MEG PROJECT

SN
1

DETAIL
ACTIVITY
Excavation

EQUIPMENT / TOOLS
Hand tools:
shovels, picks
Power handtools:
Jack hammer
air compressor
Mechanical excavator
Backhoe, Payloader
Dump truck/s
Dewatering pump

Submitted by : Nasser S.Al-Hajri Corp.

RISK INVOLVE
1. Injury due to defective tools
2. Injury due to incompetence of worker
3. Injury due to wrong use of tool
4. Injury due to collapse of excavation
or cave-in.
5. Injury due to fall of personnel into
excavation.
6. Injury due to scattered materials
7. Breakdown of equipment.
8. Injury due to fall of dump truck and .
other heavy equipments into excavation
9. Injury due to accidental hit by
back-tracking equipment
10. Injury due to incompetence of
driver, operator.
11.Injury to personnel and damage to
vehicle due to traffic confusion
12. Injury due to inhalation of fumes
from air compressor.
13. Injury due to ignorance of
personnel in operating the air
compressor and jack hammer.

Page 1 of 10

PREVENTIVE MEASURE
1. All hand tools shall be kept in good
condition. They must be kept clean
and stored properly. Handles shall be
inspected frequently for damages and
shall remain tightly secured. Defective
tools shall be removed from service and
repaired or disposed.
2. Train the personnel on how to handle
and operate the equipments or tools
properly.
3. Provide adequate shoring and
bracing system to protect the wall from
collapsing.Wall shall be sloped when
excavating in an open area.
4.Provide hard barricades around the
excavation site and bar any unwanted
personnel, provide ladder for access
in and out of the excavation. Ladder
shall be extended min.1m. above ground
level.Provide handrail at least on one
side of the ladder.
5. Daily house keeping shall be done.
6. Conduct regular check of equipments
to maintain good operating condition
and avoid breakdown during operation.
7. Barricades the excavation site.
Assign one trained person to lookout
and give signal to operator/driver.
8. Backhoe, dump truck/s payloader,
shall be provided with

RESPONSIBLE
PERSON
Safety Supervisor
Site Supervisor

MEG PROJECT
SN

DETAIL
ACTIVITY

EQUIPMENT / TOOLS

RISK INVOLVE

PREVENTIVE MEASURE

RESPONSIBLE
PERSON

back tracking alarm or signal


to alert personnel on site.
9. Only licenced and certified driver/
operator shall be allowed to handle
and operate or drive.
10.Assign one personnel wearing an
orange reflectorized vest to direct traffic
among equipments and other vehicles.
11. Conduct regular check up and
maintain good working condition
of the air compressor. Use proper PPE
by all personnel at the location.
12. Personnel must be trained about the
proper usage and handling of tools.
2

Operation of
Dewatering system

Diesel powered
dewatering pump

1. injury due to fire.


2. Injury due to inhalation of fumes
and noise pollution.

1. Check the engine for fuel leaks.


Repair and keep good maintenance.
2. Use dust mask and ear plugs when
working close to the pump.

Safety Supervisor
Site Supervisor

Scaffolding work

scaffolding materials :
pipes
clamps
wooden planks
spanners

1. Injury due to collapse of scaffolding


due to everloading
2. Injury due to sway and fall of scaffolding
3. Injury due to fall of personnel
4. Injury due to fall of any material from
the top of the scaffolding over personnel
on the ground.
5. Injury due to unsafe scaffolds.

1. Scaffolds shall be designed by a qualified person and shall be constructed


and loaded in accordance with that design.
2. Scaffold and component shall be capable of supporting, without failure, its
own weight and at least 4 times the
maximum intended load applied or
transmitted to it.
3. Guys, ties, and braces shall be installed at the closest horiontal member
to the 4:1 height and be repeated vertically at locations of horizontal members every 26 ft. or less thereafter.
4. The top guy, tie or brace of completed
scaffolds shall be placed no further than
the 4:1 from the top. Such guy, tie and

Safety Supervisor
Site Supervisor
Scaffold foreman

Submitted by : Nasser S.Al-Hajri Corp.

