Documente Academic
Documente Profesional
Documente Cultură
DRAFTFinalReport
Preparedby:
February2015
PauldingComprehensiveTransportationPlan
DraftFinalReport
TableofContents
1.0
INTRODUCTION...............................................................................................................................1
2.0PUBLICANDSTAKEHOLDERINPUT.......................................................................................................3
3.0
INVENTORYOFEXISTINGCONDITIONS.........................................................................................4
4.0
ASSESSMENTOFCURRENTANDFUTURENEEDS.........................................................................6
4.1
INTERSECTIONIMPROVEMENTS.............................................................................6
4.2
ROADWAYCAPACITYIMPROVEMENTS..................................................................7
4.3
NEWROADWAYCONNECTIONS...........................................................................13
4.4
TRANSITANDTRAVELDEMANDMANAGEMENT.................................................13
4.5
PEDESTRIANFACILITIES,BICYCLEFACILITIESANDMULTIUSETRAILS.................15
4.6
BRIDGES................................................................................................................17
5.0
PROJECTCOSTESTIMATING........................................................................................................19
6.0
PROJECTPRIORITIZATION............................................................................................................20
7.0
8.0
6.1
INTERSECTIONIMPROVEMENTS..........................................................................20
6.2
ROADWAYCAPACITYIMPROVEMENTS................................................................23
6.3
NEWROADWAYS..................................................................................................24
6.4
TRANSITANDTRAVELDEMANDMANAGEMENT.................................................25
6.5
PEDESTRIANFACILITIES,BICYCLEFACILITIES,ANDMULTIUSETRAILS................25
REVENUEFORECASTING..............................................................................................................29
7.1
FEDERALFUNDING................................................................................................30
7.2
STATEFUNDING....................................................................................................30
7.3
LOCALFUNDING....................................................................................................31
PROJECTRECOMMENDATIONSANDIMPLEMENTATIONPLAN................................................32
8.1
IMPLEMENTATIONPLANSCENARIOMODELING..................................................39
9.0
TRANSITANDTRAVELDEMANDMANAGEMENTRECOMMENDATIONS.................................41
10.0
ACCESSMANAGEMENTCORRIDORS..........................................................................................43
11.0
BICYCLEANDPEDESTRIANRECOMMENDATIONS......................................................................45
Page ii
February2015
PauldingComprehensiveTransportationPlan
DraftFinalReport
11.1
PEDESTRIANFACILITIES.........................................................................................47
11.2
BICYCLELANES......................................................................................................49
11.3
MULTIUSETRAILS................................................................................................49
11.4
FUNDINGFORRECOMMENDEDBICYCLEANDPEDESTRIANFACILITIES..............50
12.0
BRIDGERECOMMENDATIONS.....................................................................................................52
13.0
FREIGHTRECOMMENDATIONS...................................................................................................55
14.0
CONCLUSIONS...............................................................................................................................57
ListofFigures
Figure1.0:CTPDevelopmentProcess...........................................................................................1
Figure8.0:FiscallyUnconstrainedProjects..................................................................................34
Figure8.1:FiscallyConstrainedImplementationPlan.................................................................35
Figure11.0:RecommendedBicycleandPedestrianProjects......................................................46
ListofTables
Table4.0:UniverseofIntersectionOperationsNeeds...................................................................6
Table4.2:NewRoadwayConnectionNeeds................................................................................13
Table4.3:NewTransitorShuttleServiceNeeds..........................................................................14
Table4.4:NewParkandRideLotNeeds......................................................................................14
Table4.5:VanpoolNeeds.............................................................................................................14
Table4.1:AccessManagementCorridors....................................................................................15
Table4.6:SidewalkSegmentNeeds.............................................................................................15
Table4.7:PotentialTrailheadsontheSilverCometTrail............................................................17
Table4.8:MultiUseTrailNeeds...................................................................................................17
Table4.9:BicycleLaneandExtendedShoulderNeeds................................................................17
Page iii
PauldingComprehensiveTransportationPlan
DraftFinalReport
Table4.10:BridgeswithReplacementandMaintenance/RehabilitationNeeds........................17
Table6.0:IntersectionImprovementPrioritizationResults.........................................................20
Table6.1:RoadwayCapacityImprovementPrioritizationResults..............................................23
Table6.2:NewRoadwaysImprovementPrioritizationResults...................................................24
Table6.3:TransitandTravelDemandManagementImprovementsPrioritizationResults........25
Table6.4:PedestrianFacilitiesPrioritizationResults...................................................................26
Table6.5:OnStreetBicycleFacilitiesPrioritizationResults........................................................27
Table6.6:MultiUseTrailFacilitiesPrioritizationResults............................................................28
Table7.0:TotalEstimatedFundingbyImplementationPhaseandSource.................................30
Table8.0:FiscallyUnconstrainedProjectList..............................................................................32
Table8.1:PhaseIShortRangeImplementationPlan(20152019)..........................................36
Table8.2:PhaseIIMidRangeImplementationPlan(20202030)............................................37
Table8.3:PhaseIIILongRangeImplementationPlan(20312040).........................................38
Table8.4:RoadwayCapacityImprovementScenarios.................................................................39
Table8.5:RoadwayCapacityScenariosModelingResults...........................................................40
Table11.0:PrioritySidewalkRecommendations.........................................................................47
Table11.1:RecommendedBicycleLanes.....................................................................................49
Table11.2:RecommendedMultiUseTrails.................................................................................50
Table12.0:BridgeProject/ImprovementRecommendations......................................................53
Table14.0:RecommendedProjectImplementationPlan............................................................57
Page iv
PauldingComprehensiveTransportationPlan
DraftFinalReport
Appendices
AppendixAPublicOutreachSummary
AppendixBInventoryofExistingConditions
AppendixCAssessmentofCurrentandFutureNeeds
AppendixDProjectCostEstimates
AppendixEProjectPrioritization
Page v
PauldingComprehensiveTransportationPlan
DraftFinalReport
1.0 INTRODUCTION
The Paulding Comprehensive Transportation Plan (CTP) Update is longrange plan with a
planning horizon year of 2040. The initial CTP for unincorporated Paulding County and the
CitiesofBraswell,Dallas,andHiramwascompletedin2008.ThisCTPUpdatebuildsuponthe
foundationofthe2008CTPandpresentsshortrange,midrangeandlongrangesolutionsfor
transportation improvements based on the level of need, available funding, and stakeholder
andpublicinput.
The workflow of the CTP Update is presented below in Figure 1.0. The CTP is a multistep
processbeginningwithaninventoryofexistingconditions,whichhelpsidentifytransportation
needs in the needs assessment phase. The process concludes with project prioritization,
revenueforecastingandprojectphasing.Throughouttheprocess,stakeholderandpublicinput
fromavarietyofsourceshavebeenincorporated,asdetailedinFigure1.0.
Figure1.0:CTPDevelopmentProcess
Page 1
PauldingComprehensiveTransportationPlan
DraftFinalReport
This Final Report is the culmination of a process initiated in August of 2013. It provides an
overview of earlier project phases, including the existing conditions analysis and needs
assessment. This consists of a summary of key findings from previous reports, including the
InventoryofExistingConditionsandtheAssessmentofCurrentandFutureNeeds,whichhave
informedtherecommendationscontainedinthisdocument.
This main focus of this document is project prioritization, revenue forecasting, and the
development of a fiscally constrained implementation plan of recommended projects. In
addition to a recommended project list and phasing plan for roadway improvements, this
reportalsoincludesthefinalrecommendationsforavarietyoftransportationneedareas.This
includes recommendations for transit service, travel demand management, bridge
maintenance,accessmanagementcorridors,freighttransportationandbicycleandpedestrian
facilities.
Page 2
PauldingComprehensiveTransportationPlan
DraftFinalReport
2.0PUBLICANDSTAKEHOLDERINPUT
Publicandstakeholderinputhavebeenintegraltoidentifyinglocalprioritiesfortransportation
improvements. Input was gathered through public meetings, joint stakeholder and technical
committee meetings and through prioritization surveys given to the public and committee
members.Theseriesofmeetingsaboutprioritiesandrecommendationsisdescribedbelow.A
summaryoftheentireoutreachprocesssupportingtheCTPcanbefoundinAppendixA.
A public meeting was held on August 14th, 2014 at the Dallas Civic Center. The focus of this
meeting was to get public input on the prioritization of identified transportation needs. Each
attendeewasgivenaprioritizationsurveyandwasencouragedtoparticipateindotexercisesin
which they could vote on the most critical transportation projects within the county. Input
stations were set up focusing on roadway capacity needs, new roadway connections, multi
modalneeds,andintersectionneeds.Theprioritizationsurveywasalsomadeavailableonthe
projectswebsiteandatkioskstationsatlocallibraries.Thepublicwasinformedofthepublic
meeting, online survey, and library kiosks via a countywide mailer. This mailer generated a
highlevelofpublicengagement,interest,andsurveyresponses.Asummaryofthismeetingis
providedinAppendixAofthisdocument.
A joint Technical and Stakeholder Committee meeting was held on October 23, 2014. At this
meetingfeedbackwasreceivedfromthecommitteemembersonprojectprioritizationresults
andonreducingthenumberofproposedprojectstoamorefiscallyfeasiblelist.Theresultsof
the prioritization scoring were presented to the group for roadway capacity projects,
intersection improvements, and new roadway connections. A postmeeting survey was
distributedtocommitteememberstoprovideadditionalinformationonprojectprioritization.
AsummaryofthemeetingandsurveyresultsarealsoprovidedinAppendixA.
Public and stakeholder input were used to help prioritize transportation improvements. A
score for public and committee support was factored into the overall priority score for each
transportation need area. This includes roadway capacity, intersection improvements, new
roadway connections, transit and travel demand management, and bicycle and pedestrian
facilities. The results of the public and stakeholder outreach highlighted several projects and
areasofhighpriority.US278/SR6fromSRBusiness6totheCobbCountylinewasidentifiedas
a roadway that is a priority for improvement. For new location roadways, the West Dallas
Bypass was favored. However, participants emphasized that investment in existing roadways
wasmoreofaprioritythannewlocationroadways.Keyintersectionsthatwereprioritizedfor
improvement were US 278/SR 6 at SR 92 and East Memorial Drive at SR Business 6. The
additionofsidewalkswasseenasahighpriorityandmaintainingtheavailablePauldingTransit
servicewasalsoapriority.
Page 3
PauldingComprehensiveTransportationPlan
DraftFinalReport
3.0 INVENTORYOFEXISTINGCONDITIONS
The first major component of the CTP planning process was an assessment of existing
conditionsinthecounty.ThiswasusedtoupdatethedatausedinthepreviousCTPtoaccount
foranychangesthatmayhaveoccurredsince2008.Anumberofconditionswereexamined,
including transportation, environmental, demographic, and land use characteristics. These
factorshavebeenexaminedindetailintheInventoryofExistingConditionsReport(Appendix
B).Thissectionpresentsasummaryofkeyfindingsfromthisreportthathavehadanimpact
on identifying transportation needs and developing potential transportation improvements.
Relevantkeyfindingsareasfollows:
A comparison of 2015 and 2040 level of service (LOS) ratings from the regional travel
demandmodelshowasignificantdegradationof
the transportation network, particularly within Levelofservice(LOS)isaqualitymeasure
describingoperationalconditionsand
the eastern half of the county. This is congestionsonaroadwayingeneral
particularity evident on SR 61 and other roads terms.Lettersdesignateeachlevel,fromA
that provide a northsouth connection to toF,withLOSArepresentingthebest
Douglas County, and on SR 120, SR 360 and operatingconditionsandLOSFtheworst.
other roads that provide an eastwest
connectionwithCobbCounty.Roadsthatserve
Dallasareprojectedtoworseninfutureyears.
To further assess existing congestion levels and travel delay, an analysis of realtime
traffic data, called NAVTEQ, was conducted. Both the AM and PM peak period results
show similarly congested conditions on many of the same corridors as the regional
model data. Results for the PM peak period, however, depict more widespread and
continuous congestion along the same
roadways.
Page 4
PauldingComprehensiveTransportationPlan
DraftFinalReport
ThemostprominentcommercialretailcorridoristheUS278/SR6corridorfromthe
CobbCountylinetoUS61.CommercialusesarealsolocatedinDallas,alongtheSR120
corridor,andatintersectionsthroughoutthecounty.Becauseoftheamountofnumber
ofaccesspointsassociatedwiththeseusessafetyimprovementsmaybeconsidered
alongthesecorridors.
WhileridershipofGRTAserviceshastrendeddownoverthepastfewyears,thereare
somedemographiccharacteristicswithinPauldingCountythatsuggestthattheXpress
service may grow in ridership once the economy rebounds. Throughout the county,
there are concentrations of transit dependent residents that rely on public
transportationoptionsforaccesstoworkandothertrips.
PlaceholderAccomplishmentsofthe2008CTP
Page 5
PauldingComprehensiveTransportationPlan
DraftFinalReport
4.0 ASSESSMENTOFCURRENTANDFUTURENEEDS
Following the inventory of existing conditions the next phase identified transportation needs
for intersection improvements, roadway capacity improvements, new roadway connections,
bicycleandpedestrianimprovements,andtransitandtraveldemandmanagementoptions.A
detailed review of these needs is provided in the Assessment of Current and Future Needs
Report(AppendixC).Asummaryofthekeyfindingsinthisreportaredetailedinthissection.
4.1
IntersectionImprovements
Atotalof39operationalneedshavebeenidentifiedwithintheneedsassessmentandarepresented
belowinTable4.0.Thesehavebeenidentifiedthroughacombinationofstakeholderandpublic
input,thepreviousCTPandexistingconditionsanalysis.Existingconditionsanalysisfocusedon
intersectionswithhighcongestionlevels,freighttrafficandcrashrates.
