TECHNICAL SPECIFICATIONS
The Thermosiphon pots shall be fabricated as per our attached drwg. No
and the specifications given below :1. Vendor to follow ASME Sec. VIII Div. I.
2. Deviation in dimensions as indicated in Drawing Sheet including
thickness of plates shall be within tolerance limits as specified in
ASME Sec. VIII Div. I.
3. The plates upto 12 mm thk. shall have single V butt welded with
back gazing joint. Above 12 mm thickness shall have double V butt
weld joint.
4. DE Thickness shall not be less than min specified (Thickness) in
ASME Sec. VIII.
5. Nozzles up to 40 NB to be supported with stiffeners.
6. Surface of SS equipment to be acid pickled cleaned. Uncovered MS
parts shall be coated twice with zinc chromate primer after suitable
surface preparation.
7. All the dish ends shall be torispherical.
8. All hardware (Including nuts, bolts & washers) shall be in MS.
9. SS-304 ERW pipe of 19.05 mm OD ,2 mm thk shall be used for the
manufacture of coil.
10. All nozzles shall be socket type with female ends and of sizes as per
the drwg.
ANNEXURE - B
SCOPE OF SUPPLY, EXCLUSIONS & GENERAL
1. Scope: The scope of supply of the Vendor shall include the following
activities:-
Design & supply of drawings for approval of M/s. High Polymer Labs Ltd. as
per Drawing/Documentation clause given in the Annexure - B.
requirement of
and technical
2. Documentation/Drawings
The
vendor
shall
furnish
drawings/documents mentioned below as a part of the Purchase Order.
Documents must give sufficient details to install the equipment. The documents
must show component removal distances and space required for maintenance.
Dimensions shall be in metric system. All drawings shall be completed with
Item No., Purchase Order No., and Date.
LIST OF DRAWINGS :No. of Copies
2
2
3
1
7
3
15
7
During Stage
Inspection.
- do - do
ANNEXURE - C
INSPECTION & TESTING
1. The following inspection & tests shall be carried out by the Vendor in
the presence of High Polymer Labs Ltd. representative at the Vendor's
premises. The schedule for this shall be intimated to High Polymer
Labs Ltd. in the bar chart for manufacture :(a) Material testing : All materials for the fabrication of the equipments
shall be tested (Microstructure, Chemical & Physical) in approved
testing laboratories if required.The sample shall be taken in the
presence of HPLL representative from all the plates which shall be
marked with the HPLL seal. HPLL reserves the rights to reject the
material if found off specifications.
(b) UT Test: Vendor shall arrange to carryout UT Test in the presence of
inspection authority of HPLL on all plates .
(c) Fabrication of the equipment can be proceeded with the marked
material after UT test and final approval of the equipment is subject
to material being as per specification. Inspection of visual details
shall be done simultaneously.
(d) Dimensional Inspection of Vessels : Overall dimensions shall be
inspected and tolerance limit for the same is x 5 mm for fabricated
part where x is any dimension shown in the drawing.
Any
dimension beyond this tolerance limit is liable to be rejected unless
the vendors modifies suitably the equipment so that all dimensions
are within the said tolerance limit. For machined parts the tolerance
limit shall be as per code.
(e) Hydro Test : The equipments shall be tested at hydrostatic pressure
for leakage for Minimum Three hours. The gauge used for pressure
testing will be calibrated in the presence of High Polymer Labs's
Inspection authority. All blind flanges required for this purpose shall
be in the scope of the vendor.
(f) Welder Approval : Qualified Welders shall be approved by the
Inspection authority of HPLL. Vendor to submit WPS/PQR.
(g) D.P. Test: Vendor shall carry out 100% DP test. Vendor can proceed
further after the clearance from HPLL. Vendor shall prepare and offer
all fit up and shall carry out the root run after the clearance of
Inspection authority from HPLL. Back chipping shall be done and to
be offered for inspection.