Page 2 of 10

MEG PROJECT
SN

DETAIL
ACTIVITY

EQUIPMENT / TOOLS

RISK INVOLVE

PREVENTIVE MEASURE
bracessall be installed at each end of
of the scaffold and at horizontal intervals
not to exceed 30 ft.
5. Fall protection shall be provided for employees erecting or dismantling scaffolds.
6. A safe means of acces shall be provided, such as properly fixed ladders,
shall be provided for employees erecting
or dismantling scaffolds.
7. 100% fall protection to be used when
working 6 ft. or more from an unprotected elevtion.
8. Full body harness with two 6 ft. shock
absorbing lanyards shall be provided for
employees working on top of scaffoldings.
9. Document monthly inspections on fall
protection equipment and system. Conduct visual inspection prior touse. Ensure that the equipments are in good
condition at all times.
10.Make sure that lanyard anchorage shall
be capable of supporting 5000 lbs.
11.Horizontal lifelines shall be designed,
installed and used under the supervision
of a qualified person.
12.Each platform on all working levels of
scaffold shallbe fully planked or decked
between the the uprights and the guard
supports.
13. Barricade shall be provided around the
area where scaffolding work is going on
or where people are working on elevated
platform at any level of the scaffolding.
14. Warning signs shall be posted to caution unwary personnel from entering the
barricaded area.
15. Scaffolds shall be erected, moved,
dismantled or altered only under the su-

Submitted by : Nasser S.Al-Hajri Corp.

Page 3 of 10

RESPONSIBLE
PERSON

MEG PROJECT
SN

DETAIL
ACTIVITY

EQUIPMENT / TOOLS

RISK INVOLVE

PREVENTIVE MEASURE

RESPONSIBLE
PERSON

pervision and direction of a competent


person qualified inscaffold erection, moving, dismantling or alteration. Such activities shallbe performed only by experienced and trained personnel.
16. Footings shall be levelled, sound, rigid and capable of supporting the loaded
scaffold without setting or displacement.
17. Scaffold and its component shall be
pected for visible defects by a competent
person before each work shift, and after
any occurrence which could affect a
scaffold's structural integrity.
released to proper personnel for use.
4

Rebar work
Lifting

manual handtool:
knipper / wire cutter
bar cutter
power supplied equipment:
bar bending machine
bar cuting machine
equipment:
crane ( if necessary )

Submitted by : Nasser S.Al-Hajri Corp.

1. Injury due to defective tools


2. Injury due to incompetence of worker
3. Injury due to wrong use of tool
4. Injury due to fall of personnel working
above 1 meter height
5. Injury due to tripping over rebar
6. Injury due to protruding rebar ends.
7. Injury due to mechnical failure.
8. Injury due to overloading.
9. Injury due to crane tripping.
10. Injury due to confusion of signal to
operator.
11. Injury due to fall of suspended loads.

Page 4 of 10

1. All hand tools shall be kept in good


condition. They must be kept clean
and stored properly. Handles shall be
inspected frequently for damages and
shall remain tightly secured. Defective
tools shall be removed from service and
repaired or destroyed.
2. Personnel must be trained about the
proper usage and handling of tools.
3. All hand tools must be used only for the
intended purpose.
4. Provide scaffolding for every work above
1 meter in height. Scaffolding shall pass
SSA safety inspection prior to its use.
5. Personal protection equipment shall be
issued and used properly by personel.
6. Use ladder in ascending and
descending the scaffolding platform.
Ladders shall be extended 3 ft. and be
secured.
7. Arrange and pile rebar in order in a
manner that would give free access of
personnel in the worksite. Access shall

Safety Supervisor
Site Supervisor
Rebar Foreman
Rigger

MEG PROJECT
SN

DETAIL
ACTIVITY

EQUIPMENT / TOOLS

RISK INVOLVE

PREVENTIVE MEASURE
not be obstructed.
8. All protruding rebar ends shall be
protected. Bent bars should be arranged
where the ends are pointed to the ground
9. Crane must be inspected by client prior
to use.
10. Confirm load weights and crane
configuration.
11. Out riggers are to be fully extended,
in the down position and on pads when
on unstable ground. Level crane.
12.Qualified rigger to signal crane operator
using standard hand signals.
13. No one is permitted under loads
14. Tag lines( rope) are to be used to
control loads from swinging.
15. Maintain housekeeping for both
Site and Fabrication shop.

