ID

Task Name

Disouq Development Project

Duration

General Milestones

Start

st
e

629 days

Tue 3/29/11

629 days

Tue 3/29/11

First Gas Phase "A"

0 days

Sun 3/31/13

GAS / DLA Signature

0 days

Mon 5/23/11

JV Formation

0 days

Wed 6/8/11

JV Preparation Work

15 days

Mon 5/23/11

Start FEED

0 days

Mon 7/18/11

FEED Contractor - Basis of Design Letter of acceptance

0 days

Sun 8/21/11

Complete FEED

0 days

Tue 11/8/11

HAZOP Report

0 days

Sun 10/30/11

10

Facilities Detail Engineering Scope of work

0 days

Sun 10/30/11

11

Start Facilities Detail Engineering

0 days

Mon 2/13/12

12

Complete Facilities Detail Engineering

0 days

Wed 6/6/12

13

ESIA - (Environmental and Social Impact Assessment )

0 days

Wed 5/2/12

0 days

Tue 3/29/11

399 days

Mon 8/1/11

14
15

Construction Permit
Drilling Schedule

16

NWK 1-2 Phase (A)

39 days

Mon 8/1/11

17

NSG 1-2 Phase (A)

44 days

Mon 2/27/12

18

SSG 1-2 Phase (A)

32 days

Wed 8/15/12

19

NWSG 1-2 Phase (A)

32 days

Tue 10/2/12

173 days

Sat 10/15/11

173 days

Sat 10/15/11

20
21

ESIA - Environmental & Social Impact Assessment Study


ESIA - (ESIA - (Environmental and Social Impact Assessment)

22

prepare ESIA study

76 days

Sat 10/15/11

27

Preparaton of EIA study

22 days

Wed 1/11/12

28

Translation of EIA study

12 days

Mon 2/6/12

29

ESIA study - quality check by EGAS

15 days

Mon 2/20/12

30

Supreme council antiquities

12 days

Sun 3/25/12

31

EGAS & (EEAA) Egyptian Environmental Affairs Agency approval

22 days

Sun 4/8/12

226 days

Tue 7/5/11

32

Permitting & Agreements

Project: Disouq Development Project


Date: Thu 9/29/11

2nd 3rd 4th 1st


u u u e o ea e

Task

Rolled Up Task

External Tasks

Critical Task

Rolled Up Critical Task

Project Summary

Progress

Rolled Up Milestone

Group By Summary

Milestone

Rolled Up Progress

Deadline

Summary

Split
Page 1

2nd 3rd 4th 1st


u u u e o ea e

ID
33

Task Name

Duration

Permits (Central Plant + Well Sites)

Start

st
e

226 days

Tue 7/5/11

34

RWE Dea send an official letter to EGAS incl. maps, technical description for get a global construction permit
13 days

Tue 7/5/11

35

RWE Dea send an official letterKafr Elsheikh Agriculture Administration incl. maps, technical description for14
getdays
a global construction
Tue 7/5/11
permit

36

EGAS reviewed and distribute the letter

22 days

Wed 7/20/11

37

Ministry of Agriculture approval

50 days

Thu 7/21/11

38

governorates, local people assembly approvals

10 days

Sun 9/18/11

39

Petroleum Ministry approval to Minisitry of Agriculture

50 days

Sun 9/18/11

40

EGAS issued governorates letter

22 days

Tue 11/15/11

41

Ministry of Defense Global approval

90 days

Sun 12/11/11

42

other Ministry (enviroment.antiquities)

90 days

Sun 12/11/11

43

governorates approvals Irrigation, roads, water, drainage

30 days

Sun 9/18/11

44

compensation committee evaluation and payment

22 days

Thu 9/29/11

45

Construction Permit

46

Local Consultation Sessions

47
48

Local Consultation Sessions


FEED Study

0 days

Sat 3/24/12

60 days

Wed 1/11/12

60 days

Wed 1/11/12

193 days

Tue 3/29/11

49

Finalize Disouq Preferred Bidders

1 day

Tue 3/29/11

50

HH Approval of Strategic Demand Form

3 days

Mon 4/4/11

51

EGAS Review of Bidders List

3 days

Thu 4/7/11

52

EGAS Approval of Bidders

3 days

Mon 4/11/11

53

FEED Tender Period

48 days

Thu 4/14/11

54

Technical Evaluation

14 days

Thu 6/9/11

55

RWE Approval of Technical Recommendation

3 days

Sun 6/26/11

56

EGAS Approval of Technical Recommendation

3 days

Wed 6/29/11

57

Commercial Evaluation

7 days

Sun 7/3/11

58

RWE Treasury Creditworthiness Check

21 days

Thu 6/9/11

59

RWE Approval of Commercial Recommendation

3 days

Mon 7/11/11

Project: Disouq Development Project


Date: Thu 9/29/11

2nd 3rd 4th 1st


u u u e o ea e

Task

Rolled Up Task

External Tasks

Critical Task

Rolled Up Critical Task

Project Summary

Progress

Rolled Up Milestone

Group By Summary

Milestone

Rolled Up Progress

Deadline

Summary

Split
Page 2

2nd 3rd 4th 1st


u u u e o ea e

ID
60

Task Name

Duration

EGAS Approval of Commercial Recommendation

61

Award

62

Kickoff Meeting (Basis of Design Letter of acceptance)

