Sunteți pe pagina 1din 23

Toronto Transit Commission

CONTRACT A29-1

Section 01 50 00
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
Page 1

TEMPORARY CONTROLS

1.1

General:
.1

Refer to Contract Drawings for required hoarding, barriers and dust-tight partitions .

.2

Submit shop drawings for hoarding, barriers and dust-tight partitions in accordance with
Section 01 33 23 for review prior to the erection of Work .

.3

Repair and/or repaint damaged hoarding, barriers and dust-tight partitions within twenty
four (24) hours of damage. Maintain hoarding, barriers and dust-tight partitions graffiti free.
Remove or paint over graffiti within twenty four (24) hours or as directed by Commission's
Representative. Wash the surface of the partitions when so directed by the Commission's
Representative .

.4

Repair and restore to original condition any part of the structure or equipment broken or
damaged as a result of installation or removal of hoarding, barriers and dust-tight partitions .

.5

At Contract Completion, remove all installed and existing hoarding, barriers and dust tight
partitions unless otherwise noted on Contract Drawings or as directed by the Commission's
Representative.
Hoarding, Fencing and Barriers:

1.2
.1

Minimum setback of barrier from edges of bus stops and drop-off areas, and rapid transit
platforms shall be 1.5 m or as directed by Commission's Representative .

.2

Before commencing the Work, take over existing hoarding from Other Contractor, and
supply, erect and maintain hoarding lines as specified using plywood hoarding 2400 mm
high around entire perimeter of Site per Contract Drawings to protect public and
private property from injury or damage. Ensure lockable gates are provided within
hoarding or fence for access to Site by workers and vehicles. The Contractor shall carry
out a full survey check on the existing hoarding location and condition, and shall
report to the Commission's Representative any discrepancy or defect within
forty-eight (48) hours of handover inspection. If not reported within the time limit, the
Contractor shall be deemed to have taken full responsibility for the condition and
accuracy of set-out of the existing hoarding and shall be responsible at no cost to
the Commission for any alterations required subsequently to comply with the
Contract Documents and with all safe working requirements.

.3

Before handing over areas of the Site to Other Contractors, provide plywood hoarding
similar to the Site perimeter with lockable gates as shown on the Contract Drawings to
delineate the area to be handed over for occupation by Other Contractors .

.4

Prevent unauthorized entry to the Site. Barricade, guard, or lock access points to the
satisfaction of the Commission's Representative and post "DANGER DUE TO
CONSTRUCTION - AUTHORIZED PERSONNEL ONLY" - signs. Snow fencing is
prohibited as protection for sidewalk or other pedestrian passage without the Commission's
Representative's permission in every instance.

ADDENDUM 2

Section 01 50 00
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
Page2

Toronto Transit Commission


CONTRACT A29-1

.5

Notify Commission's Representative in writing when flag persons are required when
working on railway right of way or when Work affects railway operations, minimum three (3)
weeks in advance of any Work required .

.6

Supply and install fencing and hoarding around railway switches, allowing sufficient space
for the operation of the switches .

.7

Provide barriers and covered walkways required by governing authorities for public rights
of-way and for public access to buildings.

.8

Install signs for movement of public around Work Site as directed by the Commission's
Representative .

.9

Provide barriers around trees and plants designated to remain as per Contract Drawings.
Protect from damage.

.10

Provide secure, rigid guard rails and barricades around deep excavations, open shafts,
open stair wells, and open edges of floors and roofs as required for protection of Work,
Workers and the public.

.11

Erect hoarding as required to delineate work zone between A35-26 Contract and
A29-1 Contract in a co-ordinated and agreed location at time of Site handover.

Security:

1.3
.1

Provide and pay for security personnel to guard the Site and contents of the Site ensuring
the security of the Site at all times .

.2

Any security service provided by the Commission is for the protection of the Commission's
interest in the Work on the Site and shall not relieve the Contractor of the responsibility to
protect the Site and the Work of the Contract.

HEIGHT LIMITATION

2.1

In hydro right of way adjacent to and crossing the railway, use equipment which is in
conformance with hydro height clearance restrictions.

2.2

Do not operate equipment that will endanger existing structures, local hydro installations,
YUDC campus infrastructure services and City of Toronto or York Region traffic signals.

UTILITIES

3.1

Contractor's Electrical Plant and Temporary Lighting System (New Construction):


.1

Supply, install and maintain electrical power and necessary electrical equipment, including
overhead and underground feeders, transformers, motors, starters, protective devices and
lighting equipment. Fit outlets with ground fault circuit interceptors (GFCI) where they are
used as a supply for tools and portable equipment outdoors or in wet locations .

.2

Make all necessary arrangements for, and pay all costs for, a temporary electrical service
including all costs of energy consumed.
ADDENDUM 2

Toronto Transit Commission


CONTRACT A29-1

Section 01 50 00
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
Pagel

.3

The Contractor is responsible for providing electrical power, until the earlier of, Contract
Completion, or when permanent power is available and cabling is in place .