Table4.0:UniverseofIntersectionOperationsNeeds
ExistingConditionsAnalysis
Project
ID
O1
O2
O3
O4
O5
O6
O7
O8
O9
O10
O11
O12
O13
O14
O15
O16
O17
O18
O19
IntersectionName
SR120(CharlesHardyParkway)SRBusiness6
(AtlantaHighway)
SR92EastPauldingDrive
SR120(BuchananHighway)SR101
US278/SR6(JimmyCampbellParkway)
MountOlivetLoop
SR61(CartersvilleHighway)MountMoriah
Road
SR61(CartersvilleHighway)ShadyGrove
ChurchRoad/HighShoalsRoad
SR61(VillaRicaHighway)HartRoad
SR61(VillaRicaHighway)OldVillaRicaRoad
SR61(VillaRicaHighway)VernoyAikenRoad
SR61(VillaRicaHighway)WinndaleRoad
HiramSudieRoadDavisMillRoad
SR92(HiramAcworthHighway)OldBurnt
HickoryRoad
BurntHickoryRoadBrownsville
Extension/StoutParkway
RosedaleDriveMetromontRoad
EastPauldingDriveBrooksRackleyRoad
US278/SR6(JimmyLeeSmithParkway)SR
Business6(AtlantaHighway)
US278/SR6(JimmyLeeSmithParkway)Bill
CarruthParkway
US278/SR6(JimmyCampbellParkway)
CadillacParkway
US278/SR6(JimmyCampbellParkway)Old
HarrisRoad
Page 6
Safety
Freight
Delay
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Stakeholder
Committee
Public
Input
X
X
X
2008
CTP
X
X
X
PauldingComprehensiveTransportationPlan
DraftFinalReport
Project
IntersectionName
US278/SR6(JimmyCampbellParkway)SR61
(VillaRicaHighway)
US278/SR6(JimmyCampbellParkway)SR
120(BuchananHighway)
WestMemorialDriveSRBusiness6
(BuchananStreet)
SR61(ConfederateAvenue)SRBusiness6
(WestMemorialDrive)
EastMemorialDriveLegionRoad
SRBusiness6(MerchantsDrive)LegionRoad
EastMemorialDriveBusinessSR6
(MerchantsDrive)
US278/SR6(JimmyLeeSmithParkway)
HiramPavilionS
US278/SR6(JimmyLeeSmithParkway)
HiramPavilionN
US278/SR6(JimmyLeeSmithParkway)
DepotDrive
SRBusiness6OldHarrisRoad
SRBusiness6CoachBobbyDoddRoad
(MaclandRoad)SRBusiness6(Merchants
Drive)
SR101GoldMineRoad
SR101HollySpringsRoad
SR101OldYorkvilleRoad
SR92RosedaleDrive
SR92HiramCrossingShoppingCenter
SR92US278/SR6(JimmyLeeSmith
Parkway)
SR92PauldingCommonsShoppingCenter
O20
O21
O22
O23
O24
O25
O26
O27
O28
O29
O30
O31
O32
O33
O34
O35
O36
O37
O38
O39
ExistingConditionsAnalysis
2008
Stakeholder
Public
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Source:ARC,GDOT,Jacobs
4.2
RoadwayCapacityImprovements
Based on the roadway segment analysis, and exempting roadways already programmed for
widening,thereareeighteensegmentsinneedofadditionalcapacityinthecounty.Table4.1
liststheroadwaysthathavebeenidentifiedforpotentialadditionalcapacity.Oftheseeighteen,
eightwereidentifiedasneedingimprovementsbythe2008CTP,thestakeholdercommittee,
and/orthepublicandarecurrentlyoperatingatLOSEorF.Theseeightroadwaysegmentsare
projectedtooperateatthislevelin2030.Theseinclude:
DallasAcworthHighwayfromSR92toEastPauldingDrive
DallasAcworthHighway/MemorialDrivefromEastPauldingDrivetoSRBusiness6
US278/SR6fromSRBusiness6toCobbCountyLine
SR101/113fromCarrollCountyLinetoSR120(BuchananHighway)
SR61(VillaRicaHighway)fromtheDouglasCountyLinetoRidgeRoad
SR61(CartersvilleHighway)fromSRBusiness6toOldCartersvilleRoad
Page 7
PauldingComprehensiveTransportationPlan
DraftFinalReport
HiramSudieRoadfromSR61toSR92
EastPauldingDrivefromSR92toSR120
Page 8
PauldingComprehensiveTransportationPlan
DraftFinalReport
From
To
Improvement
Roadway Volume
Ratio/LOS
2015
2030
2008
CTP
Stakeholder
Comm.
Public
Input
2015
2030
2040
2040
Widento4lanes
0.96/E
0.97/E
1.05/F
SR92
Cedarcrest
Cobb County
Road/DA
Line
Hwy
SR92
SR120
US
278/SR
Widento4lanes
Bus6
0.93/E
0.92/E
0.96/E
SR92
US278/SR6
HiramSudie
Road
Widento4lanes
0.98/E
0.99/E
1.10/F
SR92
HiramSudie
Rd
Douglas
CountyLine
Widento6lanes
1.18/F
0.90/E
1.03/F
E. Paulding
Widento4lanes
Drive
0.94/E
1.10/F
1.22/F
Dallas Acworth
SR92
Highway
Dallas Acworth
E. Paulding
Highway/Memori
SRBus6
Drive
alDrive
Widento4lanes
1.11/F
1.24/F
1.31/F
SR
Bus US 278 (W of
MemorialDr
6/BuchananSt
Dallas)
Widento4lanes
0.97/E
1.17/F
1.34/F
US 278 (E of
Widento4lanes
Dallas)
0.97/E
1.46/F
1.72/F
SR 6/Merchants Memorial
Dr./AtlantaHwy. Drive
Page 9
January2015
PauldingComprehensiveTransportationPlan
DraftFinalReport
From
To
Improvement
Roadway Volume
Ratio/LOS
2015
2030
2040
2015
2030
2008
CTP
Stakeholder
Comm.
Public
Input
2040
US278/SR6
SR61
SRBus6
Widento6lanes
0.83/D
1.12/F
1.25/F
US278/SR6
SRBus6
CobbCounty
Widento6lanes
0.89/E
0.99/E
1.05/F
SR101/113
Carroll
CountyLine
SR
120
(Buchanan
Widento4lanes
Hwy)
0.92/E
1.14/F
1.28/F
Widento4lanes
0.94/E
1.02/F
1.11/F
Widento4lanes
0.89/E
1.08/F
1.16/F
0.93/E
0.88/E
1.03/F
SR
(Cartersville
Highway)
61
Widento4lanes
0.92/E
1.08/F
1.15/F
SR
(Cartersville
Highway)
61
0.83/D
0.99/E
1.09/F
5,000
Page 10
SRBus6
RidgeRoad
Old
Cartersville
Road
20,700 26,400
January2015
PauldingComprehensiveTransportationPlan
DraftFinalReport
From
To
Improvement
Roadway Volume
Ratio/LOS
SR
(Cartersville
Highway)
61
2015
2030
2040
2015
2030
2008
CTP
Stakeholder
Comm.
Public
Input
2040
Widento4lanes
0.75/D
0.96/E
1.04/F
SR61
Bartow
CountyLine
Widento4lanes
0.77/D
1.04/F
1.08/F
3,000
11,300 20,300
RidgeRoad
DallasNebo
Road
SR92
Widento4lanes
0.76/D
1.19/F
1.30/F
9,600
17,500 19,700
NeboRoad
DallasNebo
Road
SR92
Widento4lanes
0.96/E
1.17/F
1.31/F
Bakers
Road
RidgeRoad
Douglas
CountyLine
Widento4lanes
0.95/E
1.11/F
1.28/F
Sweetwater
ChurchRoad
Douglas
CountyLine
SR92
Widento4lanes
0.81/D
1.23/F
1.36/F
HiramSudie
Road
SR61
SR92
Widento4lanes
1.00/F
1.25/F
1.40/F
CedarcrestRoad
Harmony
Grove Church US41
Road
Widento4lanes
0.67/C
0.68/C
0.75/D
9,400
Dabbs
Road
Bridge
Bridge
Page 11
14,900 16,300
January2015
PauldingComprehensiveTransportationPlan
DraftFinalReport
From
To
Improvement
Roadway Volume
Ratio/LOS
Oak
Drive
Glen
2015
2030
2008
CTP
Stakeholder
Comm.
Public
Input
2015
2030
2040
2040
Widento4lanes
0.37/B
0.53/C
0.42/B
14,500 9,400
13,200
CedarcrestRoad
SR92
East
Drive
West
of
Brooks
SR120
RackleyRd
Widento4lanes
0.90/E
1.04/F
1.17/F
Dallas
Acworth
Highway
Widento4lanes
0.97/E
1.09/F
1.27/F
7,500
Paulding
BoboRoad
18,100 21,200
Source:ARCTDM,Jacobs,PauldingCounty.
*Previouslyprogrammedforimprovements(20142019TIP)
**Plannedforlongrangeimprovements(Plan2040RTP)
Page 12
SR120
January2015
PauldingComprehensiveTransportationPlan
DraftFinalReport
4.3
NewRoadwayConnections
An assessment of travel patterns indicates that the most demand for new investment in
vehiculartransportation,includingnewroadwayconnectionsandadditionalcapacity,willexist
primarily in the eastern portion of Paulding County or projects that facilitate eastwest
movement.Currentandprojectedpopulationandemploymentdensitiessupportthatneedas
theyareprojectedtooccurprimarilywithintheeasternportionofthecounty.
The growing percentage of commutes taking place within Paulding County will increase the
needforadditionalcapacityonalreadyheavilytravelledroads.Asexistingroadwaysbecome
congested, drivers may be well served by additional roadway options that can meet their
connectivity needs. The roads that connect the City of Dallas, SR Business 6 and Jimmy
Campbell Parkway, experience conflicts between through movement and local trips. New
roadwayalternativescouldhelptoseparatethroughtrafficfromlocaltrafficandaddressthis
latentmobilityneed.
Basedontheanticipatedtraveldemandandlackofefficientdirectconnectionsbetweenorigins
anddestinations,fivenewroadwayconnectionswereidentifiedaspotentialneeds.Theseare
listedbelowinTable4.2,whichindicatesthesourceoftheidentifiedneed.
Table4.2:NewRoadwayConnectionNeeds
Connection Name
WestDallasBypass
EastDallasBypass
HiramParallelRelieverSouth
HiramParallelRelieverNorth
CedarcrestRdSR61Connector
From
SR61
SR6/US278
SR92
SR92
SevenHillsBlvd
To
SR6/US278
SR61
MetromontRoad
LakeRoad
SR61
2008
CTP
X
Stakeholder
Committee
X
X
X
Public
Input
X
Source:Jacobs,2008CTP
4.4
TransitandTravelDemandManagement
Transit needs identified within the Assessment of Current and Future Needs Report were
grouped in four distinct areas: new transit improvements, locations for new shuttle service,
locationsfornewparkandridelotsorvanpoolloading,andthecontinuationofhumanservices
transit.Theneedfornewserviceinthesefourareaswasevaluatedintermsofinclusioninthe
2008CTP,supportfortheimprovementfromtheStakeholderCommittee,confirmationofthe
needintheexistingconditionsanalysis,andinputregardingtheimprovementfromthegeneral
public.Transitandtraveldemandmanagementneedsaredetailedinthefollowingthreetables,
Tables4.3,4.4,and4.5.
Page 13
PauldingComprehensiveTransportationPlan
DraftFinalReport
Table4.3:NewTransitorShuttleServiceNeeds
NewService
PauldingNorthwestAtlantaAirport
PauldingCountyGovernmentComplex
WellStarPauldingHospital
ChattahoocheeTechnicalInstitute
DallasCirculator
HiramCirculator
FixedRouteBusfromPauldingNorthwestAtlanta
AirporttoDallas/HiramalongUS278/SR6
ArterialBRT/HOVSR120CharlesHardyPkwy
Arterial BRT/ HOV/ or Truck Preferred Lanes US
278/SR6
ArterialBRT/HOVSR92/DallasAcworthHwy
ExtendGRTAviaSR6toDallas
New GRTA Service to Marietta (CCT Hub) via SR
120
NewGRTAServicetoCumberlandviaSR360
ExistingConditions
Analysis
Travel
Demographics
Trends
2008
CTP
Stakeholder
Committee
Public
Input
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Source:Jacobs,2008CTP
Table4.4:NewParkandRideLotNeeds
NewParkandRideLots
ExistingConditionsAnalysis
Travel
Demographics
Trends
2008
CTP
Stakeholder
Committee
X
X
X
X
X
X
X
PauldingNorthwestAtlantaAirport
CrossroadsCommunityCenter
US278andSeaboardDrive
US 278 and SR 120 (Charles Hardy
Parkway)
Public
Input
Source:Jacobs,2008CTP
Table4.5:VanpoolNeeds
VanpoolNeeds
CrossroadsCommunityCenter
SR120andUS278
DevelopmentofPauldingCountyVanpool
Program
Development of CobbPaulding County
VanpoolLocation
NewGeorgiaCommunity
ExistingConditionsAnalysis
Travel
Demographics
Trends
2008
CTP
Stakeholder
Committee
Public
Input
X
X
X
X
X
X
Source:Jacobs,2008CTP
Theneedsassessmentidentifiedtheneedforaccessmanagementtreatmentsoneightpriority
corridorswithinthecounty.ThesearedetailedbelowinTable4.1.Themajorityofthesewere
identifiedinthepreviousplanandhavebeenconfirmedtobeinneedofaccessmanagement
throughananalysisofexistingconditions,thatexaminedsafety,congestionanddevelopment
characteristics.RecommendationsforthesecorridorsareprovidedinSection11ofthisreport.
Page 14
PauldingComprehensiveTransportationPlan
DraftFinalReport
Table4.1:AccessManagementCorridors
Roadway
From
SR120(CharlesHardyPkwy)
CobbCountyLine
SR360(MaclandRoad)
CobbCountyLine
SR92
BillCarruthPkwy
Bill Carruth Pkwy Ext. (East
HiramBypass)
RosedaleDrive
US278/SR6
SRBus6
Previous
Plan
To
DouglasCountyLine
US278/SR6
US278/SR6
SR 120 (Charles
HardyPkwy)
CobbCountyLine
SR92
BillCarruthParkway
SR92
CobbCountyLine
US278/SR6(Eastof
Dallas)
ExistingConditions
Analysis
Land
Crash Delay
Use
X
X
X
X
X
X
US278/SR6
US278/SR6
SR120
US278/SR6(Westof
Dallas)
X
X
X
X
X
X
Source:Jacobs,2008CTP
4.5
PedestrianFacilities,BicycleFacilitiesandMultiUseTrails
Needswereidentifiedforbicycleandpedestrianfacilitiesincludingsidewalksegments,multi
use trails, pedestrian crossings, trailheads, bicycle lanes, and extended bicycle shoulders. A
detailedsidewalkanalysiswasconductedthatfocusedononequartermileradiiaroundmajor
pedestrian destinations, such as park entrances, commercial centers, schools, colleges,
libraries,SilverCometTrailaccesspointsandtheGRTAparkandridelot(onequartermileis
considered a comfortable walking distance). A detailed Silver Comet Trail analysis was
conductedandidentifiedtheneedfornewaccesspointsalongtheSilverCometTrail.Bicycle
andpedestrianneedsaredetailedinthefollowingTables4.6,4.7,4.8and4.9below.