63
64

Start

st
e

3 days

Thu 7/14/11

1 day

Mon 7/18/11

2 days

Mon 8/15/11

Work of WBS

64 days

Wed 8/17/11

Stage 1

4 days

Wed 8/17/11

65

FEED Execution Plan / FEED manual

4 days

Wed 8/17/11

66

Basis of Design Review

4 days

Wed 8/17/11

67

BOD Acceptance Letter

0 days

Sun 8/21/11

68
69

Long Lead Items, skid-mounted equipment and potential suppliers: identification


Stage 2

70

Basic CAPEX / OPEX Estimate 20%

71

HAZID / ENVID Report incl. Identification and Quantification List

72
73

Basic Plot Plan(s) for all sites incl. access road(s)


Stage 3

4 days

Wed 8/17/11

60 days

Mon 8/22/11

18 days

Mon 8/22/11

7 days

Sun 10/23/11

6 days

Mon 9/5/11

30 days

Mon 9/26/11

74

LLI & MTO and potential suppliers procurement preparation (datasheets, MTOs)

6 days

Mon 9/26/11

75

Cause & Effect Diagram for the entire field

6 days

Mon 9/26/11

76

Operation Control Philosophy

5 days

Tue 10/4/11

77

Building permissions for all civil constructions

0 days

Sun 10/9/11

78

Update all P&IDs and U%IDs for all sites processes

79

Scope of Work for Detailed Design

80

Stage 4

81
82

Thu 10/13/11

15 days

Thu 10/13/11

HAZOP Report

15 days

Thu 10/13/11

42 days

Mon 9/12/11

7 days

Tue 11/1/11

84

RWE FEED Peer Review

87

FEED Close out Report


Detailed Design
Finalize Disouq Preferred Bidders

Project: Disouq Development Project


Date: Thu 9/29/11

Wed 10/5/11

15 days

Scope of work of site preparation and accomodation construction

86

Sun 10/23/11

Packages Specification for Procurement

83

85

7 days
22 days

0 days

Tue 11/8/11

188 days

Tue 11/1/11

1 day

Tue 11/1/11

2nd 3rd 4th 1st


u u u e o ea e

Task

Rolled Up Task

External Tasks

Critical Task

Rolled Up Critical Task

Project Summary

Progress

Rolled Up Milestone

Group By Summary

Milestone

Rolled Up Progress

Deadline

Summary

Split
Page 3

2nd 3rd 4th 1st


u u u e o ea e

ID

Task Name

Duration

Start

st
e

88

EGAS Review of Bid List

3 days

89

EGAS Approval of Bidders

0 days

Sat 11/5/11

90

HH Approval of Strategic Demand Form

3 days

Sun 11/6/11

91

ITT for Detail Design

5 days

Thu 11/3/11

92

Detail Engineering Tender Period

35 days

Wed 11/9/11

93

Technical Evaluation

28 days

Tue 12/20/11

94

RWE Approval of Technical Recommendation

3 days

Sun 1/22/12

95

EGAS Approval of Technical Recommendation

3 days

Wed 1/25/12

96

Commercial Evaluation

7 days

Sun 1/29/12

97

RWE Approval of Commercial Recommendation

3 days

Mon 2/6/12

98

EGAS Approval of Commercial Recommendation

3 days

Thu 2/9/12

99

Award

1 day

Mon 2/13/12

100

Kickoff Meeting (Start work)

101

WBS Work

102

- Civil Engineering

Wed 11/2/11

1 day

Tue 2/14/12

95 days

Wed 2/15/12

81 days

Wed 2/15/12

103

Review & Verify FEED Civil Deliverables

23 days

Wed 2/15/12

104

Detailed Civil Drawings, Spacifications & Datasheets (IFA, IFD, IFC & Reviewal Periods)

40 days

Tue 3/13/12

105

Start Issuing AFC Drawings & IFF Specification & Datasheets

18 days

Sun 4/29/12

106
107

Finalizing MTOs (30, 60, 85 & & 100%)


- Process Engineering

30 days

Sun 4/15/12

65 days

Wed 2/15/12

108

Review & Verify FEED Process Deliverables

15 days

Wed 2/15/12

109

Detailed Process Drawings, Spacifications & Datasheets (IFA, IFD, IFC & Reviewal Periods)

