2014 Construction Meeting #25
Distribution/Attendance:
City of Ithaca
Downtown Ithaca Alliance
Sasaki Associates
Labella Associates
Vacri Construction / ACP /
Power & Construction Group
Verizon
NYSEG Gas
DDS
NYSEG Electric
Next Time
10:00 AM
Prepared By
Michael Kuo
Location
Commons Project Office 215 East State St Ithaca, NY
(Present at meeting unless noted: A absent)
Michael Kuo, Jessica Buckley, Nicole Mason
Tammy Baker
Susannah Ross, Eamonn Hutton(A), Kimberly Michaels TWM
Dan Walker, James Matzat(A)
Ralph Avery, Andy Breznay, Matt Thomas(A), Roberto DeVincentis(A),
Bob Bellavigna ACP
Lou Zupan, Bill Planert(A)
Gloria Moran(A), Jeff Utter(A)
Doug Stafford(A), Jack Barker(A), Dawn Stillwell(A), John Mattiace(A)
Jeff Bubb(A), Flint Brann(A)
Jack Czapranski, Dennis Kuhn(A)
Item / Description
1. RFIs, SUBMITTALS
1.1. Vacri (Contract #3A):
1.1.1.Granite Coordination (#87R2): Play
Benches
1.1.2.Structural Soil (#90R2): Vacri to
update on status of re-submittal;
testing lab and TWLA are in
agreement on patented mix
1.1.3.Gateway (#106, #114a/b): Under
review by Selux/HLB for EX9
mounting
1.1.4.Double Check Valve (#116): City
plumbing inspector okd DCVA;
Sasaki to review
Notes
Gateway: Selux has not responded, DE is
out of office until Monday; Conduit to be
stubbed up through base plate; #87: 14
2x2 bench block was thought to be
deleted; Bronze inlay was deducted,
however small benches were not
deleted; Open question remains about
how the benches are to be installed; SR is
working with Hanover on reviewing
etched paver samples; A sample of the
etching in granite bench is to be
submitted to SR; Bronze inlays deduct
were not accepted by the City, BB to
review; #90R2: Results from lab expected
on 09/11; Sasaki is expecting submittal
on lettering for trolley circle; #110 has
been rejected; Glass canopy sample has
been sent to Sasaki; Glass canopy mock
up to be assembled most likely at
Emerson; All RFIs anwered; RA to submit
Page 1 of 3
Due
SR to issue
Page 2 of 3
ADDITIONAL NOTES:
Submittal 68R1 - detectable warnings: curb ramp detail update is included in compliance set
Page 3 of 3