Sunteți pe pagina 1din 7

R07

Code No: 07A51401

Set No. 2

III B.Tech I Semester Supplementary Examinations,June 2010


INDUSTRIAL MANAGEMENT
Mechatronics
Time: 3 hours
Max Marks: 80
Answer any FIVE Questions
All Questions carry equal marks
?????
1. Surface roughness measurement are taken for five samples of turned pieces. On
each piece 5 measurements have been taken along the length. These pieces have
been selected randomly from a lot of 60. The observations have been shown in
the following table. Compute the control limits for S and R charts and draw the
observation from these trial control limits
[16]
Sample No
1
2
3
4
5

1
10.14
10.16
10.16
10.19
10.14

2
10.17
10.18
10.15
10.16
10.18

Five measurements of samples(x)


3
10.16
10.15
10.16
10.15
10.10

4
10.18
10.13
10.04
10.13
10.15

5
10.15
10.18
10.18
10.14
10.03

2. Write the differences between stopwatch time study and work sampling.

[16]

3. What is Human Resource Management? Compare it with Personal Management.


[16]
4. The following table gives details about the various activities of a project
Activity Optimistic time
1-2
10
2-3
6
2-4
5
2-5
1
3-6
3
4-6
4
5-7
1
6-7
3
7-8
9
7-9
3
8-9
0

Times(days)
Most likely time
11
10
8
5
7
9
2
7
12
5
0

Pessimistic time
12
14
11
9
5
14
3
11
15
7
0

(a) Draw the network


(b) Find the critical path and its expected project duration
(c) The probability that the project will be completed within 50 days

[16]

Code No: 07A51401

R07

Set No. 2

5. The following information is about a group of items.. Classify the items as A, B


and C
Item no
501
502
503
504
505
506
507
8
9
10
Annual use 30000 280000 3000 110000 4000 220000 15000 80000 60000 8000
Price
10
15
10
5
5
10
5
5
15
10
[16]
6. Distinguish between:
(a) Management and administration
(b) Science and Art

[16]

7. (a) What is boundaryless organization? Give its chart, advantages and disadvantages.
(b) Explain salient features of inverted pyramid structure.

[16]

8. Consider 5 industrial sectors in India, identify the existing locations of these industries in India and give separate reasons for the location of these industries in those
regions.
[16]
?????

Code No: 07A51401

R07

Set No. 4

III B.Tech I Semester Supplementary Examinations,June 2010


INDUSTRIAL MANAGEMENT
Mechatronics
Time: 3 hours
Max Marks: 80
Answer any FIVE Questions
All Questions carry equal marks
?????
1. Define Time study. Explain steps in time study for determining standard time.
[16]
2. Explain salient features of line organization. What are its advantages and limitations.
[16]
3. A company requires 10000 units of an item per annum. The cost of ordering is
rs.100 per order. The inventory carrying cost is 20%. The unit price of the item
is Rs.10. Calculate a) the economic order quantity b) Optimal total annual cost c)
time between the orders.
[16]
4. Explain the relationship between Marketing Mix and Marketing strategy

[16]

5. A network consists of following activities with indicated duration in days


Activity Duration in days
10-20
15
10-30
20
10-60
5
20-50
15
30-50
10
30-40
15
40-60
16
50-60
12
40-50
5
(a) Draw the network diagram
(b) Calculate project duration and identify critical path
[6+10]
6. Explain the nature and significance of management.

[16]

7. A number of samples are selected and their average values and ranges are tabulated
below;

Code No: 07A51401


Sample No
A
B
C
D
E
F
G
H
I
J

mean X
8.0
8.5
8.0
9.0
10.0
7.0
8.0
8.5
9.0
8.0

R07

Set No. 4

Range (R)
2.5
2.0
3.0
2.5
3.5
2.0
3.0
3.0
2.5
3.0

Draw the X chart and the R-chart. If the tolerance limit specified for mean dimension is given as 2.0, calculate the process capability figure Cp and process capability
factor Cpk
[16]
8. Suppose you like to start cement industry or process industry then explain variousfactors you would consider for identifying location for that industry.
[16]
?????

