Sunteți pe pagina 1din 22

A

LDMR 23/1999
B

IN THE LANDS TRIBUNAL OF THE


HONG KONG SPECIAL ADMINISTRATIVE REGION

MISCELLANEOUS REFERENCE APPLICATION NO. 23 OF 1999


D

_________________
E

BETWEEN

Pennys Bay Investment Company Limited

and
Director of Lands

Applicant

Respondent
H

_________________
I

LDMR 1/2005
K

IN THE LANDS TRIBUNAL OF THE


L

HONG KONG SPECIAL ADMINISTRATIVE REGION


MISCELLANEOUS REFERENCE APPLICATION NO. 1 OF 2005

_________________
N

BETWEEN
O

Pennys Bay Investment Company Limited

and

Director of Lands

__________________

Applicant

Respondent

-2-

Before: Deputy Judge KOT, Presiding Officer, Lands Tribunal and


Mr K K CHIU, Temporary Member of the Lands Tribunal

Date of Hearing: 19 December 2014


C

Date of Decision: 16 January 2015


D

_________________

DECISION

__________________
G

Background
H

1.

This is the cross application for leave to appeal by the parties

in this case against the judgment handed down by this Tribunal on 15


October 2014 (Main Judgment).

abbreviations used in the Main Judgment.

2.

We shall adopt the same

used

In the Main Judgment, we have found that Lot 22 can be


for

shipbuilding

and

mid-stream

operation

before

the

extinguishment of its marine rights (Before Value). The Before Value

is enhanced by the prospect of the Container Terminal Scheme going


N

ahead.

It is also our finding that after the marine rights being

extinguished with more certainty that the Container Terminal Scheme

would go ahead, Lot 22 can be used for industrial purpose, which is the
P

highest and best use when compared to the mid-stream use (After
Value).

3.

It is our conclusion that since the Before Value is in excess

of the After Value, the applicant is entitled to receive compensation for

the extinguishment of its marine rights in the sum of $10,952,500.


T

-3-

Leave to Appeal
B

4.

Section 11(2) of the Lands Tribunal Ordinance (LTO)

provides that :
C

Subject to section 11AA and the provisions of any Ordinance


relating to appeals from the Tribunal, any party to proceedings
before the Tribunal may appeal to the Court of Appeal against a
judgment, order or decision of the Tribunal on the ground that
such judgment, order or decision is erroneous in point of law.

5.

(6) Leave to appeal shall not be granted unless the Tribunal,


the Court of Appeal or the registrar hearing the application for
leave is satisfied that

(a) the appeal has a reasonable prospect of success; or

(b) there is some other reason in the interests of justice why


the appeal should be heard.

Section 11AA(6) of the LTO provides that :

6.

Reasonable prospect of success involves the notion that the

prospects of succeeding must be reasonable and therefore more than


L

fanciful without having to be probable (SMSE v KL [2009] 4


HKLRD 125 at 17). And if a finding of facts is perverse or irrational;

or there was no evidence to support it, or it was made by reference to


N

irrelevant factors or without regard to relevant factors, the decision may


be quashed (Edwards v Bairstow [1956] AC 14).

7.

Bearing in mind these legal principles, we shall deal with

each ground of appeal raised by the parties in seriatim.

-4-

Applicants Application
B

Ground 1
8.

This Tribunal erred in adopting inconsistent approach in

reflecting the uncertainty as to whether the Container Terminal Scheme


D

might proceed in the Before and After Value.

Whilst the Tribunal

accepted that there is a risk factor in the Before Value to reflect the
E

uncertainty inherent in the factual expectation as to whether the Container


F

Terminal Scheme might proceed at all, it had failed to do the same in the
After Value when the Tribunal also acknowledged that there was still

remained a degree of uncertainty for the scheme not proceeding at all.


H

9.

The Tribunal erred in law in holding that artificial

assumption about marine rights had any impact, or even significant


J

impact upon the factual expectation as to whether the Container Terminal


Scheme might proceed at all.

10.

It is beyond argument that this Tribunal had not applied the

same formula to reflect the uncertainty inherent in the factual expectation

as to whether the Container Terminal Scheme would proceed in the


N

Before and After Value. This Tribunal has given 50% discount to the
hope value in the Before Value to reflect the uncertainty whilst there is

none awarded in the After Value. This is because as one can see from
P

Section F.(7) and H.(4) to H.(6) of the Main Judgment, it is the finding of
this Tribunal that since the marine access had already extinguished, the

only uncertainty in the After Value is the delay involved, hence there is
R

no hope value to be reflected in the After Value and the formula adopted
in the Before Value is not applicable.

