UNIFIED SCHEDULE OF RATES FOR
SEWERAGE WORKS
2013

FOREWORD
Ever since it's establishment in 1888 by the erstwhile British rulers in India, in the last
125 years of the history of its existence Mumbai Municipal Corporation has catered
to every aspect of the citizen of Mumbai that can be conceived of. Think of Engineer
Victor Tulloch, who through his unparalleled immense efforts conceived the water
supply scheme fetching running over from distance of more than 100 km by
constructing a dam across river Tansa, to feed the population of Mumbai, then only a
few thousands in number. The items have changed with technological advancement
and the works like Roller Compacted Concrete Dam at Middle Vaitarna or numerous
underground tunnels for water supply and sewerage disposal, for example, have
become hallmark of MCGM's dedication to the citizen of Mumbai. The challenges
have always been daunting, nevertheless, always met with.
Every civilization be it 5000 years old Harrappan civilization on the bank of
Sindhu River, or Mumbai on the west coast of the Indian Ocean, require
infrastructure like water supply and sewerage system, storm water drainage system,
road, bridges, etc. and hospitals, markets, recreation centers etc. The exponentially
growing population of Mumbai and the technological explosion in the field of
engineering has made every aspect of contracting of works highly challenging.
M.C.G.M. is one of the largest local self government in the Asian Continent.
In observance of historic traditions of strong civic activism, with the change in time
and living conditions to match with the urbanization, M.C.G.M. has mainly focused in
providing variety of engineering services viz, storm water drain, sewerage, water
supply projects, roads, bridges, solid waste management, environmental services.
Beside this, the Corporation is also providing dedicated services in the Health sector
by establishing numbers of Major and Peripheral hospitals.
To update and modernize the mechanism being used for working on projects
from the stage of conceptualization upto execution, the need was realized to revise
prevailing Schedule of Rates along with specifications which were in operations
with various departments and being prepared individually as per their need and
used to revised at different span of time, resulting into various anomalies. Therefore,
to overcome all these, it was essential to revise the schedule of rates, not only with
simple mechanized revision, major changes to keep up with the pace of urbanization,
civilization, construction techniques / mechanization and voluminous developments
by restructuring items in the schedule as per requirements. This exercise would

provide comfort with field requirements and designs and will assist in effective
checks on creation of extra items during execution.
A conscious decision has been taken to keep pace with the changing time
and preparation of Unified Schedule of Rates is the first step forward in this direction.
Since long time, there have been demands made by the stake holders like Municipal
Engineers and Contractors about non-uniformity, anomalies and discrepancies in
various schedules of rates for work contracts of various departments of MCGM.
Every department had its own expertise and way of functioning which got reflected in
its independent schedule of rates, which, however, had no linkage with the fair
market schedules of other departments and resulting into extra items and fair rates.
In place of earlier 9 Schedule of Rates, the Unified Schedule of Rates is an effort &
seeks to rectify the defects, discrepancies and non uniformities which will provide,
not to mention about the ease and accuracy of estimation to the Engineers.
In view of the enormous and voluminous nature of work, keeping time
frame in perspective and above all, to ensure professionalism, the work of
preparation of Unified Schedule of Rates was awarded to the eminent consultants
M/s.Tata Consulting Engineers Ltd. M/s.Tata Consulting Engineers Ltd were directed
to conduct a thorough factual market research for major materials from
stockists/manufacturers/dealers and to study schedules of rates of Govt bodies like
C.P.W.D. and P.W.D. The new Rate Analysis are based on Factual Market research
done by M/s.Tata Consulting Engineers Ltd.
The anomalies in rate are minimized after extensive market research and
collection of quotations from reputed large scaled stockists/dealers, and also after
comparison with rates of CPWD, PWD etc.
The SOR is linked with its comprehensive specifications of basic important
activities so as to have clarity in execution. These specifications follow a chronology
of general scope of the item, material required, processing of material, construction
operation, finishing and mode of measurement.
All the rates are now linked to their detailed specifications and wherever
required, with drawings. Though there are about 12500 items, every item is now
given a Unique Code No. which will eliminate the repetition.
It has been our endeavour to include all the necessary modern materials and
technologies in SOR, for example, the concept of green building, which will go a long

way to have control on creation of extra items and fair rates. A salient feature of this
USR is 'Starring of items' specified, categorically which can be used only at certain
works or locations.
Another salient features is 'Dynamic Rate System' which will be based on
study of data base of quantities and bidding prices of awarded contracts on the basis
of which necessary corrections can be applied to the Unified Schedule of Rates at
specified intervals. The MCGM will be now in position to revise the Unified Schedule
of Rates every year after incumbency period of M/s.Tata Consulting Engineers Ltd of
one year, to work with and correct the system as and when necessary.
I hope this 'Unified Schedule of Rates' will be a milestone in civic governance
by MCGM. This self-contained publication shall be of great help and guidance to the
officers engaged in the project work of MCGM.

A.M.C. (Project)

Municipal Commissioner

SE SCHEDULE 2013

GENERAL NOTES
A. COMMON GENERAL NOTES

1. The schedule of rates will be operative from 16-09-2013


2. The unified schedule of rates includes following department:
i.

Buildings

ii. Water Supply Projects


iii. Hydraulic Engineering
iv. Sewerage Projects
v. Storm Water Drainage
vi. Roads
vii. Bridges
viii. Traffic and Signals
ix. Mechanical and Electrical
x. Garden Works
3. Volume-I contains USR, basic rate list and approved makes and Volume-II
contains specification along with drawings wherever necessary and mandatory
tests.
4. The specification of the items shall be as per latest Indian Standard Codes unless
otherwise specified.
5. The rates of the items in this schedule of rates are worked out assuming average
lead for Greater Mumbai area for all sorts of materials.
6. The rates are inclusive of transportation, duties, taxes and charges of all
Government, Municipal or any other statutory body, applicable from time to time
but exclusive of Works Contract Tax and Labour Cess levied by Government of
Maharashtra.
7. The rate analysis also includes Contractors Profit & Overheads @ 15%, the
break up for which is as follows :
Water Charges, cost of tools and plants: 5 %
Contractors Profit: 10%

Municipal Corporation of Greater Mumbai

SE SCHEDULE 2013

8. Rates of common material and labour is attached in the Annexure-A in Volume-I.


9. The building Schedule of Rates 2013 includes the existing items of FMA, FMB
2009, SIC and Fair items, with deletion of obsolete items, merger of similar items
and value addition of new items in line with modern technology and trends in
accordance with latest rules, regulation, byelaws etc.
10. As per the Government policy the use fly ash is done for framing the items of
work in accordance with the latest provisions of IS Codes. Also green building
items have been introduced in new schedule to minimize the consumption of
energy during construction and occupancy of building and also maintaining
ecological balance.
11. From safety, health and environment point of view two legged steel tubular
scaffolding shall be used, without making any holes in the outer face of the
building or any structure. And no extra payment shall be made for works like
scaffolding, centering for any height unless otherwise specified.
12. All materials shall be as per approved list of MCGM or equivalent material having
quality standards as per relevant IS codes and shall be of first quality unless
otherwise specified.
13. Following basic rates are considered in the USR:
i.

Cement : Rs. 6,000/ MT

ii. Mild Steel : Rs. 47,400/ MT


iii. HYSD Steel (Fe415) : Rs. 48,400/ MT
iv. T.M.T. (Fe500) : Rs. 49,400/ MT
v. Structural Steel : Rs. 53,400/ MT
14. Rates given in SOR are for estimation purpose.
15. Rates of items and specification for excavation, concrete, plaster and brickwork
shall be referred from common schedule unless and otherwise not mentioned in
concerned departments schedule.
16. Coding of items:
The Coding procedure for Basic master material is as follows:
Code will start with the common prefix of MA which stands for materials

Municipal Corporation of Greater Mumbai

SE SCHEDULE 2013

Followed by Abbreviation code for each schedule of rate for eg H.E. for
Hydraulic engineering, SE for Sewerage, WSP for water supply and so on
and so forth.
The first item category in the list will be numbered as 1
The last part of the code will be a number starting with a to indicate the item
number in the master list.
The alpha numeric will be separated by (dash).
The code will look like: MA-SE-01
The Coding procedure for SOR is as follows:
Code will start from abbreviation for Department name HE or WSP or SP
The USR will be subdivided into chapters according to the item classification;
these chapters will be numbered as 1, 2, 3 ..
The items under the chapter will be numbered from 1
The sub items will be numbered as a, b, c .
The code will look like SE-1-1-a
Abbreviations to be used for Department
Sr. No.
Department

Abbreviation

Building works/Common
Schedule

CS

Roads

RW

Traffic and Signaling

RT

Bridges

BW

Water Supply Projects

WSP

Hydraulic Engg.

HE

Sewerage Projects

SE

Storm Water Drains

SWD

Mechanical and electrical

ME

10

Garden Works

GW

Municipal Corporation of Greater Mumbai

SE SCHEDULE 2013

B. SALIENT FEATURES OF SOR FOR BUILDING WORKS


1) All the rates are for all heights and levels unless noted otherwise.
2) Chloropyrifos EC 20 has been considered for anti termite treatment.
3) Artificial sand (crushed sand) has been considered for flooring bedding and for
concrete work.
4) All the items are excluding fixtures otherwise not specified in respective item. In such
case, items of Hardware section shall be used for fixtures.
5) For plastering and mortar work, river sand has been considered.
6) For plastering work all the rates are for all heights and levels and architectural
decorative surface.
7) All external plaster items are including waterproofing compound except plastering
item for structures like compound wall, masonry pedestals, pillars, etc.
8) Items for ashlar masonry, dewatering, self compacting concrete, vacuum dewatered
concrete flooring and TMT steel bars have been introduced.
9) Rates of all the items in roofing work are inclusive of staging or scaffolding for any
height.
10) Non-asbestos cement sheet provided in place of asbestos cement sheet roofing.
11) Concreting of pile shall be done with RMC only.
12) Rates of piling are inclusive of Chiseling of intermediate local boulders. No separate
payment shall be made for the same
13) While estimating the quantity for Grouting of bentonite slurry in bored precast piles
shall be measured as per bore dia and pile dia. Exact quantity can be measured
while execution and shall be paid accordingly
14) Rates considered in concrete items are including pumping of concrete upto placing
point.
15) New items like Self compacting concrete, vacuum dewatered concrete flooring and
TMT steel bars have been introduced.
16) The dismantling and demolishing chapter covers only removing old items and repair
work covers both removing old items and refixing the new.
17) For heritage works the rate includes the statutory charges for heritage committee and
conservation architect and no extra payment will be made.
18) APP (Atactic poly-propylene) modified polymeric membrane water proofing will be
used only for trial basis on approval of City Engineer and/or Chief Engineer (P&D).
19) In plumbing waterless urinals, fly ash bricks, fly ash concrete for green building
concept have been introduced.

Municipal Corporation of Greater Mumbai

SE SCHEDULE 2013

Star Rating:
In view of ambiguity related to choice of quality or grade of materials and subsequent
items of works to be used at Ward level projects, Centralised projects or Special projects
of and for smooth functioning during planning stage of a project, the new concept of Star
Rating has been introduced for building works depending on the life expectancy of
building, degree of occupancy of building and comfort to the end user. The buildings or
structures rated are as follows:
i.

Two Star **- Ward offices and Central dept. Offices, schools, Small Hospitals,
Primary Health Center, Fire Station, Crematorium, Slaughter Houses,
Markets, Swimming Pools, Zoos, Chowkies, Libraries, Staff quarters and
residential colonies, Public Toilets and Water tanks.

ii. Three Star ***- Super specialty Hospitals, Drama Theatres, MCGM Mayors
and Officers bungalow, Heritage Structures, Head Office and Engineers
Hub.
The items or work not marked as two star or three star are assumed to be
applicable for all the star buildings or structures mentioned above.

