Documente Academic
Documente Profesional
Documente Cultură
PRACTICUM REPORT
Abustan, Rosalyn V.
Biglete, Daniel Fernando P.
Casalla, Lincoll A.
Edades, Isabelo P.
Pineda, Bernadette B.
To
Professor RAUL C. ASIS
November 15, 2014
BRIEF DESCRIPTION
OF THE PROJECT
The Orchard Residences is a 46-storey twin tower condominium and 1 parking podium
that is used for commercial and residential space. It is located at Masangkay Street in Tondo,
Manila. Also, it is located besides Metropolitan Hospital and Wharton Park Suites. The Orchard
Residence is the most prominent and distinguished residence in Masangkay. This project is
planned to have a quality, elegance, and comfort meet practical design and value. It is a Fareast
Property Development Corporations project that was contracted by Golden Fortune TechnoBuilt Incorporation as the projects general contractor.
The duration of the project is started at December 9, 2013 and is estimated to be finished
in 46 months. Thus the total project duration is from 2013 to 2017.
The Orchard Residences have a comfortable Studio, 1-Bedroom Flex, and 2-Bedroom
units to choose for. Each unit size ranges from 20 m2 to 50 m2. It also have thoughtful amenities
and facilities such as Retail Arcade, Kiddie Pool, Adult Pool, Meditation Garden, Jogging Path,
Fitness Gym, Bridge Way, Game Room, Wi-Fi Enable Study Hall and more.
METHODS OF
CONSTRUCTION
Methods of Construction
1. Preparatory Works for RC Columns, Beams, and Slabs
a. Alignment and Grading
Line and Grade Engineer should see to it that alignment and grading of structural
elements are observed with regards to the plans provided prior to rebar, form, and
concrete works.
Rebar Specifications
c. Rebar Fabrication
In ordering rebars, available sizes are 6m to 15m with an increment of 1.5 meters.
In some cases, desired sizes are unavailable or out of stock and some alterations on
design of rebar placement should be done. These changes may be present on the
cutting lists provided by the quantity surveyor. Details of splicing zone, development
length of hooks, etc. are the most critical phases for fabrication of rebars.
Bending of Reinforcements
10
11
b. Scaffoldings Installation
Scaffoldings are designed and placed properly prior to rebar installation in order
to prevent hazards or injuries. These scaffoldings are used to avoid movements of
forms that may alter the alignment upon rebar and concrete works to be done.
12
13
14
Placing Boom
15
c. Inspection
Inspection prior and after a certain work at site is done by QA (Quality
Assurance)/QC (Quality Control) Engineer. QA Engineer should inspect the rebar
count and spacing after the placement of column, beam, and slab rebars.
16
Concrete Pouring
17
PROJECT QUALITY
MANAGEMENT
18
Need to perform quality checks for fabrication sequences not available for inspection
at
completion, and
GFTBI will provide a one day advance notice of impending hold points. Field
inspector conducting the quality test and inspections shall complete the daily construction
report. The daily construction report will be distributed to the Owner, CM site manager,
GFTBI PM, and or QC officer. CM will review QA test and maintain file for all field QA
documentation.
19
Objective:
To ensure that testing and inspection events are properly triggered and scheduled with
the concerned parties.
Procedure:
1. CQC Engineer gives instructions to Proceed for an activity.
2. Field Engineer requests CQC Engineer to schedule inspection/inspection.
3. CQC Engineer confirms date/time of inspection among all parties.
4. During inspection of testing, inspection Checklist or Test Certificates, respectively, are
used in documenting findings.
5. CQC Engineer checks the Testing Requested; CQC Representative and Safety Engineer
approve the inspection request.
6. Preliminary inspection is conducted by GFTBI prior to the joint inspection with IACAI.
7. Comments based on inspection by management team are compiled by GFTBI prior to
approve of any request scope of work.
20
Concrete
In the sampling and testing of concrete, before the actual pouring the concrete is subjected to
slump test with which 75mm of drop is the acceptable value.