-5-

11.
B

Having said so, we do agree that Ground 1 raised by the

applicant did involve a legal issue as to whether the artificial legal

assumption about marine rights had any impact upon the factual
C

expectation which cannot be said to be without any reasonable prospect


D

of success. Leave to appeal should be granted under this ground.

Ground 2
F

12.

The Tribunals findings that the Container Terminal Scheme

and its associated roadworks were expected to proceed is perverse. The

Tribunal failed to take into account the industry view back in 1995 which
H

is not in dispute but instead based on the pure speculation that all the
factors relied upon by the applicant should have been considered by the

Government before the proposal was first published in 1994 and that the
J

Government and the Governor in Council should have already approved


in principle to proceed with the Container Terminal Scheme.

13.

The industry view had been considered by this Tribunal in

112-118 of the Main Judgment and the findings at 114 are not

speculation but are reasonable inferences to be drawn from the fact that
N

the proposal was being published and authorized. We do not agree that
such a finding of fact is in any way perverse and amounts to an error in

law.
P

14.

We found the applicant had failed to establish any

reasonable prospect of success or there is any reason in the interests of


R

justice that this ground should be heard. Leave to appeal under this
ground is refused.

-6-

Ground 3 and 4
B

15.

The Tribunal failed to give full and proper recognition to the

intent and effect of the Before-assumption about marine rights in the


C

Before Value and adopted the value of Industrial Development which


D

wholly dependent upon the existence of road access, ie a Before Value

for the Godown/Industrial Area based on a new use without marine


E

access, contrary to its own findings in 26 of the Main Judgment.


F

16.

The Tribunal has not considered or discussed at all or in any

details the applicants case on its Scenario 3 which assessed the


H

Godown/Industrial Area with marine access and reflect the enhancement


value arising from the anticipated road access brought by the expectation

of road access without detracting from the Before-assumption about


J

marine rights.

17.
L

The Tribunal has already considered the new use of Lot 22

with marine access (i.e. mid-stream use value) but the Tribunal has also
considered the expectation which the prospective purchaser would have

in mind to reflect the enhancement value if the OZP and the Container
N

Terminal Scheme were to proceed.

18.
P

In the formula P=[(H-L)xR]+L adopted at 408 of the Main

Judgment, L is the value of the subject property for mid-stream use with
marine access whilst the value of the subject property with the

expectation of the Container Terminal Scheme going ahead is H. The


R

difference between L and H reflects the enhancement value resulted from


the anticipated road access brought by the Container Terminal Scheme.

-7-

19.
B

Having said so, we do agree that Ground 3-4 raised by the

applicant did involve a legal issue as to the interpretation of the CFA

Judgment in assessing the enhancement value which cannot be said to be


C

without any reasonable prospect of success. Leave to appeal should be


D

granted under this ground.

Ground 5
F

20.

The Tribunal erred in its adjustment made to the NKML

Comparables in relation to the Lease Term Adjustment by first

performing a time adjustment and then applying the 1995 Yield. This has
H

in effect applied statistical data which were indices for capital values to
the leases.

21.

Yield reflects the investment return in the market. A 1993

Yield does not reflect the situation in 1995 so a time adjustment must be

performed before applying the 1995 Yield. We found the applicant had
L

failed to establish any reasonable prospect of success or there is any


reason in the interests of justice that this ground should be heard. Leave

to appeal under this ground is refused.


N

Ground 6
22.

The Tribunal failed to consider the rental value suggested by

the applicants industry expert Kong.

23.
R

It is not a must that this Tribunal has to accept the rental

value suggested by Kong when such evidence is not being challenged by


the respondent. This Tribunal has adopted the unit rate derived from the

STT Comparables which are transaction prices that the Tribunal found to
T

be more reliable.

-8-

24.
B

We found the applicant had failed to establish any

reasonable prospect of success or there is any reason in the interests of

justice that this ground should be heard. Leave to appeal under this
C

ground is refused.
D

Ground 7
E

25.
F

The Tribunal erred in making a -35% adjustment on account

of Height Restriction when the evidence showed that the operation


contemplated on Lot 22 would be on the basis of 3 tiers and the

Tribunal wrongly assumed or speculated that having a higher height


H

restriction would be of substantial benefit.

26.
J

This attacks our findings at 243-245 of the Main Judgment.