Municipal Corporation of Greater Mumbai

SE SCHEDULE 2013

C. Department specific General note

List of Units used:


Sr. No.

Units

Abbreviation Symbol

Length (Running Meter)

Rmt

Weight (Metric Tonne)

MT

Weight Kilogram

Kg

Length (Meter)

Length (Millimeter)

mm

Time

Day/Shift

Remark

Day/Shift Refers to duration


of 8 Hrs

Time (Hour)

Hr

Quantity (Numbers)

Each/Nos.

Each refers to a single


quantity per entity

10

Quantity (Lump sum)

L.S

11

Volume

Cum

12

Area (Square Meter)

Sqm

List of Abbreviation used:


Sr.

Abbreviation

Remark

No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

SE:
CS:
SP:
SW PIPES:
EW:
CW:
BoQ:
EO:
RCC:
MW:
CM:
NP:
HDPE PIPES:
OD:
ID:

Code for SP
Common Schedule
Sewerage Projects
Stoneware Pipes
Earth Works
Civil Works
Bill of Quantities
Extra Over
Reinforced Cement Concrete
Masonary Works
Cement Mortar
Non pressure
High Density Polyethylene Pipes
Outer Diameter
Internal diameter

Municipal Corporation of Greater Mumbai

SE SCHEDULE 2013

16
17
18
19
20
21
22
23
24
25
26
27
28
29

DWC:
R/R:
EHD:
CI:
SFRC:
ASTM:
MS:
MA:
GN:
HE:
HC:
BLD:
LB:
CR:

Double Wall Corrugated


Rubber ring
Extra Heavy Duty
Cast Iron
Steel Fibre Reinforced Concrete
American Society for Testing and Materials
Mild Steel
Material
General
Hydraulic engineering
Hire charges
Building
Labour
Carriage Charges

Basis for labour and material Coefficients used:


The labour, material and hire charges coefficients adopted in rate analysis are worked out
taking into consideration the coefficients adopted (for similar or same item) in MJP SOR,
PWD SOR, Pune Mahanagar Palika SOR and MCGM HE SOR 2011.

The final amount appearing in SOR is completely rounded off, no decimal digits are
considered.
The final amount for an item worked out in RA template is rounded upto two decimal places.
Chapter wise Notes, Assumptions and References

Chapter 1: EXCAVATION:
Items to be referred from Common Schedule. Shoring items are kept. Mild Steel plate
shoring is introduced
Chapter 2: Concreter:
Items Rate Updated
Chapter 3: Masonry:
Stone Pitching shifted to Road Schedule
Chapter 4: Plasterer:
Rate of items updated
Chapter 5: Pipe works:
Stoneware pipes of SP2 class added

Municipal Corporation of Greater Mumbai

SE SCHEDULE 2013

RCC NP3 class pipes extended upto 2400mm diameter


HDPE, DWC pipe added
P1 pipes removed
Chapter 6: Manholes:
Manhole sizes of 3mx2m, 3mx3m, 1.8mx1.8m added. Items of SFRC cover and
copolymer steps added for all sizes of manholes.
Chapter 7: Drop Connection:
NP2 connections removed
HDPE connections introduced

Chapter 8: Inspection Chambers:


Items for SFRC cover and copolymer steps added
Chapter 9: Vent Shaft:
Generally Updated
Chapter 10: Iron Works:
Generally Updated
Chapter 11: Desilting:
Generally Updated
Diameters of pipe updated
Chapter 13: Microtunneling:
Microtunneling excavation items for NP4 class pipe and MS pipe added. Pipe jacking
items added.
Chapter 14: HDD
HDD items added

Municipal Corporation of Greater Mumbai

SE SCHEDULE 2013

INDEX
Sr.no

Chapter
code

Contents

Item Range

Page no

SE-1

EXCAVATION AND ALLIED


WORKS FOR SEWERAGE

SE-1-1 TO SE-1-6

1-2

SE-2

CONCRETOR

SE-2-1 TO SE-2-15

3-4

SE-3

MASONRY

SE-3-1 TO SE-3-17

SE-4

PLASTERER

SE-4-1 TO SE-4-13

SE-5

PIPES

SE-5-1 TO SE-5-16

7-10

SE-6

MANHOLES

SE-6-1 TO SE-6-27

11-19

SE-7

DROP ARRANGEMENT

SE-7-1 TO SE-7-14

20-21

SE-8

INSPECTION CHAMBER

SE-8-1 TO SE-8-8

22-23

SE-9

VENT SHAFTS

SE-9-1 TO SE-9-10

24

10

SE-10

IRON WORKS

SE-10-1 TO SE-10-14

25

11

SE-11

DESILTING

SE-11-1 TO SE-11-6

26

12

SE-12

MISCELLANEOUS

SE-12-1 TO SE-12-19

27-28

13

SE-13

MICROTUNNELING AND
PIPE JACKING

SE-13-1 TO SE-13-4

29-31

14

SE-14

HORIZONTAL
DIRECTIONAL DRILLING
AND PIPE INSTALLATION

SE-14-1 TO SE-14-2

32

MUNICIPAL CORPORATION OF GREATER


MUMBAI

Chapter -1
EXCAVATION AND ALLIED
WORKS FOR SEWERAGE

SE SCHEDULE 2013
Excavation and Allied Works for Sewerage

ITEM CODE

ITEM DESCRIPTION

UNIT

SE-1-1

Excavation in all types of soils(for laying pipe,construction of


chambers / manholes),such as Earth,Marine clay,Marshy
land,Running sand, Garbage, Slush, Murum,Rock boulders
etc as directed by the engineer.The rate includes pumping out
water, backfilling, removing the rank vegetation and removing
the excavated materials within a lead of 150M as directed
including levelling, ramming,etc complete, and measured from
the edge of cutting including all lifts and stackingin layers and
removing the surplus excavated materials as directed{Records
to be maintained properly}.The rate also includes supporting
public utilities such as cables,drains,pipe water mains, but
shall not include the cost of shoring etc as specified and
directed.

SE-1-1-a

upto 1.5M

Cum

SE-1-1-b

Extra over above item SE-1-1-a for lift from 1.5m to 3.0m.

Cum

SE-1-1-c

Extra over above item SE-1-1-a for lift from 3.0m to 4.5m

Cum

SE-1-1-d

Extra over above item SE-1-1-a for lift from 4.5m to 6.0m

Cum

SE-1-1-e

Extra over above item SE-1-1-a for lift from 6.0m to 7.5m

Cum

SE-1-1-f

Extra over above item SE-1-1-a for lift from 7.5m to 9.0m

Cum

SE-1-1-g

Extra over above item SE-1-1-a for lift from 9.0m to 10.5m

Cum

SE-1-1-h

Extra over above item SE-1-1-a for lift from 10.5m to 12.0m

Cum

SE-1-1-i

Extra over above item SE-1-1-a for lift from 12.0m to 13.5m

Cum

SE-1-1-j

Extra over above item SE-1-1-a for lift from 13.5m to 15.0m

Cum

SE-1-1-k

excavation in soft rock by using pickaxe

Cum

SE-1-1-l

excavation in hard strata by controlled blasting

Cum

SE-1-1-m

Do. -- by chiselling.

Cum

SE-1-1-n

Do. -- by splitter machine.

Cum

RATE

Refer CS-EW1
Refer CS-EW2-a
Refer CS-EW2-b
Refer CS-EW2-c
Refer CS-EW2-d
Refer CS-EW2-e
Refer CS-EW2-f
Refer CS-EW2-g
Refer CS-EW2-h
Refer CS-EW2-i
Refer CS-EW3
Refer CS-EW6
Refer CS-EW4
Refer CS-EW5

[Note: sanction of director/DMC (SE)/DMC(E) should be


obtained for including the item in BOQ during the approval of
Draft Tender]

MUNICIPAL CORPORATION OF GREATER MUMBAI

SE SCHEDULE 2013
Excavation and Allied Works for Sewerage

ITEM CODE

UNIT

RATE

Cum

Refer CS-EW3

Cum

Refer CS-EW3

Rmt

136.00

Cum

CS-EW-8

Cum

CS-EW-9

SE-1-4

Providing and removing open or closed shoring and strutting in


the trenches/ pits for all depths as per specifications/ drawings
and or as directed by Engineer-in-charge by including walling,
struts, open poling boards, horizontal sheeting, runners, dog
spikes by using timber etc. complete.

Sqm

369.00

SE-1-5

Leaving shoring in trenches. (New or old) including dog


spikes.

Sqm

1793.00

SE-1-6

Providing and fixing M.S plate shoring in trench consisting of


12mm thick M.S sheet, 1.5m wide MS channel 150x75mm,at
1.5m center to centre including removal after laying sewer

Sqm

2814.00

SE-1-1-o

SE-1-1-p

SE-1-2
SE-1-3

ITEM DESCRIPTION
Excavation in road carriage ways,foot path,asphalt mixed
carpet of any type upto any depth,including all lifts and
depositing excavated materials in a radius of 150M as
specified and directed
Do. -do-- in plain or reinforced concrete road including cutting
of reinforcements manually or using pneumatic jack hammer
or by any other means,-do-doProviding watching fencing etc. to trench excavation per
running meter length of trench as per drawing and as directed
by Engineer.
Transporting surplus materials upto 3 Km. including levelling.
[Note : Prior Specific sanction of Head of Deptt. should be
taken if transportation is to be done at night i.e. between 8.00
pm. to 6 am.and the rate should be reduced by 10%] {This
item will be operated with the specific sanction of the
C.E./Chief Engineer and above}
[Note : Prior Specific sanction of Head of Deptt. should be
taken if transportation is to be done at night i.e. between 8.00
pm. to 6 am. and the rate should be reduced by 10%]

SE-1-3-a

E.O. above for transporting beyond 3 km. for every 1 km.


[Note : Prior sanction of Head of Deptt. should be taken if
transportation is to be done at night i.e. between 8.00 p.m to 6
a.m. and the rate should be reduced by 10%]

MUNICIPAL CORPORATION OF GREATER MUMBAI

Chapter -2
CONCRETOR

SE SCHEDULE 2013
Concretor

ITEM CODE

ITEM DESCRIPTION

UNIT

RATE

Cum

4652.00

-do- -do- for full encasement or cradle -do- -do-do- -do- in saddle block -do- -do-do- -do- M 15 c.c. In foundation including boxing, curing etc.
complete as specified and as directed.

Cum
Cum

5171.00
5002.00

Cum

5229.00

SE-2-5

-do- -do- M 15 c.c. For full encasement or cradle -do- -do-

Cum

5761.00

SE-2-6

-do- -do- in sides and haunches and/or in block coping-do- -do-

Cum

6290.00

SE-2-7
SE-2-8
SE-2-9

do- -do- in saddle block -do- -do-do- -do- in arch work -do- -doProviding and laying M 20 c.c. In foundations -do- -do-do- -do- in sides and haunches and /or block coping -do- do-do- -do- in arch work -do- -doREINFORCED CONCRETOR
Note: 1. Wastage in cutting will not be paid for. Only steel
actually fixed in position will be paid by linear measurement
including hooks & bends. No payment will be made for binding
wires, pins be made for binding wires, pins, chairs and laps
and / or welding and this should be noted while quoting the
rates.
2. In working out the rates for .R.C.C. Items and steel
reinforcement, the basic rates for steel bars per tonne are
taken as mentioned in Basic Material Master, If steel is
controlled in future the necessary adjustment between the
controlled rate and the rates stated above will have to be
made.
3. Note of concretor: (b) is applicable here(controlled
concrete).

