appendix of this manual for detailed information.

*NOTE

MS

DA SLV/KTB
B/B MS

After reassembly of seal, setting plates/eccentric


washers must be removed before start-up.

6- 1

Maintenance
GENERAL

WARNING
WHEN PUMP IS HANDLING HOT LIQUID, EXTREME CARE MUST BE TAKEN TO ENSURE
SAFETY OF PERSONNEL WHEN ATTEMPTING
TO DRAIN PUMP. HOT PUMPS MUST BE ALLOWED TO COOL BEFORE DRAINING.

Your pump is a precision machine. Take every precaution to avoid damage or even slight burrs to the
shaft bearing areas, as well as any other ground
finished surface when dismantling your pump.
It should be understood that the information contained in this manual does not relieve operating and
maintenance personnel of the responsibility of exercising normal good judgement in operation and care
of the pump and its components.

B. If handling caustic liquid.

WARNING
WHEN PUMP IS HANDLING CAUSTIC LIQUID,
EXTREME CARE MUST BE TAKEN TO ENSURE
SAFETY OF PERSONNEL WHEN ATTEMPTING
TO DRAIN PUMP. PROTECTIVE DEVICES OF
SUITABLE PROTECTIVE MATERIALS MUST BE
WORN WHEN DRAINING PUMP.

Before performing any disassembly, maintenance


and/or inspection on the unit, the following steps
should be taken and warnings observed.
1. Tag driver controls in the off position.

WARNING

C. If on vacuum service.

BEFORE ATTEMPTING ANY INSPECTION OR


REPAIR ON THE PUMP, THE DRIVER CONTROLS
MUST BE IN THE OFF POSITION, LOCKED
AND TAGGED TO PREVENT INJURY TO PERSONNEL PERFORMING SERVICE ON THE PUMP.

WARNING
BEFORE ATTEMPTING ANY MAINTENANCE
WORK ON PUMPS IN VACUUM SERVICE,
PUMPS MUST BE ISOLATED FROM SUCTION
AND DISCHARGE SYSTEM THEN CAREFULLY
VENTED TO RETURN PRESSURE IN PUMP CASING TO ATMOSPHERE PRESSURE.

2. Isolating pump.

WARNING
BEFORE ATTEMPTING TO DISASSEMBLE PUMP
PUMP MUST BE ISOLATED FROM SYSTEM, BY
CLOSING SUCTION AND DISCHARGE SYSTEM
VALVES, DRAINED OF LIQUID AND COOLED, IF
PUMP IS HANDLING HOT LIQUID.
3. Draining pump

DA SLV/KTB

A. If handling hot liquids.

7- 1

Maintenance
PREVENTIVE MAINTENANCE SCHEDULE
Althrough your Flowserve pump has been designed for extended, trouble-free service, certain preventive maintenance measures should be performed on a regular basis to ensure optimum performance. A well planned program of routine maintenance is the best assurance of dependable operation. The following preventive maintenance (PM) inspections are suggested as a minimum, and may be supplemented by the experience of the operating personnel.
Preventive maintenance inspections should include the following
Preventive Maintenance Item

Instructions

Frequency

Check pressure differential between the gauges


the gauges located on each side of the strainer.

Daily

Pump Suction and


Discharge Flow Rates

Check suction and discharge pressure gauges


for proper pump operation.

Daily

Mechanical Seal

Inspect visually

Daily

Instrumentation

Check all related pressure gauges, temperature


Detectors, etc. to detect any abnormalities.

Daily

Shaft Rotation
(Down Periods Only)

During extended down periods rotate the shaft


by hand 1-1/4 times to ensure bearing lubrication
and to prevent shaft binding.

Weekly

Auxiliary Piping

Check for leakage around connections, ect.

Weekly

Shaft/Casing Vibration

Review all vibration data for any abnormalities


And/or sudden changes in levels.

Weekly

Bolting Tightness

Check all external bolting for proper tightness.

Monthly

Cleanliness

General clean-up soiled areas

Quarterly

Oil System

Refer to Lubrication System section of instruction


manual.

Periodically

DA SLV/KTB

Suction Strainer
(When Used)

7- 2

Maintenance
TORQUE VALUES

WARNING
USE EXTREME CAUTION NOT TO EXPOSE
MAINTENANCE PERSONNEL TO HOT LIQUIDS
WHEN REMOVING AUXILIARY PIPING OR
DRAINING BEARING HOUSINGS.

For pump hold-down torque value (and driver, if


Flowserve supplied) see PUMP DATA SHEET (1-1).
Other torque values are listed on the Assembly
Drawings included in Appendix of this manual. They
are selected to achieve the proper amount of prestress in the threaded fastener. Maintenance personnel must insure that threads are in good condition (free of burrs, galling, dirt, etc.) and that commercial thread lubricant is used. Torque should be
periodically checked to assure that it is at the recommended value.

2. Remove temperature detectors (if supplied) from


bearing housings.
3. When mechanical seal is used, loosen seal gland
bolting.
THRUST BEARING REMOVAL

WARNING

1. Remove capscrews (6-118D) from support head


(6-172). Remove support head [with gasket (6-262)
if supplied]. Place support head on blocking. Remove shim pack (6-257B).

WHEN REASSEMBLING PUMP, ALL FASTENERS


MUST BE TIGHTENED TO THE PROPER
TORQUE VALUE. FAILURE TO OBSERVE THIS
WARNING COULD RESULT IN INJURY TO OPERATING PERSONNEL.

NOTE
Tag and record thickness of shims (6-257B) for reassembly.

COUPLING REMOVAL

If pump is equipped with shaft-driven main oil pump


(6-219), the Driver Half and Rubber Spider of
coupling (6-185) should be removed and wired to
the support head (6-172).

Remove coupling guard. Remove coupling bolting


and remove the spacer piece (if used). Loosen setscrews in coupling nut and remove nut.
The coupling hub has a shrink fit to the pump shaft.
The use of a puller and heat will be required to remove it from the shaft.

2. Loosen setscrew (6-259) in pump-side flinger (6157) and slide it back on the shaft towards the stuffing box.

NOTE

3. Remove capscrews (6-118C) and dowel pins (6029C) from bearing cap (6-023). Rig eyebolt (6-333)
in bearing cap to an overhead hoist and lift bearing
cap from bearing body and place on blocking on the
floor.

DA SLV/KTB

Remove pump half coupling hub by heating to apo


o
proximately 300 F.(149 C.) in successive stages
from periphery of coupling toward center.
If
equipped with a gear type coupling, NEVER APPLY
AN OPEN FLAME TO COUPLING HUB TEETH.

4. The inboard and outboard thrust bearing assembly (6-325) can now be removed from the bearing
body (6-021). Tag assemblies to insure they will be
returned to their original position. Refer to Kingsbury drawing and instructions in Section 8 of this
manual.

DISMANTLING PROCEDURE
1. Remove all auxiliary piping and instrumentation
that will interfere with disassembly and drain oil from
bearing housings.

5. Remove upper half of bearing lining (6-191) with


pin (315A). Using a bar and a block of wood under
pump shaft, raise shaft slightly and roll out the lowerhalf bearing lining.

7- 3

Maintenance
REMOVAL OF STUFFING BOX PARTS

6. Install two eyebolts in diagonally opposite corners


of bearing body (6-021) and rig to an overhead hoist.
Remove dowel pins (6-029A) and capscrews (6118A) holding bearing body to casing and remove
bearing body and place on blocking on the floor.

1. If pump is equipped with a mechanical seal (4429) or stuffing box packing (4-064), refer to SHAFT
SEALING section of this manual and remove the
seal or stuffing box packing.