As found at 244, AW also admitted that 8 layers of containers are


possible for the storage of empty containers. With the height restriction,

Lot 22 must be disadvantaged in the storage of, at least, empty containers.


L

With a higher height restrictions allowed, it allows more flexibility for the
operators and can be considered a benefit.

27.

We found this is just a matter of opinion and the applicant

had failed to establish any reasonable prospect of success or there is any

reason in the interests of justice that this ground should be heard. Leave
P

to appeal under this ground is refused.

Ground 8
R

28.

The Tribunal erred in making a -20% adjustment on account

of Quay Length based on the wrong assumption or speculation that

having a more than optimal quay length would be of substantial benefit.


T

-9-

The fact that the quay length can be split into 3 should not be a
B

disadvantage which warranted a downward adjustment.

29.
D

We found this is just a matter of opinion and the applicant

had failed to establish any reasonable prospect of success or there is any

reason in the interests of justice that this ground should be heard. Leave
E

to appeal under this ground is refused.


F

Ground 9
30.

The Tribunal erred in making a -41% adjustment on account

of Location and an additional -15% adjustment on account of Remoteness


which is wrong in principle and against the evidence.

31.

We found this is just a matter of opinion and the applicant

had failed to establish any reasonable prospect of success or there is any

reason in the interests of justice that this ground should be heard. Leave
L

to appeal under this ground is refused.

Ground 10 and 11
N

32.

The Tribunal erred in finding that the KCTL Comparables

are appropriate comparables ignoring all matters and contentions raised

by the applicant. And the Tribunal proceeded on the erroneous basis that
P

the only difference between Lot 22 and the KCTL Comparables was
location, lack of road access and time. The Tribunal also speculated that

the KCTL Comparables were conducted on the basis that the bidder
R

would consider that marine rights would continue undisturbed for the
entire 50 year lease.

- 10 -

33.
B

We found this is just a matter of opinion and the applicant

had failed to establish any reasonable prospect of success or there is any

reason in the interests of justice that this ground should be heard. Leave
C

to appeal under this ground is refused.


D

Ground 12
E

34.
F

The Tribunal erred in rejecting the evidence of Kong on a

false premise and speculated there were hidden reasons rendering Lot 22
unattractive and wrongly assumed that the owners of Lot 22 were keen to

lease out the lot.


H

35.

As stated in 331 of the Main Judgment, this Tribunal came

to the conclusion that there were hidden reason because the owner was
J

willing to accept a rental substantially below the rental of $8/sq ft which


Kong believed to be the market rental. This is a reasonable inference to

be drawn from the evidence. And the fact that there were the China
L

Merchants offer to lease the Lot and upon the falling through of it,
another tenancy agreement with the CLP, this Tribunal is entitled to come

to the conclusion that the owners were keen to lease out the Lot.
N

36.

We found the applicant had failed to establish any

reasonable prospect of success or there is any reason in the interests of


P

justice that this ground should be heard. Leave to appeal under this
ground is refused.

Ground 13
37.

The Tribunal erred in not valuing the Non-Shipbuilding Area

at a rate at least no less than the properly adjusted rate for the
T

- 11 -

Shipbuilding Area since the Non-Shipbuilding Area is found to be


B

capable for use for ship repairing purpose.

38.
D

By the Non-Shipbuilding Area, this is termed as the

Industrial/Godown Area of Lot 22 in the Main Judgment. It is never the

parties case that the Industrial/Godown Area can be used for shipE

repairing purpose and should be valued as such. The applicant and the
F

respondent

have

contended

that

the

optimum

use

of

the

Industrial/Godown Area should be for mid-stream and industrial

developments respectively. In any event, it is the finding of this Tribunal


H

that the optimal use of the Industrial/Godown Area is mid-stream use.

39.
J

Furthermore, it is our findings at 176 of the Main Judgment

that most of the comparables were less than 64,583.4 sq ft and it is


unlikely and unreasonable that the entire remaining lot of over 1,725,000

sq ft at Lot 22 will be used for ship repairing purpose. Taking into


L

account the marketability and the unreasonably large in area for ship
repairing use, it is not reasonable to apply the rate for the Shipbuilding

Area on the remaining portion of Lot 22.


N

40.

We found the applicant had failed to establish any

reasonable prospect of success or there is any reason in the interests of


P

justice that this ground should be heard. Leave to appeal under this
ground is refused.

Ground 14
41.

The Tribunal erred in failing to take into account the set up

costs for covered or warehoused storage based on the wrong assumption


T

that there was no evidence adduced.