40 days

Sun 3/4/12

110
111

Start Issuing AFC Drawings & IFF Specification & Datasheets


- Mechanical Engineering

10 days

Thu 4/19/12

65 days

Wed 2/15/12

112

Review & Verify FEED Mechanical Deliverables

15 days

Wed 2/15/12

113

Detailed Mechanical Drawings, Spacifications & Datasheets (IFA, IFD, IFC & Reviewal Periods)

40 days

Sun 3/4/12

114
115

Start Issuing AFC Drawings & IFF Specification & Datasheets


- Piping Engineering

116

Project: Disouq Development Project


Date: Thu 9/29/11

Review & Verify FEED Piping Deliverables

2nd 3rd 4th 1st


u u u e o ea e

10 days

Thu 4/19/12

95 days

Wed 2/15/12

15 days

Wed 2/15/12

Task

Rolled Up Task

External Tasks

Critical Task

Rolled Up Critical Task

Project Summary

Progress

Rolled Up Milestone

Group By Summary

Milestone

Rolled Up Progress

Deadline

Summary

Split
Page 4

2nd 3rd 4th 1st


u u u e o ea e

ID

Task Name

Duration

Start

st
e

117

Detailed Piping Design Gas,..)

45 days

Sun 3/4/12

118

Start issuing AFC drawings

10 days

Wed 4/25/12

119

Detailed Isometric Drawings (IFA, IFD, IFC & Reviewals Periods)

30 days

Tue 5/1/12

120

3D Model

20 days

Wed 4/25/12

121

Finalizing MTOs (30, 60, 85 & & 100%)

30 days

Tue 5/1/12

122

65 days

Wed 2/15/12

123

Review & Verify FEED Electrical Deliverables

15 days

Wed 2/15/12

124

Detailed Electrical Design & Drawings

40 days

Sun 3/4/12

125

Start issuing AFC drawings

10 days

Thu 4/19/12

126

Finalizing MTOs (30, 60, 85 & & 100%)

30 days

Tue 3/27/12

127

- Electrical Engineering

65 days

Wed 2/15/12

128

- Instrument Engineering
Review & Verify FEED Instrument Deliverables

15 days

Wed 2/15/12

129

Detailed Instrument Design & Drawings

40 days

Sun 3/4/12

130

Start issuing AFC drawings

10 days

Thu 4/19/12

131
132

Finalizing MTOs (30, 60, 85 & & 100%)


- Telecom Engineering

30 days

Tue 3/27/12

65 days

Wed 2/15/12

133

Review & Verify FEED Instrument Deliverables

15 days

Wed 2/15/12

134

Detailed Instrument Design & Drawings

40 days

Sun 3/4/12

135

Start issuing AFC drawings

10 days

Thu 4/19/12

136

Finalizing MTOs (30, 60, 85 & & 100%)