7. Loosen setscrews (6-259B) in locknut (6-128)


and remove locknut using a pin spanner wrench (not
provided).

2. If pump is equipped with cooled stuffing box extensions (4-264), remove nuts (4-279B) and washers
(4-246B). Stuffing box extensions with their O
rings (4-456B) can now be removed from pump.

8. Remove thrust collar (6-028) and key (6-054). It


may be necessary to apply heat to thrust collar to
remove it. Do not allow temperature to rise above
o
o
220 F.(104 C.) when heating thrust collar. Temperature can be checked with tempil stick.

ROTOR REMOVAL
1. Remove capnuts (3-179) washers (3-246) holding
upper half casing to lower half. Remove dowel pins
(3-029C). Using jack screws (3-118B) in lower half
casing, break the seal between upper and lower half
casings. Rig upper half casing to overhead hoist
using two cast lifting lugs.

9. Remove shims (6-257A). Record thickness of


shims and tie together to prevent shims from being
separated. Remove inboard thrust-bearing seal ring
and flinger (6-157) from pump shaft.
PLAIN BEARING REMOVAL

WARNING

1. Loosen setscrew (5-259B) from coupling-side


flinger (5-157) and remove flinger from end of shaft.

THE CAST LIFTING LUGS PROVIDED ON UPPER


HALF CASING ARE FOR LIFTING UPPER HALF
CASING ONLY. DO NOT LIFT PUMP FROM
THESE LUGS.

2. Loosen setscrew (5-259B) from pump-side flinger


(5-157) and slide flinger back on shaft towards the
stuffing box.

Carefully lift upper half casing and place on boards


to protect machined surfaces.

3. Remove capscrews (5-118A) and dowel pins (5029B) from bearing cap (5-023). Rig eyebolt (5-333)
in bearing cap to an overhead hoist and lift bearing
cap from bearing body and place on blocking on the
floor.

2. Rig slings (that will not damage shaft) around


shaft close to impellers. Rig rotor slings to overhead
hoist. Carefully lift rotor (3-184) from lower half casing and place on horses for further dismantling.

DA SLV/KTB

4. Remove upper half of bearing lining (5-191) with


pin (315). Using a bar and a block of wood under
pump shaft, raise slightly and roll out the lower-half
bearing lining.

NOTE
Casing wearing rings (3-006), channel rings (3-060),
throttling bushing (3-441), center bushing (3-407)
and stuffing box bushings (3-088) (if used) will be
removed with rotor.

5. Install two eyebolts in diagonally opposite corners


of bearing body (5-021) and rig to an overhead hoist.
Remove capscrews (5-118B) and dowel pins (5029A) from bearing body. Using the overhead hoist,
lower and remove bearing body from casing and
place on blocking on the floor.

Block to prevent rolling.


3. Remove stuffing box bushings (3-088) (if used)
and throttling bushing (3-441) from shaft ends.

6. Remove flinger (5-157) from pump shaft.

4. Remove casing rings (3-006) from first-stage impellers on each bank.

7- 4

Maintenance
B. Remove split ring (1-252).

5. Remove channel rings (3-060) from impeller back


ring at each impeller. Channel rings are horizontally
split and are held together by shoulder screws 329B).

C. Throttling sleeve (1-440) can now be removed


from end of shaft.

NOTE

D. Remove throttling sleeve key (1-291).

Channel rings are precision machined as a set, after


being dowelled. They should be match marked and
numbered for reassembly purposes. It is suggested
that the two halves be placed back together immediately.

3. Heat (per procedure on next page) and remove


the first outboard impeller (1-003B), split ring (1-252)
and impeller key (1-011).

6. Remove center bushing (3-407) from center


(back to back) impellers. Center bushing is horizontally split and held together by socket head capscrews (3-118A) and dowel pins (3-029A).

WHEN HEATING PARTS, GLOVES OR OTHER


SUITABLE PROTECTION MUST BE WORN.

WARNING

After impeller is heated, it will have to be pushed


toward the center of the pump, the split rings (1-252)
removed and quickly pulled from the end of the
shaft.

DISMANTLING THE ROTOR


1. If pump is furnished with a packed box, remove
the plain/thrust end shaft sleeves (4-008).

NOTE

A. Remove outboard retaining rings (4-397).

The shaft is step machined at each impeller fit to


ease the disassembly process. It is recommended
that each impeller be marked with stage number to
insure proper reassembly.

B. Pull shaft sleeve (4-008) towards shaft end as


far as it will go. This will move the shaft sleeve
key (4-291) over the retaining ring groove.

HEATING IMPELLERS FOR REMOVAL

C. Push shaft sleeve (4-008) back into position.

A. Apply heat (torch with fine tip) to periphery [outer


1.5 in.(38 mm)] of impeller until temperature
o
o
o
reaches 375 F.(191 C.) (minimum) to 400 F.
o
(204 C.) (maximum). Use tempilstick to determine temperature.

D. Remove shaft sleeve key (4-291).


E. Shaft sleeve (4-008) can now be removed from
shaft.

DA SLV/KTB

F. Remove inboard retaining rings (4-397).

2. Remove throttling sleeve (1-440).

B. Maintaining temperature between 375 400 F.


o
o
(191 204 C.) at the periphery, apply heat down
through the vane passages, thus heating the
hub.

The throttling sleeve (1-440) has a shrink fit to the


shaft and will have to be heated to be removed.
Heat throttling sleeve O.D. evenly throughout its
o
o
length to approximately 300 F.(149 C.), using a
torch with a fine tip.

C. Do not apply heat directly to shaft; this will cause


it to expand.
D. With periphery, shroud and hub at temperature,
remove impeller.

A. Push throttling sleeve (1-440) inboard (toward


impeller).

7- 5

Maintenance
2. Wire-brush the pump parts thoroughly. Clean off
all scale, carbon, etc. Examine parts for wearing,
corrosion and erosion.

E. If the impeller does not move freely off the shaft,


additional heat may be necessary. THIS HEATING SHOULD BE STARTED AT THE PERIPHERY OF THE IMPELLER, NOT THE HUB. (Additional heating of the hub area at this time will
tighten the impeller on the shaft, not loosen it.)
If the impeller still fails to come free, the impeller
and shaft should be allowed to cool completely
and the heating process repeated starting at
Step A.

3. Check shaft sleeve, throttling sleeve and center


sleeve for wear. Replace if required.
4. The casing rings/impeller rings are renewable
and should be replaced when badly grooved, and/or
when pump performance does not meet the system
requirements. Whenever it becomes necessary to
replace either wearing ring, both rings involved (casing ring and impeller ring) must be ordered and replaced as they are furnished standard size only [impeller rings approximately .08 in.(2.03 mm) oversize]. Be sure to re-establish the original running
clearance between the two wearing rings involved.
A. If new casing rings are used, make sure that they
seat in both the upper and lower half casing and that
the anti-rotation device is properly located in its respective lower half casing fit. The use of a scraper
on the ring to casing fit will help to fit the ring to the
casing.
B. Impeller ring removal and installation.
Remove impeller rings by removing the setscrews
(1-259) and machine off, or, grind two slots diametrically opposite across the face of the ring so it can be
split apart. Exercise caution if rings are removed by
grinding so as not to damage impeller hubs. See
sketch.

Single Suction Impeller


4. Remove casing ring (1-006) from the next impeller on the outboard impeller bank.
5. Repeat Steps 3 and 4 until all impellers are removed on the outboard impeller bank.