- 12 -

42.
B

It is not the finding of this Tribunal that the set up costs need

not be taken into account because there was no evidence in this regard.

Instead it is the finding of this Tribunal at 228 of the Main Judgment


C

that the mid-stream use is for open storage so no covered or warehouse


D

storage is involved, hence no set up costs is required to be considered.

43.
F

We found this is just a matter of opinion and the applicant

had failed to establish any reasonable prospect of success or there is any


reason in the interests of justice that this ground should be heard. Leave

to appeal under this ground is refused.


H

Respondents Application

Ground 1
J

44.

This Tribunal erred in failing to make allowance for a period

of demolition of unauthorized structures on Lot 22 based on the finding

that such demolition could take place whilst construction work


L

commenced on the unbuilt areas of Lot 22. However, this is inconsistent


with the findings of the Tribunal that the construction of industrial

structure on the unbuilt area was not expected to commence for some
N

years after the valuation date. Under such circumstances, it does not
make sense to say that there should be no period allowed for the

demolition.
P

45.

Since it is the finding by this Tribunal that there should be a

deferment of 6 years in the construction work to commence, no additional


R

period of demolition is required.

46.
T

We found this is just a matter of opinion and the applicant

had failed to establish any reasonable prospect of success or there is any

- 13 -

reason in the interests of justice that this ground should be heard. Leave
B

to appeal under this ground is refused.

Ground 2
D

47.

The Tribunal erred in adopting a wrong figure in the

assessment of demolition costs.

Whilst the Tribunal accepted the

estimate of demolition costs of $11,091,798 suggested by Mok (the


F

respondents expert), the Tribunal had adopted a figure of $8,049,200


without any apparent addition for professional fees or development profit.

48.

The Tribunal admitted that we made a mistake for not

accounting for professional fees of 6% and development profit of 30% in

345 and leave to appeal should be granted.


J

49.

If professional fee and development profit is taken into

account, the value of Lot 22 for mid-stream use will be as follow:


L

(a)
(b)

Less
P

Shipyard Value
285,000 sq ft @751.6/sq ft
Mid-stream Use
1,725,000 sq ft @200/sq ft

$214,206,000
$345,000,000

$559,206,000
Demolition Costs (excluding canteen as $11,091,798
only illegal structures would be
demolished)

$8,049,200
R

Fee @6%
Development Profit @30%

x1.06
x1.3

$548,114,202
Say $548,114,000

- 14 -

50.
B

For the benefit of the appeal hearing, the following figures in

the respective paragraphs of the Main Judgment stated below would also

be affected:
C

408

So, applying the assessed figures to the formula:

= [(H-L) x R] + L

= [($841,828,000 - $548,114,000) x 0.5] + $548,114,000

= $293,714,000 x 0.5 + $548,114,000

= $694,971,000

The Before Value of Lot 22 is $694,971,000.

480

The amount of compensation is the amount of Before

Valuation in excess of After Valuation.

Before Valuation
After Valuation
Amount of Compensation

$694,971,000
$685,540,000
$9,431,000

Ground 3
O

51.

The Tribunal erred in making no downward adjustment for

the limited use within the shipyard area based on the incorrect factual
P

premise that ship repairing use as well as godown use can occur at the
Q

same time at the remaining portion of Lot 22.

52.
S

Ship repairing and godown uses are permitted uses under the

lease condition.

Taking into account the huge size of the remaining

portion of Lot 22, the Tribunal cannot exclude the possibility that both

- 15 -

uses can practically occur at the same time. As the optimum use of the
B

site was found to be mid-stream uses for open storage , it is possible that

the occupier can use part of the remaining portion which is adjacent to
C

shipbuilding area with marine frontage for ship repairing, if necessary.


D

With this flexibility for using portion of the remaining lot for ship

repairing use, whenever necessary, we do not think there is a need to


E

make any adjustment for the limited use within the Shipyard Area.
F

53.

We found this is just a matter of opinion and the applicant

had failed to establish any reasonable prospect of success or there is any


H

reason in the interests of justice that this ground should be heard. Leave
to appeal under this ground is refused.

Ground 4
54.

The Tribunal erred in finding that the stacking of containers

in the open air as part of their transit was a godown use in line with
L

Special Condition 3(a).

55.
N

We accept this ground involved the interpretation of the

terms of the Special Condition which is a point of law and leave to appeal
should be given for the same to be considered by the Court of Appeal.

Ground 5
56.