30 days

Tue 3/27/12

137

- Safety Equipments MRQ

138
139

50 days

Sun 3/4/12

Issue MRP for Safety Equipments

20 days

Sun 3/4/12

Issue MRQ for Safety Equipments

30 days

Tue 3/27/12

30 days

Tue 5/1/12

140

HAZOP Report Preparation

141

HAZOP REPORT

1 day

Tue 6/5/12

142

Facilities Detail Engineering Close out Report

1 day

Wed 6/6/12

143

Delivery of Materials

351 days

Mon 10/31/11

144

Packages

351 days

Mon 10/31/11

281 days

Mon 10/31/11

145

Slug Catcher Skid

Project: Disouq Development Project


Date: Thu 9/29/11

2nd 3rd 4th 1st


u u u e o ea e

Task

Rolled Up Task

External Tasks

Critical Task

Rolled Up Critical Task

Project Summary

Progress

Rolled Up Milestone

Group By Summary

Milestone

Rolled Up Progress

Deadline

Summary

Split
Page 5

2nd 3rd 4th 1st


u u u e o ea e

ID

Task Name

Duration

Start

st
e

146

ITT

10 days

147

Bid Phase

25 days

Sat 11/12/11

148

Technical & Commercial Evaluation and Decision

35 days

Sun 12/11/11

149

Lead time

168 days

Sat 1/21/12

150

Transport

40 days

Sat 8/4/12

151
152

Ready for Construction


JT/LTS Skid

Mon 10/31/11

3 days

Wed 9/19/12

298 days

Mon 10/31/11
Mon 10/31/11

153

ITT

10 days

154

Bid Phase

35 days

Sat 11/12/11

155

Technical & Commercial Evaluation and Decision

42 days

Thu 12/22/11

156

Lead time

168 days

Thu 2/9/12

157

Transport

40 days

Thu 8/23/12

158
159

Ready for Construction


HIPPS System / Valves

3 days

Tue 10/9/12

351 days

Mon 10/31/11

160

ITT

10 days

Mon 10/31/11

161

Bid Phase

23 days

Sat 11/12/11

162

Technical & Commercial Evaluation and Decision

35 days

Thu 12/8/11

163

Lead time

240 days

Wed 1/18/12

164

Transport

40 days

Wed 10/24/12

165

Ready for Construction

3 days

Mon 12/10/12

166

Condensate Shipping Pumps

303 days

Mon 10/31/11

167

ITT

10 days

Mon 10/31/11

168

Bid Phase

23 days

Sat 11/12/11

169

Technical & Commercial Evaluation and Decision

35 days

Thu 12/8/11

170

Lead time

192 days

Wed 1/18/12

171

Transport

40 days

Wed 8/29/12

172
173

Ready for Construction


Wellhead adjustable chokes

174

Project: Disouq Development Project


Date: Thu 9/29/11

ITT

2nd 3rd 4th 1st


u u u e o ea e

3 days

Mon 10/15/12

297 days

Mon 10/31/11

10 days

Mon 10/31/11

Task

Rolled Up Task

External Tasks

Critical Task

Rolled Up Critical Task

Project Summary

Progress

Rolled Up Milestone

Group By Summary

Milestone

Rolled Up Progress

Deadline

Summary

Split
Page 6

2nd 3rd 4th 1st


u u u e o ea e

ID

Task Name

Duration

Start

st
e

175

Bid Phase

176

Technical & Commercial Evaluation and Decision

35 days

Thu 12/1/11

177

Lead time

192 days

Wed 1/11/12

178

Transport

40 days

Wed 8/22/12

179

Ready for Construction

3 days

Mon 10/8/12

180

17 days

Sat 11/12/11

254 days

Mon 10/31/11

181

ITT

10 days

Mon 10/31/11

182

Bid Phase

35 days

Sat 11/12/11

183

Technical & Commercial Evaluation and Decision

42 days

Thu 12/22/11

184

Lead time

144 days

Thu 2/9/12

185

Transport

20 days

Thu 7/26/12

186

Ready for Construction

3 days

Sun 8/19/12

187

Produced Water Skid

Produced Water Tank

239 days

Mon 10/31/11

188

ITT

10 days

Mon 10/31/11

189

Bid Phase

35 days

Sat 11/12/11

190

Technical & Commercial Evaluation and Decision

42 days

Thu 12/22/11

191

Lead time

144 days

Thu 2/9/12

192

Transport

5 days

Thu 7/26/12

193
194

Ready for Construction


Gas Compression Skid

3 days

Wed 8/1/12

321 days

Mon 10/31/11

195

ITT

10 days

Mon 10/31/11

196

Bid Phase

31 days

Sat 11/12/11

197

Technical & Commercial Evaluation and Decision

45 days

Sun 12/18/11

198

Lead time

192 days

Wed 2/8/12

199

Transport

40 days

Wed 9/19/12

200

Ready for Construction

3 days

Mon 11/5/12

201

Fuel Gas Skid

265 days

Mon 10/31/11

202

ITT

10 days

Mon 10/31/11

203

Bid Phase

33 days

Sat 11/12/11

Project: Disouq Development Project


Date: Thu 9/29/11

2nd 3rd 4th 1st


u u u e o ea e

Task

Rolled Up Task

External Tasks

Critical Task

Rolled Up Critical Task

Project Summary