DA SLV/KTB

6. Remove center sleeve (1-408).


7. Continue to disassemble the impellers by repeating Steps 3 and 4 until all inboard impellers (1-003A)
are removed from the shaft.

INSPECTION & RENEWAL OF PARTS


1. Having completely dismantled the rotor, check
the shaft for runout using V blocks or rollers placed
under the normal bearing areas. Runout not to exceed .002 in.(.051 mm) TIR.
Impeller Ring Removal
7- 6

Maintenance
Make sure ring fit on impeller is free of nicks and
o
o
burrs. Heat new ring to 225 F.(107 C.) and install on
impeller. Drill and tap two new holes in impeller (located from clearance holes in ring) for No. 1024X1/4 setscrews spaced half the circular distance
from the previously used holes in the impeller. See
sketch below.

Grinding Impeller For Dynamic-Balance


5. If pump is equipped with a cooled stuffing box
extension (4-264) and has a packed box arrangement, the stuffing box extension will have a stuffing
box bushing (4-088) tack-welded in the bottom of the
box. If this bushing has to be removed for any reason, the tack welds will have to be ground off and
the bushing pressed from the extension. Do not reuse stuffing box bushing if removed from extension
for any reason.

Typical Screw Installation For Impeller Rings


NOTE
Impeller rings must be machined to re-establish
original diameter and running clearance, which can
be found on Assembly Drawing.

6. Clean the casing of all foreign material.


7. Renew all gasket and packing.

C. Dynamic-balance impeller.

PARTING FLANGE GASKET

DA SLV/KTB

Whenever an impeller is tampered with, (i.e. new


impeller, wear rings installed etc.) the impeller must
be dynamic-balanced before being reassembled to
shaft.

Remove all traces of old gasket (2-170) material.


When using any tool to remove gasket material, do
not gouge or mar machined surfaces. Use only
Flowserve recommended replacement materials.

To balance, remove metal from the front or back


shroud of the impeller at the point of unbalance. The
metal must be removed in such a manner that it will
not disfigure the contour of the surface from which it
is removed.

1. Using proper recommended 1/64 in.(.397 mm)


thick gasket material, locate and cut stud holes, using upper half casing as a template.
2. Lay gasket on lower half casing, using either a
gasket adhesive or a band of shellac approximately
1/2 in.(13 mm) wide on the outer edge of lower casing.
3. Place upper half casing on top of gasket and allow time for gasket adhesive or shellac to set up.

7- 7

Maintenance
First pass 50% specified torque value
Second pass - 90% specified torque value
Final pass 100% specified torque value

4. Remove upper half casing.


5. Using a sharp knife, cut gasket with downward
strokes only. Make sure all cuts are neat and exact,
especially on internal edges of casing. If this is not
done, the high pressure liquid will bypass and erode
the ring fits.

Tighten the cap nuts in the following sequence during each pass:
1. Torque both center cap nuts marked 0.

IMPORTANT

2. Torque the cap nuts shown in section number 3,


marked 0. Start approximately in the center of the
pump and proceed towards the suction nozzle.

Do not use any hammering device to cut gasket.

CAUTION
WHEN CUTTING PARTING FLANGE GASKET, DO
NOT FORGET TO CUT OPENING FOR DISCHARGE PASSAGE.

3. Torque the cap nuts on the opposite corner of the


pump as indicated in section 4, marked 0. Again,
start at the center of the pump and work towards the
opposite end.

PARTING FLANGE TORQUE PROCEDURE

4. Torque the cap nuts in section 5, marked 0, in a


similar manner.
5. Torque the cap nuts in section 6, marked 0, in a
similar manner.

DA SLV/KTB

View Of Parting Flange


Assemble upper half casing to lower half casing and
secure with washers and cap nuts listed on the parts
list for the casing. Torque the cap nuts in three or
more complete passes of increasing torque values
until the torque value on the pump assemble drawing are achieved.

6. Repeat the same sequence two or more times


using increasing torque values with each full pass.

Minimum recommended torque passes:

REASSEMBLY OF PUMP
When reassembling pump, all fasteners must be
tightened to the proper torque values. Refer to
TORQUE VALUE section of this manual.

7- 8

Maintenance
REBUILDING ROTOR

7. Assemble outboard impellers (1-003B) per Steps


1, 3 and 5.

CAUTION

8. Due to the heat required to assemble impellers to


shaft, the Loctite used to secure the impeller ring
setscrews may have broken down.

BEFORE UPSTAGING OR DESTAGING A PUMP


(ADDING OR REMOVING IMPELLERS), CONTACT FLOWSERVE ENGINEERED PUMP DIVISION, CUSTOMER SERVICE DEPARTMENT FOR
INSTRUCTIONS, TO AVOID PERMANENT DAMAGE TO THE PUMP ROTOR.

CAUTION
ALL SETSCREWS (1-259) USED TO HOLD
PELLER RINGS TO IMPELLERS MUST BE
MOVED. LOCTITE GRADE AVV IS TO BE
PLIED TO SETSCREWS AND SETSCREWS
PLACED.

1. Install center-stage impeller key (1-011), into keyway in shaft and pre-fit split rings (1-252) to shaft.
Do NOT align the split area of the ring with the impeller key. This will result in excess liquid leakage
thru the keyway and undue shaft washing. Ensure
o
that the ring split-to-key offset is at least 45 split
rings to fit snug in groove.

9. Install throttling sleeve key (1-291) to shaft and


pre-fit split rings (1-252) in shaft to fit snut in groove.
Heat the throttling sleeve and slide onto shaft far
enough to expose split ring groove. Install split ring
and pull sleeve back to seat against split ring.

2. All impeller bores and shaft outside diameters are


to be miked.

10. If pump is equipped with a packed box, install


retaining ring (4-397) to shaft at inboard side of shaft
sleeve. Lubricate O ring (4-456A) with silicone
grease and install to bore of shaft sleeve (4-008).
Install shaft sleeve to shaft.

CAUTION
IMPELLER-TO-SHAFT FIT MUST BE MINIMUM
OF .001 IN.(.0254 MM)-.003 IN.(.0762 MM) INTERFERENCE FIT.

NOTE

3. Heat the last inboard impeller (1-003A), using


heating procedure as outlined in the HEATING IMPELLERS FOR REMOVAL section, and assemble
to shaft, moving the impeller past the split ring
groove in the shaft. Quickly install split ring (1-252)
and pull impeller back to seat against split ring.

Extreme care is to be taken, when sliding shaft


sleeve onto shaft, not to damage O ring when it
passes over retaining ring groove and keyway.
Install shaft sleeve key (4-291) to shaft and push into
keyway in shaft sleeve.

NOTE

Install retaining ring (4-397) to shaft at outboard side


of shaft sleeve.

Make sure impellers are installed for proper rotation.

DA SLV/KTB

IMREAPRE-

INDICATE AND DYNAMIC-BALANCE ROTOR

4. Install center sleeve (1-408) from the opposite end


of shaft. Center sleeve is to be seated against the
impeller hub installed in Step 3.

1. Place the rotor assembly on V blocks or rollers.


The runout of all impeller wear rings and bushings is
not to exceed .003 in.(.0762 mm) TIR.

5. Place casing ring (1-006) on impeller front ring.

2. All pump rotors with more than 6 stages and/or


pumps running at speeds in excess of 3600 RPM
are to by dynamic-balanced.

6. Continue to assemble remaining inboard impellers (1-003A) per Steps 1, 3 and 5.

7- 9

Maintenance
The following formula is given as a guide for acceptable unbalance.

