OVERVIEW
Procurement varies with contracting strategy & project size
Procurement functions for larger project: Purchasing,
Expediting, Inspection, Receiving, Account Payable
Split of responsibility: equipment & critical bulk material
by main contractor, bulk material by subcontractor
Procurement involves much more than just placing
purchase order: vendor screening, vendor list, expedite
certified drawing & vendors activities, inspect vendor shop
& facilities, witness equipment inspection, testing &
acceptance, shipment & delivery
Effective procurement require tremendous paper work and
record keeping: Inquiry, bid analysis, communication with
vendors, procurement logs (Requisition, PO, Inspection &
acceptance, invoice and payment), claim processing
okt-2001
yta-unpar
INQUIRY guidelines
Bidder list must be based on qualification &
ability to perform
Spec must be complete & sufficiently detailed to
ensure meaningful bids but avoid over-specifying
Search hungry vendors
Pre-qualify bidders of special equipment
Allow reasonable time for bidding but avoid
premature inquiries
Requests to extend bidding deadline may be early
indicator of future troubles (work accumulation
and indication of unreliability)
okt-2001
yta-unpar
INQUIRY (2)
Competitive bidding is highly desirable
Sole sourcing may be considerable yet must
be justified & documented
Request firm price quotation including unit
prices and required spares
All contact with bidders/ vendors should be
channeled through purchasing agent
okt-2001
yta-unpar
okt-2001
yta-unpar
yta-unpar
PURCHASE ORDER
Make sure all negotiated changes have been
incorporated
Make sure verbal confirmations on critical items
are documented
If P/O involves start up &/or check out assistance
ascertain that appropriate documents &
information are included in P/O (insurance
certificate etc)
Do not issue open ended P/O
Selecting a vendor and placing the P/O is usually
the easiest part of procurement
okt-2001
yta-unpar
yta-unpar
EXPEDITING
Contractors normally use field inspectors or
design engineers for expediting
Expeditor is expected to
Verify and obtain vendor schedule for critical/ long
lead items
Ascertain vendor drawing requiring approval
Obtain un-priced copies of vendor sub-order
Review shop fabrication schedule and evaluate to meet
overall schedule
Discover vendor potential problem
Prepare reports to inform Project Manager
okt-2001
yta-unpar
INSPECTION
Pre-purchase inspc: Vendor facilities, capabilities
assessment (engineering, equipment, fabrication
techniques, welding certifications, QA/QC)
Post-purchase inspc
okt-2001
10
INSPECTION-2
Inspection must be performed by qualified
personnel
Even when it is handled by contractor, the owner
must retain the option to do independent
inspection
Equipment normally included in an inspection and
testing: tanks & pressure vessel, heat exchangers,
process equipment (dryer, filter, centrifuges etc),
compressor and turbines, special pumps, special
valves, boilers/ furnace, package equipment
okt-2001
yta-unpar
11
PERFORMANCE TESTING
Testing either in vendor shop or field
Degree of test should be established before issuing
P/O
No load testing and functioning aux equipment
Full performance test
Frequent test procedures are available from
ASME, API etc