Table4.6:SidewalkSegmentNeeds
Map
Key
Sidewalk
Segment
1
2
BakersBridgeRoad
BrownsvilleRoad
CedarcrestRoad
CedarcrestRoad
5
6
CedarcrestRoad
CenterStreet
RidgeRoad
SR92
FloydShelton
Elementary
HarmonyGrove
ChurchRoad
CobbCountyLine
SeaboardAvenue
ClontsRoad
WileyDrive
ColbertRoad
CowboyPath
AbneyElementary
EastPaulding
HomePark
10
11
CrossroadsChurch
Road
DepotDrive
Page 15
From
To
CharityDrive
SweetwaterPass
TheShoppesat
CedarcrestCommons
X
X
ArthurHillsDrive
HighcrestDrive
SR92
HalHutchens
Elementary
LegacyPointeDrive
ForestHillsDrive
WintervilleDrive
YorkvillePark
RosedaleDrive
US278/SR6
SourceofNeedsIdentification
Pedestrian
Stakeholder
Public
Analysis
Committee
Input
PauldingComprehensiveTransportationPlan
DraftFinalReport
Map
Key
Sidewalk
Segment
12
DueWestRoad
13
EastFosterAvenue
14
EastPauldingDrive
15
EastPauldingDrive
16
17
18
19
GravesRoad
HiramSudieRoad
HollySpringsRoad
LesterDrive
DallasAcworth
Highway
DallasCityPark
LostMeadows
Drive
DallasAcworth
Highway
GravesRoadSpur
SR61
WoodwindDrive
DallasCityPark
20
MaclandRoad
SR92
21
22
24
MeinMitchellRoad
MetromontRoad
MulberryRock
Road
MustangDrive
25
NeboRoad
26
27
28
29
30
NeboRoad
OakStreet
OldVillaRicaRoad
OldVillaRicaRoad
PineShadowsDrive
31
PineValleyRoad
32
PineValleyRoad
33
34
35
36
37
RidgeRoad
RidgeRoad
RidgeRoad
ScogginsRoad
SeaboardAvenue
38
SouthMainStreet
39
SR101
40
SR61
RidgeRoad
US278/SR6
DokeCochran
Road
HeritageWay
NeboElementary
School
DallasNeboRoad
SR92
SR61
SR61
NeboRoad
TaylorFarmPark
West
TaylorFarmPark
East
DallasNeboRoad
HughesRoad
HughesRoad
SR61
TowneParkDrive
Constitution
Boulevard
CrossroadsChurch
Rd
OscarWay
41
SR92
HardyCircle
42
SR92
43
US278/SR6
WaysideLane/Clear
US278/SR6
CreekDrive
WestMemorial
BagbyPath
Drive
JADobbinsMiddle
WilliamsLakeRoad
School
23
44
45
46
Page 16
From
OldBurntHickory
Road
DepotDrive
To
AutumnCreekDrive
HardeeStreet
HopeDrive
Mt.TaborPark
GravesRoad
SouthernOaksDrive
Highway101
SR6
SR120(CharlesHardy
Pkwy)
CountryVillageDrive
RosedaleDrive
X
X
SR61
DonbieDrive
PineShadowsDrive
SwanDrive
SeaboardAvenue
IvyTraceLane
StationDrive
SmithFergusonRoad
X
X
X
X
X
X
X
NorthviewLane
WinterParkLane
AustinBridgeRoad
RidgeRunDrive
FarmStreet
SugarMillDrive
PowderSpringsStreet
X
X
X
X
X
X
X
X
SeaboardDrive
RunnellRoad
KirkDrive
EastPauldingMiddle
School
RoyalSunsetDrive
CleburneParkway
PooleElementary
School
PauldingMemorial
Hospital
FourOaksDrive
SourceofNeedsIdentification
Pedestrian
Stakeholder
Public
Analysis
Committee
Input
PauldingComprehensiveTransportationPlan
DraftFinalReport
Source:Jacobs
Table4.7:PotentialTrailheadsontheSilverCometTrail
SourceofNeedsIdentification
SilverCometAnalysis
Stakeholder Committee
Location
IsleyStamperRoad
BillCarruthParkway(EastLoop)
MetromontRoad
ThompsonRoad/CoppermineRoad
BillCarruthParkway(WestLoop)
X
X
X
X
X
PublicInput
Source:Jacobs
Table4.8:MultiUseTrailNeeds
NewTrail
Location
NorthofHulseyTownRoad
NearPegColeBridgeRoad
StricklandParkConnection
SouthMainandUS278(Dallas)
BetweenPauldingNorthwestAtlanta
AirportandHulseyTownRoad
BetweenGeorgiaParkwayandPegCole
BridgeTrail
BetweenWeddingtonRdandStrickland
Park
BetweenGovernmentComplexand
SeaboardTrailhead
SourceofNeedsIdentification
SilverComet Stakeholder Public
TrailAnalysis Committee
Input
Source:Jacobs
Table4.9:BicycleLaneandExtendedShoulderNeeds
PedestrianCrossing
SourceofNeedsIdentification
Stakeholder
Public
Committee
Input
Location
MulberryRockRoad
NearSR61
RidgeRoad
BetweenBakersBridgeRoadandSR61
SR 61 (Cartersville
BetweenMt.MoriahRoadandDabbsBridgeRoad
Hwy)
Between Harmony Grove Church Road and Seven Hills
CedarcrestRoad
Boulevard
SR61
BetweenRidgeRoadandGeorgianParkway
X
X
Source: Jacobs
4.6
Bridges
To identify bridge needs within the county this study coordinated with the GDOT Office of
Bridges and Structures and Paulding County staff to identify bridges in need of replacement
rehabilitationormaintenance.Theanalysisofbridgedataidentifiedeightbridgesasbeingin
needofreplacementorrehabilitation.ThesearedetailedbelowinTable4.10below.
Table4.10:BridgeswithReplacementandMaintenance/RehabilitationNeeds
Structure
ID
FacilityCarried
Page 17
Feature
Intersected
Sufficiency
Rating
BridgeNeeds
PauldingComprehensiveTransportationPlan
DraftFinalReport
Structure
ID
FacilityCarried
22350120
22350400
22300260
22350290
22300250
22350450
22350640
22350110
WillowSpringsRoad
MorningsideDrive
DallasAcworth
Highway
PineValleyRoad
DallasAcworth
Highway
DueWestRoad
CarringtonLake/
OberlochenWay
Mt.OlivetRoad
Feature
Intersected
Sufficiency
Rating
SilverCometTrail
LickLogCreek
15.88
49.01
Replacementcompleted12914
Replacement
PickettsMillCreek
49.95
SettobeginCSTin201516
SweetwaterCreek
56.28
Replacement/Maintenance/Rehabilitation
PossumCreek
57.42
SettobeginCSTin201516
PickettsMillCreek
SweetwaterCreek
Tributary
Pumpkinvine
Creek
60.64
Maintenance/Rehabilitation
Maintenance/Rehabilitationperformedin2009,
tobemonitoredforfutureneeds
61.50
64.81
BridgeNeeds
Replacement/Maintenance/Rehabilitation
Source:GDOT,PauldingCounty
Page 18
PauldingComprehensiveTransportationPlan
DraftFinalReport
5.0 PROJECTCOSTESTIMATING
To assist with project prioritization and development, phased project implementation plan
planninglevelcostestimatesweredevelopedforpotentialprojects.Detailedcostestimates
for each proposed transportation improvement can be found in Appendix D. The Atlanta
Regional Commissions (ARC) Planning Level Cost Estimation Tool was used to develop these
costestimates.Asexplainedinitsusermanual,theARCtoolusesthefollowingten,standard
andcustomaryelementstoascertainplanninglevel,longrangecostestimates:
Freewaywidening
Managedlanes(HOV,HOT,TOT)
Generalpurposeroadwaycapacity
Interchangesandgradeseparations
Intersectionimprovements
Bridges
Nonmotorizedelements(sidewalks,trails,bikelanes)
Walls(soundbarrier,retaining)
IntelligentTransportationSystems(ITS)
RightofWay(ROW)acquisition
TheARCtoolbasesitscostsinsimilarprojectsthathavegonetolet.Additionalcostsorcost
savings may be determined during later phases of project development. For the purposes of
project phasing project costs have been estimated for the beginning year of each
implementationphase(2015,2020,2031).
Page 19
PauldingComprehensiveTransportationPlan
DraftFinalReport
6.0 PROJECTPRIORITIZATION
With limited funding available to address transportation needs within the county, proposed
improvements were prioritized to identify the most pressing transportation needs in the
county. A detailed prioritization analysis was conducted that examined many key factors.
These factors included a wide range of quantitative and qualitative measures. This section
providesanoverviewoftheprioritizationmeasures,scoring,andweighting,andisorganizedby
improvement type. This section includes a description of the overall scoring results. The
completeprioritizationscoringforeachproposedimprovementhasbeenincludedinAppendix
E.Theserankingswereusedtoassistwithdevelopingthefiscallyconstrainedprojectlistand
phasingplan.
6.1
IntersectionImprovements
Project
ID
1
2
2
3
4
O38
O1
O20
O17
O36
Page 20
IntersectionLocation
SR92(HiramAcworthHighway)atUS278/SR6(JimmyCampbellParkway)
SR120(CharlesHardyParkway)atSRBusiness6(AtlantaHighway)
US278/SR6(JimmyCampbellParkway)atSR61(VillaRicaHighway)
US278/SR6(JimmyCampbellParkway)atBillCarruthParkway/SR120
SR92(HiramAcworthHighway)atRosedaleDrive
Overall
Priority
Score
29
28
28
27
26
PauldingComprehensiveTransportationPlan
DraftFinalReport
Priority
Ranking
Project
ID
5
5
5
6
6
7
7
7
8
8
9
10
10
11
11
12
13
14
14
15
15
15
15
15
16
17
18
18
19
19
19
20
21
22
O37
O39
O29
O32
O2
O27
O28
O16
O19
O18
O23
O25
O31
O21
O30
O12
O26
O4
O7
O34
O14
O10
O8
O24
O13
O15
O9
O33
O3
O11
O22
O6
O5
O35
IntersectionLocation
SR92(HiramAcworthHighway)atHiramCrossingShoppingCenter
SR92(HiramAcworthHighway)atPauldingCommonsShoppingCenter
US278/SR6(JimmyCampbellParkway)atDepotDrive
MaclandRoadatSRBusiness6
SR92(HiramAcworthHighway)atE.PauldingDrive
US278/SR6(JimmyCampbellParkway)atHiramPavilionS
US278/SR6(JimmyCampbellParkway)atHiramPavilionN
US278/SR6(JimmyLeeSmithParkway)atSRBusiness6(AtlantaHighway)
US278/SR6(JimmyCampbellParkway)atOldHarrisRoad
US278/SR6(JimmyLeeSmithParkway)atCadillacParkway
SR61(ConfederateAvenue)atSRBusiness6(WestMemorialDrive)
SRBusiness6(MerchantsDrive)atLegionRoad
SRBusiness6atCoachBobbyDoddRoad
US278/SR6(JimmyCampbellParkway)atSR120(BuchananHighway)
SRBusiness6atOldHarrisRoad
SR92(HiramAcworthHighway)atOldBurntHickoryRoad
EastMemorialDriveatSRBusiness6(MerchantsDrive)
US278/SR6(JimmyCampbellParkway)atMountOlivetLoop
SR61(VillaRicaHighway)atHartRoad
SR101atHollySpringsRoad
RosedaleDriveatMetromontRoad
SR61(VillaRicaHighway)atWinndaleRoad
SR61(VillaRicaHighway)atOldVillaRicaRoad
EastMemorialDriveatLegionRoad
BurntHickoryRoadatBrownsvilleExtension/StoutParkway
EastPauldingDriveatBrooksRackleyRoad
SR61(VillaRicaHighway)atVernoyAikenRoad
SR101atGoldMineRoad
SR120(BuchananHighway)atSR101
SR120(HiramSudieRoad)atDavisMillRoad
WestMemorialDriveatSRBusiness6(BuchananStreet)
SR61(CartersvilleHighway)atShadyGroveChurchRoad
SR61(CartersvilleHighway)atMountMoriahRoad
SR101atOldYorkvilleRoad
Overall
Priority
Score
25
25
25
23
23
22
22
22
21
21
20
18
18
17
17
16
15
14
14
13
13
13
13
13
11
10
9
9
8
8
8
7
6
3
Source:Jacobs
Page 21
PauldingComprehensiveTransportationPlan
DraftFinalReport
Figure6.0:IntersectionImprovements
Page 22
PauldingComprehensiveTransportationPlan
DraftFinalReport
6.2
RoadwayCapacityImprovements
The roadway capacity projects, similar to the operational improvements, were also prioritized by
bothquantitativeandqualitativemeasures.Thequantitativemeasuresconsistedofcongestionand
delay, traffic volumes, and public comment/support. The congestion and delay measures were
basedon2015and2030levelsofservice(LOS)and2030and2040volumetocapacity(V/C)ratios.
EachLOSmeasurewasattributedascorethatwasbasedona05ranking(with5beingworst/F)
forthe2015LOSanda03(with3beingworst/F)rankingforthe2030LOS.Theroadwaycapacity
projectswerealsomeasuredbytheir2030V/Cratiosthatwerebasedona13score(with3being
themostcongested)andtheir2040V/Cratiosthatwerebasedona02score(with2beingthe
most congested). Using the average score from these four criteria, a total congestion score was
createdtoeffectivelyranktheroadwaycapacityprojectsfromahighof13toalowof1.Thetraffic
volumes were from 2015 (existing) and 2030 (projected) for both major corridors as well as for
freight(truck)trafficandrankedbasedonpossiblescoreof15(for2015volumes)and02(for
2030volumes).Byaddingthescoresfrombothyearsforeachproject,atotalscorewascalculated.
The public and committee support was strictly based on combining total votes from an advisory
committee meeting with total votes from a general public meeting for each of the projects to
developatotalcombinedscore.
Evaluation measures that were qualitative in nature consisted of land use, safety, and
constructabilityfactors.Thelandusefactorwasbasedonwhetherornottheprojectservedhigh
growthareas,waslocatedalongamajorcommuterrouteorservedaPauldingCountyemployment
center.Thesafetyfactorwasbasedonaspatialanalysistodetermineiftheprojectswerelocatedin
a high accident location (crash hot spot) with a high, medium, and low crash rate. Finally, the
constructabilityfactorwassimplybasedonwhethertherewereanyenvironmentalconstraintsin
thevicinityoftheproposedimprovements.
Despitebeingaquantitativeorqualitativefactor,eachfactorwasweightedagainstothersbasedon
relativeimportance.Similartotheoperationalimprovements,thesafety,congestion(delay),and
land use characteristics were weighted equally and most heavily. The traffic volumes and
public/committeesupportwerealsoweightedheavily,althoughtoaslightlylesserextentthanthe
previouslymentionedfactors.TheresultsoftheprioritizationanalysisarepresentedbelowinTable
6.1.
Table6.1:RoadwayCapacityImprovementPrioritizationResults
Priority
Ranking
1
2
3
4
5
6
7
RC6
RC5
RC3
RC2
RC1
RC4
RC9
Page 23
Project
ID
ProjectLocation
US278/SR6fromSRBusiness6toCobbCountyLine
US278/SR6fromSR61toSRBusiness6
SRBus6fromUS278/SR6(WestofDallas)toMemorialDrive
DallasAcworthHwy/MemorialDrivefromEastPauldingDrivetoSRBus6
DallasAcworthHighwayfromSR92toEastPauldingDrive
SRBus6fromMemorialDrivetoUS278/SR6(EastofDallas)
SR61(VillaRicaHighway)fromHiramSudieRoadtoUS278/SR6
Overall
Priority
Score
37
36
33
32
31
30
28
PauldingComprehensiveTransportationPlan
DraftFinalReport
Priority
Ranking
8
9
10
11
12
13
14
15
16
16
17
17
18
21
22
Project
ID
RC10
RC8
RC14
RC15
RC18
RC12
RC16
RC22
RC20
RC17
RC21
RC19
RC13
RC11
RC7
ProjectLocation
SR61(CartersvilleHighway)fromSRBusiness6toOldCartersvilleRoad
SR61(VillaRicaHighway)fromDouglasCountyLinetoRidgeRoad
RidgeRoadfromDallasNeboRoadtoSR92
NeboRoadfromDallasNeboRoadtoSR92
HiramSudieRoadfromSR61(VillaRicaHighway)toSR92
SR61(CartersvilleHighway)fromDabbsBridgeRoadtoBartowCountyLine
BakersBridgeRoadfromDouglasCountyLinetoRidgeRoad
BoboRoadfromDallasAcworthHighwaytoSR120(CharlesHardyParkway)
CedarcrestRoadfromSR92toSevenHillsBoulevard
SweetwaterChurchRoadfromDouglasCountyLinetoSR92
EastPauldingDrivefromSR92toSR120(CharlesHardyParkway)
CedarcrestRoadfromSevenHillsBoulevardtoCobbCountyLine
DabbsBridgeRoadfromSR61(CartersvilleHighway)toBartowCountyLine
SR61(CartersvilleHighway)fromMt.MoriahRoadtoDabbsBridgeRoad
SR101/113fromCarrollCountyLinetoSR120(BuchanonHighway)
Overall
Priority
Score
26
25
24
21
20
18
16
15
14
14
12
12
11
6
6
Source:Jacobs
6.3
NewRoadways
Unlikethoseusedinprioritizingoperationalimprovementsandroadwaycapacityprojects,the
prioritization factors for the new roadway projects are all qualitative in nature. The same
factors:congestiondelay,landuse,safety,trafficvolumes(2015&2030),publiccomment,and
constructabilityareallusedinthisprocessfornewroadways.Forthisanalysis,however,ofthe
performanceofeachproposednewroadwaywithineachcategorywasmeasuredqualitatively,
basedonitsprojectedperformancerelativetootherproposedprojects.Forexample,theLOS
andV/Cfeatureswerebasedonathresholdoflow,medium,andhighasweretheassessments
forthelandusefactor.Also,thecrashdataforthesafetyfactoralongwiththe2015and2030
trafficvolumesforcarsandfreightvehicleswereassessedbasedonaspatialanalysisofcrash
locations (hot spots) on a low, medium, or high threshold on existing parallel or adjacent
facilities.Next,thepubliccommentfactorwas,asforotherprojecttypes,basedontheamount
ofvotesreceivedfrommeetingattendeesthatwerethenbrokendownintothreecategoriesof
low, medium, and high. Finally, the constructability factor was based on whether or not a
proposednewroadwaywaslocatedinanareawithanyenvironmentalconstraints.