CAUTION
WHEN LOWERING ROTOR INTO CASING, BUSHINGS AND CASING RINGS MUST BE PROPERLY
LOCATED TO INSURE THAT LOCATING PINS (2315) ARE ENGAGED.
IF THIS IS NOT DONE,
PINS COULD BE BENT OR CRUSHED.

4W
U= N
U = Acceptable Unbalance in ounce inches.
W = Rotor Weight, Lbs.

7. Lower rotor into casing slowly, making sure it is


seated properly.

N = Maximum Rotor Speed.

8. Install the upper half of center bushing (3-407)


and seat taper dowel pins (3-029A). Install capscrews (3-118A) and tighten.

Refer to INSPECTION & RENEWAL OF PARTS


section for Grinding For Balance information.
INSTALLING ROTOR IN CASING

9. Install upper half of channel rings (3-060) and


seat shoulder screws (3-029B).

1. The stuffing box bushings (2-088) (if used), throttling bushing (2-441), channel rings (2-060) and center bushing (2-407) should be checked to make sure
they seat in both the upper and lower half casing
and that the locating pins (2-315) are properly located in their respective lower half casing fits. The
use of a scraper on the bushing to casing fit will help
to fit the bushing to the casing.

10. Rig upper half casing (3-002) to an overhead


hoist. Refer to LIFTING EQUIPMENT section.
Position upper half casing over lower half and lower
carefully, making sure all rings and bushings enter
their proper fit.
Install main parting flange dowel pins (3-029C) and
seat.

2. Install main parting flange gasket (2-170). Refer


to PARTING FLANGE GASKET.

Install main parting flange washers (3-246) and nuts


(3-179) and torque to the recommended value.

3. Place the lower half of the center bushing (2-407)


in lower half casing (2-001).

NOTE

4. Place the lower half of all channel rings (2-060) in


lower half casing, in the same sequence as they
were removed.

Make sure parting flange jack screws (3-118B), in


lower half casing, are backed out far enough so as
not to protrude above parting flange machined surface.

NOTE

DA SLV/KTB

Channel rings are precision-machined as a set, after


being dowelled. Be sure they are reassembled as a
set.

ASSEMBLE STUFFING BOX EXTENSION


If pump is equipped with a cooled stuffing box extension (4-264) if must be assembled to pump at this
time.

5. Place casing rings (2-006), throttling bushing (2441) and stuffing box bushings (2-088) (if used) in
their proper positions on pump rotor.

1. Renew O ring (4-456B) and assemble to O


ring groove on stuffing box extension.

6. Rig rotor (2-184) to an overhead hoist. Refer to


LIFTING EQUIPMENT section of this manual.

2. Assemble stuffing box extension (4-264) to the


casing. Assemble washers (4-241B) and nuts (4279B). Tighten nuts to the proper torque value.

Position rotor over lower half casing and position


bushings and casing rings, making sure anti-rotation
holes and slots are in the down position and that
they enter their respective fits in lower half casing.
7-10

Maintenance
CHECK ROTOR VERTICAL LIFT

4. Measure and record the total rotor end float between the two lines. The acceptable minimum end
float is given on the pump assembly drawing (included in Appendix). If this minimum end float is not
obtained, the cause must be investigated and corrected. Two of the most likely causes could be:

It is necessary to check and record the vertical lift of


the rotor within the casing.
1. Place a dial indicator on the upper half casing
with the indicator tip resting on the top of the shaft.
Zero the indicator.

A. Impellers not properly seated against the split


ring.

2. Using a bar and a block of wood under the shaft,


lift the shaft and record the movement. Take measurements at both ends of the pump.

B. Improperly machined part, i.e. impeller ring or


channel ring.
5. Mark another line midway between the first two
lines. This Center line represents the centering of
the impellers within their volutes. Masking tape is to
be left on shaft for use in CENTRALIZE ROTOR
AXIALLY.

3. The minimum acceptable vertical movement is


the minimum back ring clearance on the suction end
of the pump and the minimum throttling bushing
clearance on the discharge end of the pump. For
clearances, refer to the assembly drawings included
in Appendix of this manual.

HORIZONTAL AND VERTICAL SHAFT ALIGNMENT

4. If this minimum movement is not obtained, the


cause must be investigated and corrected.

1. Assemble Plain Bearing


CHECK ROTOR AXIAL FLOAT
A. Assemble bearing body (5-021) to casing. Install
dowel pins (5-029A) and snug down capscrews (5118B). Install both the horizontal and vertical adjusting screws (5-259A) in the bearing body mounting
flange. Remove dowel pins (5-029A).

1. Push the rotor (3-184) toward the coupling end


as far as it will go.

CAUTION

B. Wipe a film of oil on lower half of bearing lining


(5-191) and pump shaft journal area. Roll in lower
half bearing lining.

DO NOT FORCE ROTOR.


NOTE

2. Assemble Thrust Bearing

DA SLV/KTB

Some of the rotor weight may have to be supported


externally. The rotor is now being supported by the
impeller rings contacting the channel rings.

A. Install shim pack (6-257A) against shoulder of


shaft. If shim thickness was not recorded at disassembly or if rotor was rebuilt completely, install approximately 1/16 of shims.

2. Place a piece of masking tape on the shaft (if


seal is used) or shaft sleeve (if packed box is used),
in the stuffing box area, at the thrust end of the
pump. Place a scale across the face of the stuffing
box and make a line on the masking tape.

B. Assemble thrust collar key (6-054) and Dummy


Thrust Collar to shaft.
NOTE

3. Push the rotor toward outboard end as far as it


will go. Using scale, mark another line on masking
tape.

It is recommended a Dummy Thrust Collar (not


furnished) be used when making rotor settings.
Dummy Thrust Collar A thrust collar with the
same dimensions as thrust collar (6-028) except the
bore is opened so it has a slide fit with pump shaft
(.0005 to .0010 loose).
7-11

Maintenance
Secure Dummy Thrust Collar with locknut (6-128).

This distance is how far the rotor is to be moved either inboard or outboard.

C. Assemble thrust bearing body (6-021) to casing.


Install dowel pins (6-029A) and snug down capscrews (6-118A). Install both the horizontal and vertical adjusting screws (6-259A) in bearing body
mounting flange. Remove dowel pins (6-029A).

3. To move rotor inboard (toward coupling end),


shims (6-257A) will have to be added between thrust
collar and shoulder of shaft. To move rotor outboard
(toward thrust end), shims will have to be removed.

D. Wipe a film of oil on lower half of bearing lining


(6-191) and journal area of pump shaft. Roll in lower
half bearing lining.

4. Remove thrust collar locknut (6-128) and Dummy


Thrust Collar.
FINAL BEARING ASSEMBLY

3. Using a set of inside-spring calipers and the adjusting screws (5-259A), adjust the horizontal and
vertical position of the shaft at the plain bearing end
so that the distance between the shaft sleeve or
shaft and the stuffing box bore is the same all the
way around.

1. Remove inboard thrust bearing assembly (6-325).


2. Remove both lower half bearing linings (5-191
and 6-191).
3. Remove both bearing bodies (5-021 and 6-021).

4. Repeat Step 3 on thrust end, then recheck plain


end. Pump shaft should turn free with no indication
of binding or rubbing. This should be taken into
consideration when making adjustments.

4. Remove thrust collar locknut (6-128) and Dummy


Thrust Collar.
5. Install both completely assembled mechanical
seals (4-429) to shaft. Insert into stuffing box. Do
not tighten gland nuts (4-279A) or mechanical seal
drive collar setscrews at this time.

5. When vertical and horizontal alignment is obtained, tighten bearing housing bolting except the
two top bolts at the adjusting screws. Ream dowel
holes and install dowel pins (5-029A and 6-029A).
Loosen adjusting screws and tighten the two top
bearing housing bolts.