.4

Upon Contract Completion, remove electrical plant from the Site, except the distribution
system and hydro service equipment required to keep the lighting in operation .

.5

Where temporary lighting system is not removed submit all as-built and record drawings in
accordance with Section 01 33 23, showing all electrical and lighting installations that
remain permanently.

3.2

Contractor's Temporary Water Usage:


.1

Supply and install a temporary water meter at all connections to existing water supply
piping. All cost for equipment, piping and water consumed shall be the responsibility of the
Contractor.

.2

No connections shall be made to existing taps, hose bibs or faucets.

3.3

Temporary Water Shutdown:


.1

3.4

If in the performance of Work, it is necessary to shut off the water supply either completely
or partially in an existing facility, Contractor shall inspect and operate in the presence of the
Commission's Representative all plumbing fixtures affected by the shut off to ensure their
proper operation.
Temporary Heating:

.1

Provide temporary heating required during construction period, including attendance,


maintenance and fuel.

.2

Temporary fuel fired heating devices to meet OHSA requirements .

.3

Construction heaters used inside buildings must be vented to the outside or be flameless
type. Solid fuel salamanders are not permitted .

.4

Maintain temperatures of minimum 10 deg C in areas where construction is in progress


unless otherwise indicated in the Specifications. Maintain all areas beneath temporary road
decking at a temperature of 5 deg C minimum at all times to protect exposed and adjacent
services from freezing .

.5

Repair at no cost to the Commission any such services, buildings or other utilities disrupted
by freezing .

.6

Ventilate heated areas and keep structures free from exhaust combustion gases.

ADDENDUM 2

Section 01 50 00
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
Page4

Toronto Transit Commission


CONTRACT A29-1

Contractor's Drainage System:

3.5
.1

Supply, install and maintain a temporary drainage system of sufficient capacity and
efficiency to maintain excavations free of water during the construction period. Submit a
Plan and install plant as required to safeguard the Site and downstream sites from flooding
in the event of a weather related event and/or utility breaks. Do not use any portion of the
permanent drainage system without the permission of the Commission's Representative.
Remove the temporary system upon Contract Completion, unless otherwise indicated on
the Contract Drawings as to be handed over to others in good working order at an interface.
Accommodation for Workers:

3.6
.1

Supply, install and maintain in a clean condition suitable and convenient water closet and
drinking water accommodation for Workers in accordance with the Occupational Health and
Safety Act and Regulations for Construction Projects. Remove accommodations upon
Contract Completion.
Temporary Utility Support:

3.7
.1

Inspect and assume ownership of maintaining and repairing all components of


support system for utilities, including temporary bridge structure, in accordance with
Section 02 4113.

POWER WASHING AND VIDEOTAPING OF SANITARY AND STORM DRAINAGE


SYSTEM

4.1

Power wash and videotape storm drainage system in accordance with this Section on two
occasions:
.1

Prior to construction activities .

.2

Prior to scheduling commissioning for final acceptance.

4.2

Co-ordinate and schedule with Work by plumbing trade. Power wash to remove existing
drainage system debris and any construction debris. Drainage systems to be protected
from debris at all times during construction.

4.3

Repeat power washing and videotaping process where debris not cleared to satisfaction of
the Commission's Representative.

4.4

Submit the following:


.1

Schedule for power washing and videotaping two (2) weeks prior to commencing for
witnessing at the Commission's Representative's discretion .

.2

Power washing report identifying level of debris encountered .

.3

Videotape confirming drainage systems clear of debris to satisfaction of the Commission's


Representative.

ADDENDUM 2

Toronto Transit Commission


CONTRACT A29-1

Section 01 50 00
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
PageS

.4

Videotape index correlating videotape counter with drawing entry points and distance
travelled through drainage system (refer to S01500.11 and S01500.12 attached) .

.5

Drawings indicating system entry points (video start points) and extent of videotaping (video
stop points) corresponding to videotape counter (refer to S01500.11 and S01500.12
attached).
Storm Drainage System: Identify all the following fixtures and equipment on drawings.
Refer to the Contract (Mechanical) Drawings for extent and details of drainage system.

4.5

.1

Roof Drains .

.2

Cleanouts .

.3

Rain Water Leaders (RWL).

.4

Drainage Piping .

.5

Underground Storm Mains .

.6

Maintenance Hole/Catchbasin .
Sanitary Drainage System: Identify following fixtures and equipment on the drawings. Refer
to the Contract (Mechanical) Drawings for extent and details of drainage system.

4.6

.1

Cleanouts .

.2

Floor Drains .

.3

Area Drains/Catch Basins .

.4

Drainage Piping .

.5

Underground Sanitary Mains .

.6

Maintenance Holes .