Progress

Rolled Up Milestone

Group By Summary

Milestone

Rolled Up Progress

Deadline

Summary

Split
Page 7

2nd 3rd 4th 1st


u u u e o ea e

ID

Task Name

Duration

204

Technical & Commercial Evaluation and Decision

205
206
207
208

Start

st
e

35 days

Tue 12/20/11

Lead time

144 days

Mon 1/30/12

Transport

40 days

Mon 7/16/12

Ready for Construction


MEG Regen. Unit

3 days

Sat 9/1/12

326 days

Mon 10/31/11

209

ITT

10 days

Mon 10/31/11

210

Bid Phase

36 days

Sat 11/12/11

211

Technical & Commercial Evaluation and Decision

45 days

Sat 12/24/11

212

Lead time

192 days

Tue 2/14/12

213

Transport

40 days

Tue 9/25/12

214

Ready for Construction

215

Glycol Tank & Condensate Tanks

3 days

Sun 11/11/12

216 days

Mon 10/31/11

216

ITT

10 days

Mon 10/31/11

217

Bid Phase

28 days

Sat 11/12/11

218

Technical & Commercial Evaluation and Decision

28 days

Wed 12/14/11

219

Lead time

144 days

Mon 1/16/12

220

Transport

3 days

Mon 7/2/12

221

Ready for Construction

3 days

Thu 7/5/12

222

Condensate Treatment Unit

280 days

Mon 10/31/11

223

ITT

20 days

Mon 10/31/11

224

Bid Phase

28 days

Wed 11/23/11

225

Technical & Commercial Evaluation and Decision

45 days

Mon 12/26/11

226

Lead time

144 days

Thu 2/16/12

227

Transport

40 days

Thu 8/2/12

228
229

Ready for Construction


Export Gas Metering

3 days

Tue 9/18/12

254 days

Mon 10/31/11

230

ITT

10 days

Mon 10/31/11

231

Bid Phase

35 days

Sat 11/12/11

232

Technical & Commercial Evaluation and Decision

42 days

Thu 12/22/11

Project: Disouq Development Project


Date: Thu 9/29/11

2nd 3rd 4th 1st


u u u e o ea e

Task

Rolled Up Task

External Tasks

Critical Task

Rolled Up Critical Task

Project Summary

Progress

Rolled Up Milestone

Group By Summary

Milestone

Rolled Up Progress

Deadline

Summary

Split
Page 8

2nd 3rd 4th 1st


u u u e o ea e

ID

Task Name

Duration

Start

st
e

233

Lead time

144 days

234

Transport

20 days

Thu 7/26/12

235

Ready for Construction

3 days

Sun 8/19/12

236

Condensate Gas Metering

Thu 2/9/12

254 days

Mon 10/31/11

237

ITT

10 days

Mon 10/31/11

238

Bid Phase

35 days

Sat 11/12/11

239

Technical & Commercial Evaluation and Decision

42 days

Thu 12/22/11

240

Lead time

144 days

Thu 2/9/12

241

Transport

20 days

Thu 7/26/12

242

Ready for Construction

3 days

Sun 8/19/12

243

Flare System

272 days

Mon 10/31/11

244

ITT

10 days

Mon 10/31/11

245

Bid Phase

26 days

Sat 11/12/11

246

Technical & Commercial Evaluation and Decision

45 days

Mon 12/12/11

247

Lead time

168 days

Thu 2/2/12

248

Transport

20 days

Thu 8/16/12

249
250

Ready for Construction


Gas Engine Gen Set

3 days

Sun 9/9/12

344 days

Mon 10/31/11

251

ITT

10 days

Mon 10/31/11

252

Bid Phase

36 days

Sat 11/12/11

253

Technical & Commercial Evaluation and Decision

40 days

Sat 12/24/11

254

Lead time

235 days

Wed 2/8/12

255

Transport

20 days

Thu 11/8/12

256

Ready for Construction

3 days

Sun 12/2/12

257

Diesel Em Gen Set

265 days

Mon 10/31/11

258

ITT

20 days

Mon 10/31/11

259

Bid Phase

36 days

Wed 11/23/11

260

Technical & Commercial Evaluation and Decision

42 days

Wed 1/4/12

261

Lead time

144 days

Wed 2/22/12

Project: Disouq Development Project


Date: Thu 9/29/11

2nd 3rd 4th 1st


u u u e o ea e

Task

Rolled Up Task

External Tasks

Critical Task

Rolled Up Critical Task

Project Summary

Progress

Rolled Up Milestone

Group By Summary

Milestone

Rolled Up Progress

Deadline

Summary

Split
Page 9

2nd 3rd 4th 1st


u u u e o ea e

ID

Task Name

Duration

262

Transport

263
264

20 days

Ready for Construction


Instrument Air Skid

Start

st
e

Wed 8/8/12

3 days

Sat 9/1/12

331 days

Mon 10/31/11

265

ITT

10 days

Mon 10/31/11

266

Bid Phase

23 days

Sat 11/12/11

267

Technical & Commercial Evaluation and Decision

35 days

Thu 12/8/11

268

Lead time

240 days

Wed 1/18/12

269

Transport

20 days

Wed 10/24/12

270
271

Ready for Construction


Fire Water Pump (Diesel & Electrical)

