Documente Academic
Documente Profesional
Documente Cultură
REFERENCE DRAWING
DRG. NO.
O
REV
DETAILS
13.10.2013
DATE
LH
DRAWN
Nizam
CHKD.
AM
APPVD.
REVISIONS
CONTRACTOR
P.O. Box 21757
Al Wakra Tower (6th Floor), Old Salata Road,
Corniche Area, Doha, Qatar.
T '+974 4456 0222
F '+974 4456 0378
W 'www.siemens.com
PROJECT CONSULTANT
QSC
DRG./DOC.
NO.
SCALE 1:1
SHEET NO.
E -
E B -
E - 7 4
DATE
0 3
SIZE
9
A4
DSGND. BY
DRAWN BY
13.10.2013
CHKD. BY
13.10.2013
APPVD. BY
13.10.2013
DRG./DOC. E-EB-E-74-I003
REV.
0
Page 1 of 9
PROJECT
CLIENT
CONSULTANT
: MOTT MACDONALD
Page 2 of 9
1. PURPOSE:
The purpose of this method statement is to define and establish a systematic
and quality procedure for different activities required for:
Installation of GI Cable Tray and Trunking for the QATAR STEEL 220/66KV
SUBSTATION.
This process ensures that all works are carried out in a safe manner in
accordance with the contract specifications and approved shop drawings.
2. SCOPE:
This method statement covers all activities related to:
Installation of GI Cable Tray and Trunking for the QATAR STEEL 220/66KV
SUBSTATION.
For the satisfaction and approval of the KM, QS, MML
3. REFERENCES:
This method statement should be read in conjunction with the latest
approved revisions of following documents:
3.1
3.2
3.3
3.4
Project Specifications
Project IFC drawings
Qatar Construction Specifications 2007
Inspection and Test Plan for GI Cable Tray, Trunking
Page 3 of 9
4. RESPONSIBILITIES:
4.1
4.2
4.3
4.4
4.5
4.6
Project Manager
Project Engineer
QA/QC Engineer
Foreman
Safety Officer
Safety Inspector
5. TOOLS
o
o
o
o
o
Hack-saw
Measuring Tape
Jig Saw Machine
Hammering/ Drilling Machine
Portable Hand Tools
6. PROCEDURE
6.2.1 Handling & Storage:
6..1
6..2
6..3
Page 4 of 9
6..4
6..5
6..6
Material found not suitable for the project will be removed from the
site immediately.
6.2.1 Preparation:
6..1
Ensure that the work area is ready and safe to start the installation of
cable trays and trunking.
6..2
Check and ensure that shop drawings and materials ready to use for
installation are latest and approved for construction.
6..3
Ensure that the materials and accessories received from site store for
the installation of cable trays/trunking and accessories are free of rusty
parts and damages.
6..4
The correct size and type of cable trays, trunking & accessories shall
be ascertained from the approved shop drawings prior to installation.
6.2.1 Installation:
6..1
Mark and line out the route of Cable Tray and Trunking as per
approved shop drawings with marking threads.
6..2
6..3
Page 5 of 9
6..4
6..5
Mark locations of the supports and drill the holes in the slab/wall for
anchor fixing as per appropriate size complying to the approved
drop in anchor as follows:
Supports shall be selected form the following types, to suit the site
conditions:
M12 steel threaded drop rods fixed to ceilings complete with
Gl channels or brackets
Wall support brackets
Cantilever arms
Steel channels.
6..6
shop
drawings
and
6..7
6..8
6..9
6..10
6..11
6..12
Page 6 of 9
6..13
6..14
6..15
6..16
7. SAFETY:
All hand and portable power tools to be used shall be of good order and
be used for the purpose intended.
Page 7 of 9
8. Records
Inspection Request duly signed by QC/KM/MML.
9. Attachments
Page 8 of 9
Job Location
Analyst
HSE Department
Hazard Type
Description of
Risk
Risk of getting injury while working in the night with poor lighting effect.
4 Safe and reasonable access shall be provided for the working areas.
5 Specified/ recommended industrial sockets/ plugs shall be used
for extension wires.
6 Power supply will be switched off when the power tool is kept idle
for longer period.
7 Sufficient lighting to be provided while night work is to be carried out.
Comments
Page 9 of 9