CAUTION
CARE MUST BE TAKEN NOT TO DAMAGE
SHAFT SLEEVE O RING WHEN SLIDING MECHANICAL SEAL (4-429) OVER SHAFT KEYWAYS AND SPLIT RING GROOVES.

CENTRALIZE ROTOR AXIALLY


1. Pour a small amount of oil on Dummy Thrust
Collar and thrust shoes. Install inboard Kingsbury
thrust bearing assembly (6-325). Push rotor toward
coupling as far as it will go (tight against inboard
thrust bearing assembly).

6. Position inboard flingers (5-157 and 6-157) and


outboard flinger (5-157) on shaft at their approximate
positions.

DA SLV/KTB

NOTE

7. Slide inboard thrust bearing seal ring over shaft


(refer to Kingsbury drawings and instructions). Rest
it on shaft in its proper position. (Refer to Pump Assembly drawing).

Refer to Kingsbury drawing and instructions in Appendix of this manual.


2. Place a scale across the face of the coupling end
stuffing box. Measure the distance from the edge of
the scale to the Center line on the masking tape as
marked in Step 5 of CHECK ROTOR AXIAL FLOAT
instructions.

8. Insure the proper thickness of shims (6-257A) is


seated against the shaft shoulder.
9. Install thrust collar key (6-054), thrust collar (6028) and locknut (6-128). Tighten locknut and
tighten setscrews (6-259B) in locknut.

7-12

Maintenance
NOTE

18. Pour a small amount of oil on thrust collar (6028) and thrust bearing assembly (6-325). Assemble inboard and outboard thrust bearings to bearing
body. (Refer to Kingsbury drawing and instructions
included in Appendix of this manual).

Before installing thrust collar (6-028) onto shaft, heat


o
the thrust collar to 220 F. Maximum in successive
stages working from periphery toward center.

NOTE

10. Assemble bearing bodies (5-021 and 6-021) to


casing. Install dowel pins (5-029A and 6-029A) and
snug down bolting. Seat dowel pins.

Rotate base ring so the keys of the base ring enter


their keyways at the parting flange in the bearing
body.

NOTE

19. Ensure bearing body (6-021) and bearing cap


(6-023) parting flange surfaces are clean and free of
dry permatex. Coat with a thin layer of permatex.
Assemble bearing cap (6-023) to bearing body. Install dowel pins (6-029C) and tighten capscrews (6118C) to the proper torque value.

When assembling bearing bodies to casing, ensure


flingers are properly positioned with the inner part of
the flinger in the bearing housing (refer to Assembly
drawing).
11. Tighten bearing body to casing bolting (5-118A
and 6-118A) to the proper torque value.

SET THRUST BEARING AXIAL END PLAY


NOTE
1. Remove support head (6-172) from bearing body.
Assemble driver half of coupling (6-185) to shaft.

Insure dowel pins (5-029A and 6-029A) are properly


seated.

2. Place shims (6-257B) against outboard thrust


bearing base ring. Assemble end cover to bearing
body and cap. Tighten capscrews (6-118D) to
proper torque value.

12. Pour a small amount of oil on bearing lining (5191) and shaft journal area. Roll lower half of bearing lining under shaft.

3. Install a dial indicator on coupling-end bearing


housing so the indicator contacts the end of the
shaft. Push the rotor outboard (towards thrust bearing) and set indicator at zero. Push rotor inboard.
Indicator should read .010 (0.25 mm) to .015 (0.38
mm). Add or remove shims (6-257B) to obtain
proper end play. Coat end of bearing body and cap
with permatex and reassemble end cover, torque
and recheck end play.

13. Place upper half of bearing lining (5-191) in position on top of shaft.
14. Ensure bearing body (5-021) and bearing cap
(5-023) parting flange surfaces are clean and free of
dry permatex. Coat with a thin layer of permatex.
Assemble bearing cap (5-023) to bearing body. Install dowel pins (5-029B) and tighten capscrews (5118A) to the proper torque value.

FINAL ASSEMBLY

DA SLV/KTB

15. Assemble lower half of bearing lining (6-191) to


thrust bearing body in same manner as Step 12.

1. Position flingers (5-157 and 6-157) .040 away


from bearing bodies. Tighten setscrews (5-259B
and 6-259C). Assemble rest of coupling (6-185) and
oil pump (6-219).

16. Assemble upper half of bearing lining (6-191) in


same manner as done in Step 13.
17. Assemble outboard thrust bearing seal ring to
shaft and temporarily assemble support head (6172) to bearing body. Secure with two capscrews
(6-118D).

2. Insure mechanical seal gland is seated properly


in stuffing box bore. Assemble gland washers (4246A) and tighten gland nuts (4-279A) to the proper
torque value.

7-13

Maintenance
NOTE

5. Check coupling/shaft alignment as described under ALIGNMENT PROCEDURE and assemble


coupling.

Refer to STUFFING BOX section of this manual.

6. Install coupling guard.

3. Using a strap, rotate pump shaft to be sure rotor


is properly aligned and does not bind.

7. Replace all auxiliary piping, instrumentation and


pipe plugs.

CAUTION

8. Fill oil reservoir (refer to LUBRICATION section


instructions).

DO NOT ROTATE PUMP SHAFT EXCESSIVELY.


INTERNAL PARTS DEPEND ON THE LIQUID BEING PUMPED FOR LUBRICATION.

9. Refer to OPERATION section for starting procedure.

DA SLV/KTB

4. Install coupling key, pump half coupling, coupling


nut and set coupling nut setscrews. (Refer to
COUPLING REMOVAL section).

7-14

Parts Information

WARNING
THE USE OF PARTS OTHER THAN FLOWSERVE CORP. APPROVED PARTS MAY CREATE HAZARDOUS
CONDITIONS OVER WHICH FLOWSERVE CORP. HAS NO CONTROL. SUCH HAZARDOUS CONDITIONS
CAN LEAD TO INJURY, OR RESULT IN DAMAGE TO THE EQUIPMENT. FLOWSERVE CORP. DOES NOT
SUPPORT NOR WILL BE RESPONSIBLE FOR THE USE OF NON FLOWSERVE CORP. FURNISHED PARTS
NOR THE USE OF MATERIALS WHICH ARE NOT AS ORIGINALLY FURNISHED WITHOUT THE EXPRESSED WRITTEN APPROVAL OF FLOWSERVE CORP.

SERVICE CONDITIONS
For 24-hour emergency repair service, contact the Flowserve Service Department at 1-800-547-8671 or contact
the nearest Flowserve Service Center.

ORDERING INSTRUCTIONS
To place an order, contact the nearest Flowserve Office listed on pg. 8-10
For 24-hour parts ordering service, call the Flowserve Parts Distribution Center at 1-800-526-3569
The information following should be included when ordering any parts for your pump:
FLOWSERVE ORDER: See Pump Data Sheet
PUMP SERIAL NUMBER: See Pump Data Sheet/Pump Nameplate
PUMP SIZE: See Pump Data Sheet/Pump Nameplate
Refer to the Assembly Drawing and Parts List (found in appendix of this manual) for part numbers, quantities, and
recommended spare part classifications.
EXAMPLE
PART DESCRIPTION
Shaft

QUANTITY

62000000

Front Ring For Impeller 62000001

DA SLV/KTB

Impeller Ring

PART NUMBER

8- 1

Parts Information
RECOMMENDED SPARE PARTS
A recommended spare parts classification is offered for Flowserve parts furnished on this unit. The classification
of a required part can be identified by referring to the appropriate assembly drawing and parts list included in the
appendix of this manual.
The recommended spare parts are divided into three classifications which are defined below.
CLASS 1 (Minimum):
Covers recommended spare parts for a single unit where additional spare parts are ordinarily available from
branch or dealer stock. Suggested for Domestic Service handling non-corrosive liquids where interruptions in
service are not objectionable.
CLASS 2 (Average):
Covers recommended spare parts for a single unit where additional spare parts are not readily available. Suggested for Domestic Service handling abrasive or corrosive liquids where some interruptions in service are
permissible.
CLASS 3 (Maximum):
Covers recommended spare parts for a single unit where maximum protection from major shutdown must be
afforded. Suggested for Export Service or Domestic Service where minimum loss of service is essential.

