Documente Academic
Documente Profesional
Documente Cultură
MARION COUNTY, AL
2014 STGE CONFERENCE MOBILE, AL
Spring 2012
October 2012
Repair Cross-Section
After 2nd Failure
Spring 2013
Summer 2013
Summer 2013
Topographic Map
3rd, 4th, & 5th Failures
Topographic Map
3rd, 4th, & 5th Failures
What Now??
To this point, we had been REACTING to a problem we
didnt know existed.
We assumed that the trigger for the failure was a weak layer
at the base of the first failure, focusing our analyses and
designs at this location
In actuality, the trigger was ABOVE the first failure
Isolated, perched groundwater flows were seeping out the face of
the slope, saturating the soil beneath it and reducing the shear
strength of the clays to the point of incipient failure.
Each additional cut into the slope we made only shortened the
drainage path of the flows, increasing seepage forces at the face of
the slope
What do we Need?
Stabilization at multiple, discrete levels of the slope
Stabilization system needed to include a robust drainage
system capable of draining perched groundwater from deep
within the slopeat unknown locations & elevations
With the wet season approaching, we needed a system
capable of rapid construction
Stay within the current ROW footprint
Contracting
Terminated contract with existing contractor
Coordinated with ALDOT 2nd Division personnel to produce
contract drawings specifying location, height, and batter of
required soil nail walls, along with surface drainage features
and grading plan
ALDOT approved soil nail contractors were invited to bid on
the project
N
E
W
S
Exit 16
Hamilton
Guin
W
S
I-22
Westbound
Lanes
N
E
Exit 16
Hamilton
Guin
I-22
Westbound
Lanes
Project Award
Design and Construction Submittals
Mobilization
Site Office and Site Yard
Erosion Control and Construction Stormwater Management
Excavation in Five (5) Foot Lifts
Soil Nailing, Horizontal Drains, Drainage Composite, Steel Mesh,
Steel Plates, Hex Nuts and Shotcrete
Underdrains and Surface Water Concrete Drainage Swales
Top Soil, Mulching and Seeding
Rip-Rap Lined Ditches
Project Finish
Project Engineer:
Vasco Duke, PE
Project Manager:
Marty Flaherty
Soil
Conditions
7
Moisture
Sensitive
Silty Clay
Sand Seams
with Ground
Water
Construction
Office and Site
Yard
11-08-13
Excavation
and Grading
Started
11-08-13
Excavation
and Grading
Started
First Lift Drilled & Grouted, Drain Strips and Steel Mesh
Second Lift Drilled & Grouted, Drain Strips and Steel Mesh
Construction
Office and Site
Yard
Lower Wall
Haul Road
Stormwater
Fill Area
View of Site From Between the Upper and Lower Tier Facing East
Upper Wall
Concrete Flume
Lower Wall
Excavation
Underdrains
Underdrains
Once the Site Thawed Out Seed Mulch and Rip Rap
Were Installed to Finish The Project
Thank You !
Questions !