Allevaluationfactorswereweightedequallyinthisanalysis.Theresultsoftheprioritizationanalysis
arepresentedbelowinTable6.2.
Table6.2:NewRoadwaysImprovementPrioritizationResults
Priority
Ranking
1
1
2
3
NC3
NC4
NC1
NC2
Page 24
Project
ID
ProjectLocation
HiramParallelRelieverSouthofUS278/SR6fromSR92toBillCarruthParkway
HiramParallelRelieverNorthofUS278/SR6fromSR92toLakeRoad
WestDallasBypassfromSR61(CartersvilleHighway)toUS278/SR6
EastDallasBypassfromSRBusiness6toSR61(CartersvilleHighway)
Overall
Priority
Score
26
26
23
22
PauldingComprehensiveTransportationPlan
DraftFinalReport
NC5
Source:Jacobs
6.4
CedarcrestRoadSR61Connector
TransitandTravelDemandManagement
The transit and travel demand management element is composed of only three factors,
multimodal travel, land use, and public comment, which are prioritized using qualitative
measures. The multimodal travel factor consists of the following elements from the 2010
Census:zerocarhouseholds,lowincome,elderlydensity,populationdensity,andemployment
densityalongwithanotherqualitativeelementofwhetherornotaproposedprojectpromotes
bicycleand/orpedestriantravel.Thefivecensuselementsareweightedonalow,medium,or
highscale,whilethepromotionofbicycleand/orpedestriantravelisrankedfrom12basedon
whetheraproposedprojectprovideslocalserviceorcommuterservice.Meanwhile,theland
usefactorisprioritizedbasedonwhetheraproposedprojectservesahighgrowtharea(low,
medium,orhighgrowth)orislocatedalongamajorcommuterroute(yesorno).Finally,the
publiccommentfactorisbasedontwoelements:oneisthevotingbytheadvisorycommittee
on each proposed project and theother is based on a threequestion survey administered to
thegeneralpublictogaugetheirinterestinexpandingtransitservices.
Similartotheotherimprovementtypes,eachofthenewtransitandtraveldemandmanagement
projectfactorswasweightedequallyagainsteachother.Theresultsoftheprioritizationanalysisare
presentedbelowinTable6.3.
Table6.3:TransitandTravelDemandManagementImprovementsPrioritizationResults
Priority
Ranking
ProjectID
1
2
3
4
5
6
7
8
9
10
11
12
13
T2
T5
T11
T3
T4
T7
T9
T8
T6
T13
T1
T10
T12
Source:Jacobs
6.5
ProjectLocation
TransitServicetoPauldingCountyGovernmentComplex
DallasCirculatorShuttle
ExtendGRTAviaSR6toDallas
TransitServicetoWellstarPauldingHospital
TransitChattahoocheeTechnicalCollege
FixedRouteBusfromSilverCometFieldtoDallas/HiramalongUS278/SR6
ArterialBRT/HOValongUS278/SR6
ArterialBRT/HOValongSR120(CharlesHardyParkway)
HiramCirculatorShuttle
NewGRTAServicetoCumberlandviaSR360
SilverCometFieldShuttle
ArterialBRT/HOValongSR92/DallasAcworthHighway
NewGRTAServicetoMarietta(CCTHub)viaSR120
OverallPriority
Score
25
25
25
24
23
22
22
18
14
13
12
12
12
PedestrianFacilities,BicycleFacilities,andMultiUseTrails
The pedestrian facilities element is composed of five factors, multimodal travel, land use,
safety, major transportation corridors, and public comment, which are prioritized using
qualitative measures. Similar to the transit and travel demand management projects, the
Page 25
PauldingComprehensiveTransportationPlan
DraftFinalReport
multimodal travel factor for pedestrian facilities consists of the following features from the
2010 census: zero car households, low income, population density, and employment density
alongwithanotherqualitativeelementofwhetherornotaproposedfacilitypromotestransit
ridershipbyconnectingtoexistingtransit.Thefourdemographicfactorsarerankedonalow,
medium,orhighscale,whilethepromotion of transitridershipisrankedfrom01.Theland
usefactorisprioritizedbasedonwhetheraproposedprojectservesahighgrowtharea(low,
medium,orhigh)orifitprovidesconnectivitytotheSilverCometTrail(yesorno).Thesafety
factorisbasedonaspatialanalysistodetermineifaproposedfacilityislocatedalongaroute
withsignificantpedestrianaccidents. Thefinaltwofactors,stillqualitative,arebasedonthe
functional classification of the roadway along with public input. As in the case of the other
proposed improvements, the public and committee support is ranked by combining the
advisorycommitteevoteswiththoseofthegeneralpublic.
Theevaluationmeasuresusedtoprioritizepedestrianfacilitieswereweightedequallyagainsteach
other.TheresultsoftheprioritizationanalysisarepresentedbelowinTable6.4.
Table6.4:PedestrianFacilitiesPrioritizationResults
Priority
Ranking
1
2
3
4
4
5
6
7
8
8
8
8
9
9
9
9
10
10
10
10
10
10
10
11
11
11
11
12
12
12
BP40
BP47
BP45
BP11
BP43
BP38
BP22
BP24
BP13
BP14
BP15
BP28
BP19
BP20
BP29
BP41
BP2
BP5
BP6
BP16
BP17
BP42
BP46
BP9
BP27
BP31
BP37
BP4
BP12
BP26
Page 26
ProjectID
ProjectLocation
SR61fromOscarWaytoKirkDrive
SRBus6/OldHarrisRoadfromMerchantsDrivetoCommerceDrive
WestMemorialDrivefromBagbyPathtoPauldingMemorialHospital
DepotDrivefromUS278/SR6(JimmySmithParkway)toRosedaleDrive
US278/SR6fromDepotDrivetoCleburneParkway
SouthMainStreetfromConstitutionBoulevardtoSeaboardDrive
MetromontRoadfromUS278/SR6toRosedaleDrive
MustangDrivefromHeritageWaytoDonbieDrive
EastFosterAvenuefromDallasCityParktoHardeeStreet
EastPauldingDrivefromLostMeadowsDrivetoHopeDrive
EastPauldingDrivefromDallasAcworthHighwaytoMt.TaborPark
OldVillaRicaRoadfromSR61toIvyTraceLane
LesterDrivefromDallasCityParktoSRBus6
MaclandRoadfromSR92toSR120(CharlesHardyParkway)
OldVillaRicaRoadfromSR61toStationDrive
SR92fromHardyCircletoEastPauldingMiddleSchool
BrownsvilleRoadfromSR92toSweetwaterPass
CedarcrestRoadfromCobbCountyLinetoHighcrestDrive
CenterStreetfromSeaboardAvenuetoSR92
GravesRoadfromGravesRoadSpurtoGravesRoad
HiramSudieRoadfromSR61toSouthernOaksDrive
SR92fromCedarcrestRoadtoRoyalSunsetDrive
WilliamsLakeRoadfromJADobbinsMiddleSchooltoFourOaksDrive
CowboyPathfromEastPauldingHomeParktoForestHillsDrive
OakStreetfromSR92toSeaboardAvenue
PineValleyRoadfromTaylorFarmParkWesttoNorthviewLane
SeaboardAvenuefromTowneParkDrivetoPowderSpringsStreet
CedarcrestRoadfromHarmonyGroveChurchRoadtoArthurHillsDrive
DueWestRoadfromDallasAcworthHighwaytoAutumnCreek
NeboRoadfromDallasNeboRoadtoSwanDrive
Overall
PriorityScore
23
22
21
20
20
19
18
17
16
16
16
16
15
15
15
15
14
14
14
14
14
14
14
13
13
13
13
12
12
12
PauldingComprehensiveTransportationPlan
DraftFinalReport
Priority
Ranking
ProjectID
12
12
12
12
13
13
13
13
14
14
14
15
16
16
16
17
17
18
Source:Jacobs
BP32
BP33
BP34
BP35
BP1
BP3
BP7
BP21
BP23
BP25
BP36
BP30
BP8
BP18
BP48
BP10
BP39
BP44
ProjectLocation
PineValleyRoadfromTaylorFarmParkWesttoWinterParkLane
RidgeRoadfromDallasNeboRoadtoAustinBridgeRoad
RidgeRoadfromHughesRoadtoRidgeRunDrive
RidgeRoadfromHughesRoadtoFarmStreet
BakersBridgeRoadfromRidgeRoadtoCharityDrive
CedarcrestRoadatFloydSheltonElementary
ClontsRoadfromWileyDrivetoHalHutchinsElementary
MeinMitchellRoadfromRidgeRoadtoCountryVillageDrive
MulberryRockRoadfromDokeCochranRoadtoSR61
NeboRoadfromNeboElementarySchooltoPineShadowsRoad
ScogginsRoadfromSR61toSugarMillDrive
PineShadowsDrivefromNeboRoadtoSmithFergusonRoad
ColbertRoadfromAbneyElementarytoLegacyPointDrive
HollySpringsRoadfromWoodwindDrivetoHighway101
PedestrianCrossingatWilliamsLakeRoadwestofJADobbinsMiddleSchool
CrossroadsChurchRoadfromWintervilleDrivetoYorkvillePark
SR101fromCrossroadsChurchRoadtoRunnellRoad
WaysideLane/ClearCreekDrivefromUS278/SR6toPooleElementarySchool
Overall
PriorityScore
12
12
12
12
11
11
11
11
10
10
10
9
8
8
8
6
6
5
The evaluation criteria for the onstreet bicycle facilities element is composed of only two
qualitative factors, truck volumes (2015 & 2030) and public and committee support. For the
fourproposedprojects,the2015and2030truckvolumeswereassessedonalow,medium,or
highscale,whilethepubliccommentfactorwasbasedontheamountofvotesreceivedfrom
meeting attendees that were then broken down into three categories of low, medium, and
high.
Similar to the evaluation process for the sidewalk segments, each of the four proposed onstreet
bicyclefacilitiesprojectswereweightedequallyagainsteachother.Theresultsoftheprioritization
analysisarepresentedbelowinTable6.5.
Table6.5:OnStreetBicycleFacilitiesPrioritizationResults
Priority
Ranking
Project
ID
1
2
3
4
BP59
BP58
BP61
BP60
Source:Jacobs
Project Location
RidgeRoadBetweenBakersBridgeRoadandSR61
MulberryRockRoadNearSR61
CedarcrestRoadBetweenHarmonyGroveChurchRoadandSevenHillsDrive
SR61(CartersvilleHwy)BetweenMt.MoriahRoadandDabbsBridgeRoad
Overall
Priority
Score
16
14
13
11
The evaluation criterion for multiuse trails consists of three factors; multimodal travel
support, land use, and public/stakeholder committee support. These were scored using
qualitativemeasures.Themultimodaltravelsupportmeasureconsistsofthreedemographic
factors from the 2010 Census, including zerocar households, low income populations, and
overallpopulationdensity.Thethreedemographicfactorswererankedonalow,medium,or
high rating scale. The land use evaluation criteria assessed a proposed trails location within
Page 27
PauldingComprehensiveTransportationPlan
DraftFinalReport
highgrowthareas(low,medium,orhighranking),abilitytoservecommunityfacilities(yesor
no), or if it provides connectivity to the Silver Comet Trail (yes or no). Stakeholder advisory
committeesupportwasanothermeasureusedtoprioritizepotentialtrailprojects.Theresults
oftheprioritizationanalysisarepresentedbelowinTable6.6.
Table6.6:MultiUseTrailFacilitiesPrioritizationResults
Priority
Ranking
1
2
3
4
4
5
ProjectID
BP57
BP56
BP54
BP52
BP53
BP55
ProjectLocation
BetweenGovernmentComplexandSeaboardTrailhead
StricklandParkConnectionBetweenWeddingtonRoadandStricklandPark
NorthofHulseyTownRoadBetweenSilverCometFieldandHulseyTownRoad
WithinthePauldingForestWMASouthofSilverCometTrail
WithinthePauldingForestWMANorthofSilverCometTrail
NearPegColeBridgeRoadBetweenGeorgiaParkwayandPegColeBridgeTrail
Overall
Priority
Score
21
14
9
6
6
3
Source:Jacobs
Page 28
PauldingComprehensiveTransportationPlan
DraftFinalReport
7.0 REVENUEFORECASTING
Threeimportantstepsweretakentoarriveatafinalrecommendedprojectlistandimplementation
plan from the universe of transportation needs identified within the Assessment of Current and
FutureNeedsReport.Thesestepswereprojectcostestimation,projectprioritization,andrevenue
forecasting.Revenueforecastingisrequiredtodeterminethefundingamountsthatwillrealistically
beavailabletofundtransportationprojectsinthefuture.TheCTPisafiscallyconstrainedplanwhich
strivestoachieverealisticprojectdeliverybaseduponforecastedfundinglevelsavailablewithinthe
2040 planning horizon. The CTP also includes a fiscally unconstrained list of projects, which
representsamorecompleteprojectlistifmorefundingbecomesavailablethanisanticipated.
Transportationprojectscanbefinancedthroughfederal,state,local,andoccasionallyprivatefunds,
andareoftenfundedthroughacombinationofsources.Thisrevenueforecastingexerciseprovides
estimatesoflikelyfundinglevelsfromfederal,stateandlocalsourcesfrom2015through2040.This
was conducted through an analysis of projected Special Purpose Local Option Sales Tax (SPLOST)
revenues.ItalsoincludesananalysisofprojectedGeorgiaDepartmentofTransportation(GDOT)
LocalMaintenanceandImprovementGrant(LMIG)fundsandisbasedonhistoricspendingtrendsin
theARCsTransportationImprovementPlan(TIP).Privatefundingisusuallylocatedonaprojectby
projectbasisandasresultitisnotincludedinthisfundingforecast.
Table7.0providestheestimatedfundingamountsarrivedatbytherevenueforecastingexerciseby
implementationphaseandsource.Adescriptionofeachfundingsourceandthemethodologyused
toestimatethepotentialfundingamountsareprovidedinthefollowingsectionsdevotedtofederal,
stateandlocalresources.
Page 29
PauldingComprehensiveTransportationPlan
DraftFinalReport
Table7.0:TotalEstimatedFundingbyImplementationPhaseandSource
ImplementationPhaseandSource
CommittedShortTerm(20152019)
ARCTIP20142019
SPLOSTIV(20152017)
AvailableShortTerm(20152019)
SPLOSTV(20182019)
MidTerm(20202030)
FederalandState
SPLOST
LongTerm(20312040)
FederalandState
SPLOST
EstimatedFunding
$203.5M
$181.2M
$22.3M
$13.3M
$13.3M
$353.9M
$264.0M
$89.9M
$394.7M
$282.3M
$112.4M
Source: Jacobs
7.1
FederalFunding
To forecast federal funding levels within the 2040 planning horizon it was assumed that historic
levelsofcommittedfundingwouldcontinueinthefuture.Historiclevelswereestimatedthrough
federal funding amounts committed in the 20142019 TIP. An annual growth rate of 1.4% was
appliedtofederalfundinglevelswithintheTIP.ThisisthesamegrowthratetheAtlantaRegional
Commissionusestoforecastregionalfederalfunding.Thisisbaseduponthecurrentfundingclimate
andrevenueincreasesexpectedinMAP21(MovingAheadforProgressinthe21stCenturyAct).