Cum
Cum
Cum

6118.00
6504.00
5766.00

Cum

7060.00

Cum

6502.00

Note : a) Unless or otherwise stated the coarse aggregate


shall consist of metal 10 mm and 20 mm size (metal No.1 & 2)
mixed in equal proportion or as directed and the rates shall
cover the cost of complete work including boxing, ramming,
consolidating, watering and curing.
b) In controlled concrete the determination of the proportions
of cement ,aggregate and water to attain the required strength
shall be made with the preliminary test by designing the
concrete mix.
c) All the concrete items include vibrating by Mechanical
vibrator.
d) In case controlled concrete cannot be used for want of
testing due to small quantity of work M 10 may be taken as
equivalent to 1:3:6
M 15 = 1:2:4
M 20 = 1: 1 1/2 : 3
SE-2-1
SE-2-2
SE-2-3
SE-2-4

SE-2-10
SE-2-11
`

Providing & laying M 10 c.c. For foundation/bedding including


boxing, curing etc. complete as specified and as directed.

MUNICIPAL CORPORATION OF GREATER MUMBAI

SE SCHEDULE 2013
Concretor

SE-2-12

Providing M 15 R.C.C. Work in dhapas, beams and slabs etc.


with standard reinforcement of 1% including centering etc. and
finished smooth the exposed surface with cement sand
plaster 12 mm thick in the proportion 1:2 as directed.

Cum

10607.00

SE-2-13
SE-2-14
SE-2-15

-do- without reinforcement -do- do-do- M20 RCC work-do- as per item no SE-2-12
-do- without reinforcement -do- do-

Cum
Cum
Cum

6808.00
10613.00
6813.00

MUNICIPAL CORPORATION OF GREATER MUMBAI

Chapter -3
MASONRY

SE SCHEDULE 2013
Plasterer

ITEM CODE

ITEM DESCRIPTION

SE-4-1

Providing 12 mm thick cement plaster in cement mortar 1:2


including neat cement rendering.
-do- -do- with approved water proofing compound in a
proportion as specified by the manufacturers, per bag of
cement.
-do- -do- 20 mm thick -do- -do- (without water proofing
compound) -do- -do-do- -do- with approved water proofing compound in a
proportion as specified by the manufacturer's per bag of
cement.
-do- -do- 25 mm thick -do- -do- (without water proofing
compound) .
-do- -do- 25 mm thick -do- -do- with approved water proofing
compound in a proportion as specified by the manufacturers
per bag of cement.
Providing 12 mm thick cement plaster in cement mortar 1:1
including neat cement rendering.
-do- -do- 12 mm thick with approved water proofing
compound in a proportion as specified by the manufacturers
per bag of cement.
-do- -do- 20 mm thick -do- -do- (without water proofing
compound).
-do- -do- 20 mm thick with approved water proofing
compound in a proportion as specified by the manufacturers
per bag of cement.
-do- -do- 25 mm thick -do- -do- (without water proofing
compound)
-do- -do- 25 mm thick with approved water proofing
compound in a proportion as specified by the manufacturers
per bag of cement.

SE-4-2

SE-4-3
SE-4-4

SE-4-5
SE-4-6

SE-4-7
SE-4-8

SE-4-9
SE-4-10

SE-4-11
SE-4-12

SE-4-13

Extra for using approved water proofing compound in plaster


work in the ratio as per manufacturer's specifications.

UNIT

RATE

Sqm

156.00

Sqm

167.00

Sqm

240.00

Sqm

256.00

Sqm

311.00

Sqm

330.00

Sqm

189.00

Sqm

204.00

Sqm

300.00

Sqm

324.00

Sqm

400.00

Sqm

431.00

Kg

45.00

MUNICIPAL CORPORATION OF GREATER MUMBAI

Chapter -4
PLASTERER

SE SCHEDULE 2013
Plasterer

ITEM CODE

ITEM DESCRIPTION

SE-4-1

Providing 12 mm thick cement plaster in cement mortar 1:2


including neat cement rendering.
-do- -do- with approved water proofing compound in a
proportion as specified by the manufacturers, per bag of
cement.
-do- -do- 20 mm thick -do- -do- (without water proofing
compound) -do- -do-do- -do- with approved water proofing compound in a
proportion as specified by the manufacturer's per bag of
cement.
-do- -do- 25 mm thick -do- -do- (without water proofing
compound) .
-do- -do- 25 mm thick -do- -do- with approved water proofing
compound in a proportion as specified by the manufacturers
per bag of cement.
Providing 12 mm thick cement plaster in cement mortar 1:1
including neat cement rendering.
-do- -do- 12 mm thick with approved water proofing
compound in a proportion as specified by the manufacturers
per bag of cement.
-do- -do- 20 mm thick -do- -do- (without water proofing
compound).
-do- -do- 20 mm thick with approved water proofing
compound in a proportion as specified by the manufacturers
per bag of cement.
-do- -do- 25 mm thick -do- -do- (without water proofing
compound)
-do- -do- 25 mm thick with approved water proofing
compound in a proportion as specified by the manufacturers
per bag of cement.

SE-4-2

SE-4-3
SE-4-4

SE-4-5
SE-4-6

SE-4-7
SE-4-8

SE-4-9
SE-4-10

SE-4-11
SE-4-12

SE-4-13

Extra for using approved water proofing compound in plaster


work in the ratio as per manufacturer's specifications.

UNIT

RATE

Sqm

156.00

Sqm

167.00

Sqm

240.00

Sqm

256.00

Sqm

311.00

Sqm

330.00

Sqm

189.00

Sqm

204.00

Sqm

300.00

Sqm

324.00

Sqm

400.00

Sqm

431.00

Kg

45.00

MUNICIPAL CORPORATION OF GREATER MUMBAI

Chapter -5
PIPES

SE SCHEDULE 2013
Pipes

ITEM CODE

ITEM DESCRIPTION

Stoneware Pipes
Providing & laying stoneware pipes of SP2 class including
jointing with CM(1:1), filleting etc. complete as specified &
directed.

SE-5-1

SE-5-1-a
SE-5-1-b
SE-5-1-c
SE-5-2

SE-5-2-a
SE-5-2-b
SE-5-2-3
SE-5-3

SE-5-3-a
SE-5-3-b
SE-5-3-c
SE-5-4

SE-5-4-a
SE-5-4-b
SE-5-4-c
SE-5-5

SE-5-5-a
SE-5-5-b
SE-5-5-c
SE-5-6

SE-5-6-a
SE-5-6-b
SE-5-6-c
B
SE-5-7

SE-5-7-a
SE-5-7-b
SE-5-7-c
SE-5-7-d

UNIT

RATE

150mm dia
230mm dia
300mm dia

Rmt
Rmt
Rmt

460.00
730.00
1195.00

Providing & laying stoneware pipes of SP2 class including


jointing with rubber rings etc. complete as specified &
directed.
150mm dia
230mm dia
300mm dia

Rmt
Rmt
Rmt

404.00
683.00
1141.00

Each
Each
Each

233.00
571.00
1057.00

Each
Each
Each

338.00
860.00
1202.00

Each
Each
Each

580.00
1053.00
1480.00

Each
Each
Each

225.00
592.00
1117.00

Rmt
Rmt
Rmt
Rmt

687.00
986.00
1220.00
1534.00

Providing & laying stoneware bends of SP2 class including


jointing with CM(1:1), filleting etc complete as specified &
directed
150mm dia
230mm dia
300mm dia
Providing & laying stoneware single junction of SP2 class
including jointing with CM (1:1), filleting etc complete as
specified & directed
150mm dia
230mm dia
300mm dia
Providing & laying stoneware double junction of SP2 class
including jointing with CM (1:1), filleting etc complete as
specified & directed
150mm dia
230mm dia
300mm dia
Providing & laying stoneware bends/tees of SP2 class
including jointing with rubber rings complete as specified &
directed
150mm dia
230 mm dia
300 mm dia
RCC Pipes
Providing and laying R.C.C Pipe (NP3 Class) with collar joints
including jointing with CM(1:1) & filleting etc. complete as
specified and directed.
150mm dia
200mm dia
250mm dia
300mm dia

MUNICIPAL CORPORATION OF GREATER MUMBAI

SE SCHEDULE 2013
Pipes

ITEM CODE
SE-5-8

SE-5-8-a
SE-5-8-b
SE-5-8-c
SE-5-8-d
SE-5-8-e
SE-5-8-f
SE-5-8-g
SE-5-8-h
SE-5-8-i
SE-5-8-j
SE-5-8-k
SE-5-8-l
SE-5-8-m
SE-5-8-n
SE-5-8-o
SE-5-8-p
SE-5-8-q
SE-5-8-r
C
SE-5-9

SE-5-9-a
SE-5-9-b
SE-5-9-c
SE-5-9-d
SE-5-9-e
SE-5-9-f
SE-5-9-g
SE-5-9-h
SE-5-9-i
SE-5-9-j
SE-5-9-k
SE-5-9-l
SE-5-9-m
SE-5-9-n
SE-5-9-m
SE-5-10

SE-5-10-a
SE-5-10-b
SE-5-10-c
SE-5-10-d
SE-5-10-e
SE-5-10-f

ITEM DESCRIPTION

UNIT

RATE

Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt

1157.00
1754.00
1995.00
2184.00
2572.00
3096.00
4009.00
4986.00
6185.00
6808.00
8004.00
8629.00
11376.00
13910.00
16829.00
20099.00
21747.00
22596.00

Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt

753.00
1139.00
1721.00
2126.00
2674.00
3375.00
4354.00
5564.00
6849.00
8532.00
10785.00
13870.00
17572.00
22213.00
27423.00

Each
Each
Each
Each
Each
Each

982.00
1390.00
2633.00
3731.00
6362.00
7170.00

Providing and laying R.C.C. Pipes (NP3 Class) with rubber


rings jointing etc. complete as specified and directed.
300mm dia
350mm dia
400mm dia
450mm dia
500mm dia
600mm dia
700mm dia
800mm dia
900mm dia
1000mm dia
1100mm dia
1200mm dia
1400mm dia
1600mm dia
1800mm dia
2000mm dia
2200mm dia
2400mm dia
HDPE Pipes
Providing, Laying and Jointing HDPE pipes of PE-80 grade
and PN-6 class with butt joints etc.complete as specified and
directed
160 mm dia (OD)
200 mm dia (OD)
250 mm dia (OD)
280 mm dia (OD)
315 mm dia (OD)
355 mm dia (OD)
400 mm dia (OD)
450 mm dia (OD)
500 mm dia (OD)
560 mm dia (OD)
630mm dia (OD)
710 mm dia (OD) -do-do- but of PE-100 and PN6 class
800 mm dia (OD)-do-do- but of PE-100 and PN6 class
900 mm dia (OD)-do-do- but of PE-100 and PN6 class
1000 mm dia (OD)-do-do- but of PE-100 and PN6 class
Providing, Laying and Jointing HDPE bends/tees of PE-80
grade and PN-6 class with butt joints etc.complete as specified
and directed
160 mm dia (OD)
200 mm dia (OD)
250 mm dia (OD)
280 mm dia (OD)
315 mm dia (OD)
355 mm dia (OD)

MUNICIPAL CORPORATION OF GREATER MUMBAI

SE SCHEDULE 2013
Pipes

ITEM CODE

ITEM DESCRIPTION

SE-5-10-g
SE-5-10-h
SE-5-10-i
SE-5-10-j
SE-5-10-k
D
SE-5-11

400 mm dia (OD)


450 mm dia (OD)
500 mm dia (OD)
560 mm dia (OD)
630mm dia (OD)
DWC PE Pipes

SE-5-11-a
SE-5-11-b
SE-5-11-c
SE-5-11-d
SE-5-11-e
SE-5-11-f
SE-5-11-g
SE-5-11-h
SE-5-11-i

160 mm dia (OD)


200 mm dia (OD)
250 mm dia (OD)
315 mm dia (OD)
400 mm dia (OD)
500 mm dia (OD)
630mm dia (OD)
800 mm dia (OD)
1000mm dia (OD)