In addition to that, minimum of six (6) cylindrical samples were taken for compressive
strength test. The size of sample varies depending on the design mix of the concrete and it
measure 4 by 8 or 6 by 12. The six cylindrical samples are tested during its 7 th, 14th and
28th days of the concrete. Proper curing of the samples is applied to avoid any error.
Slump Test
Concrete Samples
21
The testing of concrete is based on the ASTM C39 standard and the use of Universal Testing
Machine is applied. The contractors partner testing company is the Matest located in Bambang,
Manila and Terms Concrete Testing (TCT) in Tayuman, Sta. Cruz, Manila
22
23
8 mm 20mm
25mm 32mm
36 mm
No. of Samples
Length of
Samples
Type of Test
0.6 m
Tensile
0.4 m
Bending
0.6 m
Tensile
0.5 m
Bending
0.6 m
Tensile
0.5 m
Bending
The test conforms to PNS49 standard and the universal testing machine is used to test the
samples. The steel bars are subjected to tensile and bending test. The partner for testing the
reinforcing steel bars Matest located in Bambang, Manila and Philippine Geoanalytical. Inc. in
Kamuning, Quezon City.
24
There were two(2) sample of reinfircement bar to be tested. One for tensile test and another one
for bending stress. As the testing center or the Matest requires the longer one was for tensile test
and the other one will be for bending.
25
Mechanical Coupler
In the sampling of reinforcements steel bar with mechanical couplers, they obtained two
(2) samples. They used couplers to connect the two (2) steel bars.
The test conforms to ASTM A 325 standard and the universal testing machine is used to
test the samples. Samples are subjected to tensile test. The partner for testing the reinforcing steel
bars Matest located in Bambang, Manila and Philippine Geoanalytical. Inc. in Kamuning,
Quezon City.
26
27
28
29
Concrete Pouring Request (CPR) is the one needed before pouring of concrete in every
structural member of a building. It should be signed or approved by the Trade Contractor like
Electrical, Mechanical etc., General Contractor (GFTBI) and Inspector (IACAI).
30
3. Form enclosure
In the enclosure of formworks, Engineer will be assisted by the Architect and other
Trade Contractor to inspect if the specific structural member passed the requirements or
specifications to enclose it by formworks. Form Enclosure must be approved by the inspector
to proceed.
31
Form Stripping Request is the last activity to be done. Before removing the formworks,
the checklist must be observed by the inspector. It must also be 7 days after the pouring of
concrete. It must also be complied to what the general notes says.
32
Comply with
Specifications?
YES
NO
33
34
DOCUMENTATION
AND RECORD KEEPING
35
Documentation and Record Keeping is one of the most important parts of construction.
It is a compilation of important information and data involved in the process of construction. It
includes progress reports, file documents, and details about the project. Without these reports, it
would be difficult for the company to stand firm whenever there will be issues regarding the
construction. These might serve as proofs that will support situations. And everything must be
recorded for the data collection.
Once the project has started Progress Reports and Record Keeping should, at the same
time start. Progress reports must be in a form of daily reports, weekly reports and monthly
reports. This is to further monitor the development and/or changes in the project. These reports
can be in a form of checklist, narrative observation, or a detailed report with photos and billings.
DAILY REPORTS
Daily Reports includes the work done within the day, extra work done, manpower count,
equipment, kind, number and status. This also includes the weather condition within the day
from am to pm. This is to determine how the work will be affected by the uncontrolled situations
just like the change in weather. The report is called Daily Project Log which is done daily. It is
prepared by the Planning Engineer and must be submitted to the Project-in-Charge.
Log Books is a record book that is done by the site supervisor. All the observations and
activities done during the day is recorded and kept on the office. This may serve as a reference
during a meeting. It is very important to keep hold of records of whatever happened for a specific
so that if there will be problems encountered, it would be easier to trace on what part exactly it
has started. It is necessary to have this daily logbook as part of an effective project management.
Additional forms such as Accident Reports and numerous checklists help make sure that you're
covered.
36
37
38
39
Weekly Reports is said to be the summary of daily reports. It is a compilation of all the
submittals by subcontractors within the week. It is important because it helps in guiding and
monitoring the changes and improvements on the project. The same time, the contractors will be
able to respond accordingly with legal actions. This weekly report is prepared by the
documentation team in the form of billings and/or list of submittals and submitted to the project
manager.