3 days

Sat 11/17/12

249 days

Mon 10/31/11

272

ITT

20 days

Mon 10/31/11

273

Bid Phase

35 days

Wed 11/23/11

274

Technical & Commercial Evaluation and Decision

42 days

Tue 1/3/12

275

Lead time

144 days

Tue 2/21/12

276

Transport

5 days

Tue 8/7/12

277

Ready for Construction

3 days

Mon 8/13/12

278

Fire Water Tank

233 days

Mon 10/31/11

279

ITT

10 days

Mon 10/31/11

280

Bid Phase

28 days

Sat 11/12/11

281

Technical & Commercial Evaluation and Decision

28 days

Wed 12/14/11

282

Lead time

144 days

Mon 1/16/12

283

Transport

20 days

Mon 7/2/12

284
285

Ready for Construction


Open Drain Pits

3 days

Wed 7/25/12

218 days

Mon 10/31/11

286

ITT

10 days

Mon 10/31/11

287

Bid Phase

28 days

Sat 11/12/11

288

Technical & Commercial Evaluation and Decision

28 days

Wed 12/14/11

289

Lead time

144 days

Mon 1/16/12

290

Transport

5 days

Mon 7/2/12

Project: Disouq Development Project


Date: Thu 9/29/11

2nd 3rd 4th 1st


u u u e o ea e

Task

Rolled Up Task

External Tasks

Critical Task

Rolled Up Critical Task

Project Summary

Progress

Rolled Up Milestone

Group By Summary

Milestone

Rolled Up Progress

Deadline

Summary

Split
Page 10

2nd 3rd 4th 1st


u u u e o ea e

ID

Task Name

Duration

291

Ready for Construction

Start

st
e

3 days

Sun 7/8/12

292

Nitrogen Skid

291 days

Mon 10/31/11

293

ITT

10 days

Mon 10/31/11

294

Bid Phase

26 days

Sat 11/12/11

295

Technical & Commercial Evaluation and Decision

40 days

Mon 12/12/11

296

Lead time

192 days

Sat 1/28/12

297

Transport

20 days

Sat 9/8/12

298

Ready for Construction

3 days

Mon 10/1/12

299

Control System

294 days

Mon 10/31/11

300

ITT

10 days

Mon 10/31/11

301

Bid Phase

29 days

Sat 11/12/11

302

Technical & Commercial Evaluation and Decision

40 days

Thu 12/15/11

303

Lead time

192 days

Tue 1/31/12

304

Transport

20 days

Tue 9/11/12

305
306

Ready for Construction


Bulk Material

3 days

Thu 10/4/12

70 days

Tue 5/1/12

307

Bulk Piping, Fittings & Valves

40 days

Tue 6/5/12

308

Safety Equipment

40 days

Tue 5/1/12

309

Structural Bulks

40 days

Sun 5/20/12

310

Electrical Bulks

40 days

Tue 5/1/12

311

Field Instruments

40 days

Tue 5/1/12

312

Telecoms

40 days

Tue 5/1/12

313

96 days

Tue 6/5/12

314

Procurement construction/installation Central Plant & Well Sites


RFQ/ITT

15 days

Tue 6/5/12

315

Bid Phase

35 days

Sat 6/23/12

316

Technical Evaluation

28 days

Thu 8/2/12

317

Commercial Evaluation

14 days

Tue 9/4/12

318

purchase order

3 days

Thu 9/20/12

319

Contract Award

1 day

Mon 9/24/12

Project: Disouq Development Project


Date: Thu 9/29/11

2nd 3rd 4th 1st


u u u e o ea e

Task

Rolled Up Task

External Tasks

Critical Task

Rolled Up Critical Task

Project Summary

Progress

Rolled Up Milestone

Group By Summary

Milestone

Rolled Up Progress

Deadline

Summary

Split
Page 11

2nd 3rd 4th 1st


u u u e o ea e

ID
320

Task Name

Duration

Procurement for CTP site preparation and accomodation construction

Start

st
e

96 days

Mon 10/31/11

321

RFQ/ITT

15 days

Mon 10/31/11

322

Bid Phase

35 days

Thu 11/17/11

323

Technical Evaluation

28 days

Wed 12/28/11

324

Commercial Evaluation

14 days

Mon 1/30/12

325

purchase order

3 days

Wed 2/15/12

326

Contract Award

1 day

Sun 2/19/12

289 days

Sun 3/25/12

90 days

Sun 3/25/12

40 days

Sun 3/25/12

40 days

Sun 3/25/12

80 days

Thu 4/5/12

199 days

Sun 7/8/12

199 days

Sun 7/8/12

334

Site Utilities Supply Corridors Construction (Electrical cables, Water Supply, Drainage & Fire Fitting network)
40 days

Sun 7/8/12

335

Foundations: Packages, Tanks & Infrastructures concrete & Flare Pad

Sun 7/8/12

336

Packages and equipment placing

45 days

Wed 12/5/12

337

Interconnecting of Packages (Piping and Cabeling)

60 days

Mon 12/17/12

327
328
329

Construction
CTP Site preparation and accomodation construction
mobilization & site preparation

330
331
332
333

Site Cleaning, Leveling & Preparation + Fences + Access Roads


Plant Infrastructures Construction (Accommodation building, Control Room, Pipe racks)
Construction for Central plant & Well sites
Central Plant

60 days

338

Piping

60 days

Mon 12/17/12

339

Cabeling

30 days

Mon 12/17/12

30 days

Mon 1/21/13

0 days

Sun 2/24/13

340

Testing : Piping Hydrotest

341

Mechanical Completion

342

Installation of equipment E&I

30 days

Mon 12/17/12

343

Testing : E&I

35 days

Sat 12/29/12

344

Cold Commissioning

20 days

Sat 12/29/12

345

hot commissioning

15 days

Mon 1/21/13

346
347

E&I Certification
Well Sites

348

Project: Disouq Development Project


Date: Thu 9/29/11

NSG 1-1 / 1-2

0 days

Sun 2/24/13

198 days

Sun 7/8/12

198 days

Sun 7/8/12

2nd 3rd 4th 1st


u u u e o ea e

Task

Rolled Up Task

External Tasks

Critical Task

Rolled Up Critical Task

Project Summary

Progress

Rolled Up Milestone

Group By Summary

Milestone

Rolled Up Progress

Deadline

Summary

Split
Page 12

2nd 3rd 4th 1st


u u u e o ea e

ID

Task Name

349

Duration
mobilization & site preparation

350

30 days

Site Cleaning, Preparation + Fences + Access Roads

30 days

Start

st
e

Sun 7/8/12
Sun 7/8/12

351

Site Utilities Supply Corridors Construction (Electrical cables, Water Supply, Drainage & Fire Fitting
30 days
network)