SE-5-12

SE-5-12-a
SE-5-12-b
SE-5-12-c
SE-5-12-d
SE-5-12-e
SE-5-12-f
SE-5-12-g
E
SE-5-13

SE-5-13-a
SE-5-13-b
SE-5-13-c
SE-5-14

SE-5-14-a
SE-5-14-b
SE-5-14-c

UNIT

RATE

Each
Each
Each
Each
Each

8078.00
9083.00
10093.00
11303.00
12711.00

Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt

548.00
819.00
1129.00
1490.00
2383.00
3026.00
5811.00
9433.00
14679.00

Each
Each
Each
Each
Each
Each
Each

724.00
1032.00
1555.00
2248.00
2534.00
3549.00
4465.00

Rmt
Rmt
Rmt

32.00
42.00
63.00

Rmt
Rmt
Rmt

11.00
16.00
32.00

Providing, Laying and Jointing Double Wall Corrugated


(DWC) PE pipes of SN 8 class with R/R joint with PE coupler
as per ISO21138-3 complete as specified and directed

Providing, Laying and Jointing bends/tees of Double wall


corrugated (DWC) PE pipes of SN 8 class with R/R joints with
PE coupler joints as per ISO 21138-3 complete as specified
and directed
160 mm dia (OD)
200 mm dia (OD)
250 mm dia (OD)
315 mm dia (OD)
400 mm dia (OD)
500 mm dia (OD)
630mm dia (OD)
Transportation of Pipes and Fittings
Transporting stoneware pipe from municipal stores or factory
stores anywhere in City/H&K/L&M/P&R/N S & T Wards to the
work site including, loading unloading & stacking near the
work site as directed.
150mm dia
230mm dia
300mm dia
Transporting stoneware bends,single T,double T from
municipal
stores
or
factory
stores
anywhere
in
City/H&K/L&M/P&R/N S & T Wards to the work site including,
loading unloading & stacking near the work site as directed.
150mm dia
230mm dia
300mm dia

MUNICIPAL CORPORATION OF GREATER MUMBAI

SE SCHEDULE 2013
Pipes

ITEM CODE

ITEM DESCRIPTION

UNIT

RATE

SE-5-15

Transporting R.C.C(NP3 CLASS )pipes and collars from


Municipal stores anywhere in City /H&K /P&R /L&M /N&S&T
wards to the work site including loading unloading and
stacking near the work site as directed.
150mm dia
200mm dia
250mm dia
300mm dia

Rmt
Rmt
Rmt
Rmt

26.00
35.00
41.00
52.00

Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt

327.00
331.00
341.00
355.00
368.00
460.00
546.00
764.00
989.00
1331.00
1365.00
1365.00
2116.00
2116.00
2867.00
3009.00
3151.00
3363.00

SE-5-15-a
SE-5-15-b
SE-5-15-c
SE-5-15-d
SE-5-16

SE-5-16-a
SE-5-16-b
SE-5-16-c
SE-5-16-d
SE-5-16-e
SE-5-16-f
SE-5-16-g
SE-5-16-h
SE-5-16-i
SE-5-16-j
SE-5-16-k
SE-5-16-l
SE-5-16-m
SE-5-16-n
SE-5-16-o
SE-5-16-p
SE-5-16-q
SE-5-16-r

Transporting R.C.C pipe (NP3 CLASS) with rubber rings from


Municipal stores or factory stores anywhere in City /H&K /P&R
/L&M /N&S&T wards to the work site including loading
unloading and stacking near the work site as directed.
300mm dia
350mm dia
400mm dia
450mm dia
500mm dia
600mm dia
700mm dia
800mm dia
900mm dia
1000mm dia
1100mm dia
1200mm dia
1400mm dia
1600mm dia
1800mm dia
2000mm dia
2200mm dia
2400mm dia

10

MUNICIPAL CORPORATION OF GREATER MUMBAI

Chapter -6
MANHOLES

SE SCHEDULE 2013
Manholes

ITEM CODE

ITEM DESCRIPTION

UNIT

RATE

SE-6-1

Constructing on sewer brick masonry conical manholes 1.2M


dia. at bottom 0.56 M. dia. at top, built in brick masonry in
cement mortar 1:3, plastered both inside and outside with 20
mm thick cement mortar 1:2 and neat cement rendering so as
to give a smooth surface, including 300 mm thick M.15
cement concrete in foundation and in haunches and channels
finished smooth with 20mm thick cement plaster in cement
mortar 1:1 and providing C.I. steps (weighing 5.4 kg each)
staggered at 300 mm. c/c including 75mm wide vata all round
the external portion of the manhole and the foundation
concrete in cement mortar 1:1 and supporting the incoming
pipes with brick masonry wherever necessary including C.I.
extra heavy duty (EHD) air-tight circular frame & cover
(minimum 230 Kg.) with hinge/chain resting on 30 cm high
cement concrete M.20 cap with necessary centering etc. all
complete as per standard specifications and directions
including finishing the cap with cement plaster on both sides
1:2 and neat cement rendering so as to give a smooth surface
in line and level with the brick masonry surface and as per
drawing inDyCh.E.(Sewerage)P&D's office without excavation
depth upto 1.5 M.(Depth of Manhole measured from top of
manhole cover to Invert level of manhole)

Each

39023.00

m.depth

9895.00

Each

49372.00

m.depth

13101.00

m.depth
m.depth
m.depth
m.depth

14159.00
14280.00
16928.00
17646.00

Each

61119.00

SE-6-1-a

SE-6-2-b

SE-6-2-c
SE-6-2-d
SE-6-2-e
SE-6-2-f
SE-6-2-g

SE-6-3

SE-6-3-a
SE-6-3-b

Extra over above per metre depth above 1.5 M. and upto 2.3
M. depth -do- -doConstructing on sewer brick masonry conical manhole 1.5 M.
dia. at bottom and 0.56 M dia. at top including C.I.
Extra.Heavy Duty circular air tight frame and cover etc.
complete as per description in item No.SE-6-1 depth upt0 2.3
M.
Extra for above manhole per metre depth above 2.3M and
upto 5 M including safety chain and extra C.I steps on other
side of benching-do-doDo- -do- above 5 M & upto 9 M -do- -doDo- -do- above 9.M & upto 11 M -do- -doDo- -do- above 11M & upto 12 M -do- -doDo- -do- above 12 M and upto 14 M depth -do- -doConstructing on sewer brick masonary conical manhole 1.8M
dia. at bottom 0.56M dia at top, including C.I. Extra heavy Duty
airtight circular frame and cover etc. complete as per
description in Item No.SE-6-1 depth upto2.9 M

Extra for above manhole per metre depth above 2.9M and
upto 5 M including safety chain and extra C.I steps on other m.depth
side of benching-do-doDo- -do- above 5 M. and upto 9M -do- -dom.depth

11

21387.00
29362.00

MUNICIPAL CORPORATION OF GREATER MUMBAI

SE SCHEDULE 2013
Manholes

ITEM CODE

ITEM DESCRIPTION

UNIT

RATE

SE-6-3-c
SE-6-3-d
SE-6-3-e

Do- -do- above 9 M. and upto 11M -do- -doDo- -do- above 11M and upto 12M -do- -doDo- -do- above 12 M and upto 14 M depth -do- -doConstructing on sewer brick masonary trapezoidal manhole
1.5M x 0.9M at bottom and 0.9M x 0.45M at top, including C.I.
EHD airtight rectangular frame and cover weighing minimum
225 kg . complete as per description in Item No.SE-6-1 depth
upto 1.2M
Extra for above manhole above 1.2M and upto 2.3M depth doConstructing on sewer brick masonary trapezoidal manhole
1.5M x 1.2M at bottom and 0.9M x 0.6M at top, including C.I.
EHD airtight rectangular frame and cover weighing minimum
270 kg . complete as per description in Item No.SE-6-1 depth
upto 1.2M
Extra for above manhole above 1.2M and upto 2.3M depth doConstructing on sewer brick masonry trapezoidal manhole
1.8M x 1.5 M at bottom and 0.9 M x 0.6M at top, including C.I.
EHD airtight rectangular frame and cover weighing minimum
270 kg . complete as per description in Item No.SE-6-1 depth
2.9 M
Extra for above manhole per metre depth above 2.9M and
upto 5 M including safety chain and extra C.I steps on other
side of benching-do-doDo- -do- above 5 M depth and upto 9 M depth -do- -doDo- -do- above 9M and upto 11M depth
-do- -doDo- -do- above 11 M and upto 12 M depth -do -doDo- -do- above 12 M and upto 14 M depth -do- -do-

m.depth
m.depth
m.depth

38910.00
45079.00
46903.00

Each

36869.00

m.depth

11716.00

Each

42572.00

Each

12511.00

Each

77276.00

m.depth

28116.00

m.depth
m.depth
m.depth
m.depth

39464.00
46361.00
68945.00
85426.00

SE-6-4

SE-6-4-a

SE-6-5

SE-6-5-a

SE-6-6

SE-6-6-a
SE-6-6-b
SE-6-6-c
SE-6-6-d
SE-6-6-e

12

MUNICIPAL CORPORATION OF GREATER MUMBAI

SE SCHEDULE 2013
Manholes

ITEM CODE

SE-6-7

SE-6-7-a
SE-6-7-b
SE-6-7-c
SE-6-7-d

SE-6-8

SE-6-8-a
SE-6-8-b
SE-6-8-c
SE-6-8-d
SE-6-8-e

SE-6-9

ITEM DESCRIPTION

Constructing brick masonary trapezoidal manhole on sewer


2.4M x 1.5M at bottom and 0.9M x 0.6M at top built in brick
masonary in C.M. 1:3 plastered both inside and outside with
20 mm thick cement plaster in C.M. 1:2 and neat cement
rendering so as to give a smooth surface 300 mm thick M 20
cement concrete in foundation and in haunches and channels
finished smooth with 20 mm cement plaster in C.M. 1:1 and
providing C.I. steps (approximately weighing 5.4 kg
each)staggered at 300mm c/c. including 75 mm wide vata all
round the external portion of the manhole and the foundation
concrete in cement mortar 1:1 and supporting the incoming
pipes with brick masonary wherever necessary including 0.9m
x 0.6M C.I. EHD airtight rectangular frame and cover weighing
minimum 270 kg resting on 300mm high cement concrete
M20 cap with necessary centering including cement plaster
(1:2) on both sides neat cement rendering so as to give a
smooth surface in line and level including safety chain and
extra C.I steps on other side benching complete as per
standard specifications & directions and as per drawing in
Dy.Ch.E. (SP) P&D's office without excavation depth upto
4.5M

UNIT

RATE

Each

168169.00

Extra per metre depth of the above manhole -do- -do- as per
m.depth
above item -do- -do- from 4.5 to 9M depth.
Do- -do- above from 9M and upto 11M depth -do- -dom.depth
Do- -do- above from 11 M and upto 12 M depth -do -dom.depth
Do- -do- above 12 M and upto 14 M depth -do- -dom.depth
Constructing on sewer brick masonry scraper manhole 1.5M
x 1.5 M at bottom and 1.2 M x 0.9M at top, including C.I. EHD
airtight rectangular frame and cover weighing minimum 900 kg
. complete as per description in Item No.SE-6-1 depth 2.9 M
Extra for above manhole per metre depth above 2.9M and
upto 5 M including safety chain and extra C.I steps on other
side of benching-do-doDo- -do- above 5 M depth and upto 9 M depth -do- -doDo- -do- above 9M and upto 11M depth
-do- -doDo- -do- above 11 M and upto 12 M depth -do -doDo- -do- above 12 M and upto 14 M depth -do- -doConstructing on sewer brick masonry scraper manhole 1.8M x
1.5M at bottom and 1.2M x 0.9M at top , including C.I. EHD
airtight rectangular frame and cover weighing minimum 900 kg
etc. complete as per description in item No. SE-6-1 depth upto
2.9M