This report includes:
40
41
Weekly Forecast
This part of the report indicates the projected start and finish of a work within a certain
week. It is said to be the schedule that needs to be followed. This is prepared by the planning
engineer and is submitted to the project-in-charge.
Weekly Accomplishment
In this part of the report, the accomplishment made on the project within a certain week is
compared to the projected schedule. Through illustration, the comparison will be clearer. In here,
it could be seen if there are delays or the work done is ahead of time. This is prepared by the
planning engineer and is submitted to the project manager. After this, an Accomplishment
Report will be made accordingly, to further explain the details regarding the accomplishment
which is also made by the planning engineer.
42
43
Progress Photos
This will serve as supporting details to the accomplishment report. These are taken
photos on the changes made on the construction of the structure. It is detailed in such a way, that
in each zones per floor, changes are documented. This is done by the site engineer and/or
planning engineer and compiled by the documentation controller.
44
45
46
47
48
49
Monthly Progress Report is a more detailed report compared to the weekly report. It
includes details about the current progress of the project. This includes the list of activities done,
currently doing and needs to be done on the project. Together with this, attached are the billing
forms, change of orders, current status and/or date of completion. This also includes problems
encountered on the project with corresponding solutions made and/or plans to address the
problem. This monthly report is subdivided into three parts: written report, project tracking
schedule, and activity management schedule.
50
Written report is a summary of: progress for the month against defined objectives;
financial progress (i.e. expenditure against budget and cash flow projection; physical progress;
problems encountered and the actions proposed to resolve the problems; and information
required which has an impact on undertaking the work at hand).
Project tracking schedule is an excel-based schedule which the following details for
each project: project details, project budget and expenditure to date, project physical progress
and problems encountered, project employment data and current status of the project.
Activity management schedule is an excel-based schedule that lists all of the major
activities and objectives that must be achieved within the timetable and/or deadline. This tracks
the planned completion dates for the key activities as well as the actual completion of the
activity.
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
III.
3.1
3.2
3.3
3.4
Executive Brief
Project Description
Project Organization
Health, Safety and Environment Program
Updates for the Period - September 1-25, 2014
Accomplishment Report
As per MS Project Master Schedule (Original Contract)
As per Bar Chart/Cash Flows
Construction Update
Activities last Period
Activities this Period
Activities next Period
Weather Chart
Three-Months Look-Ahead Schedule
Submittal Logs of Materials West and East Tower
Submittal Logs of Shop Drawings West and East Tower
Submittal Logs of Methodology
Submittal Logs of Product Data/Sample
Submittal Logs of Test Results
Master Submittal List
Annexes
Master Schedule
51
3.5
Progress Photos
Updates for the Period
This part of the report includes the summary of accomplishment and variance (if theres
any) of the project. This will inform the owner of the works done in that particular month.
Accomplishment Report
In this part, Golden Fortune Techno-Built Inc. based on the MS Project Master Schedule
and the Bar Chart/Cash Flows. This is shown using figures to further visualize the
accomplishment done compared to the work that needs to be done.
Construction Update
It is a detailed list of activities for the last period, current period and next period. This is
done to inform the owner and project manager of the works done in the project so they will be
guided accordingly, and they would further study it to improve the sequence of work or stick to
what is planned.
52
Weather Chart
It is very important for the contract to be updated of the weather forecast. One of the
uncontrolled variables in construction is the change in weather; it highly affects the work, cost,
time and progress. This is done to systematize the sequence of work and further adjustments on
the construction. This is important because, a work cannot be pursued if there is a coming storm
or typhoon, not only for the contractor but also for the safety of the workers.
53
54
55
56
COST DOCUMENTATION
Cost Documentation is basically the cost estimation of the whole project, starting from
the manpower utilizations, equipment utilizations and material cost. Every cost related matters
on the site must be kept recorded and documented. It is very important for the owner to be
updated and properly informed on this matter.