DA SLV/KTB

The Flowserve Sales Representative in your area will gladly review the class of spares best suited to your requirement.

8- 2

Parts Information

TYPICAL ROTOR ASSEMBLY PARTS LIST

NOUN CODE

PART NAME

003A

IMPELLER ASSEMBLY L.H. *

003B

IMPELLER ASSEMBLY R.H. *

006

RING - CASING

010

SHAFT

011

KEY IMPELLER

252

RING - SPLIT

291

KEY THROTTLING SLEEVE

408

CENTER SLEEVE

440

SLEEVE - THROTTLING

DA /DAH ALL

* IMPELLER ASSEMBLY 003A/B CONSISTS OF


003

IMPELLER

004

RING IMPELLER (FRONT)

005

RING IMPELLER (BACK)

259

SETSCREW

NOTE
REFER TO ASSEMBLY DRAWINGS AND PARTS LISTS (FOUND IN APPENDIX OF THIS MANUAL) FOR PART NUMBERS, QUANTITIES, AND
RECOMMENDED SPARE PART CLASSIFICATIONS.

EXPLODED VIEW NO. 1


TYPICAL ROTOR ASSEMBLY
8- 3

Parts Information

LOWER HALF BUSHINGS, ROTOR AND CASING ASSEMBLY PARTS


LIST

NOUN CODE
001

PART NAME
LOWER HALF CASING

006

RING - CASING

060

CHANNEL RING (LOWER HALF)

088

STUFFING BOX BUSHING *

170

GASKET MAIN PARTING FLANGE

184

ROTOR COMPLETE

315

LOCATING PIN

407

CENTER BUSHING (LOWER HALF)

441

THROTTLING BUSHING

DA /DAH ALL

* THIS STUFFING BOX BUSHING IS NOT USED WITH A COOLED STUFFING BOX EXTENSION IN COMBINATION WITH A PACKED BOX

NOTE
REFER TO ASSEMBLY DRAWINGS AND PARTS LISTS (FOUND IN APPENDIX OF THIS
MANUAL) FOR PART NUMBERS, QUANTITIES, AND RECOMMENDED SPARE PART
CLASSIFICATIONS.

8- 4

EXPLODED VIEW NO 2
LOWER HALF BUSHINGS,
ROTOR & CASING ASSEMBLY

Parts Information

UPPER HALF BUSHINGS AND CASING ASSEMBLY PARTS LIST

NOUN CODE

PART NAME

001

LOWER HALF CASING

002

UPPER HALF CASING

006

RING - CASING

029A

DOWEL PIN (CENTER BUSHING)

029B

SHOULDER SCREW (CHANNEL RING)

029C

DOWEL PIN (CASING)

060

CHANNEL RING (UPPER HALF)

088

STUFFING BOX BUSHING *

118A

CAP SCREW (CENTER BUSHING)

118B

SCREW - JACKING

170

GASKET (MAIN PARTING FLANGE)

178

STUD (MAIN PARTING FLANGE)

179

CAP NUT (MAIN PARTING FLANGE)

184

ROTOR COMPLETE

246

WASHER (MAIN PARTING FLANGE)

407

CENTER BUSHING (UPPER HALF)

417

PIPE PLUG

441

THROTTLING BUSHING

DA /DAH ALL

* THIS STUFFING BOX BUSHING IS NOT USED WITH A COOLED STUFFING BOX EXTENSION IN COMBINATION WITH A PACKED BOX

NOTE
REFER TO ASSEMBLY DRAWINGS AND PARTS LISTS (FOUND IN APPENDIX OF THIS
MANUAL) FOR PART NUMBERS, QUANTITIES, AND RECOMMENDED SPARE PART
CLASSIFICATIONS.

8- 5

EXPLODED VIEW NO 3
UPPER HALF BUSHINGS,
& CASING ASSEMBLY

Parts Information

SHAFT SEALING PARTS LIST


NOUN CODE
178
183
184

PART NAME
STUFFING BOX STUDS
CASING COMPLETE
ROTOR COMPLETE
PACKED BOX

008
014
016
064
118
246A
279A
291
397
417
456A

SHAFT SLEEVE
SEAL CAGE
GLAND
PACKING
CAP SCREW (GLAND)
GLAND WASHER
GLAND NUT
KEY SHAFT SLEEVE
RETAINING RING
PIPE PLUG
O-RING (SHAFT SLEEVE)
MECHANICAL SEAL

246A
279A
429

GLAND WASHER
GLAND NUT
MECHANICAL SEAL COMPLETE

DA /DAH ALL

NOTE
REFER TO ASSEMBLY DRAWINGS AND PARTS LISTS (FOUND IN
APPENDIX OF THIS MANUAL) FOR PART NUMBERS, QUANTITIES, AND RECOMMENDED SPARE PART CLASSIFICATIONS.

EXPLODED VIEW NO. 4


SHAFT SEALING
8- 6

Parts Information

PLAIN BEARING END PART LIST

NOUN CODE

PART NAME

021

BEARING BODY

023

BEARING CAP

029A

DOWEL PIN (BRG. BODY TO CASING)

029B

DOWEL PIN (BRG. CAP TO BODY)

031*

OIL RING

043

OIL SIGHT GLASS

097

BREATHER CAP

118A

CAPSCREW (BRG. CAP TO BODY)

118B

CAPSCREW (BRG. BODY TO CASING)

157

FLINGER

191

BEARING LINING

258

NUT (DOWEL PIN)

259A

SETSCREW (BRG. BODY ADJUSTING)

259B

SETSCREW (FLINGER)

315

LOCATING PIN

333

EYEBOLT

417A

PIPE PLUG

417B

PIPE PLUG

456*

O RING (BRG. LINING)

DA SLV/KTB

* ONLY USED WITH OIL RING (OPTIONAL CONSTRUCTION)

NOTE
REFER TO ASSEMBLY DRAWINGS AND PARTS LISTS (FOUND IN APPENDIX OF THIS
MANUAL) FOR PART NUMBERS, QUANTITIES, AND RECOMMENDED SPARE PART
CLASSIFICATIONS.