TheexistingTIP(20142019)includesaseriesofSR92wideningprojects.Thesearerecognizedas
beingaspecialregionalprioritythatwouldreflectanartificiallyhighfuturefundinglevelifprojected
intothefuture.Itisnotanticipatedthatthisleveloffundingwouldbeconsistentlyavailablethrough
the2040horizon.Toaccountforthisspecialexistingpriorityinthetrendanalysis,onequarterof
thefundingamountallocatedforSR92intheTIPwasassumedtobeavailableduringthe20202030
and20312040forecastperiods.
7.2
StateFunding
GDOTprovidesfinancialassistancetolocalgovernmentsthroughLMIGfundscollectedthroughthe
state motor fuel tax. LMIG funds are administered based on a formula that determines a
jurisdictionsshareofatotalstatewideallotment.Thesefundsrequirea30%localmatchfromthe
county.LMIGfundscanbeusedforawidevarietyofinvestments,includingresurfacing,patching,
intersection improvements, turn lanes, new location roads, widening, sidewalks/bike lanes within
existing rightofway, signal installation/improvement, bridge repair/replacement, preliminary
engineeringandconstruction.Theyarenotpermittedtobeusedtopurchaserightofwayonstate
routes.Eventhoughthesefundsmaybeusedforavarietyofusesitisassumedthattheywillbe
Page 30
PauldingComprehensiveTransportationPlan
DraftFinalReport
usedforthepurposesofroadwaymaintenanceandpavementresurfacingwithinthecounty,which
hasbeenthehistoricpattern.
TheformulausedtodetermineLMIGfundsisbasedonacomparisonofthejurisdictionspopulation
androadmileageofstaterouteswithinthejurisdictiontothestateofGeorgiatotal.WhilePaulding
Countyspopulationisexpectedtogrowfasterthanthestateaverage(118.5%vs71%,respectively)
by2040,themannerinwhichthisisfactoredintheformulawouldnotresultinasignificantincrease
inlocalallocation.
PauldingCountystotalallotmentofLMIGfundsin2014was$1,371,834.Toforecastthisfunding
source within the planning horizon of 2040, a growth factor of 1.33% was used. This factor was
sourcedfromGDOTsStatewideTransportationPlanUpdate(20052035)inwhichrevenueforecasts
forthestatewidemotorfueltaxrevenueswereconducted.Thesetaxrevenuesdonottrackwith
inflationrates,becausetheyaretiedtoincreasesinstatewideVMTinadditiontoretailsalestax.
InadditiontoLMIGfunding,othersourcesofstatefundinghavebeenestimatedfromhistoriclevels
intheTIP.Thestatefundingtotalsfromthe20142019TIPhavebeenprojectedtoincreaseatan
annual growth rate 2.2%. This growth rate is used by the Atlanta Regional Commission (ARC) to
forecastregionalstatefundinglevelswithintheRTP.Asdescribedintheprevioussectiononfederal
funding,onlyaportionofthefundingallocatedtoSR92projects(25%),hasbeenincludedinfunding
calculations.
7.3
LocalFunding
Local governments in Georgia typically fund transportation projects through two main sources:
county and city general funds and SPLOST revenues. Financing transportation improvements
throughthecountysgeneralfundhasnotbeenthehistorictrendinPauldingCounty.Asaresultall
futurelocalrevenuesareassumedtobeprovidedthroughthePauldingCountysSPLOSTprogram.
The SPLOST program is in its fourth iteration, having been consistently approved through voter
referendum.ItisassumedthattheSPLOSTwillberenewedandbeineffectthroughoutthe2040
planninghorizon.
The current SPLOST (SPLOST IV, 20112017) provides transportation revenues of $47.5 M. This
averagesapproximately$7.9Mayear.Theserevenuesareexpectedtoremainatsimilarlevelsover
theplanninghorizonandincreaseatanannualrateof3%duetoinflation.Itisanticipatedthata
componentofthisfundingwillbeusedforlocalmatchingfundstoaccessLMIGfunding.Asaresult
30%oftheestimatedLMIGfundingamountisassumedtobeunavailablefromSPLOSTrevenuesto
fund proposed transportation improvements. LMIG funding is discussed in more detail in the
previoussectionfocusingonstatefunding.
Page 31
PauldingComprehensiveTransportationPlan
DraftFinalReport
8.0 PROJECTRECOMMENDATIONSANDIMPLEMENTATIONPLAN
This section presents the recommended project list and phased implementation plan for
operationalimprovements,roadwaycapacityimprovements,andnewroadwayconnections.It
also includes a fiscally unconstrained list of proposed improvements identified through the
need assessment analysis. The recommended project list and implementation plan represent
thefinalculminationoftheCTPplanningprocess,builtupontheneedsidentificationanalysis,
projectprioritization,andrevenueforecastinganalysis.
AfiscallyunconstrainedprojectlistisdetailedbelowinTable8.0andtheprojectlocationsare
displayed geographically in Figure 8.0. Given the limited funding estimated through revenue
forecasting,therewasaneedtofiscallyconstrainthisuniverseofneedsintoarealisticmulti
phase implementation plan. To develop the phased implementation plan, the results of the
prioritization process were considered in conjunction with available funding in each time
period.
The plan isphased over three timeperiods, which include Phase I Shortrange (20152019),
PhaseIIMidrange(20202030),andPhaseIIILongrange(20302040).Theimplementation
planisdisplayedinFigure8.1.Theindividualprojectdetailsincludingfinancialinformationare
detailedinTables8.1,8.2and8.3attheendofthissection.
Table8.0:FiscallyUnconstrainedProjectList
ProjectID
OperationalImprovements
O1
O2
O3
O7
O8
O9
O10
O11
O12
O13
O14
O15
O17
O20
O21
O22
O23
O24
O25
O26
O27
O29
O32
SR120(CharlesHardyParkway)atSRBus6
SR92(HiramAcworthHighway)atE.PauldingDrive
SR120(BuchananHighway)atSR101
SR61(VillaRicaHighway)atHartRoad
SR61(villaRicaHighway)atOldVillaRicaRoad
SR61(VillaRicaHighway)atVernoyAikenRoad
SR61(VillaRicaHighway)atWinndaleRoad
SR120(HiramSudieRoad)atDavisMillRoad
SR92(HiramAcworthHighway)atOldBurntHickoryRoad
BurntHickoryRdatBrownsvilleExtension/StoutParkway
RosedaleDriveatMetromontRoad
EastPauldingDriveatBrooksRackleyRoad
US278/SR6(JimmyLeeSmithPkwy)atBillCarruthPkwy/SR120
US278/SR6(JimmyCampbellParkway)atSR61(VillaRicaHwy)
US278/SR6(JimmyCampbellParkway)atSR61(VillaRicaHwy)
WestMemorialDriveatSRBus6(BuchananStreet)
SR61(ConfederateAve)atBusinessSR6(WestMemorialDr)
EastMemorialDriveatLegionRoad
SRBus6(MerchantsDr)atLegionRoad
EastMemorialDriveatSRBusiness6
US278/SR6(JimmyLeeSmithPkwy)atHiramPavilionSouth
US278/SR6(JimmyLeeSmithPkwy)atDepotDrive
SR360(MaclandRoad)atSRBus6
Page 32
Description
From
To
PauldingComprehensiveTransportationPlan
DraftFinalReport
ProjectID
Description
O33
SR101atGoldMineRoad
O35
SR101atOldYorkvilleRoad
O36
SR92(HiramAcworthHighway)atRosedaleDrive
O38
SR92(HiramAcworthHighway)atUS278/SR6
RoadwayCapacity
RC1
DallasAcworthHighway
RC5
US278/SR6
RC6
US278/SR6
RC9
SR61(VillaRicaHighway)
RC13
DabbsBridgeRoad
RC14
RidgeRoad
From
To
RC19
CedarcrestRoad
RC20
CedarcrestRoad
SR92
SR61
SRBus6
DallasNeboRoad
SR61
DallasNeboRoad
HarmonyGrove
ChurchRd
OakGlenDrive
RC21
E.PauldingDrive
SR92
E.PauldingDr.
SRBus6
CobbCountyLine
SR92
BartowCountyLine
SR92
CobbCountyLine
SR92
WestofBrooksRackley
Rd
NewRoadwayConnections
NC1
WestDallasBypass
NC2
NC3
NC4
NC5
EastDallasBypass
HiramParallelRelieverSouth
HiramParallelRelieverNorth
CedarcrestRoadtoSR61Connector
SR61(Cartersville
Hwy)
SRBus6
SR92
SR92
CedarcrestRoad
Source:Jacobs
US278/SR6
SR61
BillCarruthPkwy
LakeRoad
SR61
Page 33
PauldingComprehensiveTransportationPlan
DraftFinalReport
Figure8.0:FiscallyUnconstrainedProjects
Page 34
PauldingComprehensiveTransportationPlan
DraftFinalReport
Figure8.1:FiscallyConstrainedImplementationPlan
Page 35
PauldingComprehensiveTransportationPlan
DraftFinalReport
Table8.1:PhaseIShortRangeImplementationPlan(20152019)
PhaseIShortRange20152019
ProjectID
Roadway/Location
From
ARCTIP20142019
PA062
PA063
PA027
NewRoadwayatTechnologyPark(Ph1)
NewRoadwayatTechnologyPark(Ph2)
SR92BridgeReplacementandWidening
CO367
PA061C1
AR5307PA
PA092A
PA092B1
PA092C
PA092E
PA095
PA101A
PA101B
SR360(MaclandRoad)Widening
SR61(VillaRicaHighway)Segment3Widening
FTASection5307/5340FormulaFunds
SR92(HiramDouglasvilleHighway)Widening
SR92(HiramDouglasvilleHighway)Widening
SR92(HiramAcworthHighway)Widening
SR92(DallasAcworthHighway)Widening
JohnstonSt,GriffinSt,SpringSt,andParkStPedFacility
PauldingCountyATMSSystemExpansionPhase1
PauldingCountyATMSSystemExpansionPhase2
AirportParkway
AirportParkway
SouthernRRinHiram
SR120(CharlesHardy
Pkwy)
DallasNeboRoad
Brown/MaloneSt
NeboRd
E.PauldingMiddleSchool
CedarcrestRoad
To
Description
Jurisdiction
Sponsor
TotalEstimated
Cost
Phase
Federal
State
Local
Total
Estimated
Funding
NewCuldeSac
NewCuldeSac
NewLocationProject
NewLocationProject
Roadway/BridgeCapacity
Paulding County
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
GDOT
ROW, UTL
ROW,CST
CST
$4,794,398
$2,993,988
$2,767,901
$1,606,500
$1,000,000
$2,214,321
$0
$0
$553,580
$2,774,513
$1,817,988
$0
$0
$0
$0
$4,381,013
$2,993,988
$2,704,901
LostMtn.Rd(Cobb)
JimmyCampbellPkwy
NeboRd
SR120(MariettaHwy)
OldBurntHickoryRd
CobbCo.Line
Roadway/Capacity
Roadway/Capacity
Transit/FormulaLumpSum
Roadway/Capacity
Roadway/Capacity
Roadway/Capacity
Roadway/Capacity
LastMile/Ped Facility
Roadway/Ops&Safety
Roadway/Ops&Safety
CobbCounty
PauldingCounty
PauldingCounty
Regional NWGA
Regional NWGA
Regional NWGA
Regional NWGA
PauldingCounty
PauldingCounty
PauldingCounty
CobbCounty
GDOT
PauldingCounty
GDOT
GDOT
GDOT
GDOT
CityofDallas
PauldingCounty
PauldingCounty
UTL,CST
PE,ROW
CST
UTL,CST
UTL,CST
PE,ROW
PE,ROW
ALL
PE,CST
PE,CST
TotalTIP
$57,868,088
$48,506,194
$2,956,065
$69,618,200
$61,031,294
$53,377,464
$23,058,693
$2,886,170
$2,144,319
$1,633,922
$333,636,696
$46,294,470
$10,970,999
$2,364,852
$54,894,561
$15,893,711
$15,223,792
$2,276,308
$1,840,936
$1,494,855
$1,162,338
$157,237,643
$11,573,618
$2,742,750
$0
$13,723,639
$3,973,428
$3,805,948
$569,077
$0
$0
$0
$36,942,040
$0
$0
$591,213
$0
$0
$0
$0
$845,234
$649,464
$471,584
$7,149,996
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$44,838,088
$13,713,749
$2,956,065
$68,618,200
$19,867,139
$19,029,740
$2,845,385
$2,686,170
$2,144,319
$1,633,922
$188,412,679
BridgeReplacement
BridgeReplacement
SidewalkandNewBridge
IntersectionImprovements
IntersectionImprovements
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PE,ROW,CST
PE,ROW,CST
CST
PE,ROW,CST
PE,ROW,CST
TotalSPLOST1517
$2,335,000
$2,330,000
$526,770
$1,800,000
$2,000,000
$9,011,770
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$2,335,000
$2,330,000
$526,770
$1,800,000
$2,000,000
$9,011,770
$0
$0
$0
$0
$0
$0
$2,335,000
$2,330,00
$526,770
$1,800,000
$2,000,000
$9,011,770
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
ALL
ALL
ALL
ALL
ALL
ALL
ALL
$2,935,000
$576,000
$3,521,000
$90,000
$168,000
$3,790,000
$364,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$2,935,000
$576,000
$3,521,000
$90,000
$168,000
$3,790,000
$364,000
$0
$0
$0
$0
$0
$0
$0
$2,935,000
$576,000
$3,521,000
$90,000
$168,000
$3,790,000
$364,000
LMIGLocalMatchingFunds
PauldingCounty
PauldingCounty
N/A
$873,573
$0
$0
$873,573
$0
$873,573
PedestrianImprovements
PauldingCounty
PauldingCounty
ALL
$1,108,950
$0
$0
$1,108,950
$0
$1,108,950
TransportationStudies
PauldingCounty
PauldingCounty
N/A
$300,000
$14,111,523
$0
$0
$0
$0
$300,000
$14,111,523
$14,210,000
$98,477
$0
$0
$0
$300,000
$14,111,523
$14,210,000
$98,477
Bond
SPLOSTIVFundedProjects20152017
SP1
SP2
SP3
SP4
SP5
PickettsMillCreekBridgeReplacementatDallasAcworthHwy
PossumCreekBridgeReplacementatDallasAcworthHwy
SouthMainStreetBridgeandSidewalkImprovements
BoboRdandMt.TaborChurchRdatSR360(MaclandRd)
DallasAcworthHighwayatFryRd/Mt.TaborRd
GovernmentComplex
Seaboard
Phase1CTPRecommendedProjects(fundedviaSPLOSTV20182019)
IntersectionImprovements
O20
US278/SR6(JimmyCampbellPkwy)atSR61(VillaRicaHwy)
O32
SR360(MaclandRoad)atSRBusiness6
O24/25/26 E.MemorialDriveatLegionRd,SRBus6atLegionRd,E.MemorialDriveatSRBus6
O23
SR61(ConfederateAvenue)atSRBus6
O14
RosedaleDriveatMetromontRoad
O33
SR101atGoldMineRoad
O21
US278/SR6(JimmyCampbellPkwy)atSR120(VillaRicaHwy)
RoadwayMaintenance
CountywideRoadwayMaintenanceLocalMatchingFunds
PedestrianImprovements
Constructionofsidewalksinthevicinityofschools,parks,andotheractivitycenters
TransportationFeasibilityStudies
Corridorstudiesandfeasibilitystudiesforimprovingeasttowestconnectivitywithinthecounty.
