0 evaluări0% au considerat acest document util (0 voturi)
40 vizualizări1 pagină
Design of a tunnel lining is not a structural problem, but a groundstructure interaction problem. Sprayed concrete lining (shotcrete) can itself have time-dependent characteristics. In most cases in hard rock, the bending strength and stiffness of structural linings are small compared with those of the surrounding ground.
Design of a tunnel lining is not a structural problem, but a groundstructure interaction problem. Sprayed concrete lining (shotcrete) can itself have time-dependent characteristics. In most cases in hard rock, the bending strength and stiffness of structural linings are small compared with those of the surrounding ground.
Design of a tunnel lining is not a structural problem, but a groundstructure interaction problem. Sprayed concrete lining (shotcrete) can itself have time-dependent characteristics. In most cases in hard rock, the bending strength and stiffness of structural linings are small compared with those of the surrounding ground.
Ground improvement techniques and lining systems 109
CHARACTERISTICS OF LINING BEHAVIOUR
A list of common characteristics that pervade all lining systems are (after Kuesel and King 1996):
The processes of ground pre-treatment (e.g. grouting), excavation and
ground stabilization (e.g. rock bolting) alter the pre-existing state of stress in the ground, before the lining comes into contact with the ground. A tunnel lining is not an independent structure acted upon by well-defined loads. The loads acting on a tunnel are not well defined, and its behaviour is governed by the properties of the surrounding ground. Design of a tunnel lining is not a structural problem, but a groundstructure interaction problem, with the emphasis on the ground. Defining the loads on the tunnel lining is one of the most challenging aspects for a civil engineer on a tunnel project. Tunnel lining is a four-dimensional problem. During construction, the ground conditions at the tunnel heading involve both transverse and longitudinal arching, or cantilevering from the excavated face. All the ground properties are time-dependent, particularly in the short-term, which leads to the commonly observed phenomenon of stand-up time, without which most practical tunnel construction methods would be impossible. The timing of the lining installation is an important variable. In addition, some tunnel linings such as sprayed concrete lining (shotcrete) can itself have time-dependent characteristics. In the case of sprayed concrete lining the stiffness is extremely time-dependent and the effects of early creep have to be taken into account before the lining reaches its full strength. The most serious structural problems encountered with actual lining behaviour are related to the absence of support rather than to the intensity and distribution of the load, for example inadvertent voids left behind the lining. However, exceptions exist and poor ground conditions could result in additional, unexpected loading on the lining. In most cases in hard rock, the bending strength and stiffness of structural linings are small compared with those of the surrounding ground. The properties of the ground therefore control the deformation of the lining, and changing the properties of the lining will not significantly change this deformation. It is important that the lining has adequate ductility to conform to the imposed deformations, and adequate strength to resist bending stresses is therefore secondary. The lining therefore forms a flexible ring confined by the ground.
4.3.2 Sprayed concrete (shotcrete)
Sprayed concrete is concrete which is conveyed under high pressure through a pneumatic hose and projected into place at high velocity, with simultaneous compaction (DIN 2005). Sprayed concrete can also be called shotcrete and both terms are used in this book.