2014 Construction Meeting #14
Distribution/Attendance:
City of Ithaca
Downtown Ithaca Alliance
Sasaki Associates
Labella Associates
Vacri Construction / ACP
Power & Construction Group
Verizon
NYSEG Gas
DDS
NYSEG Electric
Next Time
10:00 AM
Prepared By
Jessica Buckley
Location
Commons Project Office 215 East State St Ithaca, NY
(Present at meeting unless noted: A absent)
Michael Kuo, Jessica Buckley, Nicole Mason, Michael Thorne
Tammy Baker
Susannah Ross, Eamonn Hutton(A), Kimberly Michaels TWM
Dan Walker(A), James Matzat(A)
Ralph Avery, Andy Breznay, Matt Thomas(A), Roberto DeVincentis(A),
Bob Bellavigna ACP, Ken Hight
Lou Zupan, Bill Planert, Brian Planert(A)
James Edwards(A), Dave Comer(A)
Doug Stafford(A), Jack Barker, Dawn Stillwell, John Mattiace
Jeff Bubb(A), Flint Brann(A), Andy GanA(A)
Jack Czapranski, Dennis Kuhn(A)
Item / Description
1. RFIs, SUBMITTALS
1.1. Vacri (Contract #3A):
1.1.1.Gateway Structure Shops #TBD
1.1.2.Granite Shop #87
1.1.3.WF Vault #73R2
Notes
Vacri waiting on shops from sub; Granite
by (07/3), Granite blocks lead time 8 wks
(09/01); Lift is needed to bring granite in;
City request no equipment tracking on
new pavers; WFV in production, Sasaki &
sub to review coring submittal; Granite
curb sample sent to Sasaki for review;
Sequence is: curbing footers, curbing,
slab, handrails and granite; Roadside curb
stock item
Selux to have submittal for review
tomorrow; Light pole color chip sent to
Sasaki; PCG and ACP need to work closely
for EX6 lights-what size slot and cores in
granite; City electrician approved sheath
cable rated for the outdoors, one
continuous cable from HH to fixture,
which would coil in granite; Stage floor
box submittal 12 needed for concrete
floor