R07

Code No: 07A51401

Set No. 1

III B.Tech I Semester Supplementary Examinations,June 2010


INDUSTRIAL MANAGEMENT
Mechatronics
Time: 3 hours
Max Marks: 80
Answer any FIVE Questions
All Questions carry equal marks
?????
1. (a) What is Standard Time? Describe the procedure to calculate Standard Time
from the observed time obtained by time study.
(b) What are advantages and limitations of stopwatch time study.

[8+8]

2. Explain various components of job specification sheet

[16]

3. The following data shows the values of sample mean S and the range R for 10
samples of size 5 each. Calculate the values for central line and control limits for
mean chart and range chart and determine whether the process is under control.

Sample No
S
R

1
2
3
4
5
6
7
8
9
10
11.2 11.8 10.8 11.6 11.0 9.6 10.4 9.6 10.6 10.0
7
4
8
5
7
4
8
4
7
9

[16]

4. An engine manufacturing company stocks the items as shown in the following table
in its stores. The unit price, annual consumption quantity in terms of units/year
are also given in the same table. Classify the items into A, B, and C categories.
Component Code
C001
C002
C003
C004
C005
C006
C007
C008
C009

Description
Price /unit
Connecting rod
500
Crank case
4000
Cylinder
2000
Cylinder head
3000
Crank shaft
4000
Cam
500
Nozzle
500
Valve set
1000
Fuel injection pump
1500

Unit/year
600
600
600
600
600
1200
600
1200
600

[16]

5. Define direction. Explain its elements and features.

[16]

6. Draw the network of the project with following situation:


P is prerequisite of S.
Q is prerequisite of S and T
R is prerequisite of T

S and T are prerequisites of U.

[16]

7. (a) What location factors make small cities and towns attractive to companies.
5

Code No: 07A51401

R07

Set No. 1

(b) Select a major manufacturing facility in your community or immediate Geographic area and identify the factors that make it a good or poor site in your
opinion.
[8+8]
8. Explain the following in detail
(a) Effective delegation
(b) Communication
(c) Dividing and Grouping work

[16]
?????

Code No: 07A51401

R07

Set No. 3

III B.Tech I Semester Supplementary Examinations,June 2010


INDUSTRIAL MANAGEMENT
Mechatronics
Time: 3 hours
Max Marks: 80
Answer any FIVE Questions
All Questions carry equal marks
?????
1. (a) Explain the procedure involved in PERT analysis for a network to determine
critical path and the probability of completing the project by due date .
(b) Compare PERT and CPM

[8+8]

2. (a) What is meant by term management? Explain its importance.


(b) Define Management. Explain its nature and significance.
3. Explain various considerations in a plant location problem

[8+8]
[16]

4. (a) How do you classify inventories into A class, B class and C class items.
(b) Mention the control procedures to be exercised on A class, B class and C
class items
[8+8]
5. Define work sampling. Explain the procedure of work sampling for calculating
standard time.
[4+12]

6. List out various methods of job evaluation. Explain any two of them in detail [16]
7. What are the causes of conflict between line and staff? What can be done to
develop line and staff members into integrated team
[16]
8. (a) Explain the sensitivity of p charts
(b) The Western Jeans company produces denim jeans. The company wants to
establish p-chart to monitor the production process and maintain high quality.
The company believes that approximately 99.74% are accepted.

The company has taken 20 samples, each containing 100 pairs of jeans and inspected
them for defects, the results of which are as follows:
Sample number 1 2 3 4 5 6
No.0f defectives 6 0 4 10 6 4

7 8 9 10
12 10 8 10

Sample number 11 12 13 14 15 16
No.0f defectives 12 10 14 8 6 16

17 18 19 20
12 14 20 18

Construct a p -chart and determine when the production might be out of control.