Documente Academic
Documente Profesional
Documente Cultură
Issued: 1/88
SOP #8
PROCEDURES FOR WELDING OR HOT
TAPPING ON EQUIPMENT NOT
DEPRESSURED TO CLEARED
Revised: 9/98
Page 1
A request for welding or hot tapping on equipment not depressured and cleared will be initiated
by the use of the Welding or Hot Tapping Approval form (RR-178). The originator on the form
is the person requesting the hot tap.
II.
The Welding or Hot Tapping Approval form will be sent to the Operations Manager or the
Products Control Manager, as appropriate, for approval. It will be the responsibility of
Operations, Products Control and Maintenance Supervision to minimize the use of hot taps and
welding on lines that are not depressured or cleared. The following alternatives must be
considered:
A.
Installation delay must be seriously considered, so that connections can be made at a time
when equipment or piping is not in service.
B.
Alternate locations for connections should be investigated to prevent the need for a hot tap
or welding.
C.
Every attempt possible must be made to isolate equipment or process systems when it is
decided to make connections which would otherwise require hot tapping or welding.
Once a hot tap or welding is deemed necessary, the Operations Manager or Products Control
Manager will sign off on the final approval section after the questions in the section have been
answered by the Unit Foreman and Area Supervisor. The location shall be identified on the pipe,
tank or vessel and approved by the Unit Foreman.
III.
The Welding or Hot Tapping Approval form will then be forwarded to Engineering. The
Engineering Manager will sign off on the final approval section after the questions in the section
have been answered by the responsible engineer. API 2201 Procedures for Welding or Hot
Tapping on Equipment Containing Flammables shall be followed where applicable.
Chemistry of Line or Vessel Contents
The oxygen level within the equipment must be controlled to prevent the formation of a vapor/air
mixture within flammable or explosive ranges. In addition, contents of the line or vessel being
hot tapped must not contain:
IV.
Issued: 1/88
SOP #8
PROCEDURES FOR WELDING OR HOT
TAPPING ON EQUIPMENT NOT
DEPRESSURED TO CLEARED
Revised: 9/98
Page 2
1.
Hydrogen, if the equipment is operated above the Nelson curve limits, because of the
possibility of hydrogen attack of the metal (see API Publication 941).
2.
3.
4.
Caustic or amine, if the concentration and temperature are such that the fabrication
specifications call for stress relieving.
5.
The Welding or Hot Tapping Approval form will then be forwarded to the Inspection
Department. The Inspection Supervisor will sign off on the final approval after the questions in
the section have been answered by the responsible inspector. The following should be carefully
considered:
Burn Through
The risk of burn-throughs can be minimized if the equipment is properly inspected for adequate
wall thickness and absence of defects, if controlled welding techniques are done by experienced
welders to prevent overheating, and if other appropriate safety procedures are followed. A
thorough and complete inspection of each connection area must verify that the metal thickness is
adequate for the pressure and temperature involved, and that there are no laminations or other
defects. Welding or hot taps can only be made in lamination free areas. To minimize the
possibility of burn-through, the first weld pass to the equipment should be made with a 3/32 inch
diameter welding electrode, and the remaining passes should be made with electrodes not to
exceed 1/8 inch diameter if actual metal thickness does not exceed 1/2 inch.
For heavier wall thicknesses where burn-through is not a primary concern, larger diameter
electrodes may be desirable to compensate for the larger mass. This will minimize the potential
for fusion defects.
Metal Thickness
Generally, a minimum base metal thickness of 3/16 inch is recommended for hot tapping.
Exceptions to the recommended thickness may be permitted when metallurgical requirements and
pressure limitations specified by the Inspection Department are met.
Issued: 1/88
SOP #8
PROCEDURES FOR WELDING OR HOT
TAPPING ON EQUIPMENT NOT
DEPRESSURED TO CLEARED
Revised: 9/98
Page 3
The Inspection Supervisor will sign off on the final approval section, after the questions in the
section have been answered by the Inspector. API 2201 Procedures for Welding or Hot Tapping
on Equipment Containing Flammables shall be followed where applicable.
V.
The Maintenance Planning Supervisor will sign off on the final approval section after the
questions in the section have been answered by the Area Planner. API 2201 Procedures for
Welding or Hot Tapping on Equipment Containing Flammables shall be followed where
applicable.
Flow in Lines
In certain cases where there may be insufficient or interrupted flow, such as a flare line, it may be
necessary to continually purge or flood the line with steam, inert gas or hydrocarbon gas to ensure
that the line or equipment does not contain a flammable mixture during the welding operation.
Suggested product velocities during welding are:
1.
2.
2.
Heating coils
Turn off all heating coils during the hot tap or welding procedure.
3.
VI.
The Maintenance Manager will sign off on the final approval after the questions in the section
have been answered.
VII.
The Work Order and Welding or Hot Tapping Approval package (form, drawings and written
procedure) will be issued to the Area Maintenance Foreman. The following procedure will be
used in the actual performance of the hot tap connection and hot tap:
Before Welding or Hot Tap Connection Begins
Before proceeding with the welding or hot tap, the following conditions must be satisfied:
1.
The Area Maintenance Foreman, Unit Foreman and Chief Operator will verify that
each section of the Welding or Hot Tapping Approval form has been filled out and
signed.
2.
The area to which a connection is to be made has been identified, physically marked
and the metal thickness measured.
3.
Review welding or hot tap connection/hot tap written procedure and attached drawings
as necessary.
4.
A Unit Operator will be at the work site during the welding or hot tapping.
5.
A work clearance permit (hot work) has been secured, and all necessary gas tests have
been made to ensure a safe environment.