PROTECTION

5.1

Protection of Public and Station Area, surrounding properties and roads:


.1

Protect surrounding private and public property from damage during performance of the
Work .

.2

Provide and maintain at all times appropriate protection to fully weatherproof all areas of the
building which may become exposed due to demolition, removals and construction.
Ingress of water, snow, etc., into the station interior or building components will not be
permitted. All cost for cleanup and restoration of damages resulting from failure to comply
shall be the responsibility of the Contractor.

ADDENDUM 2

Section 01 50 00
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
Page6

5.2

Toronto Transit Commission


CONTRACT A29-1

Protection of Existing Equipment:


.1

Equipment and existing Work moved or altered to facilitate construction, movement of


material or equipment shall be stored, protected with dust tight covers and subsequently
returned to its original location .

.2

The Commission's Representative's approval is required for the installation of temporary


support devices into existing roof or wall members for the erection of equipment or
machinery. Repair roof and wall members used for this purpose to the satisfaction of the
Commission's Representative .

.3

Provide necessary screens, covers and hoardings as required .

.4

All existing (in use) and new equipment damaged while carrying out the Work shall be
restored with new Products matching the original equipment.

5.3

Fire Protection:
.1

Take precautions to prevent fires. Provide and maintain temporary fire protection
equipment of a type appropriate to the hazard anticipated in accordance with authorities
having jurisdiction, governing codes, regulations, by-Jaws and to the satisfaction of the
Commission's Representative and insurance authorities .

.2

Supply and install heat detectors, wiring and end of line resistors on the construction side of
any hoarding and dust-tight partitions. The number of heat detectors shall be as required
by the code. Interconnect the heat detectors and the end of the line resistors to the existing
fire alarm panel in each station. After the Work is completed, remove the heat detectors,
end of line resistors and its wiring.
Install heat detectors in accordance with
CAN/ULC S524-M .

.3

Bulk storage of flammable liquids and other hazardous materials is not allowed on Site.
Supplies for daily use only are permitted. Flammable liquids must be handled in approved
containers that are labelled in accordance with WHMIS and maintained in good order
complete with all spouts, caps and gaskets. Keep containers for flammable liquids closed
at all times when not directly in use. Empty containers are dangerous and must be kept
with their caps and spouts in place .

.4

Open burning of rubbish is not permitted on the Site .

.5

The bringing in, use and disposal of flammable materials shall be as required by authorities
having jurisdiction .

.6

Provide fire extinguishers of the non-freezing chemical type in each temporary building,
enclosure and trailer.

.7

Use fire-proofed tarpaulins.

ADDENDUM 2

Toronto Transit Commission


CONTRACT A29-1

5.4

Section 01 50 00
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
Page7

Protection of Workers:
.1

Workers shall comply with the Occupational Health and Safety Act and Regulations for
Construction Projects .

.2

Workers scheduled to perform Work at track level, or where there is an overhead electrical
hazard, or when interfacing with the Commission's operating and maintenance personnel
within the Commission's transit system or maintenance operations, shall attend and
successfully meet the requirements of the Commission's rule book training program prior to
the commencement of such Work. Refer to Section 01 59 00.

5.5

Protection of Finished Structures Adjacent to Work Areas:


.1

The Contractor shall provide a Storm and Site Water Management Plan (SSWMP) for the
construction Work area. The Plan shall address measures to minimize or manage water
that would enter the excavation and/or partially completed subsurface works and tunnels as
a result of weather related events or interruption and/or damage to utilities. The submittal
will include sealed engineering documents that includes plans showing construction staging
and sequences, plant to be provided and supporting analysis.

TEMPORARY BUILDINGS

6.1

Supply and install the following facilities for the sole use of the Commission at or near the
Site for the duration of the Contract in locations approved by the Commission's
Representative:
.1

York University Station Site - Main Office and Change Room Furnishings:
.1

Location shown on Contract Drawings:

Structure

Quantity

Description

Details

Modspace or equal. New or


pre-owned if acceptable to the Commission's
Representative.
Must meet regulatory requirements for
disabled persons - (wheelchair users,
ambulant, disabled people).
Double steel doors, self closing with electronic
security control and security padlock bar
arrangement.
Single steel door, self closing with electronic
security control and security padlock bar
arrangement.
Complete with electronic security control and
metal bars or expanded metal.
1829 mm x 2438 mm (6' x 8") rubber mat,
commercial grade, including cleaning.
914 mm x 1829 mm (3' x 6') rubber mat,
commercial grade, including cleaning.
Bristled scraper.

