(ADSSC)
DIVISION 3 CONCRETE
ADSSC/GSCW
Division 03
Section 03400
Precast Concrete
Rev: 02
Jan. 2011
Page 1 of 13
Date
01
April 2008
First Issue.
02
Jan. 2011
03
04
05
06
07
08
09
10
ADSSC/GSCW
Division 03
Section 03400
Precast Concrete
Rev: 02
Jan. 2011
Page 2 of 13
TABLE OF CONTENTS
1
GENERAL ....................................................................................................... 4
1.1
1.1.1
1.1.2
1.1.3
1.1.4
1.1.5
1.2
1.3
1.4
1.4.1
1.4.2
1.4.3
1.4.4
1.5
1.6
PRODUCTS ..................................................................................................... 9
2.1
2.2
EXECUTION .................................................................................................. 10
3.1
3.2
3.3
3.4
ADSSC/GSCW
FABRICATION ................................................................................... 10
PRECAST CONCRETE MANHOLE UNITS ....................................... 11
SURFACE TREATMENT AND REPAIR ............................................. 12
ERECTION......................................................................................... 12
Division 03
Section 03400
Precast Concrete
Rev: 02
Jan. 2011
Page 3 of 13
GENERAL
1.1
1.1.1
j)
The yard shall be equipped with a stationery concrete pump with suitable
piping system and all necessary conveyors, chutes and hoppers
required for satisfactory concreting procedures.
ADSSC/GSCW
Division 03
Section 03400
Precast Concrete
Rev: 02
Jan. 2011
Page 4 of 13
1.1.2
1.1.3
COATING YARD
a) The yard shall be fully covered and enclosed and shall have a minimum
area of 50m2
b) The yard shall be equipped with both manual and spray painting
equipment and be provided with a sand blasting facility.
c) Equipment for tests on coating (i.e. coating thickness, pull off tests,
holiday tests, etc.) and humidity and temperature measuring devices
shall be readily available.
d) The coating work shall be supervised by experienced and qualified
personnel.
1.1.4
1.1.5
SITE LABORATORY
a) A sufficiently equipped laboratory shall be provided on site to carry out
the concrete and aggregates tests as specified in Section 03300.
Qualified and trained QC personnel shall be appointed to carry out the
testing works in the site laboratory. Minimum requirements for the
laboratory shall be established on site depending on the contractors
proposal whether or not he intends to employ an independent testing
laboratory.
b) Within a reasonable time prior to commencement of precast concrete
work, the Contractor shall schedule a pre-construction meeting with the
Engineer to discuss design, materials, methods of work, forming
systems, quality control, testing, transporting and erection.
ADSSC/GSCW
Division 03
Section 03400
Precast Concrete
Rev: 02
Jan. 2011
Page 5 of 13
1.2
RELATED DOCUMENTS
The following sections of the specification shall be read in conjunction with
this section.
Section 01000-07
Section 01000-08
Section 01000-09
Section 03100
Section 03200
Section 03300
Section 03500
Section 03600
Section 05100
1.3
Submittals
Quality control
Materials and equipment
Concrete formwork
Concrete reinforcement
Cast in place concrete.
Concrete repair and grouting.
Concrete protection and waterproofing.
Structural steelwork.
STANDARDS
All activities relating to this section of the specification shall comply with the
following or approved equal standards.
BS 5911-1
BS EN 1916
BS EN 1917
BS EN 13369
ISO 9000
1.4
SUBMITTALS
1.4.1
iv.
ADSSC/GSCW
Division 03
Section 03400
Precast Concrete
Rev: 02
Jan. 2011
Page 6 of 13
v.
1.4.2
Design standards.
Design loadings.
Reinforcement details.
Hoisting requirements.
Connection details.
Anchoring devices.
Stability requirements.
METHOD STATEMENTS
a) The Contractor shall submit method statements to the Engineer for
approval 4 weeks in advance of commencing the site activity in
accordance with Section 01000-07 of the specification. These shall
comprise but not necessarily be limited to:
i.
ii.
1.4.3
DRAWINGS
a) The Contractor shall submit drawings to the Engineer for approval in
advance of commencing the site activity in accordance with Section
01000-07 of the specification. These shall comprise but not necessarily
be limited to:
i.
1.4.4
Reinforcement details.
