Documente Academic
Documente Profesional
Documente Cultură
20 July 2012
1.0
1.1.
1.2.
Problems Encountered
(Lettered items correspond to lettered items in 1.1 above)
A. Out of a total 168 Sub-clauses, the following changes have been made:
Such a high level of changes is due to the fact that FIDIC Yellow Book was designed to be
used as a design/supply and install contract. When you try to make the contract off-shore
only and remove the installation component from the scope, then the contract has to be redesigned.
Typically, if you have to make so many changes to the conditions of contract, then you are
probably using the wrong form of contract
B. Contract cannot be linked to the Supply Contract in any way in order to prevent show-cause
for enjoinment.
C. The Supply Contract and the Supervision and Commissioning Services Contract have the
same end date - namely when the Employer issues the Taking Over Certificate. So all the
Contractor's obligations under the Supply Contract (i.e. performance guarantee, liability for
defective plant, clear and concise installation drawings, etc.) remain in force during the
Page | 1
20 July 2012
2.0
2.1.
OPTION 1 - Using the NEC3 Supply Contract 2007 and NEC3 Professional Services
Contract
This would be similar to our current contracting strategy - having a separate off-shore Supply
Contract and an on-shore Construction and Commissioning Management PSC.
The New Engineering Contract (NEC) system is a division of the Institution of Civil Engineers
(ICE). NEC3 is a family of standard contracts with the following notable characteristics:
Its use stimulates good management of the relationship between the two
parties to the contract;
It can be used in a wide variety of commercial situations, for a wide variety of
types of work and in any location;
It is a clear and simple document - using language and a structure which are
straightforward and easily understood ('Legalese' is removed).
Page | 2
20 July 2012
Option A - Priced contract with activity schedule - a lump sum priced contract
in which the risks of performing the Scope of Services at the agreed price are
borne mostly by the Contractor;
Option C - Target contract - where the financial risks are shared by the
Employer and the Contractor in agreed proportions;
Option G - Term contract -where various items of work are priced on a time
basis.
Page | 3
20 July 2012
4 One Programme so managing cause and effect issues is a lot more simple.
5 A separate Interface Agreement letter is not necessary to link a Supply Contract
and a separate Supervision and Commissioning Services Contract.
B. The term 'EPCM' is still relatively unknown amongst a large part of the construction
fraternity. Under the EPCM model the contractor does no building or construction - rather
he develops the design, supplies the equipment and manages the construction process on
the Owner's behalf. An EPCM contract is a professional services contract which has a
radically different risk allocation and different legal consequences when compared to a
standard EPC contract. The key difference is that under an EPCM contract, other parties
[the Employer for example] constructs the project.
The following forms of contract could be used:
2.3.
20 July 2012
The NEC3 Supply Contract (the conditions are well suited and only certain parts of
the Contract Data sections would need to have two parts - one for the off-shore
supply component and one for the on-shore construction management services
component.
Recommendation
Actually, I would recommend having both of the options outlined above included into our new
tendering and contracting strategies.
To simplify the new tendering strategy, and also the contract administration after execution, I
would recommend going with OPTION 2 above if we intend to use one Contractor for both the
supply and the construction management.
If we ever decide to contract one company to supply the equipment and then a separate
company to perform the construction/commissioning management, then of course OPTION 1
above would be appropriate.
Prepared by:
Jeff Barnes
Commercial Manager
Hedcor - Engineering and Construction Dept.
Page | 5