Documente Academic
Documente Profesional
Documente Cultură
The fields of application where the Pipe Thruster can be used are described below.
1. Auxiliary tool for Horizontal Directional Drilling (HDD)
2. Installation of pipelines into existing boreholes or tunnels
3. Recovery of pipelines from the ground
4. The Direct Pipe Method (DP)
5. The Pipe Express Method (PEX)
2.1. Auxiliary tool for HDD (Horizontal Directional Drilling)
The Pipe Thruster is installed on the pipe-site and can be used during pipe pull-in to
help to push the pipeline into the borehole (in case of too high pull forces). The Pipe
Thruster provides additional installation forces, the applied push force is added to the
pull force of the HDD-Rig. A HK500PT Pipe Thruster and a 400-ton HDD-Rig for
example can apply 900 tons of installation force. In most of the cases the Pipe
Thruster is installed as a reserve, but not always needed.
Figure 2: Pipe Thruster as auxiliary tool for HDD on a project in Saudi Arabia
Rig-site with HDD-Rig
Figure 3: Pipe Thruster installing a concrete coated pipeline into an existing tunnel in Australia with a length of
14,270ft (4,35 km)
Figure 4: Pipe Thruster installing a pipeline into an existing tunnel in India with a length of 8,200ft (2,5 km)
separation plant
Control container
Pipe Thruster
Direct Pipe machine
Comparable with the jacking frame used for standard pipe jacking (Microtunnelling)
with short concrete pipes, the Pipe Thruster acts as the thrust unit in Direct Pipe. It
4
hydraulically grips the pre-fabricated and outlaid pipeline and pushes it into the
ground in strokes of five meters. Coated product pipes (with a diameter range
between 28 and 60) can be pushed directly. The required bore hole is excavated by
the Direct Pipe machine (AVN slurry machine). The machine is deployed at the front
end of the pipeline and pushed into the ground together with the pipeline. The
excavated material removed by the slowly rotating cutterhead at the tunnel face is
mixed inside the machine with the drilling fluid (bentonite suspension) and then fed
through a discharge line through the entire pipeline to the separation plant on the
surface (through a separate discharge line). After treatment, the material is pumped
back into the circuit via a feed line. The drilling fluid thus not only discharges the
excavated material but also supports the tunnel face.
2.5. The Pipe Express method (PEX)
In contrast to Direct Pipe the Pipe Express method was developed for the half-open
installation of pipelines where larger diameter pipelines (36 - 60) with lengths of up
to 6,500ft (2,000m) can be installed. During the installation process, the soil is
excavated by the Pipe Express machine and transported directly to the surface by a
chain trencher and conveyor belt. The tunnelling machine is accompanied on the
surface by a buggy and the operators control vehicle. The pipe thruster installed in
the launch pit pushes the machine and the pipeline through the ground. The
simultaneous excavation of the soil and insertion of the product pipe creates an
optimum pipe bedding situation.
Figure 8: The Pipe Thruster used to push the pipeline into the borehole created from the Pipe Express machine
Chain trencher
Pipe Express machine
Pipe Thruster
The PEX system is used on projects where the open-cut installation of pipelines
would cause high investment due to special requirements. The system has many
advantages in unstable soil or where the open-cut installation of pipelines would
require measures such as groundwater lowering.
HK300PT
HK500PT
HK750PT
3,000 / 300
5,000 / 500
7,500 / 750
36
48
60
Attack angle ()
Weight (tons)
Dimensions (m)
0 to 15
40
53
78
Figure 10: Clamping unit of the Pipe Thruster with clamping inserts with vulcanized contact rubber
Table 2: Comparison of characteristics of different pipeline coatings with the impact of the Thruster
SPECIFIC VALUES OF FACTORY-COATED STEEL PIPELINES
(STANDARD CHARACTERISTICS)
Coating Material
Shear Strength /
Shear Force [N/mm]
Compression Strength /
Contact Pressure [N/mm]
IMPACT OF PIPE
THRUSTER
Polypropylen (PP)
Polyethylene (PE)
HK500PT / HK750PT
10
> 10
< 1,2
1)
17,5 - 20
> 10
< 3,5
2)
Figure 11 and 12 show exemplary the specific clamping plates for a 48-pipeline
(OD=1290 mm) for the pipe Thruster HK500PT and HK750PT. Also marked are the
loads given onto the clamping plates (and therewith to the coating and/or pipeline)
under full clamping pressure of the hydraulic system (in the clamping cylinders
pressing the clamping plates onto the pipe).
Figure 11: Clamping plates of Pipe Thruster HK500PT for a 48-pipe (clamping area = 5.240.000 mm) and loads
of hydraulically driven clamping plates (4 x 4181 kN)
1)
shear force with an advance force of 5000 kN (500 to) / 7.000 kN (700 to) from Pipe Thruster (steel pipe DN1200 = 48).
2)
contact pressure on the coating caused by the clamp of the Pipe Thruster HK500PT / HK750PT (steel pipe DN1200 = 48).
Figure 12: Clamping plates of Pipe Thruster HK750PT for a 48-pipe (clamping area = 7.264.000 mm) and the
loads of hydraulically driven clamping plates (4 x 6272 kN)
Within the framework of these tests, two field joint coating materials were tested. At
clamping a PE-shrink slieve as well as a wrapping tape and additional onecomponent GRP mat - in opposition to the factory-made coating - clear damages on
the field joint coating were generated. The resulting consequence is that the field join
coating must not be clamped with the Pipe Thruster. It is recommended that the
operator has to recess this area with an additional safety zone. The clamp can only
be attached were no irregularity on the coating is recognized.
Together with the Dutch
(Polypropylen) was tested.
Gas
supplier
Nederlandse
Gasunie
PP-coating
Figure 14: Test with a PP-coated 48-pipe with a Pipe Thruster HK500PT
Thrust direction
Reserve force for the pipeline pull-in in difficult HDD projects (large diameter,
long distance)
Central component for the Direct Pipe and Pipe Express method
Installation of pipelines into existing tunnels / boreholes
Maximum push and pull force of up to 7.500 kN (750 tons)
Installation of 2 or 3 Pipe Thrusters behind each other possible (push or pull
forces are added
Clamping unit highly flexible in case of moving pipeline due to mounting of the
hydraulic thrust cylinders onto the cardan joint
Minimum 22 Pipe Thruster successfully operating in the market since 2006
More than 60 successful projects without any damages neither on the coating nor
the pipeline
Several coating tests executed with several pipeline coatings where is shown
that the coating is not damaged by the Pipe Thruster: Polyethylene (PE),
Polypropylene (PP), Glasfibre Reinforced Plastic (GRP), Fusion Bonded Epoxy
(FBE), Concrete Coating
Maximum shear stress on the pipeline coating (between clamping unit and
coating)
is 1,2 N/mm
Maximum surface pressure on the pipeline coating (between clamping unit and
coating)
is 3,5 N/mm
Power transmission via two big hydraulic cylinders
Cardan joint as connection for the hydraulic cylinders to the steel base frame with
0-15 vertical deviation and minimum 1,5 deviation to each side in the horizontal
Ability to fully open the clamping unit to fit it over the pipeline and thus no need to
guide the clamping unit over the product pipe
Infinitely adjustable clamping pressure
Infinitely adjustable push-/pull force
Easy centralizing of the pipeline in the clamping unit by a top-carriage
Integrated and height adjustable pipe-support
Measuring of the twist of the pipeline, for safe handling of the pipe