High-level timetable for the full Licence

The SoS has decided the Licences should come into force at the same time as the next price control, on
1 April
p 2014, to avoid disturbing
g the current settlements. This has the benefit of enabling
g the Licences to
be developed alongside the development of revised price and service quality regulation. This timetable is
subject to change and Parliamentary approval of the draft Civil Aviation Bill.
Date

Milestone

January 2012

CAA submits advice to the SoS on an indicative airport Licence for Heathrow to aid
Parliaments scrutiny of the draft Civil Aviation Bill. This advice is published.

January
y - June 2012

Discussions with stakeholders about the development


p
of airport
p licences.

April 2012

CAA to publish next consultation on the development of revised price and service
quality regulation. This will include a consideration of Licence development issues.

Julyy December 2012

CAA will look in detail at the financial arrangements


g
at each airport
p before determining
g
if and how financial resilience conditions should be imposed.

April 2013

The CAA to publish initial proposals for revised price and service quality arrangements.
Alongside this publication the CAA will publish initial proposals for the full Licences.

April September 2013

Detailed discussions with stakeholders to fine tune the Licence drafting (and review
the initial proposals for price and service regulation).

September 2013

CAA to publish a notice proposing to grant the Licences with the proposed price and
service
i quality
lit regulation
l ti conditions.
diti

January 2014

CAA to publish a notice granting the Licences with the revised price and service quality
regulation conditions.

April 2014

Licence conditions for revised price and service quality regulation come into effect
effect,
subject to any appeal.
CAA advice to SoS January 2012, Page 1

High-level timetable for the full Licence


Apr May Jun

Jul

2011

Aug Sep

Oct Nov Dec

Jan

2012

Feb Mar Apr May Jun

Jul

Aug Sep

Oct Nov Dec

Jan

2013

Feb Mar Apr May Jun

Jul

Aug Sep

Oct Nov Dec

Jan

2014

Feb Mar Apr

Q5(+1)
Q5(
1)
expires

ParliamentaryProcess
Parliamentarystagesincludingcommencement

CAAassumptionisPart1
oftheActiscommenced
byApril2013

SoSdecisiononwhether
toremovethemandatory
CCreferenceunderAA86

Q6underAER
Consultationon
developmentofQ6
andLicenceissues

Competition
Assessments

Indicative Discussionwithstakeholders Detailedreviewoffinancial


aboutdevelopmentof
Licence
arrangementsateach
f P
forP
Li
Licence
airport

Competition
p
Assessments

Final
Final
proposals
consultation

Q6

Q6

decision

starts

Draft
Li
Licence

Proposalto
grant Licence
grantLicence

Licence Conditions
granted effective

ConstructiveEngagement

Licensingstrategy

Q6underAA86

IInitial
ii l
proposals
consultation

Detaileddiscussionwith
stakeholderstofinetune
theLicence

ConstructiveEngagement
Update
CAAreview&proposals
compassess

CCreviewandreport

CAAproposal&decision

CAA advice to SoS January 2012, Page 2