352

Foundations :Packages, Tanks concrete

40 days

Wed 7/25/12

353

Packages and Equipment Placing

18 days

Thu 12/13/12

354

Piping Installation : wing valve to pipeline

30 days

Thu 12/13/12

355

Packages connection

20 days

Thu 1/17/13

356

Installation of equipment E&I

10 days

Thu 1/17/13

357

Mechanical Completion

358

Testing : E&I

Thu 7/19/12

0 days

Sat 2/9/13

22 days

Tue 1/29/13

359

Cold Commissioning

10 days

Tue 1/29/13

360

hot Commissioning

12 days

Sun 2/10/13

361
362
363

E&I Certification
SSG 1-1 / 1-2
mobilization & site preparation

364

Site Cleaning, Preparation + Fences + Access Roads

0 days

Sat 2/23/13

198 days

Sun 7/8/12

30 days

Sun 7/8/12

30 days

Sun 7/8/12

365

Site Utilities Supply Corridors Construction (Electrical cables, Water Supply, Drainage & Fire Fitting
30 days
network)

Thu 7/19/12

366

Foundations :Packages, Tanks concrete & Flare Pad

40 days

Wed 7/25/12

367

Packages and Equipment Placing

18 days

Thu 12/13/12

368

Piping Installation : wing valve to pipeline

30 days

Thu 12/13/12

369

Packages connection

20 days

Thu 1/17/13

370

Installation of equipment E&I

10 days

Thu 1/17/13

371

Mechanical Completion

372

Testing : E&I

0 days

Sat 2/9/13

22 days

Tue 1/29/13

373

Cold Commissioning

10 days

Tue 1/29/13

374

Hot Commissioning

12 days

Sun 2/10/13

375
376
377

Project: Disouq Development Project


Date: Thu 9/29/11

E&I Certification
NWSG 1-1
mobilization & site preparation

2nd 3rd 4th 1st


u u u e o ea e

0 days

Sat 2/23/13

198 days

Sun 7/8/12

30 days

Sun 7/8/12

Task

Rolled Up Task

External Tasks

Critical Task

Rolled Up Critical Task

Project Summary

Progress

Rolled Up Milestone

Group By Summary

Milestone

Rolled Up Progress

Deadline

Summary

Split
Page 13

2nd 3rd 4th 1st


u u u e o ea e

ID

Task Name

Duration

378

Site Cleaning, Preparation + Fences + Access Roads

30 days

Start

st
e

Sun 7/8/12

379

Site Utilities Supply Corridors Construction (Electrical cables, Water Supply, Drainage & Fire Fitting
30 days
network)

Thu 7/19/12

380

Foundations :Packages, Tanks concrete & Flare Pad

40 days

Wed 7/25/12

381

Packages and Equipment Placing

18 days

Thu 12/13/12

382

Piping Installation : wing valve to pipeline

30 days

Thu 12/13/12

383

Packages connection

20 days

Thu 1/17/13

384

Installation of equipment E&I

10 days

Thu 1/17/13

385

Mechanical Completion

0 days

Sat 2/9/13

386

Testing : E&I

387
388
389
390
391

22 days

Tue 1/29/13

Cold Commissioning

10 days

Tue 1/29/13

Hot Commissioning

12 days

Sun 2/10/13

0 days

Sat 2/23/13

198 days

Sun 7/8/12

30 days

Sun 7/8/12

E&I Certification
NWSG 1-2
mobilization & site preparation

392

Site Cleaning, Preparation + Fences + Access Roads

30 days

Sun 7/8/12

393

Site Utilities Supply Corridors Construction (Electrical cables, Water Supply, Drainage & Fire Fitting
30 days
network)

394

Foundations :Packages, Tanks concrete & Flare Pad

40 days

Wed 7/25/12

395

Packages and Equipment Placing

18 days

Thu 12/13/12

396

Piping Installation : wing valve to pipeline

30 days

Thu 12/13/12

397

Packages connection

20 days

Thu 1/17/13

398

Installation of equipment E&I

10 days

Thu 1/17/13

399

Mechanical Completion

0 days

Sat 2/9/13

400

Testing : E&I

401
402
403
404
405
406

Project: Disouq Development Project


Date: Thu 9/29/11

Thu 7/19/12

22 days

Tue 1/29/13

Cold Commissioning

10 days

Tue 1/29/13

Hot Commissioning

12 days

Sun 2/10/13

0 days

Sat 2/23/13

198 days

Sun 7/8/12

30 days

Sun 7/8/12

30 days

Sun 7/8/12

E&I Certification
NWK 1-1
mobilization & site preparation
Site Cleaning, Preparation + Fences + Access Roads

