MEETING MINUTES

Ithaca Commons Repair & Upgrade Project


Date
07/15/2014

Start
10:00 AM

End
10:45 AM

Purpose
2014 Construction Meeting #17
Distribution/Attendance:
City of Ithaca
Downtown Ithaca Alliance
Sasaki Associates
Labella Associates
Vacri Construction / ACP
Power & Construction Group
Verizon
NYSEG Gas
DDS
NYSEG Electric

C#3A Surface, C#3B Electric


Next Date
07/22/2014

Next Time
10:00 AM

Prepared By
Jessica Buckley

Location
Commons Project Office 215 East State St Ithaca, NY
(Present at meeting unless noted: A absent)
Michael Kuo, Jessica Buckley, Nicole Mason
Tammy Baker
Susannah Ross, Eamonn Hutton (A), Kimberly Michaels TWM
Dan Walker, James Matzat (A)
Ralph Avery, Andy Breznay, Matt Thomas (A), Roberto DeVincentis (A),
Bob Bellavigna ACP
Lou Zupan, Bill Planert, Brian Planert (A)
James Edwards (A), Dave Comer (A)
Doug Stafford (A), Jack Barker, Dawn Stillwell, John Mattiace (A)
Jeff Bubb (A), Flint Brann (A), Andy Gana (A)
Jack Czapranski (A), Dennis Kuhn (A)

Item / Description
1. RFIs, SUBMITTALS
1.1. Vacri (Contract #3A):
1.1.1.Granite Shop #87 - EX6 Roughing
Coordination AC+P and P&CG
1.1.2.Roadway Curb sample photos to
be sent to Sasaki

1.2. P&CG (Contract #3B):


1.2.1.Lighting Submittal #13R2 Status?
1.2.2.Stage Floor Boxes #12

Notes
Mark up returned on granite shop
drawing; PCG to resend EX6 granite detail
to Vacri; Conduit to be daylighted and
installed below 12 slab & 6 of sub base;
PCG to have electrical inspector to
approve; Vacri to send a submittal sheet
on curb sample to Sasaki
PCG to follow up with accessory details for
the catenary pole submittal; All light
fixtures are to be included in one
submittal; EX2 pole submittal to be sent
by PCG next week; PCG to submit on stage
floor boxes today

2. DESIGN, FIELD DIRECTIVES


2.1. TTC Alley & Home Dairy Alley: Survey
MK to follow up with Sasaki on HD Alley
issued 6/26
2.2. Electric Panel & Kiosk Housekeeping Pads: City is in contact with kiosk manufacturer
Bulletin #13 issued 7/14/14
about switch cabinet; PCG to submit on
kiosk today; Bulletin #13, SKL-16 may be
revised

Page 1 of 2

Due

2.3. Cayuga St Gateway: Architect to analyze


shifting entire gateway to the north
3. CRITICAL PATH ITEMS
3.1. Simeons: Demo and temp exterior wall
to be complete in one week

3.2. P&CG: Target date for completion of Bank


Alley; Quazite boxes arrive yet?; See
Bulletin #13 issued 7/14

3.3. NYSEG Gas: Stub out Aurora St south,


install branch saddles, stub out Aurora St
north, pressure test and gas up; Target
date for gassing up main; Temp asphalt
required for all NYSEG/DDS work
3.4. NYSEG Electric: JC to provide start date
for pulling wire to Aurora St; Wizzard to
run overhead wire across intersection at
Aurora
3.5. 202 E State Waterproofing: Notify
property owner of schedule for demo
paving above vault
3.6. Pavilion Lighting: City Inspector and City
Electrician to advise on access points
4. M&PTP: MAINTENANCE & PROTECTION
OF TRAFFIC & PEDESTRIANS
4.1. Fence Reinstallation: PCG to reinstall
fence in front of Trader Ks
4.2. Vacri to submit work sequence to City for
review of pedestrian access, etc. prior to
start of Bank Alley work (sidewalk demo,
grading/compaction testing, set valve
boxes, MH covers, slab pour, pavers, etc.)
4.3. Site Maintenance: Vacri to mark out
boxes; DDS & P&CG to locate and dig out
valve boxes and remove excess material;
All trash and debris must be removed on
a weekly basis
5. New Business: Open RFIs, submittals,
concerns, etc.

Sasaki to issue Cayuga St gateway; Vacri to


reschedule helical pile
Vacri to dig test pit to determine
proximity of footer to areaway vault;
Simeons demo will take place for one
more week
Quazite boxes arrived yesterday; RFI #19
requesting to remove stub on back
order, BP to follow up with a proposed
detail for bollard foundation, Sasaki to
review
NYSEG Gas planned to do temp asphalt for
services; MK asked to have Cayuga St
sidewalk cleaned up, DS to check; LZ
concerned with cutting old gas main out
of the way of catenary light poles with
close proximity of DB
MK to follow up

City inspector and electrician to provide


feedback to project team

PCG to reinstall fence


Vacri is to submit

PCG to reinstall the Welcome to the


Commons sign at Seneca St

ADDITIONAL NOTES

Page 2 of 2