Documente Academic
Documente Profesional
Documente Cultură
Session 7
Objectives
The objective of this session is to introduce :
Page No. 2
Process Groups
Knowledge Areas
Page No. 3
Page No. 4
Page No. 5
Estimates are needed to determine how long the project should take and its cost
Estimates are needed to develop time phased budgets and establish the project
baselines
Page No. 6
Planning Horizon
Project Duration
People
Padding estimates
Organization Culture
Other factors
Page No. 7
Page No. 8
Page No. 9
Estimate Activity Resources is the process of estimating the type and quantities of material,
people, equipment or supplies required to perform each activity. Closely coordinated with
Costs
INPUTS
OUTPUT
Activity List
Expert Judgment
Activity Attributes
Alternative Analysis
Activity Resource
Requirements
Resource Calendars
Enterprise Environmental
Factors
Bottom Up Estimating
Organizational Process
Assets
Resource Requirement
Structure
Project Document
Updates
Page No. 10
Activity
Resource
Requirements:
Resources required for each activity
Resource
Breakdown
Structure:
Hierarchical structure of Resources by
Resource Category and Resource type
Project Documents:
Activity List, Activity Attributes, Resource
Calendars
Page No. 11
Output
Page No. 12
Estimate Activity Duration is the process of approximating the number of work periods
needed to complete individual activities with estimated resources. Estimating activity
durations uses Information on activity scope, required resource types, quantities and
calendars. The duration is progressively elaborated
INPUTS
OUTPUT
Activity List
Expert Judgment
Activity Attributes
Analogous estimating
Parametric estimating
Resource Calendars
Reserve Analysis
Enterprise Environmental
Factors
Organizational Process Assets
Page No. 13
Activity Resource Requirements: For ex if lower skilled resources are assigned, there
maybe reduced productivity due to increased communication, training and co-ordinations
Resource Calendars: The availability, capability, type could affect schedule duration. For
eg. when a senior resource is assigned full time, activity could be completed in less time
Input
Page No. 14
Parametric
Reserve Analysis
PERT
Optimistic:
Pessimistic
Expected Duration
A reserve (buffer) is
added to the overall
schedule . It can be
percentage of
estimation duration
or developed using
quantitative analysis
As more information
about the project
becomes available,
the contingency
reserve may be
used, reduced or
eliminated
Page No. 15
Output
Scenario 1
Page No. 16
You have won a project for developing a website for a B2C Client. The client wants the
website delivered in 4 months. The website would allow the customers to interact with the
client company . this requires that careful consideration of user experience
In the past you have delivered similar projects. You are fairly confident about the technology
that will be used. However, in the past you delivered such projects for clients in B2B area.
Scenario 2
Page No. 17
You own a firm which specializes in Painting Office spaces (both exteriors and interiors)
You are invited to bid for painting of an upcoming commercial complex and need to provide
estimates of time and cost
the commercial complex is large and expected to be delivered compared to world class
standards.
Scenario 3
Page No. 18
You have recently been assigned a new large enhancement on an existing project. You
estimate the project to take approx 36 weeks.
However, when you speak to HR about recruiting an resource with niche skill for the project,
you realize he may be onboarded 4 weeks later. this could clearly impact the schedule.
However, there is also an probability that you are evaluating of leveraging resusable
components from past projects for this enhancement. you expect to cut down time on this
enhancement by atleast 6 weeks if it goes through.
Scenario 4
Page No. 19
Your estimate for the project is 24 months. However, you foresee following risks in terms of
timelines:
-
Part of the material is expected to be imported. again there might be issues getting
approval for importing material.
Some of the equipment to be used has limited capacity and you will need to factor in
the delays due to unavailability
Page No. 20