Documente Academic
Documente Profesional
Documente Cultură
A Final Paper
Presented to the
Faculty of the
School of Engineering
In Partial Fulfillment
Bachelor of Science in
Safety Engineering
By
Stacy, MN.
ii
ABSTRACT
trenching and excavation related fatalities each year. Since 1971, the
the Eastern Research Group which was in line with OSHA’s statistics
showed that accidents are under reported; therefore the reported numbers
workers per year were fatally injured in excavation related accidents. From
2004). These numbers show that since OSHAs regulations have taken
effect we have seen about a 33% drop in trench fatalities. Some view this
ii
industry professionals, as well as personal history within the business
presented a unique study of the data. With the ongoing injuries and deaths
attributed to excavation work, little will change unless the mind set of
those working in excavations change. This is not the only problem, with an
focus on excavations and their attempt to make the standards more user
friendly and the efforts of consultation to get the word out, little has been
iii
TABLE OF CONTENTS
Chapter 1 1
Introduction 1
Overview 9
Definition of Terms 9
Chapter 2 13
Chapter 3 28
Methodology 28
Research Approach 28
Database of Study 29
Data Validity 30
Summary of Chapter 3 31
Chapter 4 33
iv
Data Analysis 33
Project Evaluation 38
Warning Systems 55
Air Monitoring 58
Excavation Inspections 76
Fall Protection 77
Systems 78
Soil Classification 81
Chapter 5 100
Summary 100
Recommendations 101
v
Conclusion 103
References 105
Appendices
vi
CHAPTER 1
Introduction
referred to as the OSH Act, was brought about by a need for control
14,000 workers died and more than two million others suffered
the OSH Act (Occupational Safety and Health, 2007). Before the
1
occupations, including construction
public contracts
2
that day. Fourteen miners were able to escape while 13
each year. The initial rule under 29 CFR 1926 subpart P was
3
methods already in use and difficult to interpret by others
4
recommendations for changes to subpart P. The rules in
5
fraction that is seriously injured, but all of these accidents
accidents.
6
shielding methods and attitudes on worker safety. The
misunderstood rules.
regulations.
7
upholding the contractor’s desires to control their jobs, little
“By the middle of the last decade it was apparent that the
safety and health legislation had been left to the states. But
weak state laws, except for those states with strong safety
8
Overview
Definition of Terms
requirements, 1998).
9
identifying existing and predictable hazards in the
Safety, 2007).
10
excavation which is designed to prevent cave-ins (Safety
requirements, 1998).
greater than the width, but measures less than 15 feet at the
Acronyms
Transportation Officials
Health
11
ERG - Eastern Research Group
Health
12
Chapter 2
13
changes. These five regional workshops, held across the
Engineers.
standard.
14
participants felt that the language was strong enough to
15
purpose of worker protection shows a somewhat limited
16
by any agencies, it is still referenced within contracts and
Final rule.
17
in the Federal Register/ Vol.54, No. 209/ Rules and
18
years, for example “...unintentional injury deaths were
19
areas of interest, for instance, Part 1903 refers to
construction.
has links to state plans giving you the option of viewing your
20
given the power to run their own plan; however, at a
regulations.
OSHA 2226.
exposure records.
21
Mickle, J.L., (2002) Excavation Safety (1990-2002),
22
use, it was adopted by OSHA for its use in determining soil
dry, damp and saturated show how water can affect the
23
matrix. Several reasons for stabilizing are discussed along
duties on the job. Some lists are question and answer types
24
formats to check for compliance. Daily trench logs are shown
regulations.
stamp.
25
University of California at San Francisco as a cooperative
staff.
26
During the interviews, a number of reasons were
potential hazards.
27
Chapter 3
Methodology
Research Approach
study.
28
business presented a unique study of the data. The internet
website.
Database of Study
29
which are all too frequent, provided a 20/20 view of the
Data Validity
professional opinion.
The statistics are based on reported data, and given the fact
30
data to the entire population for unreported or under-
Summary
seams to ring true that most job sites where fatal injuries
Construction sites all over the United States are set back
place, people get hurt. It is not to say that all projects where
31
groups, organized labor and some portions of the industry
work force.
extra sets of eyes on the job, pointing out things that needed
32
Chapter 4
Data Analysis
wording has changed within the standard, but the intent has
organizations.
33
practices, there are steps management can take to ensure
method. This was intended to leave the door open for new
entire industry would suffer from not allowing the use of new
34
With a few clicks on the keyboard, OSHAs
the state OSHA office. The OSHA offices are generally split
the regulations and also prevent the other arm of OSHA from
compliance.
35
Scope, Application and Definitions
person” –
eliminate them.”
36
These instances of distinction can make a difference
proper training, might cock his head and say “We are all
know what a competent person is, what their duties are and
what they are responsible for. Such a person would not only
37
subparts within the construction standard that could
Project Evaluation
this may include the depth of the excavation and the type of
38
freeze. This cannot be excavated with a trencher in most
applications.