CTPOverallProjectTotal
EstimatedFundingTotal
Difference
Page 36
January2015
PauldingComprehensiveTransportationPlan
DraftFinalReport
Table8.2:PhaseIIMidRangeImplementationPlan(20202030)
PhaseIIMidRange20202030
ProjectID Roadway/Location/Project
RoadwayCapacityImprovements
PA092B1
PA092C
PA092E
SR92
SR92
SR92
TotalEstimated
Cost
State
Local
Bond
TotalEstimated
Funding
To
Description
Jurisdiction
Sponsor
NeboRoad
EastPauldingMiddleSch
CedarcrestRoad
SR120(CharlesHardy
Pkwy)
OldBurntHickoryRd
CobbCountyLine
Wideningfrom2to4lanes
Wideningfrom2to4lanes
Wideningfrom2to4lanes
PauldingCounty
PauldingCounty
PauldingCounty
GDOT
GDOT
GDOT
Widening2to4lanes
Widening2to4lanes
Wideningfrom2to4lanes
Wideningfrom2to4lanes
Wideningfrom2to4lanes
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
GDOT
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
UTL,CST
ALL
ALL
ALL
ALL
$33,002,000
$76,163,000
$55,895,174
$41,100,000
$22,500,000
$26,402,000
$54,837,360
$0
$32,058,000
$18,000,000
$6,600,000
$14,470,970
$0
$9,042,000
4,500,0000
$0
$10,662,820
$55,895,174
$0
$0
$0
$0
$0
$0
$0
$33,002,000
$76,163,000
$55,895,174
$41,1000,000
$22,500,000
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
ALL
ALL
ALL
ALL
ALL
ALL
ALL
ALL
ALL
ALL
ALL
ALL
ALL
ALL
$1,419,000
$1,445,000
$4,932,000
$2,165,000
$270,000
$3,053,000
$4,340,000
$11,742,000
$960,000
$528,000
$1,382,000
$4,405,000
$254,000
$26,000,000
$0
$0
$0
$1,602,1000
$0
$0
$0
$8,571,660
$0
$0
$0
$3,083,500
$0
$3,000,000
$0
$0
$0
$319,338
$0
$0
$0
$1,996,140
$0
$0
$0
$440,500
$0
$3,000,000
$1,419,000
$1,445,000
$4,932,000
$243,563
$270,000
$3,053,000
$4,340,000
$1,174,200
$960,000
$528,000
$1,382,000
$881,000
$254,000
$20,000,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$1,419,000
$1,445,000
$4,932,000
$2,165,000
$270,000
$3,053,000
$4,340,000
$11,742,000
$960,000
$528,000
$1,382,000
$4,405,000
$254,000
$26,000,000
LMIGMatchingFunds
PauldingCounty
PauldingCounty
ALL
$5,239,970
$0
$0
$5,239,970
$0
$5,239,970
PedestrianImprovements
PauldingCounty
PauldingCounty
N/A
$7,042,191
$0
$0
$7,042,191
$0
$7,042,191
Transit
PauldingCounty
PauldingCounty
N/A
$39,877,648
$364,180,809
$31,902,118
$213,075,863
$213,902,688
$826,825
$0
$49,482,163
$50,187,382
$705,220
GeneralFund
$94,647,254
$95,114,533
$467,280
$0
$0
$0
$0
$31,902,118
$357,205,279
$190,467,143
$1,999,324
FTASection5307/5340FormulaFundsAllocation(FY20202030)
OverallProjectTotal
EstimatedFundingTotal
Difference
Federal
From
RC9(PA
061C1)
SR61
DallasNeboRoad
US278/SR6
RC6
US278/SR6
CobbCountyLine
SRBus6
RC1
DallasAcworthHighway
EastPauldingDrive
SR92
RC21
EastPauldingDrive
SR92
SR120
RC19
CedarcrestRoad
HarmonyGroveChurchRd
CobbCountyLine
IntersectionImprovements
O36
SR92(HiramAcworthHighway)atRosedaleDrive
O1
SR120(CharlesHardyParkway)atSRBusiness6
O2
SR92(HiramAcworthHighway)atEastPauldingDrive
O27
US278/SR6(JimmyLeeSmithPkwy)atHiramPavilionSouth
O12
SR92(HiramAcworthHighway)atOldBurntHickoryRoad
O7
SR61(VillaRicaHwy)atHartRoad
O8
SR61atOldVillaRicaRoad
O38
SR92HiramAcworthHwy)atUS278/SR6
O9
SR61(VillaRicaHwy)atVernoyAikenRoad
O10
SR61(VillaRicaHighway)WinndaleRoad
O13
BurntHickoryRoadatBrownsvilleExt./StoutPkwy
O29
US278/SR6(JimmyLeeSmithParkway)atDepotDrive
O15
EastPauldingDriveatBrooksRackleyRoad
GeneralFundforSafetyandOperationalImprovementsSpecificlocationstobedeterminedthroughfutureanalysis
RoadwayMaintenance
CountywideRoadwayMaintenanceLocalMatchingFunds
PedestrianImprovements
Constructionofsidewalksinthevicinityofschools,parks,andotheractivitycenters
HumanServicesTransit
Phase
UTL,CST
$36,747,155
$29,397,724
$7,349,431
$0
$0
$36,747,155
UTL,CST
$33,847,724
$27,078,179
$6.769,545
$0
$0
$33,847,724
UTL,CST
$19,586,305
$16,870,102
$2,716,203
$0
$0
$19,586,305
SR92ProjectTotalsarenotcalculatedinOverallProjectTotalduetotheiruseindevelopingtheEstimatedFundingTotals
Page 37
January2015
PauldingComprehensiveTransportationPlan
DraftFinalReport
Table8.3:PhaseIIILongRangeImplementationPlan(20312040)
PhaseIIILongRange20312040
ProjectID
Roadway/Location
From
To
RoadwayCapacityImprovements
RC5
US278/SR6
SRBus6
SR61
RC13(PA032A)
DabbsBridgeRoad
SR61
US41inCobbCounty
RC20(PA036C)
CedarcrestRoad
SevenHillsExt
SR92
RC14
RidgeRoad
DallasNeboRoad
SR92
IntersectionImprovements
O11
SR120(HiramSudieRoad)atDavisMillRoad
O35
SR101atOldYorkvilleRoad
O3
SR120(BuchananHwy)atSR101
O17
US278/SR6(jimmyLeeSmithParkway)atBillCarruthParkway
O22
WestMemorialDriveatSRBus6(BuchananStreet)
GeneralFundforSafetyandOperationalIntersectionImprovementsSpecificlocationstobedeterminedthroughfutureanalysis
NewRoadwayConnections
NC5
CedarcrestRoadtoSR61Connector(PEOnly)
CedarcrestRoad
SR61
NC2
EastDallasBypass(PEOnly)
SRBus6
SR61
RoadwayMaintenance
CountywideRoadwayMaintenanceLocalMatchingFunds
PedestrianImprovements
Constructionofsidewalksinthevicinityofschools,parks,andotheractivitycenters
HumanServicesTransit
FTASection5307/5340FormulaFundsAllocation(FY20312040)
OverallProjectTotal
EstimatedFundingTotal
Difference
Page 38
Description
Jurisdiction
Sponsor
Phase
TotalEstimatedCost
Federal
State
Local
Bond
Total
Estimated
Funding
Wideningfrom4to6lanes
Wideningfrom2to4lanes
Wideningfrom2to4lanes
Wideningfrom2to4lanes
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
GDOT
PauldingCounty
PauldingCounty
PauldingCounty
ALL
ALL
ALL
ALL
$89,351,000
$93,278,877
$32,606,000
$70,331,000
$62,545,700
$60,164,876
$16,303,000
$35,165,500
$10,772,120
$16,323,803
$8,151,500
$14,066,200
$16,083,180
$15,857,409
$8,151,500
$21,099,300
$0
$0
$0
$0
$89,351,000
$92,346,088
$32,606,000
$70,331,000
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
IntersectionImprovements
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
ALL
ALL
ALL
ALL
ALL
ALL
$1,719,000
$385,000
$1,382,000
$7,946,000
$1,382,000
$33,000,000
$0
$0
$0
$0
$0
$3,000,000
$0
$0
$0
$0
$0
$4,000,000
$1,719,000
$385,000
$1,382,000
$7,946,000
$1,382,000
$26,000,000
$0
$0
$0
$0
$0
$0
$1,719,000
$385,000
$1,382,000
$7,946,000
$1,382,000
$33,000,000
NewRoadway
NewRoadway
PauldingCounty
PauldingCounty
PauldingCounty
PauldingCounty
ALL
ALL
$3,564,000
$10,017,000
$0
$0
$3,564,000
$0
$0
$10,017,000
$0
$0
$3,564,000
$10,017,000
LMIGLocalMatchingFunds
PauldingCounty
PauldingCounty
N/A
$5,980,110
$0
$0
$5,980,110
$0
$5,980,110
PedestrianImprovements
PauldingCounty
PauldingCounty
ALL
$1,108,950
$0
$0
$1,108,950
$0
$1,108,950
Transit/FormulaLumpSum
PauldingCounty
PauldingCounty
N/A
$50,768,481
$351,984,091
$40,614,785
$224,150,661
$224,982,459
$831,798
$0
$55,827,623
$57,313,438
$1,485,815
GeneralFund
$111,687,803
$117,845,653
$6,157,850
$0
$0
$0
$0
$300,000
$391,666,087
$400,141,550
$8,475,463
January2015
PauldingComprehensiveTransportationPlan
DraftFinalReport
8.1
ImplementationPlanScenarioModeling
To help evaluate the benefits of the capacity improvements proposed within the
implementation plan a series of modeling scenarios were tested within the ARCs Travel
Demand Model. Five total scenarios were tested, which include the capacity improvements
contained in Phase II (2030), Phase III (2040), and all capacity improvements within the
unconstrained project list (2040). These were compared to base scenarios for the years 2030
and 2040. The base scenarios assume projects with funding committed in the TIP to be
constructed and operational within the model. The capacity improvements modeled in each
buildscenarioarepresentedbelowinTable8.4.
Table8.4:RoadwayCapacityImprovementScenarios
Phase II (2030)
RC6: US 278/SR 6 from SR Bus 6 to RC6: US 278/SR 6 from SR Bus 6 to RC6: US 278/SR 6 from SR Bus 6 to
CobbCountyLine
CobbCountyLine
CobbCountyLine
RC9: SR 61 from DallasNebo Road to RC9: SR 61 from DallasNebo Road to RC9: SR 61 from DallasNebo Road to
US278/SR6
US278/SR6
US278/SR6
RC19: Cedarcrest Road from Harmony RC19: Cedarcrest Road from Harmony RC19: Cedarcrest Road from Harmony
GroveChurchRoadtoCobbCountyLine GroveChurchRoadtoCobbCountyLine GroveChurchRoadtoCobbCountyLine
RC20: Cedarcrest Road from Oak Glen RC20: Cedarcrest Road from Oak Glen RC20: Cedarcrest Road from Oak Glen
DriveandSR92
DriveandSR92
DriveandSR92
RC5: US 278/SR 6 from SR Bus 6 to SR RC5: US 278/SR 6 from SR Bus 6 to SR
61
61
RC13:DabbsBridgeRoadfromSR61to RC13:DabbsBridgeRoadfromSR61to
US41inCobbCounty
US41inCobbCounty
RC1: Dallas Acworth Highway from SR
92toEastPauldingDrive
RC21: East Paulding Drive from SR 120
toWestofBrooksRackleyRoad
RC14: Ridge Road from DallasNebo
RoadtoSR92
Source:Jacobs
The results from the modeling scenarios are presented in Table 8.5 below. The modeling
results for the Phase II improvements indicate that there is a small increase in daily Vehicle
Miles Traveled (VMT) within the county (0.3%) that would result from these improvements.
This shows that widenings will promote a very small uptick in driving within the county,
althoughsignificantreductionsintraveldelaywillberealized.Themodelindicatesthatdaily
Page 39
PauldingComprehensiveTransportationPlan
DraftFinalReport
hoursoftraveldelaywilldecreaseby12.1%withinthecounty.Theestimated20yearbenefits
oftheseimprovementsis$94,684,000.
The modeling results for Phase III improvements indicate a similar small increase in county
wideVMT,althoughamoresignificantreductionindailyhoursofdelayisshown.DailyVMTis
projectedtoincreaseby0.8%anddailyhoursofdelayareprojectedtodecreaseby20.1%.The
20yearfinancialbenefitsoftheseprojectsareestimatedtototal$309,544,000.
The unconstrained project list scenario shows similar slight increases in VMT with a very
significantreductionintrafficdelay.ThemodelingresultsindicateanincreaseinDailyVMTof
0.8%andadecreaseindailyofhoursofdelayof35.8%.Thetotal20yearfinancialbenefitsof
all capacity improvements included within the unconstrained project list are estimated to be
$549,896,000.
Table8.5:RoadwayCapacityScenariosModelingResults
PerformanceMeasure
DailyVMT
DailyHoursofDelay
Estimated20YearBenefits
PerformanceMeasure
DailyVMT
DailyHoursofDelay
Estimated20YearBenefits
PerformanceMeasure
DailyVMT
DailyHoursofDelay
Estimated20YearBenefits
Base(NoBuild)
Phase II - 2030
PhaseII
Difference
%Difference
3,785,800
3,799,000
13,200
0.3%
21,500
18,900
2,600
12.1%
$94,684,000
Base(NoBuild)
Difference
%Difference
4,525,500
4,559,900
34,4000
0.8%
42,200
33,700
8,500
20.1%
$309,544,000
%Difference
4,525,500
4,560,900
35,400
0.8%
42,200
27,100
15,100
35.8%
$549,896,000
Source:Jacobs,Atkins
Page 40
PauldingComprehensiveTransportationPlan
DraftFinalReport
9.0 TRANSITANDTRAVELDEMANDMANAGEMENT
RECOMMENDATIONS
Numerous transit and travel demand management needs have been identified within the
county through the previous CTP and public or stakeholder involvement. These needs have
beencorroboratedthroughdemographicanalysiswhichidentifiedhighconcentrationsoflow
incomepersons,elderly,andzerovehiclehouseholdsinparticularlocationswithinthecounty,
asdetailedintheInventoryofExistingConditionsReport.
Transitandtraveldemandmanagementneedswereprioritizedbaseduponnumerousfactors.
These include serving transit dependent demographic groups, high density population and
employment centers, major commuter corridors and projected growth areas. Other factors
include stakeholder/public support and promoting bicycle or pedestrian travel. Prioritization
identifiedthefollowingastopprioritieswithinthecounty:
Providing transit service to major activity centers including the Wellstar Paulding
Hospital, Paulding County Government Complex, Paulding Airport and Chattahoochee
TechnicalCollege.
AshuttlecirculatorserviceinthegreaterDallasandHiramareas.
ExtendingGRTAservicedeeperwithinthecountyalongUS278/SR6toalocationwithin
Dallas.
CurrentlytransitserviceinthecountyisprovidedbyGeorgiaRegionalTransitAuthority(GRTA),
PauldingTransitandDouglasCountyRideshare.Theseagenciesprovidecommuterexpressbus
service, local human services transit, and commuter vanpool service, respectively. Given the
lack of a local fixed route service provider, the ability to provide transit improvements is
limited. Based upon the existing conditions analysis, needs identification, and project
prioritization, recommendations for transit service and travel demand management are as
follows:
Expandvanpoolopportunitieswithinthecountyeitherthroughincreasingthenumber
of Douglas County Rideshare loading locations (Currently one location at SR 92 and
Page 41
PauldingComprehensiveTransportationPlan
DraftFinalReport
BrownsvilleRoadexists)orexploreopportunitiestodevelopaPauldingCountyVanpool
program. Additional locations identified for vanpool loading areas include the
CrossroadsCommunityatSR92andCedarcrestBoulevardandinthevicinityofUS278
atSR120(BuchananHighway).
