Sunteți pe pagina 1din 3

MEETING AGENDA

Ithaca Commons Repair & Upgrade Project


Date
05/20/2014

Start
10:00 AM

Purpose
2014 Construction Meeting #8
Distribution/Attendance:
City of Ithaca
Downtown Ithaca Alliance
Sasaki Associates
Labella Associates
Vacri Construction / ACP
Power & Construction Group
Verizon
NYSEG Gas
DDS
NYSEG Electric

End
11:00 AM

C#2 Utilities, C#3A Surface, C#3B Electric


Next Date
05/27/2014

Next Time
10:00 AM

Prepared By
Jessica Buckley

Location
Commons Project Office 215 East State St Ithaca, NY
(Present at meeting unless noted: A absent)
Michael Kuo, Jessica Buckley, Nicole Mason
Tammy Baker
Susannah Ross, Eamonn Hutton
Dan Walker, James Matzat
Ralph Avery, Andy Breznay, Matt Thomas, Roberto DeVincentis, Bob
Belavigna - ACP
Lou Zupan, Bill Planert, Brian Planert
James Edwards, Dave Comer
Doug Stafford, Jack Barker, Dawn Stillwell
Jeff Bubb, Flint Brann
Jack Czapranski, Dennis Kuhn

Item / Description
1. SITE MANAGEMENT
1.1. Thank you for being aware of site
sensitivities: Pedestrian access,
emergency access, business owner
requests, fence / safety maintenance,
coordinating with each other, etc.
1.2. Meeting of the Minds: Optional
superintendant daily meeting at 3:00 PM
at project office to map out work
footprint & coordinate with others on site
1.3. Lockout Tagout procedures to be put in
place by Vacri for temp lighting electric
panel
1.4. Notify JB of any storm pipe removal
1.5. Vacri is to schedule temp paving of
trenches prior to the end of the week for
Cornell graduation
1.6. Lights out on N Tioga Vacri to
investigate
2. CRICTIAL PATH ITEMS
2.1. P&CG: Status of lighting submittal; City /

Notes

Page 1 of 3

Due

Architect to respond to cat. light pole /


Verizon DB conflict; N Tioga field directive
2.2. Vacri: TTC alley storm field directive from
Engineer / Architect to be issued, Verizon
/ Danella to be scheduled to expose
conduit prior to storm work
2.3. Vacri: Water feature rough in to be issued
by Architect pending response from
water treatment plant / health
department
2.4. Vacri: City to determine vault infill at 119
3. SCHEDULE
3.1. NYSEG Gas/DDS: Tentative schedule to
be presented
3.2. NYSEG Electric to complete relocation of
secondary to Aurora St by 05/23
3.3. Vacri / AC&P:
May: Complete utilities (Storm)
June: N Tioga Site demo; Pour
foundations / footers; Site grading, curbs,
expansion joints
July: Prep & pour slab N Tioga; Paving
program
3.4. TTC / EE Root: Scheduled to reinstall
cable into TTC Alley HH 05/27; Lantech to
install separator in TMH-4
3.5. Verizon / Danella:
05/20: To work alongside NYSEG E at
Trolley Circle crossing to lower DB for WF
TTC Alley work to be scheduled
3.6. P&CG:
05/20: Realigned at NW corner of 100
block moving east
05/19 06/16: Complete N Tioga
3.7. Asphalt Restoration: Vacri, NYSEG Gas &
Signals project (P&CG) to coordinate in
intersections
4. M&PTP: MAINTENANCE & PROTECTION
OF TRAFFIC & PEDESTRIANS
4.1. Vacri / ACP, P&CG, NYSEG Gas: Please
submit typical ped. traffic M&P plan,
include list of signage available on site
4.2. Vacri to propose sidewalk demo plan
5. New Business: Open RFIs, submittals,
concerns, etc.

DATES TO REMEMBER
Page 2 of 3

5/27

May 23 to May 25 Cornell Graduation, no work on weekend


May 30 to June 1 Ithacafest, Cayuga St entrance closed

ADDITIONAL NOTES

3.1

Map of tentative NYSEG Gas schedule to be distributed in meeting

Page 3 of 3

S-ar putea să vă placă și