Sunteți pe pagina 1din 24

Project Management

THE MANAGERIAL PROCESS

Clifford F. Gray
Eric W. Larson

Third Edition

Lecture 4

Developing a Project Plan


Activity on Node (AON)

Copyright 2006 The McGraw-Hill Companies. All rights reserved.

PowerPoint Presentation by Charlie Cook

PROJECT MANAGEMENT: BACA 4132

Learning Objectives
At the end of this topic you will be able to:
Draw the Activity on Node (AON) network
Analyze the Activity on Node (AON) network

PROJECT MANAGEMENT: BACA 4132

Comparison of AON and AOA


Methods

PROJECT MANAGEMENT: BACA 4132

Introduction of AON
Node of AON
No free float

Earliest Start

Latest Start

Label, Description, Resources


Duration

Total Float

PROJECT MANAGEMENT: BACA 4132

Formula of AON Analysis

EFT = EST + Duration


LST = LFT Duration
LFT = LST + Duration
Total Float = Latest Start Time Earliest Start Time

Earliest Start Time

Latest Start Time

PROJECT MANAGEMENT: BACA 4132

Activity-on-Node Fundamentals

PROJECT MANAGEMENT: BACA 4132

Activity-on-Node Fundamentals (contd)

PROJECT MANAGEMENT: BACA 4132

Network Information

PROJECT MANAGEMENT: BACA 4132

Koll Business CenterComplete Network

PROJECT MANAGEMENT: BACA 4132

10

Network Computation Process


Forward PassEarliest Times
How soon can the activity start? (early start-EST)

How soon can the project finish? (expected time-EFT)

Backward PassLatest Times


How late can the activity start? (late start-LST)
How late can the activity finish? (late finish-LFT)

Which activities represent the critical path?


How long can it be delayed? (total float-TF)

PROJECT MANAGEMENT: BACA 4132

11

Network Information

TABLE 6.2
PROJECT MANAGEMENT: BACA 4132

12

Activity-on-Node Network

Staff report

Construction plans

15

15

Occupancy

35
Application approval

Traffic study

10

Commission approval

10

Wait for construction

170

Service check

PROJECT MANAGEMENT: BACA 4132

13

Activity-on-Node Network Forward Pass


20

Staff report

Construction plans

15

15

200
Occupancy

0
Application approval

5
Traffic study

10

20
Commission approval

10

30

35

Wait for construction

170

5
Service check

PROJECT MANAGEMENT: BACA 4132

14

Activity-on-Node Network Backward Pass


185

5
Staff report

Construction plans

15

15

200
Occupancy

0
Application approval

10
Traffic study

Commission approval

10

30

20

10

35

Wait for construction

170

15
Service check

PROJECT MANAGEMENT: BACA 4132

15

Determining Slack (or Float)


Slack (or Float)
The amount of time an activity can be delayed after
the start of a longer parallel activity or activities.

Total slack
The amount of time an activity can be delayed without
delaying the entire project.

PROJECT MANAGEMENT: BACA 4132

16

Activity-on-Node Network with Total Float


20

Staff report

Construction plans

15

185

15

165

200

200

Occupancy

Application approval

10

Traffic study

10

20

20

Commission approval

10

30

30

35

Wait for construction

170

15

Service check

10

PROJECT MANAGEMENT: BACA 4132

17

Summary Table
No.

Activity Description

Duration
(weeks)

Earliest
Start Time
(EST)

Latest
Start Time
(LST)

PROJECT MANAGEMENT: BACA 4132

Earliest
Finish
Time
(EFT)

Latest
Finish
Time (LFT)

Total Float

18

Frequently Asked Questions


1. What is the critical path?
2. How long does it take to finish the project?
3. What are the total float for the non-critical
activities?

PROJECT MANAGEMENT: BACA 4132

19

Two Errors in Logic

1. Looping
2. Dangling

PROJECT MANAGEMENT: BACA 4132

20

Illogical Loop

FIGURE 6.9
PROJECT MANAGEMENT: BACA 4132

21

Dangling

PROJECT MANAGEMENT: BACA 4132

22

Extended Network Techniques


to Come Close to Reality
Laddering
Activities are broken into segments so the following
activity can begin sooner and not delay the work.

Lags
The minimum amount of time a dependent activity
must be delayed to begin or end.
Lengthy activities are broken down to reduce the delay in the
start of successor activities.
Lags can be used to constrain finish-to-start, start-to-start,
finish-to-finish, start-to-finish, or combination relationships.

PROJECT MANAGEMENT: BACA 4132

23

ANY QUESTIONS?

PROJECT MANAGEMENT: BACA 4132

24

S-ar putea să vă placă și