Documente Academic
Documente Profesional
Documente Cultură
q=
A=
k ( H 2 - h2 )
R
ln( )
A
(1)
(2)
Where,
q = Total rate of discharge required in m3/hour
k = Permeability constant in m/sec (1 104)
H = Hydrostatic Head of Ground water level above the
impervious layer (30 m)
226
Dewatering from inside the well using extra two pumps and
through installed wells were continued till the completion of
construction of base raft along with the bottom beams.
Pumping was stopped stage wise as it was need to construct
the Flume Tunnel on the left hand side of the Scale Pit. As
the Flume tunnel has to connect the scale pit at 14 m from
the ground level, the retaining of the soil around flume tunnel
cases big problem. The soil movement around Flume tunnel
due to deep excavation may affect the pumping wells, Sheet
pile walls are installed to retain the sides of the excavation
near left hand side of scale pit (Fig. 3).
1-RCOG
in mm
0.43
3.11
3.41
3.26
3.41
3.56
3.91
3.96
4.16
4.01
4.31
3.81
2-MSOG
in mm
0.65
3.42
3.55
3.50
3.62
3.75
4.25
4.25
4.30
4.25
4.55
4.15
3-RCIC
in mm
0.39
2.88
3.28
3.13
3.31
3.68
3.93
3.98
4.23
4.13
4.43
3.98
4-MSIC
in mm
0.79
3.24
3.64
3.64
3.59
3.99
4.24
4.34
4.44
4.34
4.64
4.24
Note: RC-Roll Change Track Side, OG-Out Going, MS- Mill Motor
Side, IC- In Coming side
227
6. CONCLUSIONS
228