13

39765.00
51394.00
59098.00
59802.00

Each

116078.00

m.depth

23611.00

m.depth
m.depth
m.depth
m.depth

33055.00
38797.00
57623.00
60795.00

Each

123777.00

MUNICIPAL CORPORATION OF GREATER MUMBAI

SE SCHEDULE 2013
Manholes

ITEM CODE

SE-6-9-a
SE-6-9-b
SE-6-9-c
SE-6-9-d
SE-6-9-e

SE-6-10

SE-6-10-a
SE-6-10-b
SE-6-10-c
SE-6-10-d
SE-6-10-e

SE-6-11

SE-6-11-a
SE-6-11-b
SE-6-11-c
SE-6-11-d

SE-6-12

SE-6-12-a
SE-6-12-b
SE-6-12-c
SE-6-12-d

SE-6-13

SE-6-13-a
SE-6-13-b

ITEM DESCRIPTION
Extra for above manhole per metre depth above 2.9M and
upto 5 M including safety chain and extra C.I steps on other
side of benching-do-doDo- -do- above 5 M and upto 9 M depth - do- -doDo- -do- above 9 M and upto 11M depth -do- -doDo- -do- above 11 M and upto 12 M depth -do -doDo- -do- above 12 M and upto 14 M depth -do- -doConstructing on sewer brick masonry scraper manhole 1.8M x
1.8M at bottom and 1.2M x 0.9M at top , including C.I.
Rectangular EHD airtight frame and cover weighing minimum
900 kg etc. complete as per description in item No. SE-6-1
depth upto 2.9M
Extra for above manhole per metre depth above 2.9M and
upto 5 M including safety chain and extra C.I steps on other
side of benching-do-doDo- -do- above 5 M and upto 9 M depth - do- -doDo- -do- above 9 M and upto 11M depth -do- -doDo- -do- above 11 M and upto 12 M depth -do -doDo- -do- above 12 M and upto 14 M depth -do- -doConstructing brick masonary scraper type manhole on sewer
2.4M x 1.5M at bottom and 1.2M x 0.9M at top built in brick
masonary in C.M. 1:3 -do- -do- as per item No. SE-6-8
including C.I. Rectangular EHD air tight frame and cover
(
weighing minimum 900 kg ), safety chain and extra C.I. steps,
depth upto 4.5M
Extra for above manhole per metre depth above 4.5M and
upto 9M depth.
-do- -do- 9 M to 11M depth
-do- -do- 11 M to 12M depth
Do- -do- above 12 M and upto 14 M depth -do- -doConstructing brick masonary scraper type manhole on sewer
2.4M x 2.4M at bottom and 1.2M x 0.9M at top built in brick
masonary in C.M. 1:3 -do- -do- as per item no. SE-6-8
including C.I. Rectangular EHD airtight frame and cover
weighing minimum 900 kg, safety chain and extra C.I. steps,
depth upto 4.5 M.
Extra for above manhole above 4.5M to 9M depth
-do- -do- 9 M to 11 M depth
-do- -do- 11 M to 12 M depth
Do- -do- above 12 M and upto 14 M depth -do- -doConstructing brick masonary scraper type manhole on sewer
3M x 2M at bottom and 1.2M x 0.9M at top built in brick
masonary in C.M. 1:3 -do- -do- as per item no. SE-6-8
including C.I. Rectangular EHD airtight frame and cover
weighing minimum 900 kg safety chain and extra C.I steps,
depth upto 4.5 M.
Extra for above manhole above 4.5M to 9M depth
-do- -do- 9 M to 11 M depth

14

UNIT

RATE

m.depth

25341.00

m.depth
m.depth
m.depth
m.depth

37327.00
47356.00
65603.00
68403.00

Each

126949.00

m.depth

27071.00

m.depth
m.depth
m.depth
m.depth

41599.00
55915.00
73583.00
76012.00

Each

196748.00

m.depth

38291.00

m.depth
m.depth
m.depth

51552.00
58722.00
61264.00

Each

228212.00

m.depth
m.depth
m.depth
m.depth

47025.00
59557.00
67892.00
70817.00

Each

246808.00

m.depth
m.depth

48857.00
62390.00

MUNICIPAL CORPORATION OF GREATER MUMBAI

SE SCHEDULE 2013
Manholes

ITEM CODE

ITEM DESCRIPTION

UNIT

RATE

SE-6-13-c
SE-6-13-d

-do- -do- 11 M to 12 M depth


Do- -do- above 12 M and upto 14 M depth -do- -doConstructing brick masonary scraper type manhole on sewer
3M x 3M at bottom and 1.2M x 0.9M at top built in brick
masonary in C.M. 1:3 -do- -do- as per item no.SE-6-10
including C.I. Rectangular EHD airtight frame and cover
weighing minimum 900 kg, safety chain extra C.I. steps depth
upto 4.5 M.
Extra for above manhole above 4.5M to 9M depth
-do- -do- 9 M to 11 M depth
-do- -do- 11 M to 12 M depth
Do- -do- above 12 M and upto 14 M depth -do- -do-

m.depth
m.depth

70556.00
74724.00

Each

254152.00

m.depth
m.depth
m.depth
m.depth

64468.00
82658.00
93505.00
99377.00

Each

25180.00

SE-6-14

SE-6-14-a
SE-6-14-b
SE-6-14-c
SE-6-14-d

SE-6-15

Constructing on sewer brick masonry conical manholes 1.2M


dia. at bottom 0.56 M. dia. at top, built in brick masonry in
cement mortar 1:3, plastered both inside and outside with 20
mm thick cement mortar 1:2 and neat cement rendering so as
to give a smooth surface, including 300 mm thick M.15
cement concrete in foundation and in haunches and channels
finished smooth with 20mm thick cement plaster in cement
mortar 1:1 and providing copolymer steps staggered at 300
mm. c/c including 75mm wide vata all round the external
portion of the manhole and the foundation concrete in cement
mortar 1:1 and supporting the incoming pipes with brick
masonry wherever necessary including Steel Fibre Reinforced
Concrete (SFRC) EHD circular frame and cover resting on 30
cm high cement concrete M.20 cap with necessary centering
etc. all complete as per standard specifications and directions
including finishing the cap with cement plaster on both sides
1:2 and neat cement rendering so as to give a smooth surface
in line and level with the brick masonry surface and as per
drawing inDyCh.E.(Sewerage)P&D's office without excavation
depth upto 1.5 M.(Depth of Manhole measured from top of
manhole cover to Invert level of manhole)

SE-6-15-a

Extra over above per metre depth above 1.5 M. and upto 2.3
m.depth
M. depth -do- -do-

9895.00

SE-6-15-b

Constructing on sewer brick masonry conical manhole 1.5 M.


dia. at bottom and 0.56 M dia. at top including SFRC. EHD
circular frame and cover and copolymer steps etc. complete
as per description in item No.SE-6-15 depth upto 2.3 M.

35529.00

SE-6-15-c
SE-6-15-d

Each

Extra for above manhole per metre depth above 2.3M and
upto 5 M including safety chain and extra copolymer steps on m.depth
other side of benching-do-doDo- -do- above 5 M & upto 9 M -do- -dom.depth

15

13101.00
14159.00

MUNICIPAL CORPORATION OF GREATER MUMBAI

SE SCHEDULE 2013
Manholes

ITEM CODE
SE-6-15-e
SE-6-15-f
SE-6-15-g

SE-6-16

SE-6-16-a
SE-6-16-b
SE-6-16-c
SE-6-16-d
SE-6-16-e

SE-6-17

SE-6-17-a

SE-6-18

SE-6-18-a

SE-6-19

SE-6-19-a
SE-6-19-b
SE-6-19-c
SE-6-19-d
SE-6-19-e

ITEM DESCRIPTION
Do- -do- above 9.M & upto 11 M -do- -doDo- -do- above 11M & upto 12 M -do- -doDo- -do- above 12 M and upto 14 M depth -do- -doConstructing on sewer brick masonary conical manhole 1.8M
dia. at bottom 0.56M dia at top, including SFRC EHD circular
frame and cover and copolymer steps etc. complete as per
description in Item No.SE-6-15 depth upto 2.9 M
Extra for above manhole per metre depth above 2.9M and
upto 5 M including safety chain and extra copolymer steps on
other side of benching-do-doDo- -do- above 5 M. and upto 9M -do- -doDo- -do- above 9 M. and upto 11M -do- -doDo- -do- above 11M and upto 12M -do- -doDo- -do- above 12 M and upto 14 M depth -do- -doConstructing on sewer brick masonary trapezoidal manhole
1.5M x 0.9M at bottom and 0.9M x 0.45M at top, including
SFRC. EHD airtight rectangular frame and cover and
copolymer steps complete as per description in Item No.SE-615 depth upto 1.2M
Extra for above manhole above 1.2M and upto 2.3M depth doConstructing on sewer brick masonary trapezoidal manhole
1.5M x 1.2M at bottom and 0.9M x 0.6M at top, including
SFRC. EHD rectangular frame and cover and copolymer
steps complete as per description in Item No.SE-6-15 depth
upto 1.2M
Extra for above manhole above 1.2M and upto 2.3M depth doConstructing on sewer brick masonry trapezoidal manhole
1.8M x 1.5 M at bottom and 1.2 M x 0.9M at top, including
SFRC EHD rectangular frame and cover . complete as per
description in Item No.SE-6-15 depth 2.9 M
Extra for above manhole per metre depth above 2.9M and
upto 5 M including safety chain and extra copolymer steps on
other side of benching-do-doDo- -do- above 5 M depth and upto 9 M depth -do- -doDo- -do- above 9M and upto 11M depth
-do- -doDo- -do- above 11 M and upto 12 M depth -do -doDo- -do- above 12 M and upto 14 M depth -do- -do-

16

UNIT

RATE

m.depth
m.depth
m.depth

14280.00
16928.00
17646.00

Each

47057.00

m.depth

21387.00

m.depth
m.depth
m.depth
m.depth

29362.00
38910.00
45079.00
46903.00

Each

22681.00

m.depth

11716.00

Each

27108.00

m.depth

12511.00

Each

61536.00

m.depth

28116.00

m.depth
m.depth
m.depth
m.depth

39464.00
46361.00
68945.00
85426.00

MUNICIPAL CORPORATION OF GREATER MUMBAI

SE SCHEDULE 2013
Manholes

ITEM CODE

SE-6-20

SE-6-20-a
SE-6-20-b
SE-6-20-c
SE-6-20-d

SE-6-21

SE-6-21-1
SE-6-21-2
SE-6-21-3
SE-6-21-4
SE-6-21-5

SE-6-22

SE-6-22-a

ITEM DESCRIPTION

Constructing brick masonary trapezoidal manhole on sewer


2.4M x 1.5M at bottom and 0.9M x 0.6M at top built in brick
masonary in C.M. 1:3 plastered both inside and outside with
20 mm thick cement plaster in C.M. 1:2 and neat cement
rendering so as to give a smooth surface 300 mm thick M 15
cement concrete in foundation and in haunches and channels
finished smooth with 20 mm cement plaster in C.M. 1:1 and
providing SFRC steps (approximately weighing 5.4 kg
each)staggered at 300mm c/c. including 75 mm wide vata all
round the external portion of the manhole and the foundation
concrete in cement mortar 1:1 and supporting the incoming
pipes with brick masonary wherever necessary including 0.9m
x 0.6M SFRC EHD rectangular frame and cover resting on
300mm high cement concrete M15 cap with necessary
centering including cement plaster (1:2) on both sides neat
cement rendering so as to give a smooth surface in line and
level including safety chain and extra copolymer steps on
other side benching complete as per standard specifications &
directions and as per drawing in Dy.Ch.E. (SP) P&D's office
without excavation depth upto 4.5M

