TMP FORMAT
1. Description of the proposed works and lane/road closures.
2. Identification and assessment of traffic impacts of proposed works.
3. Detail traffic management measures to ameliorate the impacts of proposed works.
4. Assessment of public transport services affected.
5. Details of provisions made for emergency vehicles, heavy vehicles, cyclists and
pedestrians.
6. Assessment of effect of proposed traffic management measures on traffic movements
in adjoining streets.
7. Proposed public/ tenant notification process if required.
NOTES
1. The TMP should include following details:
1.1 Location of road occupancy/proposed works
Street name and number
precinct on airport
Map of where on airport
1.2 Road Occupancy Details
2. If approval is granted for the proposed works the applicant must prepare a Traffic
Control Plan (TCP) that complies with OH & S requirements to protect the safety of
workers as well as the road users. The Traffic Control Plan shall comply with Manual of
Uniform Traffic Control Devices, based on AS 1742.3 2002. Freely available from the
Department of Main Roads Queensland Website (www.mainroads.qld.gov.au)
3. With some smaller work sites/occupancies, the Traffic Control Plan can be submitted
as the Traffic Management Plan.
4. If the works/road occupancy cannot go ahead because of adverse weather conditions
or other unforseen circumstances, the applicant may reapply for another date using the
same Traffic Management Plan. Providing that there are no changes to the original
application, BAC needs to check wether the new date conflicts with any other road