A suitable fire extinguisher (preferably dry chemical or pressurized fire hose) has been
provided and a fire watch established.
6.
7.
Contact the Safety Department after the preceding steps have been completed, and
work is ready to begin.
VIII.
A Safety Department Representative will go to the work site and complete the questions under the
Safety Section of the Welding or Hot Tapping Approval form. These questions are directed
toward Maintenance/Operations personnel, as a double check, that certain items have been
completed. The Unit Foreman, Chief Operator, Maintenance Foreman and Craftsman should be
in attendance at the work site when the Safety Representative fills out this section of the
Welding or Hot Tapping Approval form. Work may begin after the Safety Representative signs
the final approval section.
IX.
Reference: API Publication 2201, Procedures for Welding or Hot Tapping on Equipment
Containing Flammables. API Standards may be found on RoadMap.
RR-178
Revised 4/98
STEP 1
Page 1 of 2
INITIATING GROUP
Date_______________________________Originator_____________________________________________________________
Description of Hot Weld or Tap______________________________________________________________________________
________________________________________________________________________________________________________
STEP 2
Yes
No
___
___
Alternate locations for connections were investigated to prevent the need for a hot tap?
___
___
3.
___
___
4.
Is the material in the line stable under heated conditions and normally free of oxygen?
___
___
1.
Installation delay was seriously considered, so that connections could be made at a time when equipment
or piping is not in service?
2.
COMMENTS____________________________________________________________________________________________
________________________________________________________________________________________________________
Area Supervisors Signature:____________________________________________
Date_______________________________
Final Approval:______________________________________________________
(Operations/Products Control Manager)
Date_______________________________
STEP 3
ENGINEERING DEPARTMENT
Yes
No
1.
Has a tie-in drawing package been issued including P&ID, isometric plan drawings and bill of material?
___
___
2.
___
___
3.
___
___
4.
Full encirclement saddles are required for size-to-size hot taps. Is proposed hot tap size-to-size, for
example 6 tap on a 6 line?
___
___
5.
Have the line or vessel contents been considered so that welding is avoided on equipment which contains
flammable mixtures which could have been embrittled by service environments such as amines, wet
H2S, or high temperature hydrogen?
___
___
Has a tie-in walk through been completed with Operations, including tagging of the tie-in location?
___
___
6.
COMMENTS_____________________________________________________________________________________________
_______________________________________________________________________________________________________
Engineering Signature:________________________________________________
Date_______________________________
Final Approval:______________________________________________________
(Engineering Manager)
Date_______________________________
STEP 4
INSPECTION
Yes
No
1.
Has the area to be welded been inspected for metal thickness (3/16 minimum)?
___
___
2.
___
___
3.
Do the flanges, bolts, gasket, pipe and valve to be installed meet the piping code for the line or vessel
to be hot tapped?
___
___
4.
COMMENTS_____________________________________________________________________________________________
_______________________________________________________________________________________________________
Inspector Signature:__________________________________________________
Date_______________________________
Final Approval:_____________________________________________________
(Inspection Supervisor)
Date_______________________________
STEP 5
PLANNING
Yes
No
1.
Are the following drawings attached to this form: Isometric, Plan and P&ID?
___
___
2.
Has a written detailed procedure been developed for this weld or hot tap and has it been attached to this
approval form? (API 2201 should be followed)
___
___
3.
Has the exact location of the hot tap on the line or vessel been identified and marked?
___
___
COMMENTS_____________________________________________________________________________________________
______________________________________________________________________________________________________
RR-178
Page 2 of 2
Planner Signature:___________________________________________________
Date_______________________________
Final Approval:_____________________________________________________
(Planning Supervisor)
Date_______________________________
STEP 6
MAINTENANCE DEPARTMENT
Yes
No
1.
Have all the previous sections of the approval form been filled out?
___
___
2.
Is the detailed written procedure for the hot tap connection and hot tap attached to this form?
___
___
COMMENTS____________________________________________________________________________________________
_______________________________________________________________________________________________________
Approval:_________________________________________________________
(Maintenance Manager)
Date_______________________________
STEP 7
PLANNING SUPERVISOR CAN NOW ISSUE WORK ORDER FOR HOT TAP
CONNECTIONS/HOT TAP
STEP 8
MAINTENANCE CRAFTSMAN WILL TAKE THIS FORM AND ALL ATTACHMENTS TO UNIT CHIEF
OPERATOR AND OBTAIN WORK CLEARANCE PERMIT. HOT TAP BEGINS WHEN WELDING
SADDLE ONTO LINE/VESSEL
STEP 9
MAINTENANCE FOREMAN, UNIT FOREMAN, CHIEF OPERATOR WILL VERIFY PROPER LINE
HAS BEEN IDENTIFIED. THEY WILL THEN CONTACT SAFETY DEPARTMENT FOR FINAL
CHECK
STEP 10
Prior to commencing the work, the planner will meet with the Unit Foreman, Chief Operator, Maintenance Foreman, Craftsman,
Inspector and Safety to ensure the Approval Form has been filled out properly. At this time Safety will answer the following
questions:
Yes
No
A. Hot Weld
1.
___
___
2.
___
___
3.
___
___
4.
___
___
5.
___
___
6.
___
___
___
___
___
___
COMMENTS____________________________________________________________________________________________
________________________________________________________________________________________________________
B. Hot Tap
1.
___
___
2.
___
___
3.
___
___
4.
___
___
5.
___
___
6.
___
___
7.
___
___
___
___
8.
COMMENTS____________________________________________________________________________________________
_______________________________________________________________________________________________________
Date__________________________________
Date__________________________________
THIS FORM SHALL BE SENT TO THE SAFETY DEPARTMENT FOR FILING UPON COMPLETION OF JOB.