Formworks
Form removal

Manual hand tools:


hammer
handsaw
Power handtools:
Jigsaw
hand drill

Submitted by : Nasser S.Al-Hajri Corp.

1. Injury due to defective tools


2. Injury due to loose electical cable
3. Injury due to exposed wirings
4. Injury due to incompetence of worker
5. Injury due to wrong use of tool
6. Injury due to fall of personnel working
above 1 meter height
7. Injury due to fall of form
8. Tripping hazard
9. Injury due to scattered materials

Page 5 of 10

1. All hand tools shall be kept in good


condition. They must be kept clean
and stored properly. Handles shall be
inspected frequently for damages and
shall remain tightly secured. Defective
tools shall be removed from service and
repaired or destroyed.
2. All power equipment and their extension
cords shall be inspected prior to use
and color-coded monthly.
3. Cords shall be protected from damage.
Any exposed wiring shall be taped and
insulated adequately.
4. All guards, mechanical and protective devices
shall remain
devices shall remain attached and in
proper working condition.
5. Personnel must be trained about the
proper usage and handling of tools.

RESPONSIBLE
PERSON

Safety Supervisor
Site Supervisor
Rebar Foreman
Rigger

Safety Supervisor
Site Supervisor
Carpenter Foreman

MEG PROJECT
SN

DETAIL
ACTIVITY

EQUIPMENT / TOOLS

RISK INVOLVE

PREVENTIVE MEASURE

RESPONSIBLE
PERSON

6. All hand tools must be used only for the


intended purpose.
7. Provide scaffolding for every work above
1 meter in height. Scaffolding shall pass
SSA safety inspection prior to its use.
Use fall protection when above 6 ft. high.
8. Personal protection equipment shall be
issued and used properly by personel.
9. Forms shall be inspected to ensure adequate support and bracing is provided.
10. Use ladder in ascending and
descending the scaffolding platform.
Ladders shall be extended 3 ft. and be
secured.
11. Arrange forms in order in a manner
that would give free access of personnel
in the worksite. Access shall not be
obstructed. Keep all materials in order.
12. Housekeeping shall be done.
6

Concrete pouring

Concrete mixer truck


concrete pump truck
concrete vibrator engine

Submitted by : Nasser S.Al-Hajri Corp.

1.Injury due to fall of concrete truck and


pump truck into the excavation
4. Injury due to accidental hit by
back-tracking equipment
5. Injury due to incompetence of driver,
operator
6. Injury to personnel and damage to
vehicle due to traffic confusion
7. Breakdown of equipment
8. Injury due to negligence of driver
9. Injury due to fall of personnel working
above 1 meter height
10.Injury due to inhalation of fumes from
concrete vibrator
11. Injury due to ignorance of personnel
in operating the vibrator engine

Page 6 of 10

1. Provide barricades around the excavation site. Assign one personnel to


look out and give signal to operator/
driver of the edge of an excavation.
2. Concrete and pump trucks shall be
provided with back tracking alarm or
signal to alert personnel on site.
3. Only licensed and certified operator
and driver shall be allowed to handle and operate or drive.
4. Assign one personnel wearing an
orange reflectorized vest for visibility
to direct traffic among equipments
and other vehicle at excavation site.
5. Conduct regular check of equipment
to maintain good operating condition
and avoid breakdown during operation.
6. Concrete trucks should not be permit-

Safety Supervisor
Site Supervisor
Mason Foreman

MEG PROJECT
SN

DETAIL
ACTIVITY

EQUIPMENT / TOOLS

RISK INVOLVE

PREVENTIVE MEASURE

RESPONSIBLE
PERSON

ted to travel with chute gates attached.


7. Provide scaffolding for every work above
1 meter in height. Scaffolding shall pass
SSA safety inspection prior to its use.
8. Personal protection equipment shall be
issued and used properly by personel.
9. Use ladder in ascending and
descending the scaffolding platform.
Ladders shall be extended 3 ft. and be
secured.
10. Conduct regular chech up and maintain
good working condition of the concrete
vibrator engine.
11. Use personal protection equipment
such as dust/gas mask, helmet, gloves,
goggles,safety harness, earmuffs , etc.
12. Train the personnel on how to handle
and operate the equipment properly.
7

Application of concrete protection

Backfilling work

Paintbrush
Polyurethane coating mat'l.