EXPLODED VIEW NO. 5


PLAIN BEARING END
8- 7

Parts Information

THRUST BEARING END PART LIST

DA SLV/KTB

NOUN CODE
021
023
028
029A
029B *
029C
031 *
043
097
118A
118B *
118C
118D
128
157
158
191
219
257A
257B
258A
258B
258C
259A
259B
259C
262
315A
315B
333
417
456 *
483

PART NAME
BEARING BODY
BEARING CAP
THRUST COLLAR
DOWEL PIN (BRG. TO CASING)
DOWEL PIN (BRG. LINING)
DOWEL PIN (BRG. TO CASING)
OIL RING
OIL SIGHT GLASS
BREATHER CAP
CAPSCREW (BRG. BODY TO CASING)
CAPSCREW (BRG. LINING)
CAPSCREW (BRG. CAP TO BODY)
CAPSCREW (END COVER TO HOUSING)
LOCKNUT (THRUST COLLAR)
FLINGER
BEARING END CAP
BEARING LINING
MAIN OIL PUMP
SHIM (THRUST COLLAR)
SHIM (THRUST BRG.)
NUT (DOWEL PIN)
NUT (DOWEL PIN)
NUT (DOWEL PIN)
SETSCREW (BRG. BODY ADJUSTING)
SETSCREW (LOCKNUT)
SETSCREW (FLINGER)
GASKET (MAIN OIL PUMP)
LOCATING PIN (BRG. LINING)
LOCATING PIN (END COVER)
EYEBOLT
PIPE PLUG
O RING (BRG. LINING)
SHAFT EXTENSION

*ONLY USED WITH OIL RING (OPTIONAL CONSTRUCTION)


NOTE

EXPLODED VIEW NO. 6


THRUST BEARING END

REFER TO ASSEMBLY DRAWINGS AND PARTS LISTS (FOUND IN APPENDIX OF THIS


MANUAL) FOR PART NUMBERS, QUANTITIES, AND RECOMMENDED SPARE PART
CLASSIFICATIONS.

8- 8

Parts Information

DA SLV/KTB

FLOWSERVE CORPORATION PUMP SERVICE CENTERS

Baton Rouge SC
4152 Rhoda Drive
Baton Rouge, LA 70816
Phone: 225-293-5780
Fax: 225-281-8134

Beaumont SC
2920 West Cardinal Drive
Beaumont, TX 77705
Phone: 409-842-5594
Fax: 409-842-5958

Benecia SC
6077 Egret Court
Benecia, CA 94510
Phone: 707-745-3773
Fax: 707-746-1568

Boothwyn SC
11 Creek Parkway
Boothwyn, PA 19061
Phone: 610-859-0700
Fax: 610-859-0711

Carson SC
24351 S. Wilmington
Carson, CA 94510
Phone: 310-522-0925
Fax: 310-522-0758

Charlotte SC
4816 Worth Place
Charlotte, NC 28216
Phone: 704-399-0446
Fax: 704-393-7296

Cleveland SC
6250 Halle Drive
Cleveland, OH 44125
Phone: 216-524-6155
Fax: 216-642-5741

Customer Field Service


942 Memorial Parkway
Phillipsburg, NJ 08865
Phone: 908-859-7066
Fax: 908-859-7836

Elgin SC
695 Church Road
Elgin, IL 60123
Phone: 847-742-9510
Fax: 847-742-9593

Fairfield SC
142 Clinton Road
Fairfield, NJ 07004
Phone: 973-227-4565
Fax: 973-227-6615

Greer SC
2431 S. Highway #14
Greer, SC 29650-8201
Phone: 864-879-7276
Fax: 864-879-0997

Houston SC
6832 Wynnwood Lane
Houston, TX 77008
Phone: 713-868-6666
Fax: 713-868-6630

Leduc/Edmonton SC
4405 70th Avenue
Leduc, Alberta
Canada T9E 7E6
Phone: 780-986-7100
Fax: 403-986-4854

Parts Distr. Center (Moosic)


Rocky Glen Road
Rocky Glen Industrial Park
Moosic, PA 18507
Phone: 717-451-2200

Pittsburgh Parts
1885 Mayview Road
Bridgeville, PA 15017
Phone: 412-257-4600
Fax: 412-257-3162

Sarnia SC
235 Henry Drive RR No. 4
Sarnia, Ontario
Canada N0N 1T0
Phone: 519-336-3614
Fax: 519-336-7410

Scranton Parts
942 Griffin Pond Road
Clark Summit, PA 18411
Phone: 570-586-8800
Fax: 570-587-5006

Tampa SC
6405 Badger Drive
Tampa, FL 33610
Phone: 813-621-8865
Fax: 813-626-1274

Texas City SC
146 FM 519 Building 4C
Texas City, TX 77568
Phone: 409-935-1977
Fax: 409-935-2269

Vancouver SC
10400 N.E. 13th Street
Vancouver, WA 98686
Phone: 360-573-5211
Fax: 360-574-7656

Wasilla SC
2051 Foundry Way
Wasilla, AK 99654
Phone: 907-376-0550
Fax: 907-376-0669

Woodbridge SC
120 Vinyl Court
Woodbridge, Ontario
Canada L4L 4A3
Phone: 905-856-1140
Fax: 905-856-2010
8-9

Parts Information
FLOWSERVE CORPORATION DOMESTIC SALES FACILITIES

Alabama
574 Azalea Road, Suite 106
Mobile, AL 36609
Phone: 334-666-0402
Fax: 334-666-7460

Arizona
8109 E. Del Timbre
Scottsdale, AZ 85258
Phone: 480-998-9698
Fax: 480-998-3836

California (Carson)
24341 S. Wilmington Ave.
Carson, CA 90745
Phone: 310-522-0925
Fax: 310-522-0758

California (Chico)
844 Broadway
Chico, CA 95928
Phone: 530-342-3551
Fax: 530-342-9667

California (Vernon)
2300 East Vernon Avenue
Vernon, CA 90058
Mailing Address:
P.O. Box 512017
Los Angeles, CA 90051-0017
Phone: 323-587-6171
Fax: 323-589-2080

Chicago (Elgin)
695 Church Road
Elgin, IL 60123
Phone: 847-741-0400
Fax: 847-741-0687

Chicago (Glen Ellyn)


800 Roosevelt Road, Bldg. B, Suite
200
Glen Ellyn, IL 60137
Phone: 630-545-0290
Fax: 630-545-0297

Florida
2568 Pine Cove Lane
Clearwater, FL 33481
Phone: 727-712-9484
Fax: 727-712-3934

Georgia (Alpharetta)
1145 Santuary Parkway, Suite
130 Alpharetta, GA 30004
Phone: 770-569-8380
Fax: 770-569-9707

Louisiana (Baton Rouge)


12134 Industriplex Blvd.
Baton Rouge, LA 70809
Phone: 225-756-0080
Fax: 225-766-4080

Louisiana (Kenner)
1500 W. Esplanade Ave., Unit
40E Kenner, LA 70065
Phone: 504-463-5994
Fax: 504-466-0218

Michigan
610 Hampden
Midland, MI 48640
Phone: 517-832-8441
Fax: 517-832-8800

Minnesota
Yankee Square Office 2, Suite
206 3470 Washington Drive
Eagan, MN 55122
Phone: 651-452-7867
Fax: 612-452-7888

New Jersey
333 Littleton Road, Suite 303
Parsippany, NJ 70054
Phone: 973-334-9444
Fax: 973-334-9455

New Orleans
9417 Nottaway PI.
River Ridge, LA 70123
Phone: 504-739-1112
Fax: 504-739-1113

New York (Stoney Point)


1 Pymn Court
Stoney Court, NY 10980
Phone: 914-947-9070
Fax: 914-947-9066

North Carolina
5600 Wedgewood Drive
Charlotte, NC 28210
Phone: 704-522-8478
Fax: 704-522-1548

Georgia (Savannah)
109 Wigmore Court
Savannah, GA 31410
Phone: 912-927-2490
Fax: 912-927-2493

DA SLV/KTB

Massachusetts
5 Gallant Rd.
Peabody, MA 01960
Phone: 978-538-7115
Fax: 508-638-7119
Missouri
12 Foxbend Court
St. Charles, MO 63301
Phone: 636-443-0250
Fax: 636-443-0251
New York (Buffalo)
716 Southside Avenue
Cherry Creek, NY 14723
Phone: 716-296-5420
Fax: 716-296-5423

