Documente Academic
Documente Profesional
Documente Cultură
W A T E R
A N D
E N E R G Y
I N T E R N A T I O N A L
HARISH BAHUGUNA
Geologist
P.C. NAWANI
Director
Abstract
Construction of underground powerhouse at Tehri was inevitable
because of non-availability of the space on the surface and the huge
excavation (required to accommodate the powerhouse) of the steep
back slopes. Excavation of the two huge cavities of the powerhouse
complex i.e., machine hall and transformer hall was tackled carefully.
Geotechnical assessment made earlier revealed that both these
cavities are located in the most competent rock mass at Tehri dam
site i.e. phyllitic quartzite massive (PQM) and phyllitic quartzite thinly
bedded (PQT) GradeI. Considering the geotechnical parameters
including the in-situ stress measurements, the alignment of these
cavities was preferred in N0209 direction. As the alignment was
also against the dip direction, the excavation in these cavities was
free from any major failure. These gigantic caverns were stabilized
by means of rock bolting and shotcreting barring a patch in the
crown of machine hall where a 5m band of deformed rock mass,
associated with a major longitudinal shear, was encountered. The rock
cover between the two cavities was insufficient (i.e. less than 2D),
because of which problem of convergence was recorded during the
excavation of the bus ducts in the common wall. Multiple bore hole
extensometers (MPBAX) and load cells were installed to monitor the
rate and extent of convergence, and a number of deep cable anchors
(blind and through) were installed to stabilize the area.
1. Introduction
Tehri project is to be developed
in two stages of 1000 MW each.
The stage I, known as HPP, has
been completed and it consists
of an underground Powerhouse
of 1000 MW (4 x 250 MW). The
three main cavities in stage I viz.,
machine hall, transformer hall, and
Special Issue on Tehri Dam Project
CK
CK