Payloader

Submitted by : Nasser S.Al-Hajri Corp.

1. Health risk due to mishandling of coating material

1. Injury due to incompetence of driver,

Page 7 of 10

1. Only skilled and properly trained personnel shall be allowed to do the application of the material.
2. Materials shall be stored properly and
released to proper personnel for use.
3.The Material Safety Data Sheet shall be
displayed and available to the site where
the application is going on.
4. Proper cleaning and disposal of waste
and residue shall be followed as recommended by the manufacturer.
5.Application of material shall be as
manufacturer's recommendation.
6.Use proper personal protection equipment when using the material such as
gloves, dust/gas mask, goggles, etc.
1. Only licensed and certified operator

Safety Supervisor
Site Supervisor
Mason Foreman

Safety Supervisor

MEG PROJECT
SN

DETAIL
ACTIVITY

EQUIPMENT / TOOLS
Excavator
Dump truck
Bobcat
plate compactor
Water Tanker

Submitted by : Nasser S.Al-Hajri Corp.

RISK INVOLVE

PREVENTIVE MEASURE

operator
2. Injury to personnel and damage to
equipment due to traffic confusion
2.
3. Breakdown of equipment
4. Injury due to accidental hit by
back-tracking equipment
5. Injury due to incompetence of compac-3.
tor operator.
6. Injury due to fall of compactor when
bringing down and up the excavation. 4.

and driver shall be allowed to handle and operate or drive.


Assign one personnel wearing an
orange reflectorized vest for visibility
to direct traffic among equipments
and other vehicle at excavation site.
Conduct regular check of equipment
to maintain good operating condition
and avoid breakdown during operation.
Train the personnel on how to handle
and operate the equipment properly.
5. Use personal protection equipment
such as dust/gas mask, helmet, gloves,
goggles,safety harness, earmuffs , etc.
6. Small compacting equipment shall be
lifted in and out of excavations by means
of approved rigging techniques.

Page 8 of 10

RESPONSIBLE
PERSON
Site Supervisor
Earthwork Foreman

MEG PROJECT
SN
1
2

DETAIL ACTIVITY

EQUIPMENT / TOOLS

Building FinishesManual hand tools:


Scaffoldings
Hammer
Handsaw
Power handtools:
Tile Cutter
Hand Drill
Block Cutter
Riveter

RISK INVOLVE
1. Injury due to defective tools
2. Injury due to loose electical cable
3. Injury due to exposed wirings
4. Injury due to incompetence of
worker
5. Injury due to wrong use of tool
6. Injury due to fall of personnel
working
above 1 meter height
7. Injury due to fall of form
8. Tripping hazard
9. Injury due to scattered materials

PREVENTIVE MEASURE

RESPONSIBLE
PERSON

Safety Supervisor
1. All hand tools shall be kept in good
condition. They must be kept clean
Site Supervisor
and stored properly. Handles shall be
inspected frequently for damages and
shall remain tightly secured. Defective
tools shall be removed from service and
repaired or destroyed.
2. All power equipment and their extension
cords shall be inspected prior to use
and color-coded monthly.
3. Cords shall be protected from
damage.
Any exposed wiring shall be taped
and
insulated adequately.
4. All guards, mechanical and
protective
devices
shallattached
remain and in
devices shall
remain
proper working condition.
5. Personnel must be trained about the
proper usage and handling of tools.
6. All hand tools must be used only for
theintended purpose.
7. Provide scaffolding for every work
above
1 meter in height. Scaffolding shall pass
safety
inspection
prior
to its
use. 6 ft.
Use fall
protection
when
above
high.
8. Personal protection equipment shall
be issued and used properly by
personel.
9. Forms shall be inspected to ensure adequate support and bracing is provided.
10. Use ladder in ascending and

Page 9 of 10

MEG PROJECT
SN

DETAIL ACTIVITY

EQUIPMENT / TOOLS

RISK INVOLVE

PREVENTIVE MEASURE
descending the scaffolding platform.
Ladders shall be extended 3 ft. and be
secured.
11. Arrange forms in order in a manner
that would give free access of personnel
in the worksite. Access shall not be
obstructed. Keep all materials in order.
12. Housekeeping shall be done.

Page 10 of 10