Documente Academic
Documente Profesional
Documente Cultură
Management:
(verb)
Cost Variance
n
Comparison of the
budgeted cost of work
performed with actual
cost
Negative CV means the
project is over budget
SV = EVPV
Schedule Variance
n
Comparison of work
performed during a period
of time to what was
scheduled to be performed
Negative SV means the
project is behind schedule
Q4
CV = EV - AC
= $???
Good News: If CV value is positive, the project is
currently under budget (spending less than
planned for the work)
Bad News: If CV value is negative, the project is
currently over budget (spending more than
planned for the work)
CPI = EV / AC
= ???
Good News: If CPI value is >1 or =1, the project
cost trend is currently under or at planned budget
Bad News: If CPI value <1, the project cost trend
is currently over budget
Q5
CV% = CV / EV
= ???%
Good News: If CV% value is positive, the project
is currently under budget by the CV%
Bad News: If CV% value is negative, the project is
currently over budget by the CV%
Awkward!!!
SV = EV - PV
= ???
Good News: If SV value is positive, the project is
currently ahead of schedule
Bad News: If SV value is negative, the project is
currently behind schedule
SPI = EV / PV
= ???
Good News: If SPI value is >1 or =1, the project
schedule trend is currently ahead or on planned
schedule
Bad News: If SPI value <1, the project schedule
trend is currently behind schedule
Q6
SV% = SV / PV
= ???%
Good News: If SV value is positive, the project is
currently ahead of schedule
Bad News: If SV value is negative, the project is
currently behind schedule
Q7
CV = -$7,500
SV = -$10,000
AC = $47,500
CPI = 0.84
SPI = 0.80
EV = $40,000
CV% = -19%
SV% = -20%
Estimate at Completion
(EAC)
Actual costs to date plus a new estimate for all
remaining work (original plan no longer valid)
EAC = AC + ETC
(ETC Estimate to Complete)
Q8
Estimate at Completion
(EAC)
Actual costs to date plus remaining budget (current
variances viewed as atypical of future variances)
Actual costs to date plus remaining budget modified
by a performance factor (CPI) (current variances are
viewed as typical of future variances)
Project: Alpha
1.6
1.4
1.2
1.0
0.8
S
S
C
S
C
C
S
S
C
S
C
S
C
S
C
Under budget
Ahead of schedule
Over budget
Behind schedule
0.6
0.4
Project Week
Project: Beta
1.6
1.4
1.2
1.0
0.8
C
S
C
S
0.6
Under budget
Ahead of schedule
Over budget
Behind schedule
0.4
1
Project Week
Project: Charlie
1.6
1.4
1.2
1.0
0.8
S
C
S
C
C
S
S
C
Under budget
Ahead of schedule
C
S
0.6
C
S
Over budget
Behind schedule
C
S
0.4
1
Project Week
Q9
Another View of
Cost and Schedule Variance
Schedule
Variance
Progress
PV
AC
EV
Time
Cost Variance
by team
Due by 11:55pm, Friday, November 2nd, 2012.
No late days review swap with another team
Complete Homework 6 Earned Value Analysis
Due by 11:55pm, Tuesday, October 16th, 2012
n