Documente Academic
Documente Profesional
Documente Cultură
Terrance A. Bellei
Ernst H. Camm
S&C Electric Company
Chicago, Illinois
Gene Ransom
ComEd
Chicago, Illinois
180-T69
I. INTRODUCTION
Current-limiting inductors are often connected in series
with shunt capacitor banks to limit the severity of outrush
currents into close-in bus faults. High-magnitude and
high-frequency outrush currents that would otherwise
occur can cause damaging overvoltages when line circuit
breakers reignite and subsequently interrupt at highfrequency current zeros [1]. The rate of rise of the
transient recovery voltage (TRV) which a line circuit
breaker will be subjected to during a close-in fault is
considerably lower than normal when a capacitor bank is
present, while the peak of the TRV is higher. The lower
rate of rise of the TRV will enable the line circuit breaker
to interrupt with a very short arcing time, thereby
increasing the possibility of reignitions in the circuit
breaker if the dielectric withstand capability of the
contact gap is exceeded after interruption with a small
contact gap.
The size of the current-limiting inductor is generally
selected to ensure that the product of the peak outrush
current and the frequency is less than 2 107 for generalpurpose circuit breakers [2, 3]. In back-to-back capacitor
bank applications, a single bank of three-phase currentlimiting inductors is usually used to limit outrush current
from two or more shunt capacitor banks.
II. BACKGROUND
In September 1999 extensive damage occurred to a
138-kV, 57.6-Mvar grounded-wye capacitor bank in
ComEds Silver Lake Substation. A 2000-ampere circuit
breaker, used to protect this bank and a second 57.6-Mvar
capacitor bank in parallel with it, was unable to interrupt
the associated fault current, causing the bus circuit
breakers to open to clear the fault. A 1-ohm currentlimiting inductor is connected on the load side of the
circuit breaker to limit outrush currents from the two
capacitor banks. Two additional 138-kV capacitor banks
are connected in a similar circuit arrangement on a second
138-kV bus. Each of the capacitor banks is switched
with a Circuit-Switcher equipped with 40-mH 5.5-ohm
pre-insertion inductors. See Figure 1.
the most likely reason why the circuit breaker was unable
to interrupt the fault current involved during the incident
at Silver Lake Substation.
Review of the special circumstances of the fault
involved in this incident by the circuit breaker
manufacturer also led to the conclusion that the evolving
nature of the fault may have contributed to the inability of
the circuit breaker to clear the fault. The circuit breaker
uses an arc-assist interrupter unit, which develops a
pressure proportional to the magnitude of the fault current
to assist with extinguishing the arc during fault current
interruption. The gradual increase in the magnitude of the
fault current, initially limited by the current-limiting
inductor and pre-insertion inductor, resulted in insufficient
pressure in the interrupter to successfully interrupt the
current.
In order to limit the severity of the initial TRV across
the circuit breaker contacts, the use of a capacitor
connected in parallel with the current-limiting inductor
was considered. The capacitance value must be selected
such that the voltage acceleration associated with the
initial TRV is less than that resulting from the ANSIspecified rate of rise of recovery voltage of 1.8 kV per
microsecond. This translates into a limiting voltage
acceleration of 175 volts per microsecond2. For an initial
peak TRV of 86.8 kV, the frequency on the load side of the
circuit breaker must be limited to less than approximately
10 kHz in order not to exceed the specified rate of rise of
recovery voltage. This would require a capacitance of at
least 94 nF across the terminals of the current-limiting
inductors in each phase. A 100 nF capacitor per phase was
recommended to be used for this purpose.
V. CONCLUSIONS
VI. REFERENCES
[1] L. van der Sluis, A.L.J. Jansen, Clearing Faults Near
Shunt Capacitor Banks, Presented at the 1990 IEEE-PES
Winter Meeting, Atlanta, Georgia, February 4 - 8, 1990.
[2] Brian C. Furumasu, Robert M. Hasibar, Design and
Installation of 500-kV Back-to-Back Shunt Capacitor
Banks, in IEEE Transactions on Power Delivery, Vol. 7,
No. 2, April 1992.
[3] ANSI C37.06-1997, AC High-Voltage Circuit Breakers
Rated on a Symmetrical Current Basis Preferred
Ratings and Related Required Capabilities.
Terrance A. Bellei received his BSEE from Marquette
University in Milwaukee, Wisconsin. He has been with
S&C Electric Company since 1974 and has held various
positions in R&D and the Power Systems Services
Division. He is currently Manager, Engineering Services,
in the Power Systems Services Division.
Within IEEE, he has served as a member of the High
Voltage Fuses Subcommittee, Working Group on External
Fuses for Shunt Capacitors, Working Group on Full-Range
Current-Limiting Fuses, and as the secretary of the
Working Group on Revision of Fuse Standards. He has
served as Chairman of a Task Force formed by the
Working Group on Revision of Fuse Standards. He was
also a former representative of S&C in the North America
Short-Circuit Testing Liaison (STLNA).
Ernst H. Camm received his BSc (Eng) degree in
Electrical and Electronic Engineering from the
University of Cape Town, South Africa in 1984 and his
MSEE degree from the Ohio State University in 1992.
From 1984 to 1990, he held various positions in Plant and
Project Engineering at S&C Electric Company. He is
currently a Senior Engineer in the Engineering Services
Department at S&C Electric Company.
Ernst has had extensive involvement in capacitor
switching transient and power quality analysis at S&C,
including analysis in the development of optimally sized
pre-insertion inductors for capacitor switching transient
mitigation. He is the author of and co-presenter of S&Cs
Seminar on Capacitor Switching Transients and Their
Impact on Your System. He is a member of the Switching
Transients Task Force of the IEEEs Modeling and
Analysis of System Transients Working Group and the
Shunt Capacitor Application Guide Working Group.
Gene Ransom received his BS degree in Electrical and
Electronic Engineering from the Illinois Institute of
Technology. He has been with ComEd since 1972 and has
held various positions in Transmission, Distribution, and
Substation engineering and construction. He is currently
Substation Engineering Manager for ComEd.