Office

(60'

Covered Entrance
Landings

(8'

Exit

Front

Exit

Rear

76')

16')

Windows

10

Mats

Horizontal
Sliders
Front Entrance

Mats

Rear Entrance

Boot Cleaners

One at each
Entrance

ADDENDUM2

Section 01 50 00
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
PageS
Structure

Quantity

Interior Office Areas

Office #1
Office #2
Reception area
Liaison office area
Small kitchen area
& unisex
washroom
Meeting room
Document Control
room
Printing area
Plan review room
Lunch room
IT room

1
1
1
1

Description

Toronto Transit Commission


CONTRACT A29-1

Details

Interior office areas to be divided as follows


(approximately):
3500 mm X 2700 mm (11'-6" X 8'-1 0")
complete with door
2700 mm x 2700 mm (8'-8" x 8'-8") complete
with door
3580 mm x 2700 mm (11'-6" x 9')
6100 mm x 10790 mm (20' x 35'-6")

1
1
1
1
1
1
1

1
Hotel room
Women's
1
washroom
1
Men's washroom
Interior Furnishing - New Only

6100 mm x 7500 mm (20' x 24'-6")


3580 mm x 7500 mm (11'-6" x 24'-6")
3580 mm x 2800 mm (11'-6" x 9'-6")
3580 mm x 5000 mm (11'-6" x 16'-6'1
4750 mm x 4750 mm (15'-6" x 15-6")
3460 mm x 5000 mm (11'-5" x 16'-4")
3460 mm x 2200 mm (11'-5" x 7'-4")
3460 mm x 2800 mm (11'-5" x 9'-4")
3460 mm x 4100 mm (11'-5" x 13'-6")
3460 mm x 4100 mm (11 '-5"x13'-6")

Workstations
Total number of workstations- 16. Typical + 1 Special Order Desk for Public Liaison Area. See
attached drawing and layout.
Total number of chairs -16.
Each workstation to be equipped with the following furniture. All furniture to be new.
Mobile partitions to be provided between each workstation.
All modular office furniture to be provided with raceway spaces for cables and jack hardware which
sits above the work surface when installed.
All furniture to be gray or black.
All workstations to have a minimum four (4) number 3-pin electrical sockets.
All workstations to have network and communication fittings and cables as specified.
With base frame 42" x 24" x 29" (1067 x 610 x
1
Desk
737), with special cut angle right 24" left leg,
14" right leg.
17.5" x 48" x 78" x 29" with 6" curved overhang
1
Corner desk
over 78", 14"1eft leg, grommet left.
Articulating
1
Keyboard
2 back corners notched fully retractable.
1
Palm rest to suit
Joiner plate to
2
suit
ADDENDUM 2

Toronto Transit Commission


CONTRACT A29-1

Structure

Quantity

Section 01 50 00
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
Page9
Description

Grommet to
suite
Free-standing 2
box/1 file
lockable
pedestal

Details

4572 mm x 533 mm x 699 mm (15' x 21" x


27.5").
660 mm x 613 mm x 1067 mm (26" x 32" x
42") Stretch back workchair with arm rests.

Chair

1
1
2
3

Waste basket
Re-cycle basket
PABX telephone
Closed lockable 914 mm x 356 mm x 1676 mm (36" x 14" x
bookcase
66").
Table
1219 mm x 1676 mm x 737 mm (48" x 66" x
29").

1. Kitchen
1
1

Refrigerator
Microwave oven

Double sink

Bottled water
Waste
bin/recycle
bin/green bin
Green Bin

1
1

Large.
1000W.
Complete with counter, base and wall mounted
cupboards.
Supplied throughout duration of contract.
One of each.

2. Meeting Room
1
12
2
1
1
3. Document Control Room
1

Table
Chairs
White Board
Projector
Projector Screen

3658 mm x 1067 mm (12' x 3.5').


Stackable, padded, steel frame.
1219 mm x 2438 mm (4' x 8').

New plain paper.

Facsimile: One
new plain paper
facsimile
machine
Paper shredder

Waste bin

Large.

1
7

Recycle bin
File cabinets

Large.
Fireproof, 1321 mm x 457 mm X 711 mm
(52"H X 18'W x 28"D).

1
1

Plan desk
Drawing cabinet

Built - in on 10 degree incline.


Steel flat file cabinet with drawers capable of
holding full size drawings. 12 drawers.

Large, heavy duty. Include costs of secure


pickup and disposal of shredding.

ADDENDUM 2

Section 01 50 00
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
Page 10
Sbucture

Quantity

Toronto Transit Commission


CONTRACT A29-1

Description

Details

Plan rack

Mobile plan rack with 12 hangers capable of


holding full size plans.