Maintain and strengthen Paulding Transit as the population of Paulding County grows
and ages. Consider recommendations presented within the Paulding County Rural
Public Transit Plan. Major recommendations include lengthening hours of operation,
hiring more drivers and adding more buses to the existing fleet. Other
recommendationsincludemeetingGDOTgoalsforvehicleutilization,coordinaterouting
throughGlobalPositioningSystem(GPS)technology,utilizingGDOTschedulingsoftware
whenavailable,andmountingbicycleracksonbusestoaccommodatebicyclists.
Work with GRTA to explore opportunities to expand commuter service deeper within
the county. Potential locations for additional commuter bus loading lots include US
278/SR 6 at SR 120, US 278/SR 6 at the Paulding County Government Complex, US
278/SR6atSR120(CharlesHardyParkway)andtheCrossroadsCommunity(SR92at
CedarcrestRoad).
Pursue funding for a feasibility study to determine what financial and logistical
requirements would be needed to create a circulator shuttle service in the Dallas and
Hiram areas. Federal Transit Administration Urbanized Area Formula Grants Sections
5307and5340wouldlikelyprovidethefundingtomakethispossible.Thesegrantsdo
requireapercentageoflocalmatchingfundsbutmayassistwithsomeoperatingfunds
incertaincircumstances.
Page 42
PauldingComprehensiveTransportationPlan
DraftFinalReport
10.0 ACCESSMANAGEMENTCORRIDORS
TheAssessmentofCurrentandFutureNeedsReportidentifiedeightprioritycorridorsinmostneed
ofaccessmanagementstrategies.Theseinclude:
SR120(CharlesHardyPkwy)fromtheCobbCountyLinetoUS278/SR6
SR360(MaclandRd)fromtheCobbCountyLinetoSR120(CharlesHardyPkwy)
SR92fromtheDouglasCountyLinetotheCobbCountyLine
BillCarruthPkwyfromUS278/SR6toSR92
BillCarruthPkwyExtension(E.HiramBypass)fromBillCarruthParkwaytoUS278/SR6
RosedaleDrfromSR92toUS278/SR6
US278/SR6fromCobbCountyLinetoSR120
SRBus6fromUS278/SR6(EastofDallas)toUS278/SR6(WestofDallas)
The policy recommendations presented within this section are particularly important and needed
alongSR92,SR360,US278/SR6,andtheBillCarruthParkwayExtension.Theseroadwaysarein
needofproactiveaccessmanagementpolicies,inadvanceofplannedwidenings,orinthecaseof
theBillCarruthParkwayExtension,beingarecentlyconstructedroadwaythroughanundeveloped
area.
Atthistime,PauldingCountydoesnothaveformallyadoptedaccessmanagementpoliciesinplace,
howeveraccessmanagementstrategieshavebeenincorporatedthroughouttheCoutny.Aformal
development of access management regulations for use in development and land use review is
recommended. The following section provides a summary of policies that Paulding County may
considerindraftingaccessmanagementregulations.
PauldingCounty,andmunicipalitieswithinPauldingCounty,couldadoptlocalzoningordinancesto
direct future growth that supports access management policies. The location and nature of
commercialdevelopmentinparticularcanhavegreatimpactontrafficpatternsandsafety.Access
management policies encourage the smooth flow of traffic by reducing the number of roadway
accesspointsthroughconsolidatingaccessintoshareddriveways,spacedatregularintervalsalonga
roadway.Toencouragesmoothtrafficflowthenumberofdrivewaysandcurbcutsalongaroadway
couldbereducedthroughthefollowingmeans:
Prohibitsinglelotdrivewaysalongthoroughfaresandrequireaccesspointstobepublicthrough
streetsthatalsoserveadjacentdevelopment.
Limit commercial strip development access and prohibit singlelot residential access along
thoroughfares.
Implementzoningregulationsthatencouragenewcommercialdevelopmentstoclustertogether
in locationsset back from majorroadways, preferablyalongaccessroads. This would permit
Page 43
PauldingComprehensiveTransportationPlan
DraftFinalReport
businesseswithinthedevelopmenttheabilitytoshareaconsolidatedaccesspoint.Thecluster
conceptcanbeappliedsuccessfullytoshoppingcenters,minimalls,andmultipleusefacilities.
Require traffic impact analyses for businesses that generate high traffic volumes along
designated access management corridors. Traffic studies can be used to identify remedial
measurestolessenthetrafficimpactsofnewdevelopments.
Managingaccessonthoseroadwaysthathavebeenidentifiedforaccessmanagement,butwhich
are not projected to undergo widening in the near future (Rosedale Road, SR Bus 6, SR 120, Bill
Carruth Parkway) pose greater challenges than managing access on newly developed or newly
redesigned roadways. Along these corridors, access management implementation is likely to
happen much more slowly, on a piecemeal basis as development or redevelopment occurs.
Opposition by existing property and business owners may disrupt access management efforts.
Access management regulations that the County should consider pursuing on already developed
corridorsareasfollows:
Adoptacorridoroverlaydistrictthatrequiresadherencetoaccessmanagementguidelineswhen
developments make substantial improvements or expansions, have significant changes in trip
generation,orwhennewconnectionpermitsarerequested.
Addcentermediansatappropriatelocationstochannelizetrafficandreduceconflictpointsfrom
turningmaneuvers.Thiswillimprovetrafficflowthroughtheeliminationofweavemovements.
The separation of leftturn median breaks from travel lanes would provide space for
deceleration,thusimprovingtrafficoperationsandreducingcrashpotential.
Develop a supportive street network that could relieve traffic pressures on the main arterial.
Thiscouldbeachievedthroughfrontageroads,backageroads,andserviceroads.
Page 44
PauldingComprehensiveTransportationPlan
DraftFinalReport
11.0 BICYCLEANDPEDESTRIANRECOMMENDATIONS
Bicycle and pedestrian facilities are an integral part of any effective transportation network.
Theyallowfortripdiversityamongtransportationmodesandpromoteahealthy,sustainable,
and active lifestyle among transportation users. Use of alternative modes can also reduce
congestion and create economic activity centers where pedestrians and bicyclists begin to
congregate. Improvements to alternative mode infrastructure also increase community
livabilitybycreatingnewaccesspointstocommunityandrecreationalfacilities.
Paulding County is poised to implement a diverse range of bicycle and pedestrian
enhancements.TheSilverCometTrailisagreatassettotheCountyandprojectswhichincrease
accessandamenitiessurroundingthisfacilityarecritical.Furthermore,PauldingCountysmany
residential neighborhoods may be enhanced through implementation of sidewalk and bicycle
facilities which allow residents to travel safely and remain healthy and active. Figure 11.0
displays allrecommended bicycle and pedestrian projectsin the Paulding County area. These
includeavarietyoffacilitytypesandarelocatedaccordingtoneedsidentifiedbythepublicand
theCTPprocess.
Anoverviewbyprojecttypeinthefollowingsectiondetailsthebenefitsassociatedwitheach
projecttype,aswellasthestrategiesusedtodeveloptheserecommendationsandtheoverall
character of the proposed bicycle and pedestrian network. Implementation strategies and
potentialfundingsourcesarealsoreviewed.
Page 45
PauldingComprehensiveTransportationPlan
DraftFinalReport
Figure11.0:RecommendedBicycleandPedestrianProjects
Page 46
PauldingComprehensiveTransportationPlan
DraftFinalReport
11.1 PedestrianFacilities
This section details recommendations for pedestrian facilities (sidewalk segments) within the
county. While pedestrian projects have historically been the purview of the Parks and
RecreationDepartment,thissectionprovidesaprioritizedlistofprojectsforimplementation,
shouldfundingbecomeavailable.ThisinformationisincludedinTable11.0,whichdetailsthe
projectlocation,extent,length,andestimatedcostforeachproject.
Sidewalk segments were prioritized based on a variety of factors. These include factors that
encourage multimodal travel, such as population and employment density and service to
transitdependent populations. Other considerations included serving areas with noted
pedestriansafetyconcernsandprovidingconnectionsalongmajortransportationcorridors.
Table11.0:PrioritySidewalkRecommendations
Priority
Ranking/
Score
1/23
2/22
3/21
Project
ID
BP40
BP62
BP45
SR61
SRBus6
WestMemorialDrive
4/20
5/20
6/19
7/18
8/17
9/16
10/16
11/16
12/16
13/15
14/15
15/15
16/15
17/14
18/14
19/14
20/14
21/14
22/14
23/14
24/13
25/13
26/13
27/13
BP11
BP43
BP38
BP22
BP24
BP13
BP14
BP15
BP28
BP19
BP20
BP29
BP41
BP2
BP5
BP6
BP16
BP17
BP42
BP46
BP9
BP27
BP31
BP37
DepotDrive
US278/SR6
SouthMainStreet
MetromontRoad
MustangDrive
EastFosterAvenue
EastPauldingDrive
EastPauldingDrive
OldVillaRicaRoad
LesterDrive
MaclandRoad
OldVillaRicaRoad
SR92
BrownsvilleRoad
CedarcrestRoad
CenterStreet
GravesRoad
HiramSudieRoad
SR92
WilliamsLakeRoad
CowboyPath
OakStreet
PineValleyRoad
SeaboardAvenue
28/12
29/12
30/12
31/12
BP4
BP12
BP26
BP32
CedarcrestRoad
DueWestRoad
NeboRoad
PineValleyRoad
Page 47
ProjectLocation
To/From
OscarWaytoKirkDrive
OldHarrisRoadtoHenryHollandDrive
BagbyPathtoPauldingMemorialHospital
US278/SR6(JimmySmithParkway)to
RosedaleDr
DepotDrivetoCleburneParkway
ConstitutionBoulevardtoSeaboardDrive
US278/SR6(JimmySmithPkwy)toRosedaleDr
HeritageWaytoDonbieDrive
DallasCityParktoHardeeStreet
LostMeadowsDrivetoHopeDrive
DallasAcworthHighwaytoMt.TaborPark
SR61toIvyTraceLane
DallasCityParktoSRBus6
SR92toSR120(CharlesHardyParkway)
SR61toStationDrive
HardyCircletoEastPauldingMiddleSchool
SR92toSweetwaterPass
CobbCountyLinetoHighcrestDrive
SeaboardAvenuetoSR92
GravesRoadSpurtoGravesRoad
SR61toSouthernOaksDrive
CedarcrestRoadtoRoyalSunsetDrive
JADobbinsMiddleSchooltoFourOaksDrive
EastPauldingHomeParktoForestHillsDrive
SR92toSeaboardAvenue
TaylorFarmParkWesttoNorthviewLane
TowneParkDrivetoPowderSpringsStreet
HarmonyGroveChurchRoadtoArthurHills
Drive
DallasAcworthHighwaytoAutumnCreek
DallasNeboRoadtoSwanDrive
TaylorFarmParkWesttoWinterParkLane
Project
Length
(Miles)
.19
1.52
.21
$148,000
$1,139,000
$164,000
.23
1.17
.26
.53
.16
.24
1.61
.44
.27
.14
1.42
.38
.43
.22
.36
.37
.33
.28
.26
.33
.24
.34
.16
.09
$179,000
$1,596,000
$203,000
$413,000
$124,000
$187,000
$1,225,000
$344,000
$211,000
$109,000
$1,106,000
$296,000
$335,000
$171,000
$280,000
$288,000
$257,000
$218,000
$203,000
$257,000
$187,000
$265,000
$124,000
$70,000
.67
.14
.26
.64
$523,000
$109,000
$203,000
$499,000
Estimated
Cost
PauldingComprehensiveTransportationPlan
DraftFinalReport
Priority
Ranking/
Score
32/12
33/12
34/12
35/11
36/11
37/11
38/11
39/10
40/10
41/10
42/9
43/8
44/8
46/6
47/6
48/5
Project
ID
ProjectLocation
To/From
BP33
BP34
BP35
BP1
BP3
BP7
BP21
BP23
BP25
BP36
BP30
BP8
BP18
BP10
BP39
BP44
RidgeRoad
RidgeRoad
RidgeRoad
BakersRidgeRoad
CedarcrestRoad
ClontsRoad
MeinMitchellRoad
MulberryRockRoad
NeboRoad
ScogginsRoad
PineShadowsDrive
ColbertRoad
HollySpringsRoad
CrossroadChurchRoad
SR101
WaysideLane/ClearCreekDr
DallasNeboRoadtoAustinBridgeRoad
HughesRoadtoRidgeRunDrive
HughesRoadtoFarmStreet
RidgeRoadtoCharityDrive
atFloydSheltonElementary
WileyDrivetoHalHutchinsElementary
RidgeRoadtoCountryVillageDrive
DokeCochranRoadtoSR61
NeboElementarySchooltoPineShadowsRoad
SR61toSugarMillDrive
NeboRoadtoSmithFergusonRoad
AbneyElementarytoLegacyPointDrive
WoodwindDrivetoHighway101
WintervilleDrivetoYorkvillePark
CrossroadsChurchRoadtoRunnellRoad
US278/SR6toPooleElementarySchool
Project
Length
(Miles)
.59
.16
.29
.28
.29
.17
.04
.78
.2
.35
.15
.44
1.01
.25
.16
.21
Estimated
Cost
$459,000
$124,000
$226,000
$218,000
$226,000
$133,000
$31,000
$608,000
$156,000
$273,000
$117,000
$344,000
$218,000
$194,000
$124,000
$164,000
Source:Jacobs
Page 48
PauldingComprehensiveTransportationPlan
DraftFinalReport
approximately $550,000 in 2018 dollars. An annual allocation has been added to the fiscally
constrainedimplementationplan,presentedinSection8.0ofthisreport.
11.2 BicycleLanes
Bicyclelanesprovidemultiplebenefitswherevertheyareimplemented.Stripedandseparated
bicyclelanescreatethesafestenvironmentforbicycletravelandmayalsoservetocalmtraffic
alongroadwayswheretheyareimplemented.Thiscreatesbothasaferandmorecomfortable
environment for pedestrians, bicyclists and others to travel. Safety is the greatestpriority for
bicycle lane implementation. Bicycle crashes with large vehicles moving at high speeds are
extremelydangerousandpotentiallyfatal.Theuseofpaintedbicyclelanesratherthanshared
lanesorotherfacilitytypesisanimportantsafetymeasurethatprotectsbicyclistsfromprimary
trafficandbooststheconfidenceoflessexperiencedbicyclists.
Withthesecharacteristicsofbicycletravelinmind,severalkeycorridorswereselectedforthe
implementation of bicycle lanes. Many of these corridors are also recommended to receive
wideningsorcapacityincreases;implementationofbicyclelanesshouldbeconductedaspart
ofthesewideningprojectswheneverpossibleinordertobalancetransportationimprovements
acrossmodesandcreateamultimodalnetwork.Simultaneousimplementationofbicycleand
capacityprojectsalsocreatesopportunitiesforincreasedcostefficiencyandsharingoffunding
sources. Table 11.1 displays the recommended bicycle lanes for Paulding County, excluding
thoseprojectsincludedaspartoflargerroadwaywideningandcapacityprojects.Bicyclelanes
includedinwideningsaredisplayedinFigure11.0.