2nd 3rd 4th 1st


u u u e o ea e

Task

Rolled Up Task

External Tasks

Critical Task

Rolled Up Critical Task

Project Summary

Progress

Rolled Up Milestone

Group By Summary

Milestone

Rolled Up Progress

Deadline

Summary

Split
Page 14

2nd 3rd 4th 1st


u u u e o ea e

ID

Task Name

Duration

Start

st
e

407

Site Utilities Supply Corridors Construction (Electrical cables, Water Supply, Drainage & Fire Fitting
30 days
network)

408

Foundations :Packages, Tanks concrete & Flare Pad

40 days

Wed 7/25/12

409

Packages and Equipment Placing

18 days

Thu 12/13/12

410

Piping Installation : wing valve to pipeline

30 days

Thu 12/13/12

411

Packages connection

20 days

Thu 1/17/13

412

Installation of equipment E&I

10 days

Thu 1/17/13

413

Mechanical Completion

414

Testing : E&I

Thu 7/19/12

0 days

Sat 2/9/13

22 days

Tue 1/29/13

415

Cold Commissioning

10 days

Tue 1/29/13

416

Hot Commissioning

12 days

Sun 2/10/13

417
418
419

E&I Certification
NWK 1-2
mobilization & site preparation

420

Site Cleaning, Preparation + Fences + Access Roads

0 days

Sat 2/23/13

198 days

Sun 7/8/12

30 days

Sun 7/8/12

30 days

Sun 7/8/12

421

Site Utilities Supply Corridors Construction (Electrical cables, Water Supply, Drainage & Fire Fitting
30 days
network)

Thu 7/19/12

422

Foundations :Packages, Tanks concrete & Flare Pad

40 days

Wed 7/25/12

423

Packages and Equipment Placing

18 days

Thu 12/13/12

424

Piping Installation : wing valve to pipeline

30 days

Thu 12/13/12

425

Packages connection

20 days

Thu 1/17/13

426

Installation of equipment E&I

10 days

Thu 1/17/13

427

Mechanical Completion

428

Testing : E&I

0 days

Sat 2/9/13

22 days

Tue 1/29/13

429

Cold Commissioning

10 days

Tue 1/29/13

430

Hot Commissioning

12 days

Sun 2/10/13

431
432
433
434
435

Project: Disouq Development Project


Date: Thu 9/29/11

E&I Certification
NWK 1-3
mobilization & site preparation
Site Cleaning, Preparation + Fences + Access Roads

0 days

Sat 2/23/13

198 days

Sun 7/8/12

30 days

Sun 7/8/12

30 days

Sun 7/8/12

Site Utilities Supply Corridors Construction (Electrical cables, Water Supply, Drainage & Fire Fitting
30 days
network)

2nd 3rd 4th 1st


u u u e o ea e

Thu 7/19/12

Task

Rolled Up Task

External Tasks

Critical Task

Rolled Up Critical Task

Project Summary

Progress

Rolled Up Milestone

Group By Summary

Milestone

Rolled Up Progress

Deadline

Summary

Split
Page 15

2nd 3rd 4th 1st


u u u e o ea e

ID

Task Name

Duration

Start

st
e

436

Foundations :Packages, Tanks concrete & Flare Pad

40 days

Wed 7/25/12

437

Packages and Equipment Placing

18 days

Thu 12/13/12

438

Piping Installation : wing valve to pipeline

30 days

Thu 12/13/12

439

Packages connection

20 days

Thu 1/17/13

440

Installation of equipment E&I

10 days

Thu 1/17/13

441

Mechanical Completion

442

Testing : E&I

443
444
445

0 days

Sat 2/9/13

22 days

Tue 1/29/13

Cold Commissioning

10 days

Tue 1/29/13

Hot Commissioning

12 days

Sun 2/10/13

0 days

Sat 2/23/13

E&I Certification

446

Pre-Commissioning

447

Commission all Packages , Tanks & Trains

448

First Gas

Project: Disouq Development Project


Date: Thu 9/29/11

0 days

Sun 2/24/13

30 days

Mon 2/25/13

0 days

Sun 3/31/13

2nd 3rd 4th 1st


u u u e o ea e

Task

Rolled Up Task

External Tasks

Critical Task

Rolled Up Critical Task

Project Summary

Progress

Rolled Up Milestone

Group By Summary

Milestone

Rolled Up Progress

Deadline

Summary

Split
Page 16

2nd 3rd 4th 1st


u u u e o ea e