1
Photocopier
All products/equipment to be new.
Sufficient electrical sockets, network and communications sockets to meet the requirements of the
equipment.
All equipment in printer area to be able to be operated from every computer in main site office
complex.
4. Foyer
2
Hand Sanitizer
(one sanitizer at either entrance).
1
Notice board
914 mm x 1829 mm (3' x 6').
5. Printing Area
All products/equipment to be new.
Sufficient electrical sockets, network and communications sockets to meet the requirements of the
equipment.
All equipment in printer area to be able to be operated from every computer in main site office
complex
1
Photocopier
Capable of making multiple copies up to A3
size, complete with sorting capabilities.
0
Scanner
Capable of multifeed A3 size.
1
Facsimile
Machine
0
Laser printer
Capable of printing to A3 size, complete with
sorting capabilities.
0
Colour plotter
Ca_pable of plotting to AO size.
1
Heavy
duty
paper shredder
1
Large waste bin
1
Large waste bin
-recycle
1
Heavy
Duty 900 mm x 1000 mm to withstand 50 kg
Table
(1361bs).
6. Lunch Room
All products/equipment to be new.
Sufficient electrical sockets, network and communications sockets to be installed.
1
Hand Sanitizer
Station
1
Sink Unit
Complete with shelving and cupboards
0
Lockers
1
Large
Microwave oven
1
Large Fridge
1
Water Heater
1
Water Cooler
1
Toaster

ADDENDUM 2

Toronto Transit Commission


CONTRACT A29-1

Structure
Quantity
7. Plan Review Room

Section 01 50 00
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
Page 11
Description

Details

Custom made
plans display
shelves.

1219 mm x 762 mm x 737 mm (48" x 30" x


29").

8. Site Security
All Products/equipment to be new.
Windows to have metal grilles on outside
Security door to have facility to open from inside electrically
All access door to be self closing.
All Entrance/exit to have access security system.
All windows to have access security system.
Building to have fire alarm system.
1
Security camera
external
1
Security camera
internal
1
Security monitor
2
Fire extinguisher 9 kg dry chemical for Class ABC fires
complete with 150 mm X 200 mm fire
extinguisher symbol mounted on wall above
fire extinguisher.
1
Complete with 150 mm x 200 mm first aid
Fire aid box
symbol mounted on wall above first aid box.
1

Public Access
Defibrillator

Compact size

9. Access
All Products/equipment to be new.
Access as shown on the drawings.
Office to meet the requirements of the Ontario
Fire Code 1997.
Office to have ramp access - 2 locations as
shown on drawings.
All access to have external lighting.
All access to be correctly sign posted.
Access to the site office shall be by stepped
and ramp access which meets the regulatory
standards. For all trailers and temporary
buildings provide wooden stairs, ramps,
platforms, boardwalks, painted and re-painted
with non skid abrasive pain
All stepped access, ramps, platform and
boardwalk to be supplied with handrails which
meet the regulatorY requirements.

ADDENDUM 2

Section 01 50 00
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
Page 12
Quantity Description
Structure
10. Office Requirements
All Products/equipment to be new.

Toronto Transit Commission


CONTRACT A29-1

Details

Office to be Disabled Person Accessible - for


wheelchair users and ambulant disabled
persons.
Office must meet the requirements of the
Ontario Building Code 2006.
Office must meet the requirements of the
Ontario Code & Guide for Sewage Systems
1997.
Office must meet the requirements of the
Ontario Code & Guide for Plumbing 1998.
Office must meet the requirements of the
Ontario Fire Code 1997.
Office must meet the requirements of the
Ontario Electrical Safety Code 24th Edition.
11.1T Room
In Building Wiring Closets:
Sites forecast to house> 10 staff occupancy:
1
Dedicated locked room {keyed 14-D3) with minimum dimensions of 2134 mm x
2438 mm (7 feet x 8 feet).
Secure standard 483 mm x 2134 mm {19" x 84") relay rack with cable
2
management trays on the sides. This rack must be bonded to building ground.
1 - Dedicated 15A, 11 OV AC duplex outlet with U-grounded receptacle on a
3
dedicated branch circuit.
4
Dedicated locked room {keyed 14-D3) with minimum dimensions of 2134 mm x
2438 mm {7 feet x 8 feet).
5
Secure standard 483 mm x 2134 mm {19" x 84") relay rack with cable
management trays on the sides. This rack must be bonded to building ground.
6
1 - Dedicated 15A, 11 OV AC duplex outlet with U-grounded receptacle on a
dedicated branch circuit.
Distribution Cabling:
All Office locations
1
2 Category 5e cable runs from the area wiring closet, or cabinet to each
computer device location within the office.
2
All Cat5e cable runs to be <89.92 m {295 feet) total.
Cable runs >89.92 {295 feet) must be implemented as fibre, or through an
3
additional wiring closet or cabinet to keep the cable <89.92 m {295 feet).
One of the two Cat5e cables is to be Blue {A runs), The other is to be Grey {8
4
runs}.
A and Bruns are to terminate on separate 24 or 48 port patch panels (sized to
5
accommodate the intended run count) at the wiring closet rack or cabinet end.
6
Horizontal cable management trays are to be located below each patch panel.
7
A and Bruns are to be terminated on labelled (numbered per TTC standards)
Cate_g_ory 5e compatible jacks at the device (user) end.
All user end and wall-mounted network jacks are to be located at 900 mm
8
{36 inches) above finished floor.