UNIT

RATE

Each

151296.00

Extra per metre depth of the above manhole -do- -do- as per
m.depth
above item -do- -do- from 4.5 to 9M depth.
Do- -do- above from 9M and upto 11M depth -do- -dom.depth
Do- -do- above from 11 M and upto 12 M depth -do -dom.depth
Do- -do- above 12 M and upto 14 M depth -do- -dom.depth
Constructing on sewer brick masonry scraper manhole 1.5M
x 1.5 M at bottom and 1.2 M x 0.9M at top, including SFRC
EHD rectangular frame and cover and copolymer steps.
complete as per description in Item No.SE-6-15 depth 2.9 M
Extra for above manhole per metre depth above 2.9M and
upto 5 M including safety chain and extra copolymer steps on
other side of benching-do-doDo- -do- above 5 M depth and upto 9 M depth -do- -doDo- -do- above 9M and upto 11M depth
-do- -doDo- -do- above 11 M and upto 12 M depth -do -doDo- -do- above 12 M and upto 14 M depth -do- -doConstructing on sewer brick masonry scraper manhole 1.8M x
1.5M at bottom and 1.2M x 0.9M at top , including SFRC
Rectangular EHD frame and cover and copolymer steps.
complete as per description in item No. SE-6-15 depth upto
2.9M
Extra for above manhole per metre depth above 2.9M and
upto 5 M including safety chain and extra co-polymer steps on
other side of benching-do-do-

17

39765.00
51394.00
59098.00
59802.00

Each

58097.00

m.depth

23611.00

m.depth
m.depth
m.depth
m.depth

33055.00
38797.00
57623.00
60795.00

Each

65796.00

m.depth

25341.00

MUNICIPAL CORPORATION OF GREATER MUMBAI

SE SCHEDULE 2013
Manholes

ITEM CODE

ITEM DESCRIPTION

UNIT

RATE

SE-6-22-b
SE-6-22-c
SE-6-22-d
SE-6-22-e

Do- -do- above 5 M and upto 9 M depth - do- -doDo- -do- above 9 M and upto 11M depth -do- -doDo- -do- above 11 M and upto 12 M depth -do -doDo- -do- above 12 M and upto 14 M depth -do- -doConstructing on sewer brick masonry scraper manhole 1.8M x
1.8M at bottom and 1.2M x 0.9M at top , including SFRC.
Rectangular EHD frame and cover and copolymer steps
complete as per description in item No. SE-6-15 depth upto
2.9M
Extra for above manhole per metre depth above 2.9M and
upto 5 M including safety chain and extra copolymer steps on
other side of benching-do-doDo- -do- above 5 M and upto 9 M depth - do- -doDo- -do- above 9 M and upto 11M depth -do- -doDo- -do- above 11 M and upto 12 M depth -do -doDo- -do- above 12 M and upto 14 M depth -do- -doConstructing brick masonary scraper type manhole on sewer
2.4M x 1.5M at bottom 1.2M x 0.9M at top built in brick
masonary in C.M. 1:3 -do- -do- as per item No. SE-6-8
including SFRC. Rectangular EHD frame and cover and
copolymer steps, safety chain and extra steps, depth upto
4.5M
Extra for above manhole per metre depth above 4.5M and
upto 9M depth.
-do- -do- 9 M to 11M depth
-do- -do- 11 M to 12M depth
Do- -do- above 12 M and upto 14 M depth -do- -doConstructing brick masonary scraper type manhole on sewer
2.4M x 2.4M at bottom and 1.2M x 0.9M at top built in brick
masonary in C.M. 1:3 -do- -do- as per item no. SE-6-17
including SFRC Rectangular EHD frame and cover with
copolymer steps, safety chain and extra steps, depth upto 4.5
M.
Extra for above manhole above 4.5M to 9M depth
-do- -do- 9 M to 11 M depth
-do- -do- 11 M to 12 M depth
Do- -do- above 12 M and upto 14 M depth -do- -doConstructing brick masonary scraper type manhole on sewer
3M x 2M at bottom and 1.2M x 0.9M at top built in brick
masonary in C.M. 1:3 -do- -do- as per item no. SE-6-25
including SFRC Rectangular EHD frame and cover with
copolymer steps, safety chain and extra steps, depth upto 4.5
M.
Extra for above manhole above 4.5M to 9M depth
-do- -do- 9 M to 11 M depth
-do- -do- 11 M to 12 M depth
Do- -do- above 12 M and upto 14 M depth -do- -do-

m.depth
m.depth
m.depth
m.depth

37327.00
47356.00
65603.00
68403.00

Each

68967.00

m.depth

27071.00

m.depth
m.depth
m.depth
m.depth

41599.00
55915.00
73583.00
76012.00

Each

135810.00

m.depth

38291.00

m.depth
m.depth
m.depth

51552.00
58722.00
61264.00

Each

166985.00

m.depth
m.depth
m.depth
m.depth

47025.00
59557.00
67892.00
70817.00

Each

185870.00

m.depth
m.depth
m.depth
m.depth

48857.00
62390.00
70556.00
74724.00

SE-6-23

SE-6-23-a
SE-6-23-b
SE-6-23-c
SE-6-23-d
SE-6-23-e

SE-6-24

SE-6-24-a
SE-6-24-b
SE-6-24-c
SE-6-24-d

SE-6-25

SE-6-25-a
SE-6-25-b
SE-6-25-c
SE-6-25-d

SE-6-26

SE-6-26-a
SE-6-26-b
SE-6-26-c
SE-6-26-d

18

MUNICIPAL CORPORATION OF GREATER MUMBAI

SE SCHEDULE 2013
Manholes

ITEM CODE

SE-6-27

SE-6-27-a
SE-6-27-b
SE-6-27-c
SE-6-27-d

ITEM DESCRIPTION
Constructing brick masonary scraper type manhole on sewer
3M x 3M at bottom and 1.2M x 0.9M at top built in brick
masonary in C.M. 1:3 -do- -do- as per item no.SE-6-25
including SFRC Rectangular EHD frame and cover with
copolymer steps, safety chain and extra steps, depth upto 4.5
M.
Extra for above manhole above 4.5M to 9M depth
-do- -do- 9 M to 11 M depth
-do- -do- 11 M to 12 M depth
Do- -do- above 12 M and upto 14 M depth -do- -do-

19

UNIT

RATE

Each

191756.00

m.depth
m.depth
m.depth
m.depth

64468.00
82658.00
93505.00
99377.00

MUNICIPAL CORPORATION OF GREATER MUMBAI

Chapter -7
DROP ARRANGEMENT

SE SCHEDULE 2013
Drop Arrangement

ITEM CODE

ITEM DESCRIPTION

UNIT

RATE

SE-7-1

Providing 150 mm dia stoneware pipes of SP2 class in


vertical drop of 0.6M including 150 mm dia stone ware pipe
fixed in brick masonary of the manhole at required level &
providing 150 mm dia stone ware right angled bend, 150 mm
x 150 mm x 150 mm S.W. double tee junction including
cutting, jointing & filleting as per detailed specifications,
encased in half brick thick masonary in cement mortar (1:3) all
round the pipes double tee, bend and extra brick work below
bend upto the foundation of the manhole and tapering portion
of the manhole, plastering the exposed surfaces after raking
out the joints of the masonary to a depth of 20 mm in C.M.
(1:2) 20 mm thick and neat cement rendering so as to give a
smooth surface, including plugging the openings etc. complete
as directed and as per drawing inDy.Ch.E.(S.P.)P&D's office.

No

2,068

SE-7-1-a
SE-7-2
SE-7-2-a
SE-7-3
SE-7-3-a

SE-7-4

SE-7-4-a
SE-7-5

Extra over above per additional metre depth -do- -do- as per
m.depth
above item.
Do- -do- 230 mm dia stone ware pipe of SP2 class in vertical
No
drop upto 0.6M -do- -do- as per item SE-7-1
Extra over above per additional metre depth -do- -do- as per
m.depth
above item.
Do- -do- 300 mm dia stone ware pipe of SP2 class in vertical
No
drop of 0-6m -do- -do- as per item SE-7-1
Extra over above per additional metre depth -do- -do- as per
m.depth
above item.
Providing 160 mm dia HDPE pipes of PE-80 grade and PN-6
class in vertical drop of 0.6m including 160mm dia HDPE
pipes fixed in brick masonary of the manhole at required level
and providing 160mm dia HDPE right angled bend,
160mmx160mmx160mm HDPE double tee junction including
cutting and jointing as per detailed specifications,encased in
half brick thick masonary in cement mortar (1:3) all round the
pipes,double tee,bend and extra brickwork below bend upto
the foundation of the manhole and tapering portion of the
manhole plastering,plastering the exposed surfaces after
raking out the joints of the masonary to a depth of 20mm in
CM(1:2) 20mm thick and neat cement rendering so as to give
smooth surface,including plugging the openings etc complete
as directed and asper drawing in Dy CE(SP)P&D's office

No

1,460
4,012
2,252
5,157
2,839

3,874

Extra over above per additional metre depth -do- -do- as per
m.depth
above item

1,874

Do- -do- 200 mm dia HDPE pipes of PE-80 grade and PN-6
class in vertical drop of 0.6M -do- -do- as in item No.SE-7-4

5,416

20

No

MUNICIPAL CORPORATION OF GREATER MUMBAI

SE SCHEDULE 2013
Drop Arrangement

SE-7-5-a
SE-7-6
SE-7-6-a
SE-7-7
SE-7-7-a

SE-7-8
SE-7-8-a
SE-7-9
SE-7-9-a

SE-7-10
SE-7-10-a
SE-7-11
SE-7-11-a
SE-7-12
SE-7-12-a
SE-7-13

SE-7-13-a

SE-7-14
SE-7-14-a

Extra over above per additional metre depth -do- -do- as per
m.depth
above item

2,837

Do- -do- 250 mm dia HDPE pipes of PE-80 grade and PN-6
class in vertical drop of 0.6M -do- -do- as in item No.SE-7-4

7,917

No

Extra over above per additional metre depth -do- -do- as per
m.depth
above item

3,373

Do- -do- 280 mm dia HDPE pipes of PE-80 grade and PN-6
class in vertical drop of 0.6M -do- -do- as in item No.SE-7-4

10,568

Extra over above per additional meter depth


Do-do -as per above item

No
m.depth

Do- -do- 315 mm dia HDPE pipes of PE-80 grade and PN-6
class in vertical drop of 0.6M -do- -do- as in item No.SE-7-4

No

4,042

18,897

Extra over above per additional metre depth -do- -do- as per
m.depth
above item

4,239

Do- -do- 355 mm dia HDPE pipes of PE-80 grade and PN-6
class in vertical drop of 0.9M -do- -do- as in item No.SE-7-4

No

23,708

m.depth

6,727

No

27,428

Extra over above per additional meter depth


Do-do -as per above item
Do- -do- 400 mm dia HDPE pipes of PE-80 grade and PN-6
class in vertical drop of 0.9M -do- -do- as in item No.SE-7-4

Extra over above per additional metre depth -do- -do- as per
m.depth
above item

8,130

Do- -do- 450 mm dia HDPE pipes of PE-80 grade and PN-6
class in vertical drop of 0.9M -do- -do- as in item No.SE-7-4

31,886

No

Extra over above per additional metre depth -do- -do- as per
m.depth
above item

9,724

Do- -do- 500 mm dia HDPE pipes of PE-80 grade and PN-6
class in vertical drop of 1.2M -do- -do- as in item No.SE-7-4

35,922

No

Extra over above per additional metre depth -do- -do- as per
m.depth
above item

11,457

Do- -do- 560 mm dia HDPE pipes of PE-80 grade and PN-6
class in vertical drop of 1.2M -do- -do- as in item No.SE-7-4

40,454

No

Extra over above per additional metre depth -do- -do- as per
m.depth
above item

13,308

Do- -do- 630 mm dia HDPE pipes of PE-80 grade and PN-6
class in vertical drop of 1.2M -do- -do- as in item No.SE-7-4

45,931

No

Extra over above per additional metre depth -do- -do- as per
m.depth
above item

21

16,376

MUNICIPAL CORPORATION OF GREATER MUMBAI

Chapter -8
INSPECTION CHAMBER

SE SCHEDULE 2013
Inspection Chambers

ITEM CODE

ITEM DESCRIPTION

UNIT

RATE

SE-8-1

Constructing brick masonary inspection chamber rectangular


0.9M x 0.45M and0.6M deep on sewer with 230mm brick
walls in cement mortar 1:3 plastered both inside & outside
with 20 mm thick cement mortar 1:2 and neat cement
rendering so as to give a smooth surface including 230mm
cement concrete bedding (M 15) and cement concrete (M 15)
in haunches and channels finished smooth with 20 mm thick
cement mortar( 1:1) and fixing C.I. extra heavy duty airtight
rectangular frame & cover of size 0.9M x 0.45M weighing
minimum 225Kg. resting on 300 mm high c.c. cap M 20 with
(1:1) cement plaster on both the sides & necessary C.I. steps (
weighing 5.4 kg each)staggered at 300mm c/c. including 75
mm wide vata all round the external portion of the chamber
and the foundation concrete in C.M. 1:1 etc. complete as per
plan in Dy.Ch.E.(SP)P&D's office( without excavation ) .