The Tribunal erred in adopting a unit rate of $1,200/sq ft for

open storage use whilst it is found by AW (applicants expert) and


R

accepted by the Tribunal that the godown use is for open storage use and
the unit rate for such use should be $1,000 only.

- 16 -

57.
B

As we have found in 227-229 of the Main Judgment, we

should consider the optimum use and this explains why we pick the

higher figure of $1,200/sq ft in the assessment.


C

58.

We found this is just a matter of opinion and the applicant

had failed to establish any reasonable prospect of success or there is any


E

reason in the interests of justice that this ground should be heard. Leave
F

to appeal under this ground is refused.

Ground 6
H

59.

The Tribunal erred in failing to make a downward

adjustment of 20% on the length of quay for the KCTL Comparables

which, like Lot 22, had quay lengths which were satisfactory by reference
J

to the optimum standard.

60.
L

The Tribunal agreed that adjustment should be made on the

length of quay for the KCTL comparables to reflect the optimum


standard. As the valuers of both parties have not touched on the quay

length of KCTL comparables, the Tribunal has not clearly stated in the
N

judgment that a downward adjustment should be made on KCTL479 and


an upward adjustment should be made on KCTL481 to reflect the

optimum standard of quay length. Actually, on the Layout Plan (page


P

2145-2147 of Bundle E1), the quay length of KCTL479 is better than that
of Lot 22, so a downward adjustment is needed. However, the shape and

quay length of KCTL481 is poorer than that of Lot 22, an upward


R

adjustment is needed.

61.
T

To be clear, the adjustment table on 305 of the Main

Judgment should be as follows:

- 17 -

Lot No
KCTL481
KCTL479

Adjusted Unit Rate


159
240

Adjustment
+30%
-20%

Revised unit rate


207
192

62.

The average unit rate was about $199.5/sq ft.

63.

The Tribunal agreed that the judgment on this section is

unclear, however this does not affect the resultant figure of unit rate
F

adopted for assessment of the KCTL Comparables.

64.
H

We found this is just a matter of opinion and the applicant

had failed to establish any reasonable prospect of success or there is any


reason in the interests of justice that this ground should be heard. Leave

to appeal under this ground is refused.


J

Ground 7
65.

The Tribunal erred in failing to make equivalent deferment

of 2 years to the KCTL Comparables for the time needed to prepare the
M

ground at Lot 22 for godown use as it had done for the STT Comparables.

66.
O

This Tribunal agreed that there should be no deferment for

the STT Comparables as well as for the KCTL Comparables.

The

Tribunal has clearly stated in 229 of the Main Judgment that the STT
P

comparables are for open storage purpose and AW has also not reflected
Q

any superstructure to be erected. As no superstructure is erected and no

deferment is necessary for STTs, the Tribunal, as stated in 229, took the
R

highest value as the optimum development (i.e. $1,200/sq ft).


S

- 18 -

67.
B

Since the KCTL Comparables are being found to be the

appropriate comparables, the fact that no deferment made cannot be

considered an error and would not affect the end figure found by this
C

Tribunal.
D

68.

We found this is just a matter of opinion and the applicant

had failed to establish any reasonable prospect of success or there is any


F

reason in the interests of justice that this ground should be heard. Leave
to appeal under this ground is refused.

Ground 8
69.

The Tribunal erred in finding that there will be a

compensation for the resumption of land for the construction of a road to


J

link Pennys Bay area and the proposed North Lantau highway. Such a
finding is inconsistent with the declaration made by the CFA that in the

Before Value, it is based on the assumption that Lot 22 enjoyed access to


L

the sea as it had done up to the valuation date. With the marine rights
remained, no container port would or could have been built and no road

would have been constructed.


N

70.

We agree that this is plainly a point of law depending on the

construction and application of the CFA Judgment and we cannot say that
P

there is no reasonable prospect of success in the appeal. So leave should


be granted in this regard.

Ground 9
71.

The Tribunal erred in adopting the higher value between a

combined shipyard and godown value on the assumption that the


T

Container Terminal Scheme did go ahead and on the assumption that it

- 19 -

did not go ahead.


B

Given the uncertainty between the 2 different

scenarios, the finding that the purchaser would pitch his bid on the higher

value is erroneous without basis.


C

72.