ADDENDUM 2

Section 01 50 00
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
Page 13

Toronto Transit Commission


CONTRACT A29-1

Details
Quantity Description
Where walls do not exist, modular office furniture systems will provide raceway
9
space for cables and jack hardware which sits above the work surface when
installed.
All 8 Category 5 conductors are to be connected per EIA!TIA T568A standards
10
straight through.
Patch cords are to be supplied for wiring closet 40 pieces (green 1219 mm
11
(4 feet) Long).
Patch cords are to be supplied for every wall jack 40 pieces (orange 27 43 mm
12
(9 feet) Long).
Both ends of each patch cord will be labelled with the same unique numbers.
13
All cables will be tested and certified by the installer for straight through polarity
14
and continuity.
Every jack must be tested to ensure that it meets level 5 requirements.
15
Warranty of Workmanship: the wiring and the related accessories must be
16
guaranteed free of defects for duration of Contract.
Bell Service Entrance:
All fibre Connected locations:
50.8 mm (2") conduit from wiring closet to the Bell Main Wiring Closet on the
1
service entrance floor.
Contractor to provide 1219 mm x 1829 mm x 19 mm (4' x 6' x %") plywood
2
Telecom backboard adjacent to main rack location.
Contractor to install fish wire.
3
12. Women's Washroom
Complete with hot and cold water, 4 sinks,
1
Vanity
4 faucets, 4 soap dispensers.
Dyson Airblade AB02 120V - Single unit order
1
Hand dryer
code 13043-01 , or equal.
Structure

Mirror

Full height/length of vanity.

Toilet

Complete with lockable door, partition, toilet


paper dispenser.

Toilet

Handicap accessible complete with lockable


door, partition, toilet paper dispenser.

1
1

Hand sanitizer
station
Towel
Paper
Holder
Waste bin
Bench

Vanity

Complete with hot and cold water, 4 sinks,


4 faucets, 3 soap dispensers.

Hand dryer

Dyson Airblade AB02 120V - Single unit order


code 13043-01, or equal.

Mirror

Full

1
1

13. Men's Washroom

ADDENDUM 2

h~ight/length

of vanity.

Section 01 50 00
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
Page 14
Structure

Quantity

Description

Details

Toilet

Complete with lockable door, partition, toilet


paper dispenser.

Toilet

Handicap accessible complete with lockable


door, partition, toilet paper dispenser.

Urinals

Complete with partitions.

1
1
1
.2

Toronto Transit Commission


CONTRACT A29-1

Hand sanitizer
station
Paper
Towel
Holder
Waste bin

In addition to the above requirements, all facilities supplied by the Contractor for the
Commission shall include the additional requirements listed below:

Quantity 1 Description
Structure
1 Details
14. Parking
Disabled Person Parking - as close to office as possible - minimum 1 space.
1
Parking for TYSSE Staff- 28 spaces.
2
15. Additional Notes
Office to be Disabled Person Accessible - for wheelchair users and ambulant
1
disabled persons.
Office/change room to meet the requirements of the Ontario Building Code
2
2006.
Office/change room to meet the requirements of the Ontario Fire Code 1997.
3
Office/change room to meet the requirements of the Ontario Code & Guide for
4
Sewage Systems 1997.
Office/change room to meet the requirements of the Ontario Code & Guide for
5
Plumbing_ 1998.
Office/change room to meet the requirements of the Ontario Electrical Safety
6
Code 24th Edition.
Each work station/desk to have minimum four (4) number 3-pin electrical
7
sockets.
Office to have ramp access- 1 location as shown on Drawing.
8
All access to have external lighting.
9
All access to be correctly sign posted.
10
Access to the site offices shall be by stepped and ramp access which meets
11
the regulatory standards. For all trailers and temporary buildings provide
wooden stairs, ramps, platform, boardwalk painted and re-painted with nonskid abrasive paint.
All stepped access, ramps, platform and boardwalk to be supplied with
12
handrails which meet the re_gulatory_ requirements.
Products and equipment to be new.
13
All user end and well mounted network jacks, phonejacks and electrical outlets
14
to be located at 900 mm (36 inches) above finished floor.