No

24138.00

SE-8-1-a

SE-8-2

SE-8-2-a

SE-8-3

SE-8-3-a

SE-8-4

SE-8-4-a

Extra over above for every additional metre depth upto 2.5M m.depth
do- -do-etc. complete as specified and directed.

6914.00

Constructing brick masonary inspection chamber rectangular


0.9M x 0.6M and 0.6M deep -do- including M 20, 30 cm thick
cap c.c. Bedding & including C.I. extra heavy duty air tight
frame and cover weighing minimum 270kg complete as per
description in item No. SE-8-1 with necessary centering etc. all
complete as per plan and directed.

28714.00

No

Extra over above for every additional metre depth upto 2.5M m.depth
do- -do- etc. complete as specified and directed.
Constructing brick masonary inspection chamber rectangular
0.75M x 0.75M and 0.6M deep -do- -do- as per description in
item no SE-8-1 including CI extra heavy duty air tight frame
No
and cover weighing minimum 275 kg complete as per plan
and directed
Extra over above for every additional metre depth upto 2.M do- -do-with necessary centering etc. all complete as per m.depth
direction.
Constructing brick masonary inspection chamber rectangular
0.6M x 0.6M and 0.6M deep -do- -do- etc. complete as per
description in item no SE-8-1 including CI extra heavy duty air
No
tight frame and cover weighing minimum 200 kg complete as
per plan and directed.
Extra over above for every additional metre depth upto 2.M do- -do-with necessary centering etc. all complete as per m depth
direction.

22

7907.00

26668.00

7923.00

22592.00

6905.00

MUNICIPAL CORPORATION OF GREATER MUMBAI

SE SCHEDULE 2013
Inspection Chambers

SE-8-5

SE-8-5-a

SE-8-6

SE-8-6-a

SE-8-7

SE-8-7-a

SE-8-8

SE-8-8-a

Constructing brick masonary inspection chamber rectangular


0.9M x 0.45M and0.6M deep on sewer with 230mm brick
walls in cement mortar 1:3 plastered both inside & outside
with 20 mm thick cement mortar 1:2 and neat cement
rendering so as to give a smooth surface including 230mm
cement concrete bedding (M 15) and cement concrete (M 15)
in haunches and channels finished smooth with 20 mm thick
cement mortar( 1:1) and fixing SFRC extra heavy
dutyrectangular frame & cover of size 0.9M x 0.45M. resting on
300 mm high c.c. cap M 20 with (1:1) cement plaster on both
the sides & necessary co-polymer. steps staggered at 300mm
c/c. including 75 mm wide vata all round the external portion
of the chamber and the foundation concrete in C.M. 1:1 etc.
complete as per plan in Dy.Ch.E.(SP)P&D's office( without
excavation ) .

No

13511.00

Extra over above for every additional metre depth upto 2.5M m.depth
do- -do- etc. complete as specified and directed.

6914.00

Constructing brick masonary inspection chamber rectangular


0.9M x 0.6M and 0.6M deep -do- including M 20, 30 cm thick
cap c.c. Bedding & including SFRC extra heavy duty frame
and cover complete as per description in item No. SE-8-5 etc.
all complete as specified and directed.

15419.00

No

Extra over above for every additional metre depth upto 2.5M m.depth
do- -do-.

8705.00

Constructing brick masonary inspection chamber rectangular


0.75M x 0.75M and 0.6M deep -do- -do- as per description in
item no SE-8-5 including SFRC extra heavy duty frame and
cover complete as specified and directed.

23576.00

No

Extra over above for every additional metre depth upto 2.M do- -do-with necessary centering etc. all complete as per m.depth
direction.

7823.00

Constructing brick masonary inspection chamber rectangular


0.6M x 0.6M and 0.6M deep -do- -do- etc. complete as per
description in item no SE-8-5 including SFRC extra heavy duty
frame and cover complete as specified and directed.

20608.00

No

Extra over above for every additional metre depth upto 2.M - m.depth
do- -do-with necessary centering etc. all complete as per

23

6805.00

MUNICIPAL CORPORATION OF GREATER MUMBAI

Chapter -9
VENT SHAFTS

SE SCHEDULE 2013
Vent Shafts

ITEM CODE

SE-9-1

SE-9-2
SE-9-3

SE-9-4

SE-9-5
SE-9-5-a

SE-9-6

SE-9-7

SE-9-8

ITEM DESCRIPTION
Providing R.C.C. Spun vent shaft 7.3M in height embedded in
M15 cement concrete Including flue chamber etc. complete
without excavation.The height of the vent shaft to be
measured from its bottom upto the top as per the drawing and
as specified and directed
C.I. Shoe bend 150 mm dia fixed complete including cutting
through masonary, cornices etc. and making good the same
including painting as directed.
Collar for C.I.pipes 150mm.dia.fixed complete including
painting.
Removing zinc galvanised sheet /cast iron vent shafts
including all fittings and appliances and making good the
masonary work including cornices painting and stacking the
material wherever directed etc.complete.
Removing and refixing -do-do-on the same site (for galvanised
sheet/cast iron vent shaft).
-do- -do- on different site in the same locality -do- -doBrick masonary flue chamber for vent shaft 0.375M x 0.375M x
0.6M deep of 230 mm brick wall in C.M.1:3 and 20 mm
cement and sand plaster on both sides in C.M. 1:2 finished
smooth including 150 mm M15 cement concrete bedding and
150 mm thick reinforcement concrete dhapas built complete
including excavation etc. as specified and directed
Removing & refixing of C.I. Vent shaft complete as directed
including transporting to municipal stores anywhere in
City/suburbs.
Removing & refixing of R.C.C Vent shaft complete as directed
including transporting to municipal stores anywhere in
City/suburbs.

UNIT

RATE

Each

30187.00

Each

1399.00

Each

874.00

Rmt

209.00

Rmt

419.00

Rmt

554.00

Each

4300.00

Each

3468.00

Each

12411.00

SE-9-9

Removing CI vent shaft complete as directed including


transporting to municipal stores/anywhere in City/Suburbs.

Each

2081.00

SE-9-10

-Do-do-RCC vent shaft-do-do

Each

2746.00

24

MUNICIPAL CORPORATION OF GREATER MUMBAI

Chapter -10
IRON WORKS

SE SCHEDULE 2013
Iron Works

ITEM CODE

ITEM DESCRIPTION

UNIT

RATE

Each

382.00

Each

308.00

Each

20016.00

Each

75354.00

Each

20239.00

Each

23620.00

Each

21585.00

Each

19168.00

Each

3607.00

Each

8995.00

Each

5015.00

NOTE
Wastage in cutting will not be paid for. Only steel actually fixed
in position will be paid by linear measurement including hooks
and bends. No payment will be made for binding wire, pins,
chairs and laps and/or welding. The contractors should note
this while quoting the rates. All iron work shall be free from
rust, scale and the rate shall be inclusive of painting with 3
coats of approved make over one coat of primer to iron work.
SE-10-1

SE-10-2

SE-10-3

SE-10-4
SE-10-5
SE-10-6
SE-10-7
SE-10-8
SE-10-9
SE-10-10
SE-10-11

Supplying and fixing C.I. Steps weighing 5.4 kg each wherever


directed.
Supply and fixing orange colour foot rest of minimum 6mm
thick plastic encapsulated on 12mm square steel bar having
minimum cross section of 24mm square and overall minimum
length of 375mm and width of 150mm as per drawing etc
complete as specified and directed
Supplying and fixing 0.56M dia C.I. Circular extra heavy duty
(EHD) airtight frame and cover weighing minimum 230 kg
fixed complete to manholes.
-do- -do- 1.2M x 0.9M rectangular C.I. frame and cover. -do- do- weighing minimum 900 kg -do- -do-with 2 nos of C.I.
covers
-do- -do- 0.9M x 0.45M rectangular C.I. frame and cover. -do- do- weighing minimum 225 kg.-do-do
-do- -do- 0.9M x 0.6M rectangular C.I. frame and cover. -do- do- weighing minimum 270 kg.-do-do
-do- -do- 0.75M x 0.75M rectangular C.I. frame and cover. -do-do- weighing minimum 275 kg.-do-do
-do- -do- 0.6M x 0.6M rectangular CI frame and cover. -do- do- weighing minimum 200 kg.-do-do
Supplying and fixing 0.56m dia circular extra heavy duty (EHD)
SFRC frame and cover as per drawing fixed complete to
manhole as specified and directed
-do-do- 1.2m x 0.9m rectangular SFRC frame and cover with
2 nos. of SFRC covers -do-do-do-do- 0.9m x 0.45m rectangular SFRC frame and cover -dodo-

SE-10-12

-do- -do- 0.9M x 0.6M rectangular frame and cover. -do- -do-

Each

5926.00

SE-10-13

Mild steel in flat, round and square bar, angle tee including all
bolts washers nuts and screws, fastenings, fittings etc.
Including forming, brackets corners, treading etc. complete.

MT

65549.00

SE-10-14

Providing 12mm thick M.S plate of required size over the


trench and removing after completion of work as directed by
Engineer

MT

65411.00

25

MUNICIPAL CORPORATION OF GREATER MUMBAI

Chapter -11
DESILTING

SE SCHEDULE 2013
Desilting

ITEM CODE

SE-11-1

SE-11-2

SE-11-3

SE-11-4

SE-11-5
SE-11-6

ITEM DESCRIPTION
Desilting functioning/non-functioning of sewers of any size
and shape upto any depth by any means including pumping
out liquid waste or sewage,plugging, diverting the flow in the
drain if necessary and stacking the removed silt in the depots
as directed within radius of 300 meters including taking
precautionary and safety measures such as test for gases
spreading bleaching powder on the depot of the removed silt
etc. complete or as directed(For payment purpose 30% voids
for silt would be deducted and for stone or boulders 40%
would be deducted on the depot measurement).
Systematically cleaning /functioning/ non-functioning sewer of
150mm dia to 230 mm dia sewer by passing ropes knots,
bamboo kamti and disc. of required size as directed and
specified including safety measures such as tests for gases,
use of safety belts, dry cell, torches, or lighting in manholes &
drains as directed and specified -do- -do- as per item No. SE11-1
Systematically cleaning /functioning/ non-functioning sewer
of300 mm dia to 600 mm dia sewer by passing ropes knots,
bamboo kamti and disc. of required size as directed and
specified including safety measures such as tests for gases,
use of safety belts, dry cell, torches, or lighting in manholes &
drains as directed and specified -do- -do- as per item No. SE11-1
Systematically cleaning / functioning / non-functioning sewer
of 700 mm dia to 1200 mm dia sewer by passing ropes
knots, bamboo kamti and disc. of required size as directed
and specified including taking necessary precautionary safety
measures such as tests for gases, use of safety belts, dry cell,
torches, for lighting in manholes & drains etc. complete
including sprinkling bleaching powder on the silt removed to
avoid bad smell -do- -do- as per item No.SE-11-1
-do- -do- 1400 mm dia to 1800 mm dia -do- -do- as per item
no SE-11-2
-do- -do- 2000 mm dia to 2400 mm dia -do- -do- as per item
no SE-11-2

26

UNIT

RATE

cum

598.00

Rmt

49.00

Rmt

70.00

Rmt

202.00

Rmt

291.00

Rmt

457.00

MUNICIPAL CORPORATION OF GREATER MUMBAI

Chapter -12
MISCELLANEOUS

SE SCHEDULE 2013
Miscellaneous

ITEM CODE

ITEM DESCRIPTION

UNIT

RATE

SE-12-1

Providing and applying solution of sodium silicate for digestion


tank and/or wherever directed in 3 coats prepared from
silicate of soda mixed with potable water in the proportion of
1:4 including spraying cleaning the surface etc. all complete as
directed.