Connection and anchorage details.
Lifting devices, locations and handling limitations.
Openings, sleeves, inserts and embedded items.
Precast concrete unit location.
Relationship to adjacent units and/or structures.
Precast concrete unit identification number.
SAMPLES
a) Representative samples, as agreed with the Engineer, must be
submitted for at least the following items at the same time as the
particulars are submitted.
ADSSC/GSCW
Division 03
Section 03400
Precast Concrete
Rev: 02
Jan. 2011
Page 7 of 13
i.
1.5
QUALITY CONTROL
a) Prior to dispatch of any product and/or material from source the
Contractor shall notify the Engineer in writing in sufficient time to allow
the Engineer the opportunity to inspect and test the product and/or
material prior to delivery in accordance with Section 01000-08 of the
specification.
b) Products and materials shall be from a manufacturer/supplier who
operates a quality system which is registered to ISO 9000 series or
approved equal.
c) To allow the Engineer to inspect the Works the Contractor shall give the
Engineer a minimum of 24 hours notice of carrying out the following
activities on site.
i.
ii.
iii.
iv.
g) Works proof load crushing test for precast concrete manhole shaft and
chamber sections and works load tests for precast concrete manhole
slabs shall be in accordance with BS 5911.
1.6
ADSSC/GSCW
Division 03
Section 03400
Precast Concrete
Rev: 02
Jan. 2011
Page 8 of 13
i.
ii.
iii.
iv.
PRODUCTS
2.1
GENERAL
a) For exposed architectural concrete obtain sufficient cement, aggregates
and water from a single source to complete the entire structural precast
concrete work to assure regularity of appearance and uniformity of
colour.
b) Materials for formwork, reinforcement, concrete, concrete repair
materials, concrete protection and waterproofing system and joints shall
be in accordance with the requirements of the relevant sections of
Division 3 of the specification.
c) Unless noted otherwise all precast concrete units shall be manufactured
using Grade C40/20 concrete as specified in Section 03300 of the
specification.
2.2
ADSSC/GSCW
Division 03
Section 03400
Precast Concrete
Rev: 02
Jan. 2011
Page 9 of 13
d) Design anchor bolts, inserts, plates, angles and other cast in items with
sufficient anchorage and embedment to support applicable loads.
e) Surfaces of precast concrete units in contact with sewage or sewage gas
aggressive liquids and/or atmospheres shall be lined in accordance with
the requirements of Section 03600 of the specification.
f)
EXECUTION
3.1
FABRICATION
a) Maintain plant records and quality control program during production of
precast concrete units. Make records available upon request. Such
records shall include:
i.
ii.
iii.
iv.
v.
vi.
Ensure reinforcing steel, anchors, inserts, plates, angles, and other cast
in items are embedded and located as indicated on the drawings and will
not be misplaced during concreting.
ADSSC/GSCW
Division 03
Section 03400
Precast Concrete
Rev: 02
Jan. 2011
Page 10 of 13
i)
j)
Tolerance
Length
5mm
Width
3mm
Flange thickness
2mm
0.2%
Straightness
3mm over 3m
End squarness
3mm
ADSSC/GSCW
Division 03
Section 03400
Precast Concrete
Rev: 02
Jan. 2011
Page 11 of 13
3.3
3.4
ERECTION
a) Verify that site conditions are ready to receive work and field
measurements are as shown on the drawings.
b) Prepare temporary support equipment for the erection procedure
required to control alignment, deflection and stress levels.
c) Contact surfaces between cast-in-place and precast concrete units shall
be prepared as specified in Section 03300 of the specification.
d) Dimensional tolerances shall be checked before the precast concrete
units are lifted into position.
e) Erect precast concrete units without damage to structural integrity,
shape, or finish. Replace, or if permitted by the Engineer repair,
damaged precast concrete units.
f)
ADSSC/GSCW
Division 03
Section 03400
Precast Concrete
Rev: 02
Jan. 2011
Page 12 of 13
Criterion
Tolerance
i)
j)
Field cutting of holes shall be carried out with power saws or core drills
up to a maximum size of 150mm all to the Engineers approval.
END OF SECTION
ADSSC/GSCW
Division 03
Section 03400
Precast Concrete
Rev: 02
Jan. 2011
Page 13 of 13