ADDENDUM 2

Toronto Transit Commission


CONTRACT A29-1

Section 01 50 00
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
Page 15

Structure
Quantity 1 Description
Details
16. Contractor to Supply and/or Install an office for the Contractor with the following:
1
Electric supply, electric lighting, heat, air conditioning, telephone, fire fighting
and first aid as required by the Workplace Safety and Insurance Board and the
Ontario Ministry of Labour and the various Ontario Building and Fire Codes.
Facilities to be installed at or near the site for the duration of the Contract in
2
locations approved by the Commission's Representative.
Temporary buildings shall have 12.7 mm exterior grade plywood for skirting
3
closure and for closing gap between trailer roof and canopy roof.
4
Do not locate any buildings, structures or equipment in a manner that interferes
with survey_ alonq the control line and reference line tanqents.
Remove temporary buildings upon Contract Completion. Restore area to match
5
the existinq planned area.
17. Contractor Supply and/or Install
All cleaning equipment and supplies for office accommodation, change-house
6
and toilets.
All Security (Hardware and Electronic} Equipment.
7
Security Notification Service offsite for unauthorized entry for fire and flood to
8
fire, police and TYSSE.
Daily janitorial services.
9
10
Compact size Public Access Defibrillator
11
Provide new photocopier capable of making multiple copies up to 279 mm x
432 mm { 11" x 17") in size, complete with sorting capabilities.
Paper Supply: Letter size - 50 reams/month, Legal size - 5 reams/month,
12
279 mm x 432 mm { 11" x 17") - 20 reams/month.
Provide empty conduit with pull strings to each proposed voice telephone
13
location terminated with a dedicated duplex junction box. The Commission will
be responsible for ordering the voice services from Bell to ensure effective 4digit dialling and TTC corporate voice mail services can be provided. Bell will
pull station cable and provide faceplates per TTC contract terms.

Provide service entrance cable for Bell services where needed. This service
must
be provided by Bell Technical Services (BTS) to ensure that entrance cable
requirements are met (conductor counts and lightning suppression).

14

15

16
17

Telephone services to serve the needs of the occupants provided by the


Commission. All call charges to the TYSSE office will be paid by the
Commission.
Network Service - highest speed available, fibre optic lines to facility. This is to
be a dedicated service for the exclusive use of the Commission.
The Commission will order the appropriate data service to serve the needs of
occupants with the service billed directly to the Commission for the duration of
the project. This ensures that the network connection can be ordered and
configured as part of the TTC corporate network. The Commission will arrange
for and pay for fibre construction to serve the facility as specified by the Bell
site survey resultinq from the service order.
Washroom supplies including dry change house.
Bottled water deliveries.
Garbage/recyclable removal service.
ADDENDUM 2

Section 01 50 00
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
Page 16

Toronto Transit Commission


CONTRACT A29-1

PROJECT IDENTIFICATION

7.1

The display of signs without the Commission's Representative's written consent is


forbidden.

7.2

Supply and install four (4) signs, each 1980 mm W x 2285 mm H x 20 mm D overlaid
Crezon plywood, mounted approximately 2.5 m above ground on hoarding or separate
posts as appropriate in locations as directed by the Commission's Representative. The
Commission shall provide the graphics for signage in electronic format.

7.3

Supply and install sufficient posts and braces of pressure treated wood with galvanized
nails and screws to withstand wind and other loads.

7.4

Relocate the signs from time to time if required to expedite the Work or to ensure that the
signs remain visible. Refer to Contract Drawings or as directed by the Commission's
Representative for details required on the signs.

7.5

Remove signs upon Contract Completion.

SITE MAINTENANCE

8.1

Maintain the Site and adjacent areas in a clean and orderly condition, free from debris and
other objectionable matter.
Remove rubbish and surplus material, equipment and
structures immediately. If the Site is not cleaned within forty-eight (48) hours after the
Contractor has been instructed to do so, the Commission's Representative may clean the
Site and retain the cost from monies due, or to become due, to the Contractor.

PUBLIC CONVENIENCE AND SAFETY

9.1

Maintain sidewalks and paved areas at and adjacent to the Site in a safe condition
throughout the Contract. Promptly remove ice and snow.

9.2

Keep haul routes free at all times from materials spilled on street surfaces and maintain
streets in clean condition to the satisfaction of the Commission's Representative and the
street authorities.
.1

The Commission's Representative may inspect haul routes, the Site and adjacent premises
daily and may halt hauling operations, withhold payment or carry out such additional
cleaning as necessary, deducting the cost from monies due, or to become due, to the
Contractor.

10

ACCESS AND EGRESS TO SITE

10.1

Access and egress to and from the Site shall be at the locations shown on the Contract
Drawings, or as directed by the Commission's Representative.

10.2

Before commencing any construction operations, provide access roads capable of


withstanding construction equipment traffic, sidewalk crossings, ramps and construction
runways as may be required for access to the Work. Maintain access roads, sidewalks,
ramps, construction runways and decked areas adjacent to the Site in a good and safe
condition throughout the Contract. Remove access roads upon Contract Completion,
unless otherwise noted, and restore area as shown on the restoration Contract Drawings.
ADDENDUM 2

Toronto Transit Commission


CONTRACT A29-1

Section 01 50 00
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
Page 17

10.3

Take precautions to avoid tracking and depositing materials, debris and mud on roads and
on the Commission's property from vehicles and equipment operating to and from the
construction Site, and be responsible for removal of such deposits by brooming and
washing to the satisfaction of the Commission's Representative.