Sqm

46.00

SE-12-2

Providing and applying polyurea coating for digestion tank


and/or
wherever directed in 1.2mm thick as per
manufacturers specifications including necessary tools,
surface preparation etc. all complete as specified and directed.

Sqm

1823.00

Pair

897.00

Each

999.00

Each

1531.00

Each

186.00

Each

315.00

SE-12-3
SE-12-4
SE-12-5
SE-12-6
SE-12-7
SE-12-8
SE-12-9
SE-12-10
SE-12-11

SE-12-12

SE-12-13
SE-12-14

Providing strut holes with set stones in manholes


Providing and Fixing150 mm intercepting stoneware sewer
trap laid complete
do-do-230 mm dia -do- -do100 mm dia to 150 mm dia pipe hole cut into masonry of
manhole of sewer and the pipe stopped round with cement
and sand filletings.
230 mm to 300 mm dia -do- -do-

350 mm to 450 mm dia -do- -doEach


500 mm to 600 mm dia -do- -doEach
Cutting down masonary work in lime or cement mortar plaster
Cum
etc. complete
Removing and cutting down completely R.C.C.slab, R.C.C.
Beams R.C.C. Columns etc. in any thickness and size and
Cum
removing away the debris.
Providing and fixing shahabad ladi (0.7m x 0.7m x 75mm
thick) over manhole opening where frame and cover are not
provided, including fixing the same over brick masonary or
Nos
concrete cap with C.M.(1:2) all round as directed etc.
complete.
Pumping out water from drainage trenches by 5 H.P. pump per
Per shift
shift of 8 hours.
-do--do- 10 H.P. -do- -doPer shift

508.00
642.00
276.00
690.00

563.00

1265.00
1668.00

SE-12-15

Extra for providing locking arrangement to C.I. EHD Circular


manhole frame and cover above the rate of providing and
fixing C.I. EHD Circular manhole frame and cover.

Nos

805.00

SE-12-16

Providing and laying 100 mm dia stone ware pipes including


jointing, filleting etc. complete.

Rmt

295.00

27
MUNICIPAL CORPORATION OF GREATER MUMBAI

SE SCHEDULE 2013
Miscellaneous

SE-12-17

Constructing coffer dams of puddle bags completely new with


clay/silt/impervious materials core including diversion of flow
removing and pumping out water etc. complete to keep
working space dry as specified and as directed.(This item
includes maintenance during the work in progress and
removal of the same after completion of work.).

Bag.

65.00

SE-12-18

Constructing coffer dams of puddle bags completely new with


clay/silt/impervious materials core including diversion of flow
removing and pumping out water etc. complete to keep
working space dry as specified and as directed.(This item
includes maintenance during the work in progress and
removal of the same after completion of work.).

Cum

1834.00

SE-12-19

Breaking the pardi by any means, including safety measure,


provided in the existing non-functioning sewer and removal of
the debris finishing the surface and cleaning etc. complete as
directed.

Cum

714.00

28
MUNICIPAL CORPORATION OF GREATER MUMBAI

Chapter -13
MICROTUNNELING AND PIPE
JACKING

SE SCHEDULE 2013
Microtunneling Pipe Jacking

ITEM CODE

ITEM DESCRIPTION

UNIT

RATE

SE-13-1

Excavate in tunnel by micro tunnel boring machine for


installing 600mm diameter sleeve or carrier for sewer line or
water main to correct grade and alignment using slurry or
mixed shields including excavation of jacking and receiving
pits as necessary for the method and the equipment and
considering the ground strata, up to any depth up to 12 m
below ground level (up to invert of the pipe to be installed) in
any type of strata including marshy land, soft clay, murum,
soft/hard rock and/ or boulders of any strength and hardness,
shoring of any type including sheet piles or concrete piles,
dewatering, disposal of muck/ excavated material to any place
as directed by the Engineer, reinstatement of excavated
surface to its original condition etc. complete as per
specifications and as directed by the Engineer.

Rmt

89362.00

800 mm dia -do- -do1000mm dia -do- -do1200 mm dia -do- -do1400 mm dia -do- -do1600 mm dia -do- -do1800 mm dia -do- -do2000 mm dia -do- -do2200 mm dia -do- -do2400 mm dia -do- -do-

Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt

96300.00
103033.00
117779.00
124745.00
137557.00
139753.00
144265.00
155601.00
174358.00

Approved 600mm diameter reinforced concrete pipe


conforming to jacking pipe standards like JSWAS A-6, ASTM
C-76 SS 183 or AS 1342 but not less than NP4 class under IS
458; supplied, jointed and installed to correct line and grade by
pipe jacking for microtunneling works etc. complete as per
specifications and as directed by the Engineer

Rmt

15013.00

800 mm dia -do- -do1000mm dia -do- -do1200 mm dia -do- -do1400 mm dia -do- -do1600 mm dia -do- -do1800 mm dia -do- -do2000 mm dia -do- -do2200 mm dia -do- -do2400 mm dia -do- -do-

Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt

18165.00
22986.00
27830.00
34351.00
40530.00
57241.00
62320.00
69539.00
72373.00

SE-13-1-a
SE-13-1-b
SE-13-1-c
SE-13-1-d
SE-13-1-e
SE-13-1-f
SE-13-1-g
SE-13-1-h
SE-13-1-i

SE-13-2

SE-13-2-a
SE-13-2-b
SE-13-2-c
SE-13-2-d
SE-13-2-e
SE-13-2-f
SE-13-2-g
SE-13-2-h
SE-13-2-i

29

MUNICIPAL CORPORATION OF GREATER MUMBAI

SE SCHEDULE 2013
Microtunneling Pipe Jacking

ITEM CODE

ITEM DESCRIPTION

UNIT

RATE

SE-13-3

Excavation to form horizontal bore manually for installing


1200mm(ID) RCC sewer line by pipe jacking method upto
invert depth of 12 m and for maximum drive length of 30 m, to
correct grade and alignment in any type of strata including
marshy land, soft clay, murum, rock and/ or boulders of any
strength and hardness. Item includes excavation of jacking
shaft in any type of strata including marshy land, soft clay,
murum, rock and/ or boulders of any strength and hardness,
shoring of any type including M.S. sheet piles or concrete
piles, dewatering, disposal of muck/ excavated material to any
place as directed by the Engineer, reinstatement of excavated
surface to its original condition and grouting completely the
annular space around pipe surface in C.M. 1:3, also
safetyarrangements, ventilation in bore etc. complete as per
specifications and as directed by the Engineer.

Rmt

76673.00

SE-13-3-a

Excavation in form horizontal bore manually for installing


1400mm(ID) RCC sewer line by pipe jacking method upto
invert depth of 12 m and for maximum drive length of 30 m, to
correct grade and alignment in any type of strata including
marshy land, soft clay, murum, rock and/ or boulders of any
strength and hardness. Item includes excavation of jacking
shaft in any type of strata including marshy land, soft clay,
murum, rock and/ or boulders of any strength and hardness,
shoring of any type including M.S. sheet piles or concrete
piles, dewatering, disposal of muck/ excavated material to any
place as directed by the Engineer, reinstatement of excavated
surface to its original condition and grouting completely the
annular space around pipe surface in C.M. 1:3, also safety
arrangements, ventilation in bore etc. complete as per
specifications and as directed by the Engineer.

Rmt

86206.00

30

MUNICIPAL CORPORATION OF GREATER MUMBAI

SE SCHEDULE 2013
Microtunneling Pipe Jacking

ITEM CODE

ITEM DESCRIPTION

UNIT

RATE

SE-13-3-b

Excavation in form horizontal bore manually for installing


1600mm(ID) RCC sewer line by pipe jacking method upto
invert depth of 12 m and for maximum drive length of 30 m, to
correct grade and alignment in any type of strata including
marshy land, soft clay, murum, rock and/ or boulders of any
strength and hardness. Item includes excavation of jacking
shaft in any type of strata including marshy land, soft clay,
murum, rock and/ or boulders of any strength and hardness,
shoring of any type including M.S. sheet piles or concrete
piles, dewatering, disposal of muck/ excavated material to any
place as directed by the Engineer, reinstatement of excavated
surface to its original condition and grouting completely the
annular space around pipe surface in C.M. 1:3, also safety
arrangements, ventilation in bore etc. complete as per
specifications and as directed by the Engineer.

Rmt

94874.00

SE-13-3-c

Excavation in form horizontal bore manually for installing


1800mm(ID) RCC sewer line by pipe jacking method upto
invert depth of 12 m and for maximum drive length of 30 m, to
correct grade and alignment in any type of strata including
marshy land, soft clay, murum, rock and/ or boulders of any
strength and hardness. Item includes excavation of jacking
shaft in any type of strata including marshy land, soft clay,
murum, rock and/ or boulders of any strength and hardness,
shoring of any type including M.S. sheet piles or concrete
piles, dewatering, disposal of muck/ excavated material to any
place as directed by the Engineer, reinstatement of excavated
surface to its original condition and grouting completely the
annular space around pipe surface in C.M. 1:3, also safety
arrangements, ventilation in bore etc. complete as per
specifications and as directed by the Engineer.

Rmt

106753.00

Rmt

0.00

Approved 1200 mm mild steel (M.S) pipe sleeve conforming to


jacking pipe as per IS 3589/ASTM/BS ; supplied, jointed and
installed to correct line and grade by pipe jacking for providing
sewer by trenchless technology etc. complete as per
specifications and as directed by the Engineer

Rmt

39988.00

1400 mm dia -do- -do1600 mm dia -do- -do1800 mm dia -do- -do-

Rmt
Rmt
Rmt

47691.00
56773.00
66845.00

SE-13-4

SE-13-4-a
SE-13-4-b
SE-13-4-c

31

MUNICIPAL CORPORATION OF GREATER MUMBAI

Chapter -14
HORIZONTAL DIRECTIONAL
DRILLING AND PIPE
INSTALLATION

SE SCHEDULE 2013
Horizontal Direction Drilling and Pipe Installation

ITEM CODE

ITEM DESCRIPTION

UNIT

RATE

SE-14-1

Installation of 280mm dia (OD) HDPE pipe line (PN 6 ClassPE 80 grade: IS 14333) to correct grade and alignment using
Horizontal Directional Drilling method in any type of ground
including soft soil, mixed ground and soft/hard rock.

Rmt

32252.00

315 mm dia -do- -do355mm dia -do- -do400 mm dia -do- -do450 mm dia -do- -do500 mm dia -do- -do560 mm dia -do- -do630 mm dia -do- -do-

Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt

32883.00
39594.00
40720.00
42111.00
52447.00
54382.00
56973.00

Installation of 710 mm dia (OD) HDPE pipe line (PN 6 ClassPE 100 grade : IS 14333) to correct grade and alignment using
Horizontal Directional Drilling method in any type of ground
including soft soil, mixed ground and soft/hard rock.

Rmt

60521.00

800mm dia -do- -do900mm dia -do- -do1000mm dia -do- -do-

Rmt
Rmt
Rmt

64778.00
84879.00
90871.00

SE-14-1-a
SE-14-1-b
SE-14-1-c
SE-14-1-d
SE-14-1-e
SE-14-1-f
SE-14-1-g

SE-14-2

SE-14-2-a
SE-14-2-b
SE-14-2-c