The term, Market Value, as defined by the International

Valuation Standard and followed by the Hong Kong Institute of


E

Surveyors is the estimated amount for which an asset or liability should


F

exchange on the valuation date between a willing buyer and a willing


seller in an arms-length transaction after proper marketing where the
parties

had

each acted

knowledgeably,

prudently and

without

compulsion. Whether the prospective purchaser would pitch his bid on


the higher value or on the lower value depends on whether it is a buyer

market or a seller market. As at 1995, the market was going up and the
J

vendor had a larger bargaining power and it is unlikely that the owner
would accept a lower value between 2 different scenarios. That is why

the Tribunal has decided to take the higher value between a combined
L

shipyard and godown value.

73.
N

We found this is just a matter of opinion and the applicant

had failed to establish any reasonable prospect of success or there is any


reason in the interests of justice that this ground should be heard. Leave

to appeal under this ground is therefore refused.


P

Ground 10
74.

The Tribunal erred in failing to reflect the existence of the

sub-tenancy of Cheoy Lee Shipyards Limited in the valuation of the midstream use on the assumption that the Container Terminal Scheme would

go ahead whilst such factor had been taken into account in the assessment
T

- 20 -

of the mid-stream use value on the assumption that the Container


B

Terminal Scheme would not go ahead.

75.
D

The Tribunal stated clearly at 343 of the Main Judgment

that assuming the Container Terminal Scheme goes ahead, the area would

be developed in accordance with the OZP. Therefore, in our assessment,


E

we have taken account of the area to be resumed for road purpose, the
F

area zoned for GI/C etc. The most important thing is the marine frontage
should be resumed for Container Terminal Scheme and the sub-tenancy

should be terminated and a 3-month notice is required.


H

76.

However, if the Container Terminal Scheme does not go

ahead as stated in 345 of the Main Judgment, the sub-tenant can


J

continue to operate its shipbuilding use on the shipyard area and the
remaining portion will be used for mid-stream purpose. Therefore, no
deferment is required.

treatment as suggested by the respondent.

77.

This explains why there had been a different

We found the respondent had failed to establish any

reasonable prospect of success or there is any reason in the interests of


justice that this ground should be heard. Leave to appeal under this

ground is refused.
P

Ground 11
78.

The Respondent contended that for the reasons submitted

above, the value of Lot 22 for mid-stream use found at 345 of the Main
Judgment is faulted.

- 21 -

79.
B

This is just a catch all ground and the reasons behind this

had already been dealt with above under respective grounds.

Ground 12
D

80.

The Tribunal erred in its finding of the ultimate Before

Value based on a radical misconception of law and was fundamentally


E

contrary to the declaration stated by the CFA, namely the Before Value
F

found is based primarily on the prospect of an industrial development of


the non-shipyard area of Lot 22 with a 50% discount for the uncertainty.

81.

The reason for our findings is based on the requirement

stated in the CFA Judgment that prospect of new uses of the land would

have entered into the valuation both with and without access to the sea.
J

82.

Having said so, we agree that this point involved a point of

law which cannot be said that there is no reasonable prospect of success


L

on appeal, so leave should be granted.

Ground 13
N

83.

The Tribunal erred in finding that in the After Value, the

reclamation work and the Container Terminal Scheme or the construction

of the linked road had not even commenced. This is inconsistent with the
P

CFA Judgment which declared that the reclamation must be taken to have
been completed by the valuation date.

The Tribunal also erred in

speculating as to the timing and the uncertainty of the Container Terminal


R

Scheme which is specifically disallowed in the CFA Judgment (at 41).

- 22 -

84.
B

We agree that this involved a point of law concerning the

interpretation of the CFA Judgment and one which may arguably have a

reasonable prospect of success, hence leave should be granted.


C

Conclusion
85.

According to Section 11AA(5) of the LTO, leave to appeal

may be granted in respect of a particular issue arising out of the


F

judgment, order or decision. Hence, we made the following orders :

(a) Leave to appeal is granted to the applicant on Ground 1,


H

3 and 4 stated in the Grounds of Appeal whilst leave to


appeal on all other grounds are dismissed.

(b) Leave to appeal is granted to the respondent on Ground


J

2, 4, 8, 12 and 13 stated in the Grounds of Appeal


whilst leave to appeal on all other grounds are

dismissed.
L

(c) Costs of this application for leave to appeal be costs in


the cause of the appeal.

Deputy Judge KOT

Mr K K CHIU

Presiding Officer

Temporary Member

Lands Tribunal

Lands Tribunal

Mr Denis Chang SC, Mr Johnny Ma and Mr Jeremy Chan, instructed by


Wilkinson & Grist, for the applicant

Mr Valentine Yim, instructed by the Department of Justice, for the


T

respondent

S-ar putea să vă placă și