10.4

Keep access routes, sidewalks, Site roads, trailer area, storage areas as well as Work
areas free of ice and snow to maintain safe operating conditions and to maintain progress
of the Work. Remove cleared snow from the Site within twelve (12) hours of a snow fall or
as directed by the Commission's Representative.

11

PARKING

11.1

No cars or trucks shall be parked on the Commission's property without the approval of the
Commission's Representative. The Commission shall not be held responsible for damage
that may occur to any vehicle operated upon or parked upon Commission property.

11.2

Parking will be permitted on Site provided it does not disrupt the performance of Work, Site
safety or the movement of vehicular or pedestrian traffic and is acceptable to the
Commission's Representative.

11.3

Provide thirty (30) parking stalls and two (2) Handicapped stall complete with reserved
signs within 20 m of the Commission's Representative's site office for the exclusive use of
the Commission's Representatives.

12

SITE VISITORS

12.1

During the progress of the Work, afford access to visitors duly authorized by the
Commission's Representative and facilitate inspections or testing which they may wish to
carry out.

12.2

Ensure Site visitors wear appropriate safety apparel.

13

RESTORATION

13.1

Repair and restore any part of any structures and properties broken or damaged by
operations performed under the Contract.

14

SITE HAZARDS

14.1

Hazards and restrictions associated with the Contract are as follows:


.1

Designated Substances, Hazardous Materials and PCBs .

.2

Refer to Section 01 57 19.

END OF SECTION

ADDENDUM 2

l ~ so1sooo.11 1 o

~:

FD~~

cyP:
1
1

@!> ,

e --<0- ---i -- -

-t --

8------- -i-- -"{--4_--- -t- #


I V6/xx) Of-? co I
..l

PARTIAL PLAN

-U---

+D
I

'

~ i----7:x
T l~~I
RD-1

co

V9/xx

I /
I /

I
,

r<v10/xx

~--~--r-eo
0

-t----B

~}V12/xx I

I /
I /

V(v13/xx

RD-2 '

'
I

- - ,--- - - -1- - - - ,--- - - I


,
I

CB

I
'

01---.-,

I" " I ,++


I
I
"- J -4'];
,
-t - - - - ~I
I
n
I
~

~,
(/)
I
FD-2 t
I
'
"I~ I
I"-8'Y
'~

I
I
-t

I
,
I

--8

PARTIAL PLAN
TYPICAL STORM DRAINAGE

VIDEO TAPE INDEX

::2

t-

START TO END POINT

TIME
(SECONDS)

V1TO V2

XX

V3 TO V4

XX

V5 TO V4

XX

VB TO V9

XX

V9 TO V10

XX

(1)

(I)

<0

u::

co#
#
"~

rFLOOR LEVEL

MH/CB

r- --"'-- -STM- -U-~


ELEVATION

# (!?
Toronto Transit
Commission

I~S015000.12I 0

VIDEO TAPE INDEX


TIME
(SECONDS)

START TO END POINT

Q)

co

c
.!!2
u::::

Drawing

Drawn

sc

SANITARY & STORM LINES


STANDARD 'Trt~
FOR VIDEO TAPE INDEX TABLE
I P. LAURIN
e. LABERINTO rheckM. BORAGINA
~
~mm ls18N-OFF l2oo9767/13lso1sooo.121Rev6
Correct

Toronto Transit
Commission

"~ ~ ~

I'
r
'

17.07m(56'-0")
3.58m

,1.42m

4.78m

r- --------------

,-

~ ~
~ ~
~ ~

1.11

r..:

15

C_

---- 1--

1-- ROOM

ltl
17

I;--

1::::1-

H~

~~

p.

3.83m
MAIN
ENTRANCE

2.7m

3.5m

(.()

t()

c--i

(J)

C"J
CX)

.-

N
N

I.T.ROOM

LUNCH

ROOM

1.11

r-- I

. TIGI
I

3.46m

FLOOR PLAN

IGENERAL LAYOUT INFORMATION

3.58m
r

Foyer

.,.:

J-~
900MeJ
r

:=\JliL!~02
co~

Recepllon

~ 7o

Pf~~ I~

"<I'

~P7o

{~.~7~

OJ

m
r--

\Z!

~~ a

10

I
~

gp=so
~ ~~ 0

7' 10"

1fl

S7199<v><v'
R;i

~<Y1o

DOCUMENTC
CONTROl.

t:f_j
Gu

REVIt:W
ROOM

<---------

PI..AN

3.46m
-

tto14 13Q~tyo12

L-

:'*,.:f:"lT

2.39ml 1.4.3m,

D~!!I!!.....

om~~~

___________

a..:r -----------

N.T.S.

IDMil/R

8
TORONTO-YORK SPADINA

SU~AY

EXTENSION

York University Station


Main Slta Office

.....

Conlracl No.

=~

,_............,.

TORONTO lRAN8IT COMMISSION

...,_A'002B-A757o
..........,

1. . .

1.....

S-ar putea să vă placă și