Documente Academic
Documente Profesional
Documente Cultură
Introduction
Why are project records important?
Record keeping under the standard form contracts
Contractual requirements for keeping records
FIDIC
JCT SBC
NEC
Establishing claims
Common deficiencies
Practical guidance
#olswangconstruction
www.constructiveblog.com
#olswangconstruction
www.constructiveblog.com
#olswangconstruction
www.constructiveblog.com
#olswangconstruction
www.constructiveblog.com
#olswangconstruction
www.constructiveblog.com
#olswangconstruction
www.constructiveblog.com
#olswangconstruction
www.constructiveblog.com
#olswangconstruction
www.constructiveblog.com
#olswangconstruction
www.constructiveblog.com
Establishing claims
The claimant will need to show:
Contractual pre-conditions
The other party was contractually responsible for the event (liability)
Loss was actually incurred (damage)
Such loss was caused by the event for which the other party was responsible
(causation)
#olswangconstruction
www.constructiveblog.com
Establishing claims
John Doyle v Laing (2004)
For a loss and expense claim to succeed, a claimant must aver and prove
three matters: first, the existence of one or more events for which the
defendant is responsible; secondly, the existence of loss and expense
suffered by the claimant; and thirdly, a causal link between the event or
events and the loss and expense."
#olswangconstruction
www.constructiveblog.com
Establishing claims
To establish entitlement as a result of a delay will require:
Documents
Witnesses of fact
Delay analysis
#olswangconstruction
www.constructiveblog.com
Establishing claims
Keating (9th Ed):
Delay analysis should be based as far as possible on contemporaneous
evidence of what actually happened on site during the progress of the
works [it is] only as reliable as the data upon which it is based. It
should be emphasized that such analysis, of course, can never be a
substitute for relevant and convincing factual evidence.
#olswangconstruction
www.constructiveblog.com
Establishing claims
Great Eastern Hotel Company Ltd v John Laing (2005)
The delay analysis took "no account of actual events which occurred on
the Project and gave rise to a hypothetical answer".
#olswangconstruction
www.constructiveblog.com
Establishing claims
Cleveland Bridge UK Ltd v SeverfieldRowen Structures Ltd (2012):
it is necessary to show that the claiming party was actually delayed by the
factors of which it complains; it simply does not follow as a matter of logic,
let alone practice, on a construction or fabrication project, that, simply
because a variation is issued or that information is provided later than
programmed or that free issue materials are issued later in the programme
than envisaged originally, the claimant is delayed.
#olswangconstruction
www.constructiveblog.com
Establishing claims
In summary:
Claims must be based on reality
Positive evidence of causation
Tribunals are essentially concerned with practical issues, not theoretical
arguments about delay analysis
#olswangconstruction
www.constructiveblog.com
#olswangconstruction
www.constructiveblog.com
#olswangconstruction
www.constructiveblog.com
Practical guidance
Contemporaneous documents
Contractual requirements
Robust procedures
Training
Auditing
Types of documents:
Programmes
Work records
Records that explain delay
Costs records
#olswangconstruction
www.constructiveblog.com