8-10

Parts Information
Ohio
3419 Grace Avenue
Cincinnati, OH 45208
Phone: 513-871-0024
Fax: 513-871-0355

Pennsylvania (Boothwyn)
Sales 103 Chelsea Parkway
Boothwyn, PA 19016
Phone: 610-859-9449
Fax: 610-859-8965

Pennsylvania (Pittsburgh)
1300 Parkway View Drive
Pittsburgh, PA 15205
Phone: 412-788-1480
Fax: 412-788-6705

Tennessee (Knoxville)
1136 Oak Haven Rd.
Knoxville, TN 37932
Phone: 423-671-4080
Fax: 423-671-4084

Texas (Beaumont)
1290 Texla Rd.
Vidor, TX 77662
Mailing Address:
P.O. Box 1449
Mauriceville, TX 77626
Phone: 409-745-5055
Fax: 409-745-5054

Texas (Houston)
4214 Bluebonnet Dr.
Stafford, TX 77477
Phone: 281-240-4120
Fax: 281-240-5182

DA SLV/KTB

West Virginia
4785 Coal River Road
Alum Creek, WV 25003
Phone: 304-756-3498
Fax: 304-766-3140

8-11

Pennsylvania (Boothwyn)
Sales/SC
1000 Creek Parkway
Naamans Creek Center
Boothwyn, PA 19061
Mailing Address:
P.O. Box 2230
Boothwyn, PA 19061
Phone: 610-859-0800
Fax: 610-859-0711
Tennessee (Memphis)
8829 Center St., Suite 200
Southaven, TN 38671
Phone: 662-280-4767
Fax: 662-280-4768
Washington
4305 Lakeview Drive S.E.
Port Orchard, WA 98366
Phone: 425-822-6116
Fax: 425-828-4046

Parts Information

DA SLV/KTB

FLOWSERVE CORPORATION INTERNATIONAL SALES FACILITIES

Argentina (Buenos Aires)


Blanco Encalada 60 (1603) Villa Martelli
PCIA. Buenos Aires Argentina
Phone: 54-11-4709-6800
Fax: 54-11-4709-7069

Argentina (Mendoza)
Chuquisaca 302
(5547) Godoy Cruz
Mendoza Argentina
Mailing Address:
Casilla de Correo 40 (5001)
Godoy Cruz, Mendoza Argentina
Phone: 54-261-2300
Fax: 54-261-427-2524

Australia/New Zealand
14 Dalmore Drive
Scoresby, Victoria 3179
Australia
Phone: 61-3-9764-8622
Fax: 61-2-9475-0618

Canada (Calgary)
5920-1 A St., S.W. Suite 106
Calgary, Alberta T2H OG3
Canada Phone: 403-252-7769
Fax: 403-259-4188

Canada (Leduc)
4405-70 Avenue
Leduc, Alberta T9E 7E6 Canada
Phone: 780-986-7100
Fax: 780-986-4854

Canada (Vancouver)
#211 Lincoln Centre
3030 Lincoln Avenue
Coquitiam, British Columbia
V3B6BR Canada
Phone: 604-464-9930
Fax: 604-464-9931

Canada (Toronto)
120 Vinyl Court
Woodbridge, Ontario
L4L 4A3 Canada
Phone: 905- 856-0701
Fax: 905-856-6990

Canada (Montreal)
2345 Michellin, Suite 200
Laval, PQ H7L 5B9 Canada
Phone: 514-973-2046
Fax: 514-973-4438

China
Rm. 1 K, Guo Men Office Building
No. 1, Zuojiazhuang
Chaoyand District, Beijing China
Phone: 86-10-64646771
Fax: 86-10-64646775

France
51 Rue Tremiere
Villiage d'Enterprises
Quartier Du Triolo, F-59650
Villeneuve D'Ascq France
Phone: 33-3-20-61-7361
Fax: 33-3-20-91-7866

Germany
Dischingerstrasse 4
D-69123 Heidelberg, Germany
Phone: 49-6221-776041
Fax: 49-6221-700353

Italy
Via Galvani 6/8
20054 Nova Milanese (MI), Italy
Phone: 39-0362-49911
Fax: 39-0362-499126

Japan
2-7-15 Hamamatsu-cho
5-25-16 Higashi-Gotanda
Minato-ku, Tokyo 105-0013
Japan
Phone: 81-3-3431-6907
Fax: 81-3-3431-6908

Mexico (Coatzacoalcos)
AV. Puente #157, Depto. 203
Las Americas
Coatzacoalcos, VIER. C.P. 96480
Mexico
Phone: 529-215-2658
Fax: 529-215-2890

Mexico (Monterrey)
Productividad #200, Parque
Industrial Promofisa
CD. Guadalupe, N.L. C.P. 67110
Mexico
Phone: 528-327-5926
Fax: 528-327-5815

Mexico (Tampico)
Tampico #203
Col Matamoros, Tampico, Tamp
C.P. 89270 Mexico
Phone: 521-214-0036
Fax: 521-212-2824

Mexico (Villahermosa)
Venustiano Carranza #235
Depto #2
Col Centro, Villahermosa, tab. C.P.
86000 Mexico
Phone: 529-314-2316
Fax: 529-314-2317

Mexico (Salina Cruz)


Av. Puerto Angel #408
Col. Centro, Salina Cruz, Oax.
C.P. 70600 Mexico
Phone: 527-845-1206
Fax: 528-327-5952

8-12

Parts Information
Netherlands
Vossendaal 29
4877 AA Etten Leur
Netherlands Phone:
31-76-5028100
Fax: 31-76-5028150
Spain
Ctra. Nacional III, Km 23'600
28500 Arganda del Rey
Madrid Spain
Phone: 34-91-8719009
Fax: 34-91-8719194

United Kingdom (Esher)


Waynflete House
74 - 76 High Street
Esher, Surrey KT10 9QS
United Kingdom
Phone: 44-1372-469695
Fax: 44-1372-460190

Saudi Arabia
P.O. Box 209
AI-Khobar 31952, Saudi Arabia
Phone: 966-3-857-3146
Fax: 966-3-857-2862

Singapore
12 Tuas Avenue
Singapore 638824 Singapore
Phone: 65-862-3332
Fax: 65-868-4603

United Arab Emerites


P.O. Box 3374
Abu Dhabi, United Arab Emirates
Phone: 971-2-317141
Fax: 971-2-326037

United Kingdom
Eastern Hemisphere &
Asia/Pacific
Harley House
94 Hare Lane, Claygate
Esher, Surrey KT10 ORB
United Kingdom
Phone: 44-1372-463700
Fax: 44-1372-463801

Venezuela (Caracas)
Edificio Agfa
3RA Transversal De Los Ruices
Piso 3-Los Ruices
Caracas, Venezuela
Phone: 2-239-00681946919369
Fax: 2-239-9761 /9512

DA SLV/KTB

Venezuela (Maracaibo)
Unicentro Virginia Avenida 3C
con Calle 67
Local 5, Planta Baja
Maracaibo, Venezuela
Mailing Address:
c/o Buzoom
P.O. Box 028537C
Miami, FL 33102 USA
Phone: 58-61-911-129
Fax: 58-61-921-904

8-13

Venezuela (Maracaibo)
Torre Ejecutiva N. 75-51 Primer
Piso, Oficina 1 B Ave. 4 Bella Vista
Entre Calles 75 & 76
Maracaibo, Venezuela
Phone: 58-61-9327671934348
Fax: 58-61-933114

S-ar putea să vă placă și