This would mean that for every foot in depth, the excavator
same excavation was made in a hard clay soil that met the
39
would not be affected in the clay example, but would need to
40
also to prevent damaging the other installations. For several
41
before excavation work commences, typically a 48-hour
some of these lines may run very shallow below the surface.
42
buried. When the assumption is made that the lines are
contacts the line. The opposite can also be the case where
through the soil using a steerable head. When the drill head
conflict.
43
2007). The choice of which method to use depends on a
44
under scaffolding subpart L also makes reference to railing,
the same soil from which the excavation was made. There
45
well as the number of entrants in the excavation. A small
employee must step out away from the box. In the event that
the box top is even with the top of the excavation, it may only
46
be a small step to the surface. However, if that surface is not
wall the excavation and the box wall. We would also need to
47
requires the minimum design and performance for the
not just public traffic, but the very vehicles which are brought
on site to make our jobs easier that in turn, also make our
jobs more deadly. Calling for the use of a vest on its own,
48
maintaining proper communication with all parties involved
defense.
49
must either remain in the vehicle’s cab or away from the
of the soil.
swung into position, a worker will grab the section and rotate
50
placed section. This practice puts the worker in an exposed
the manhole, well below the top edge where a rigging failure
51
builds. A failure in any part of this system can allow gravity to
the sky.
52
A recent example of this happened when two men
bucket was lifted up, the operator exited the cab underneath
was mucky clay that stuck to their shovels and boots. On this
After the bucket was filled, it was raised to the side of the
which had stuck onto the back of the bucket came loose.
53
With the speed generated by the swing of the bucket and the
54
The industry has addressed the issue and made strides in
Warning Systems
the excavation, the soil can handle less stress with the
greater. One must take into consideration, the soil type, the
55
the excavation. Generally, the larger the weight and/or the
2005).
Figure 1
At least 15’
away.
10’ Deep
15’
excavation bottom.
56
as the axel on that particular piece of equipment is
shift rearward when the load is raised. When the load leaves
the back of the truck, the center of gravity will move further
57
Air Monitoring
first is that since the excavation was left unattended that any
nearby sources.
58
the soil and even seemingly mundane excavations such as
The reason for this concern stems from the very real
59
material would tend to settle in lower areas displacing the
be seen:
Table 1
60
12-15 Impaired muscular coordination, perception
and judgment
vomiting
minutes 100%
probability of death
1998, p. 3)
Table 2
61
coughing, loss of sense of smell
Table 3
volume
attempting to drill into the manhole, his drill bit stuck solid in
62
succumb to the gas himself. A few hours later, after the
bodies had been removed, the air was tested and found to
concern.
a “Permit-Required-Confined-Space.”
63
two workers entered the space to start work for the day.
both men fell face first into the water. The foreman
have not shown up in time to save the foreman and the two
learned that the first two men that had fallen had drowned.
The H2S in the excavation had been released when they had
came from the leaking sewer system and had permeated the
surrounding soil.
64
The contractor on this day had an air monitor in their
unconsciousness.
workers that had worked on the same sewer line just a year
ventilation.
lighter than air, and more often than not, escapes without
65
ignition, the potential is there. Any nearby equipment or
• 02
• Fuel
• Ignition source
The fuel escaping out of the line is almost pure gas, and
the upper flammable limit (UFL). The location where the fuel
the UFL.
66
holding a lit match or lighter 100 yards from a gas station. As
enough proximity to reach the LFL. The fire from your lighter
the fire at the point of the leak due to excess gas and limited
contaminants.
67
the excavation. Looking back to what is needed to have a
fire: oxygen (02), fuel and ignition, we have the basis for fire
68
close attention to the effects of water accumulation in and
2002).
69
and lower in the fall. This area of the soil is saturated,
the soil system from above, such as rain run off, the more
level of the sand and water would start to flow into the
of the water.
Table 4
70
Silt and clay .0001 foot / day
between the grains, the soil could now be formed into balls
then to each other. This bond prevents the soil from flowing
71
A common method to create a more stable soil would
the header pipe great enough to draw the water up the point
excavation area.
environment.
72
the excavation from endangerment of water accumulation.
footing and within the angle that supports this footing, we are
73
undermining the support structure. With the removal of the
the soil, the soil could be displaced and push out into your
of the footing and the soil. If the area is large enough, deep
deep below the structure will the excavation go, how long it
74
Protection of Employees from Loose Rock and Soil
loose material often falls from the bucket or rolls down the
face.
75
Another form of protection from loose materials
Excavation Inspections
76
You are also looking for other influences such as rain
excavations left open over night and more than four feet in
excavation.
Fall Protection
77
excavations six feet or greater in depth, some form of fall
Safety and Health, 2007). If a trench that was dug two feet
wide and four feet deep was left unattended and people from
78
cave-ins. And only 24% of the excavations were properly
the front of the class and lay down on the floor. After placing
After less than two minutes, the volunteer gave up. After
150 pounds per square foot, with its effect being cumulative,
79
the deeper you are buried the more weight that is applied to
the body.