57
58
59
TIME AND
COST CONTROL
60
61
Project Schedule:
S-curve is defined a display of cumulative costs, labor hours or other quantities plotted against
time. The beginning represents a slow, deliberate but accelerating start, while the end
represents a deceleration as the work runs out.
Prior to project commencement, a schedule is prepared outlining the proposed allocation of
resources and the timing of tasks necessary to complete the project within a set time frame and
budget. This schedule is referred to as the Baseline Schedule. From this schedule, a Baseline Scurve is generated. This S-curve reflects the planned progress of the project. If the project
requirements change prior to commencement like change of scope and delayed start, the Baseline
Schedule may require revision to reflect the changed requirements.
62
63
ACTUAL
16.58%
VARIANCE
0.00%
REMARKS
On schedule
14.35%
ACTUAL
14.35%
VARIANCE
0.00%
REMARKS
On schedule
VARIANCE
PROJECTED
2.23%
ACTUAL
2.23%
VARIANCE
0.00%
REMARKS
Monthly Accomplishment
64
65
66
Delays Encountered:
Time delays happen because the actual condition in the site is not the same as planned like
weather condition and other factors that affect the work progress. Another reason is if there will
be revisions to the original plan. These delays are reflected through slippage in the S-Curve.
The owner, Orchard Residences, decided to add a basement which is not included in the original
plan that resulted to a delay of schedule compared to the S-Curve prepared from the contract.
Because of this, there will be a revised or catch-up schedule that is currently on process (46month construction). As of now, the Golden Fortune Techno-Built Inc. is still adopting the
original schedule and S-Curve (38-month construction).
Here are some solutions used by the Planning Department:
Manpower
It means that in order to meet the time scheduled, the contractor can add more workers to
do the project. However, this solution needs more budget to implement it.
System
In this solution, the Golden Fortune Techno-Built Inc. changed their formwork system
from EFCO System to Aluma System. In the West Building, they used EFCO System but
they notice that their work is delay so they change the formwork system of the East
Building to Aluma System to catch-up the schedule. Aluma System has bigger plate,
meaning it can save time in forming it and will accelerate the progress of their work. But
this solution may need extra cost since they started their work using EFCO System.
67
Cost Variances:
A variance is the difference between a budgeted/ planned cost and the actual amount. The
concept of variance is intrinsically connected with planned and actual results and effects of the
difference between those two on the performance of the general contractor. It is based on the unit
of quantities and the S-Curve. As of now, there is 0.00% variance in the project.
There are cases that negative variance occurs. It is when the actual amount is greater than the
budgeted/ planned amount. In order to avoid negative variance, the contactor should know how
to balance and control the cost of the project.
Here are some of the ways how contractor adjust the operation to address cost variance:
68
MEASURING WORKS
ACCOMPLISHMENTS AND
REPORTING WORK PROGRESS
69
Progress report is done daily, weekly and monthly. The daily and weekly reports are compiled
for the monthly report. Every progress report is composed of accomplishment (daily, weekly and
monthly), look ahead schedule, manpower and equipment schedule, submittal plan, shop
drawings and progress photographs. They measure work accomplishment by having percentage
accomplishment for that period and percent weight accomplishment based on the whole project.
Variance is zero meaning the project is on schedule.
Measuring work accomplishment for formworks, rebar, and concrete are all done by each
respective field engineers.
Formworks engineer calculates the surface area for a certain structural member and
multiply a unit rate for formworks to get the amount of phenolic boards or formworks to
be used for that certain billing period. These phenolic boards are for beams and girders
(sides and bottom), slabs (bottom), and for shear wall and column (sides).
Rebar engineer measures the work accomplishment based on the rebar installed not
delivered. Delivered rebars are equal to the installed plus the scrap. Installed rebars are
from slabs, beams and girders, columns, and shear walls. The documents attached for this
one are the cutting list and summary of installed rebars together with the scrap for each
commercial length of steel bars for that period.
Concreting engineer is responsible for compiling all the documents regarding concreting
works. Attachments involved are the estimated volume of concrete and the actual amount
of concrete installed for that billing period. Concrete installed are from slabs, beams and
girders, columns and shear walls. He calculates the actual volume of concrete and
multiplies with the unit rate for concrete.
