NAME OF PROJECT
DEPARTMENT
INSPECTION DATE
REPORT DATE
SR. NO
DATE
23-May-12
:
:
:
:
:
AREA VISITED
Cooling Tower #
1 /Eliminator
S P Karmakar
beams at cell no01
23-May-12
S P Karmakar
Laboratory
23-May-12
Cooling Tower #
S P Karmakar 1 /Fan cylinder
6B & 10A
23-May-12
Bottom Ash
Storage Silo #
S P Karmakar 1/column no - F2
(2 nos) at grid C2
& C3
23-May-12
S P Karmakar
Laboratory
23-May-12
S P Karmakar
Laboratory
ACTIVITY
OBSERVATION/DEVIATION
Concrete cube
(15x15x15) cm.
testing of M25
grade.
Concrete cube
(15x15x15) cm.
testing of M25
grade
ON REPORT
REMEDIAL ACTION
SUGGESTED
NAME OF THE
CONTRACTOR
M/s. Paharpur
Cooling Towers
Limited
M/s. Paharpur
Cooling Towers
Limited
M/s. Paharpur
Cooling Towers
Limited
Suggested at site to
the concern person of
Contractor about this
M/s. Macawber
as per JITPL
Beekay Pvt. Ltd.
specification.
M/s. Tecpro
Systems Limited
Already suggested to
M/s. Tecpro
Mr. Kashyap - QA/QC
Systems Limited
of TECPRO
STATUS
RECTIFICATION
REFERENCE WITH
DATE AND SR.
NO.
Today 02 samples of 7
days and 02 samples of
28 days testing observed.
Dimensions of concrete
cube were ok.
Open
NAME OF CLIENT
NAME OF PROJECT
DEPARTMENT
INSPECTION DATE
REPORT DATE
:
:
:
:
:
SR. NO
DATE
22-May-12
22-May-12
S P Karmakar
Laboratory
S P Karmakar
Cooling Tower # 1
/Fan cylinder 6B &
10A
22-May-12
AREA VISITED
22-May-12
Bottom Ash
S P Karmakar Silo/column no - F2 (2
nos) at grid C2 & C3
22-May-12
S P Karmakar
Laboratory
22-May-12
S P Karmakar
Laboratory
22-May-12
S P Karmakar
Township / 01 no raft
of B5 type quarter.
22-May-12
S P Karmakar
Township/C1 type
quarter
POWER LIMITED
OJECT,ORISSA
ACTIVITY
OBSERVATION/DEVIATION
SPECTION REPORT
SERVATION/DEVIATION
REMEDIAL ACTION
SUGGESTED
NAME OF THE
CONTRACTOR
M/s. Paharpur
Cooling Towers
Limited
M/s. Paharpur
Cooling Towers
Limited
M/s. Paharpur
Cooling Towers
Limited
M/s. Macawber
Beekay Pvt. Ltd.
M/s. Tecpro
Systems Limited
r 01 sample of 7 days
was found ok.
M/s. Gammon
India Limited
M/s. Gammon
India Limited
STATUS
RECTIFICATION
REFERENCE WITH
DATE AND SR.
NO.
Quality Engineer
was absent at
site.
Quality Engineer
was absent at
site.
Cubes
dimensions were
ok.
Concrete qty.3.20 m3
Cubes
dimensions were
ok.
Structure name:
JNT - 6 F12 raft
beam casting ,
BCN 6A/6B, TR - 9
& 9A tie beam, ER
- 2/6 nos raft
foundation.
NAME OF CLIENT
NAME OF PROJECT
DEPARTMENT
INSPECTION DATE
REPORT DATE
:
:
:
:
:
SR. NO
DATE
NAME OF THE
INSPECTOR
AREA VISITED
13.06.2012
D.Banerjee
Tecpro laboratory
13.06.2012
D.Banerjee
Paharpur cooling
tower (1)&(2)
13.06.2012
D.Banerjee
Tecpro laboratory
AL POWER LIMITED
PROJECT,ORISSA
ACTIVITY
Curing of structure
OBSERVATION/DEVIATION
OBSERVATION/DEVIATION
done by pipes
REMEDIAL ACTION
SUGGESTED
ok
ok
NAME OF THE
CONTRACTOR
STATUS
RECTIFICATION
REFERENCE WITH
DATE AND SR.
NO.
M/s. Tecpro
systems Limited
closed
M/s Paharpur
cooling tower
Limited
OPEN
M/s Tecpro
system limited
closed