2014 Construction Meeting #23
Distribution/Attendance:
City of Ithaca
Downtown Ithaca Alliance
Sasaki Associates
Labella Associates
Vacri Construction / ACP /
Power & Construction Group
Verizon
NYSEG Gas
DDS
NYSEG Electric
Next Time
10:00 AM
Prepared By
Jessica Buckley
Location
Commons Project Office 215 East State St Ithaca, NY
(Present at meeting unless noted: A absent)
Michael Kuo, Jessica Buckley, Nicole Mason
Tammy Baker
Susannah Ross, Eamonn Hutton(A), Kimberly Michaels TWM(A)
Dan Walker, James Matzat(A)
Ralph Avery, Andy Breznay, Matt Thomas(A), Roberto DeVincentis(A),
Bob Bellavigna ACP(A)
Lou Zupan, Bill Planert
Gloria Moran(A), Jeff Utter(A)
Doug Stafford(A) Jack Barker(A), Dawn Stillwell(A), John Mattiace(A)
Jeff Bubb(A), Flint Brann(A)
Jack Czapranski(A), Dennis Kuhn(A)
Item / Description
1. RFIs, SUBMITTALS
1.1. Vacri (Contract #3A):
1.1.1.Granite Coordination (#87R2)
Submittal #87R2 issued 8/25/14
1.1.2.Gateway (#106) see Bulletin #18
for steel cuts; need 2 diameter hole
in base plates for electric feeds
1.1.3.Irrigation (#98) Deleted from
contract
1.1.4.Structural Soil (#90R2) KM
contacted Paolangeli on 8/19;
subcontractor will prepare new mix
for week of 8/25
1.2. P&CG (Contract #3B):
1.2.1.Lighting Submittal #13R7 and #13R8
Poles and fixtures issued 8/20 and
8/25
1.2.2.Catenary Cabling #TBD PCG to
issue submittal
2. DESIGN, FIELD DIRECTIVES
2.1. TTC & Home Dairy Alley: Sasaki to issue
Notes
Granite submittal to be reviewed for
bench blocks, changes made by Totaro are
bubbled; DE is marking up gateway
submittal; Gateway at Aurora St can be
poured, there is power traffic signal;
Helical pile to be scheduled by Vacri,
second week of September; MK to discuss
volume of structural soil with the City; RA
to follow up with Paolangeli to resubmit
structural soil; RA to resubmit dcva for
hydrants; BB to resubmit epoxy
SR expects to send out reviewed lighting
submittal soon; Supplier is out of Australia
with 6-8 week lead time, BP searching for
equal supplier in the US
Page 1 of 3
Due
Page 2 of 3
ADDITIONAL NOTES:
EX6 lights in eastern stairwell: one light in the block adjacent to the stairs and then every other
stone south for a total of 4 lights.
SR to issue granite curbing submittal this afternoon
RA concerned that the length of the trench drains will cause the 4 pipe to be 4 below finish
grade directly under the pavers. SR to discuss trench drain connections with structural
engineer.
Storm lateral to Mansour Jewelers 140 E State St is to be installed in location of old sanitary MH
Delivered to Emerson and can be stored until next spring; City and DIA to find a location to store
furniture in the future
Page 3 of 3