80
USDA and NBS. These organizations use qualitative and
Soil Classification
81
excavation is in previously disturbed clay or submerged clay,
determination.
82
crack or fissure may be caused by collapsing or expanding
soil types. During wet seasons, the soil absorbs the water
to run into other soil types before reaching the bottom of the
can happen.
83
Figure 2
Figure 3
84
If we address the layered conditions with sloping, we
can slope our bottom soil type B at a 1:1 slope ratio, when
our slope reaches the type C, our slope ratio must change to
Figure 4
2007).
undermining occurs and the support for the B soil is lost, the
85
unsupported weight would fracture and slide into the
some soil types exhibit only small changes from their dryer
Figure 5:
86
Clay, when nearly saturated, holds the water tightly
methods.
87
consistency of clay. This soil sample allows a disturbed test
sample is too dry, you will not be able to form the soil as
ball into a thin thread about 1/8 of an inch thick. If the thread
taking a soil sample from the spoil pile and mixing and
88
perform your test. Using a straight-sided jar 6-8 inches in
height, put 2-3 inches of soil in the bottom, then put in 4-6
inches of water. Seal the top and shake vigorously until all
or a wrist watch available when you place the jar down. Start
Initially, the sand should settle to the bottom within the first
30 seconds; silt within the next 1-2 minutes and clay will take
material was less than 70%, you could have a granular type
2000).
89
Table 5
2000).
90
inch thick by about six inches square. Air dry the sample for
pulled from the spoil pile, try to indent the piece with your
91
means the material has been removed from the ground and
fails or is crushed.
in mind that soil layering may be involved and that each and
Type A soil ≤ 1.5 tons per square foot (tsf) =144 kPa
92
The second instrument is called a shear vane which
shear vane tests, you will have to multiply your final answer
by two.
using a pocket knife, you can cut or shave into the sample to
(Tschappet, 1998).
spoils pile can limit our choices. In a type C soil, our slope
93
applications, the number of crossing utilities can make it
4’ bucket
100 x 10 x 15 = 15,000 cu ft
100 x 10 x 4 = 4000 cu ft
94
10’ 10’
15’ 4’ 15’
14)
Now, let’s look an alternative protective method, a
95
Figure 6
10’
4’
Trench Box
96
give us sizing and spacing for each of the types. However,
for each slope type, watch for loose material on the sides of
97
need to extend to the bottom of the excavation to prevent
loss of soil.
If the top of the trench box does not reach the top of
2004). However, make sure that the data sheets are referred
on the type of soil as well as the depth. Once the shields are
98
the employee may be exposed to a different hazard. Once
on top of the box, the employee must step out away from the
box. In the event that the box top is even with the excavation
down between the side wall of the excavation and the box
has the same or similar requirements for use and each are
99
Chapter 5
Summary
the system in place work? Is OSHA not getting the word out?
100
The number of organized trade members getting hurt
relative to the overall industry is low. This does not bode well
environment.
accident rates.
Recommendations
101
their company policies and requirements for their personnel on the
beneficial.
For excavation sites that would include all relevant rules as well as
102
inspections can also be tied to the company’s incentive program.
safely. A crew that thinks safe and works safe should reap the
turnover rate which benefits not just the employer, but their
employees as well.
Conclusion
103
consultation efforts to get the word out, little has been
104
REFERENCES
http://www.doli.state.mn.us/pdf/02_fatal_log.pdf.
Administration
http://www.msha.gov/Readroom/Handbook/PH99-I-
4.pdf
http://www.osha.gov/dts/shib/shib072205a.html
105
Henderson, K. (2003). The Competent Person: The first line
Fund. p. 3.
Merriam-Webster, Incorporated.
Department.
http://www.cdc.gov/niosh/85-110.html
http://www.revisor.leg.state.mn.us/rules/?
id=5207.1000
Edition.
106
Occupational Safety and Health Administration website.
from http://osha.gov
45895.
http://osha.gov/dts/sltc/methods/validated/id194/id194
.html
Plog, B.A., Materna B., Vannoy J., & Gillen M., (2006).
Workers' Rights.
Labor.
107
Safety Requirements for Excavations (ANSI/ASSE A10.12-
from http://en.wikipedia.org/wiki/Sago_Mine_disaster:
Encyclopedia.
2002, www.cleaner.com
http://www.lhsfna.org/index.cfm?objectID=D2135898-
D56F-E6FA-96FBD66A64D98EFC
641
108
interpretations and compliance letters. Retrieved
http://www.osha.gov/pls/oshaweb/owadis.show_docu
ment?p_table=INTERPRETATIONS&p_id=21955
Training Institute.
from http:www.army.mil/usapa/eng/index.html
109
Volpe, M. (2005, January). Safety Experts Discuss Top
(2007).
Appendix A
110
Table 1
and judgment
vomiting
1998)
Appendix B
111
Table 2
protection)
Appendix C
112
Table 3
Appendix D
113
Table 4
Appendix E
114
Table 5
115