70
71
72
73
The architect assesses the claim, determines the monetary amount which the contractor is entitled
to under the contract and issues a progress certificate to the contractor
The contractor presents the progress certificate and a tax invoice to you for payment
The building contract usually states a limited time within which you must make the payment
74
75
76
77
78
PROGRESS
PAYMENTS
79
80
VARIATION ORDER
AND TIME EXTENSIONS
81
Variation Order
Variation order is also known as change order; this is an alteration or adjustment to the scope of
work in a construction contract in the form of an addition, replacement or omission from the
original scope of work.
Variations may include alteration to the:
Design
Quantities
Qualities
Working conditions
Sequence of work
Source of Conflict
Variations are often sources of argument and can cost a lot of time and money during the course
of a contract. While some variations are unavoidable, it is wise to minimize potential variations
and subsequent claims by ensuring that uncertainties are eliminated before awarding the contract.
This can be done by:
82
83
Time Extension
Extension of time is based on the ability to demonstrate that delays have occurred in
the construction schedule affecting project completion date. Time extension requests are
normally specified in contracts provision and requesting time extensions should be made
following all steps and documentation under the contract guideline. When requesting a time
extension the Contractor should notify the Project Manager, when any issue might affect the
project schedule. A formal letter must be addressed to the Contract Administrator requesting the
time extension and the reasons why those days should be added to the construction schedule. The
Contract Administrator should then, remit the letter to the Project Manager for evaluation and
approval or rejection. If the time extension is granted, then the Project Manager must answer by
written and a change order will be issued. Some contracts specify that time extension requests
should be done within a specific time frame, if not; the time extension claim will also be
rejected. Time extension document should have this following:
List of activities from project schedule being affected by the aforementioned issue
Exact amount of time being requested specifying working days or calendar days
Sketches, photographs, or pictures
Indicate the actions the contractor has taken to avoid or minimize other delays
Alternative solutions presented to Contract Administrator
Time extension requests are normally claimed due to the following circumstances:
Variation order
Lack of manpower
Shortage/Unavailability of materials
84
85
86
Problems Encountered
In a construction project although every action or activity is thoughtfully planned, still,
problems and delays occurred. Problems in the surroundings, setting up the formworks, pouring
of concrete, placing of reinforced bars and finishing should be considered to come up with a
good project. During our on-the-job training on Orchard Residences, we encountered different
kinds of problems and these are:
One of the major problems that we encountered is the honeycombs. As we can see in the
picture there are hollow spaces and cavities left in concrete mass on surface or inside the
concrete mass where concrete could not reach. These look like honey bees nest.
Honeycomb is due to non-reaching of concrete to all places due to which cavities and
hallow pockets are created, main reasons are:
1. Improper vibration during concrete.
2. Less cover to reinforcement bars.
3. Use of very stiff concrete (this can be avoided by controlling water as
per slump test).
4. Places like junction of beam to beam to column and to one or more beams
are the typical spots where honey combs are observed. This is due to
jumbling of reinforcement of beams and column rods at one place; special
attention is required at such place during concreting and vibrating.
5. Presence of more percentage of bigger size of aggregate in concrete also
prevents concrete to fill narrow spaces between the reinforcement rods.
Corrective Action:
Due to the hallow spaces and cavities the concreting engineer recommend to apply an
epoxy injection to fill up the hallow spaces and cavities.
87
88
Another major problem, the ground and second floor exceeds the property line on one
side of the building which occupied the property line of the neighboring structure.
Corrective action:
Group of surveyor was hired to investigate. After getting and analysing the data, there is
a need to demolish the parts that exceeds the property line. This is also known as
rectification methodology.
89
Another problem, the construction induced property damage on one of its neighbour.
Their neighbours are also complaining about the noise and dust pollution that they are
producing. Their neighbours are schools, church and hospitals. This is also one of the
problems that need to be considered.
Corrective action:
The owner, contractor and management of Orchard Residences set a formal meeting with
the said establishment to fix the problem.