Table11.1:RecommendedBicycleLanes
PriorityRanking ProjectID
ProjectLocation
Extent
Length(Miles) EstimatedCost
BP59
RidgeRd
BakersBridgeRdtoSR61
4.74
$14,609,000
BP58
MulberryRockRd RockCrusherRdtoSR61
1.36
$4,192,000
BP61
CedarcrestRd
HarmonyGrovetoSevenHills
0.78
$2,404,000
BP60
SR61
MtMoriahRdtoDabbsBridgeRd
4.90
$15,103,000
Source:Jacobs
11.3 MultiUseTrails
Multiusetrailsarewidepavedtrails,typically10feetwideorgreater,whichproviderecreation
opportunitiesforpedestriansandbicyclist.Motorizedtransportationonthesetypesoftrailsis
typicallyprohibited.TheSilverCometTrailisthemajorpedestrianandbicycleamenitywithin
thecounty.Thismultiusetrailrunsapproximately17.6mileswithinthecounty,transectingthe
county from east to west. Two of the multiuse trail recommendations presented in this
section involve building upon this amenity through trail spurs which would link major county
parkstotheexistingtrail.
Page 49
PauldingComprehensiveTransportationPlan
DraftFinalReport
TherecommendedtrailprojectsaredetailedinTable11.2below,withestimatedprojectcosts.
AspurfromtheSeaboardDrivetrailheadoftheSilverCometTrailisrecommendedtoconnect
tothenewlyconstructedVeteransParkandPauldingCountyGovernmentComplex.Coupled
withtheplannedexpansionofsidewalksalongSouthMainStreet,fundedthroughSPLOST,this
would provide a continuous safe pedestrian connection to downtown Dallas from the Silver
CometTrail.TheStricklandParkConnectionwouldconnectStricklandParktotheSilverComet
TrailatanaccesspointoffofRagsdaleRoad.Inadditiontothetwotrailspurs,amultiusetrailin
southernPauldingCountyisrecommendedinthewoodedareabetweenGeorgianParkwayand
PegColeBridgeTrail.
Table11.2:RecommendedMultiUseTrails
Priority
Ranking
ProjectID
BP57
BP56
BP55
ProjectLocation
BetweenGovernmentComplexandSeaboardDrive
Trailhead
StricklandParkConnectionBetweenWeddingtonRoadand
StricklandPark
NearPegColeBridgeTrailBetweenGeorgianParkwayand
PegColeBridgeTrail
Length
(Miles)
Estimated
Cost
0.48
$373,000
0.65
$504,000
0.34
$267,000
Source:Jacobs
11.4 FundingforRecommendedBicycleandPedestrianFacilities
Bicycleandpedestrianfacilitiescanbefundedthroughavarietyofsources.Thisincludeslocal,
state,andfederalsourcesandthroughnonprofitorganizations.Privatesectorentitiescanalso
be required to fund these improvements through zoning requirements. This section details
potentialfundingsourcesandprogramstobepursuedbytheCounty.Theseinclude:
SPLOSTFunding.TheCountyhasthepotentialtofundasignificantnumberofproposed
bicycle and pedestrian improvements through revenues collected through SPLOST
initiatives.ItisrecommendedthatanannualallocationofSPLOSTrevenuesissetaside
to fund needed sidewalk segments within the county. It is recommended that
approximately$500,000ayearisallocatedtowardsthispurpose.Atthisfundinglevel
all recommended sidewalk segments could be funded within the planning horizon of
2040.
MAP21 TAP Funds. The federal transportation funding bill, Moving Ahead for
Progress in the 21st Century (MAP21), provides funding for bicycle and pedestrian
improvements through the Transportation Alternatives Program (TAP). This program
combines previously separate funding programs, Transportation Enhancements,
RecreationalTrailsProgram,andSafeRoutestoSchools,intoonefundingsource.These
funds may be used construct onroad bicycle lanes, offroad multiuse trails, and
sidewalks. TAP funds are administered by the state DOT and are awarded via a
competitiveapplicationprocess.
Page 50
PauldingComprehensiveTransportationPlan
DraftFinalReport
FederalandStateFundedCapacityImprovements.Bicycleandpedestrianfacilitiesare
recommendedtoaccompanymajorroadwideningprojectsproposedwithinthecounty.
This includes bicycle lanes and sidewalks along these corridors. The cost estimates
provided in this plan for capacity projects assumes bicycle lanes and sidewalks will
accompanytheseprojects.Inthesesituations,federalandstatefundingsourcescould
beusedtoenhancepedestrianandbicycleinfrastructureinthecounty.
PATHFoundation.ThePATHFoundationisanonprofitorganizationwhosemissionisto
develop a system of interlinking multiuse trails throughout metro Atlanta. The
organizationfundstrailsthroughacombinationofpublicsources,corporatedonations
andprivategifts.ThePATHFoundationwasresponsiblefordevelopingtheSilverComet
Trail and may be in the position to expand upon this trail through the construction of
recommendedtrailspurstoVeteransParkandStricklandPark.
PauldingCountyParksandRecreationDepartment.TheCountysParksandRecreation
Department is tasked with ensuring quality recreational opportunities are available to
allcountyresidents.Bicycleandpedestrianfacilitiesprovideresidentsopportunitiesfor
recreationandarefoundatpublicparksthroughoutthecounty.Thereisthepotential
forlocalfundingtobesecuredthroughthisdepartmentforthedevelopmentofbicycle
and pedestrian infrastructure. Many recommended sidewalk segments and multiuse
trailsprovidelinkagestocountyandcityparksandwouldaidinexpandingrecreational
opportunitiestocountyresidents.
Private Sector. The private sector provides another potential funding source for the
construction of bicycle and pedestrian facilities. Developers can be required to build
facilities as a condition of zoning approval. While this approach could result in an
incomplete network of sidewalks or trails, proactive planning with an emphasis on
networkconnectivitycouldbeemployedtohelpavoidthisissue.
Page 51
PauldingComprehensiveTransportationPlan
DraftFinalReport
12.0 BRIDGERECOMMENDATIONS
This section provides an overview of the recommendations for bridge projects and their
relationship to the overall Paulding County roadway network. This study utilized information
fromtheGDOTOfficeofBridgesandStructuresaswellasfromPauldingCountytoinventory
and identify all of the bridges within the county. In this process, bridges were evaluated in
termsoftheirconditionandfunctionalityinwhatisreferredtoasasufficiencyrating.Thestate
uses a rating formula based on a number between zero and 100, with zero indicating a fully
deficient bridge and 100 representing a fully sufficient bridge. Some of the elements of a
bridgessufficiencyratingincludethenumberoflanes(relativetotheroadway),trafficcounts,
structuralcondition,anddeckcondition.
Bridge sufficiency ratings were used to identify bridges in need of repair or replacement. A
bridgemustexhibitaratingof50orbelowtoqualifyforfederalreplacementfunds.Allother
bridges list their recommended rehabilitation or maintenance recommendations from the
January16,2013GDOTInspectionReport.Thosebridgeswithsufficiencyratingsof65orbelow
were identified as needing either replacement or rehabilitation. Rehabilitation can include
maintenanceorrepairofbridgedecks,expansionjoints,bridgerailings,foundations,andpiers
etc. Bridge rehabilitation can be a costefficient solution for bridges with sufficiency ratings
below 50 if it can be demonstrated that the rehabilitation will improve the bridge to an
acceptablesufficiencyrating.
In the assessment process, bridges were divided into two categories once the data was
compiled,thoseinneedofrehabilitation/maintenanceandthosethatneedtobereplaced.Its
worth noting that some of the bridges did not have a complete National Bridge Inventory
inspection performed and therefore do not have a sufficiency rating. These structures were
mostlyprivateusebridgesthatspannedpublicroadsandGDOTisresponsibleforcheckingtheir
clearancelevelasifthereweresignificantdeficiencies.
The needs assessment identified eight bridges needing to be either replaced, repaired or
rehabilitated.Theassessmentalsodeterminedthatthreeofthedeficientbridgeswerealready
slatedforconstructionin2015.ThefollowingTable12.0providesdetailontheseeightbridges.
Page 52
PauldingComprehensiveTransportationPlan
DraftFinalReport
Table12.0:BridgeProject/ImprovementRecommendations
StructureID
22350120
Sufficiency
Rating
15.88
22350400
49.01
22300260
49.95
22350290
56.28
22300250
57.42
22350450
60.64
22350640
61.50
22350110
64.81
Facility
Carried
Willow
SpringsRd
Morningside
Drive
Dallas
Acworth
Highway
PineValley
Road
Feature
Intersected
SilverCometTrail
Dallas
Acworth
Highway
DueWest
Road
PossumCreek
Oberlochen
Way
Carrington
Lake
Mt.Olivet
Road
LickLogCreek
Comments/Recommendations
Bridgebuiltin1941.Currentlyunderbidfor
construction.
Bridgebuiltin1979.Bridgeisinneedofreplacement.
PickettsMill
Creek
Bridgebuiltin1940.Setforconstructionin2015.
Sweetwater
Creek
Thisbridgeisrecommendedforreplacementor
maintenance/rehabilitation.Thisstructurerequires
postingduetoinsufficientshearcapacityofthe
concretesuperstructure.Areplacementstructureis
requiredtoupgradethisstructuretoapointwhere
postingisnolongerrequired.Maintenance
recommendationsareprovidedtomaintainthis
structureatthecurrentrating.
Setforconstructionin2015.Bridgestructureisinfair
conditionwithcorrosionandminorsectionlossofthe
steelsuperstructure.
Thisbridgeisrecommendedformaintenanceor
rehabilitation.Thebridgestructureisinfaircondition;
Concreteencasementsonpile#1and#2andbenthave
undermined.
Thisbridgeisrecommendedformaintenanceor
rehabilitation.Thiscorrugatedmetalpipeculvert
servesasalakespillwayandoverflow.Maintenance
recommendationshavebeenidentified.
Thisbridgeisrecommendedforreplacementor
maintenance/rehabilitation.Thisstructurerequires
postingduetoinsufficientshearcapacityofthe
concretesuperstructure.Areplacementstructureis
requiredtoupgradethisstructuretoapointwhere
postingisnolongerrequired.Maintenance
recommendationshavebeenidentifiedtomaintain
currentrating.Atthetimeofinspection,theposting
signatthenorthernendofthestructurewasmissing.
Thissignisrequiredandmustbereplaced.
PickettsMill
Creek
Sweetwater
CreekTributary
Pumpkinvine
Creek
Source:GDOT
The maintenance, replacement, and repair of deficient bridges are critical to a safe
transportationsystem.Inordertoachievethis,PauldingCountyshouldcontinuetocoordinate
with GDOT for routine bridge inspections every two years, while the County continues to
review the bridge reports for any potential next steps/activities. Since the former bridge
replacement program active under SAFETEALU has expired, the County should continue to
Page 53
PauldingComprehensiveTransportationPlan
DraftFinalReport
adheretothecurrentMAP21legislationindeterminingtheconditionsandfundingeligibility
fortheirbridges.Additionalrecommendationsforthecountysbridgesinclude:
AllCountybridgeswithsufficiencyratingsof50orlowershouldbefurthermonitored
andinvestigated.
All County bridges with substantial structural issues should be prioritized for
replacement.
AllCountybridgeswithmoderateissuesshouldbeconsideredforrehabilitation.
For those County bridges that are not on state routes, once a funding source is
identified, the County should consider allocating a lineitem dollar amount per year for
maintenanceandrepairtopreservethelifeofbridges.
Page 54
PauldingComprehensiveTransportationPlan
DraftFinalReport
13.0 FREIGHTRECOMMENDATIONS
TheAssessmentofCurrentandFutureNeedsReportidentifiedfourmajortruckingrouteswithinthe
county:
SR92
US278/SR6
SR61
SRBusiness6
Thesefreightcorridorsareabletoadequatelyserveexistingandprojectedfuturetrucktrafficina
safeandefficientmanner.SR92,US278,andSR61havebeendesignatedasregionalfreight
corridorswithintheARCsAstroMap.Thesecorridorsexhibitdesigncharacteristicsthatfacilitate
heavytrucktravelincludingwideturningradii,widelanewidths,andlargeturningstorage.
ThegreatestpotentialfortruckandpassengervehiclesconflictscanbefoundwithintheCityof
Dallas.AtthistimeheavytrucktrafficisgenerallyconfinedtoSR61andSRBusiness6,bothofwhich
providereasonablethroughputcapacity,accessmanagement,andturningstoragetosafelyand
efficientlyfacilitatefreightmovement.Astheseroutesbecomemorecongestedinthecoming
decades,heavilycongestedintersectionsmaybenefitfromoperationalimprovementssuchas
increasedturninglanestorageandaccessmanagement,increasedturningradii,andexpanded
shoulders.
Increasedgrowthinindustrialandcommerciallandusesincomingdecadeswilllikelyincreasethe
demandforefficientandsafetrucktransportation.Astheseusesdevelop,PauldingCountymust
continuetoimplementtruckrelateddesignfeaturesalongindustrialandcommercialgrowth
corridors.Keytruckdesignfeaturesinclude:
Increasedturninglanestorage,whichtakesintoaccounttheimpactoftrucklengths
(approximately3.5passengercars)onintersectionneeds.
Widercurbradiiwithpedestrianrefugeislands.Thispermitstruckstoturnsafelyand
providespedestrianswithasafecrossingpointandhighvisibility.
Increasedlanewidthsandshoulders,whichreducesconflictswithothervehicles.
Accessmanagementpoliciesthatconsolidatedrivewaysandcurbcutstoincreasefreight
mobility.
Enhancedconnectionstointerstatesandotherregionalfreightcorridors,aswellas
intermodalconnections(rail,air).
Page 55
PauldingComprehensiveTransportationPlan
DraftFinalReport
Inadditiontosupportfortruckfriendlyroadways,theCountymayneedtoprovideadditional
infrastructureinthefuturewhichpermitsheavytruckstobypassurbancenters,suchasDallas.
Bypasses,liketheproposedWestandEastDallasBypassesincludedinthisplansunconstrained
projectlistmaybeusedtodiverttrucktrafficawayfromcongestedurbanstreetswithsmallerlanes
andcurbradii.Removingtrucktrafficfromurbancentersmaymakethemsaferandmoreattractive
forpedestriansorbicyclistswhomayfrequenttheareaforrecreationalorleisureactivities.
WhilemuchofPauldingCountysexistinggrowthisnoturbaninnature,itisimportanttoconsider
thepossibilitythattrucksmaystillinterferewithnewlyconstructedneighborhoodsandpublic
facilities,whetherthoseareparks,schools,orothercenters.Theprovisionofsafe,dedicatedtruck
infrastructurewouldpermitnewdevelopmentstosucceedwithoutthedangersandinefficiencies
imposedonthembyheavytrucksforcedtooperateoninadequateroadways.
Page 56
PauldingComprehensiveTransportationPlan
DraftFinalReport
14.0 CONCLUSIONS
ThefinalrecommendationsofthisplanshouldbeusedasaguidefortheCountyasitcontinues
to build upon and improve the transportation system within the county. Table 14.0 below
providesasimplifiedlistofrecommendedprojectsandaphasingplantoserveasthisguide,in
addition to the recommendations presented in previous sections addressing access
management,freight,transitandbridgeneeds.OnanannualbasistheCountyshouldreview
thisimplementationplanandmakeadjustmentsasneeded.Thefindingsofthisreportshould
be used as a foundation and starting point for future CTP updates, which should occur every
fiveyearsormoreoftenifcircumstancesrequire.
Table14.0:RecommendedProjectImplementationPlan
ProjectID
PhaseIShortRange20152019
Roadway/Location
From
ARCTIP20142019
PA062
NewRoadwayatTechnologyPark(Ph1)
PA063
NewRoadwayatTechnologyPark(Ph2)
PA027
SR92BridgeReplacementandWidening
CO367
SR360(MaclandRoad)
PA061C1
AR5307PA
PA092A
PA092B1
AirportParkway
AirportParkway
SouthernRRinHiram
SR120
SR61(VillaRicaHighway)Segment3Widening
FTASection5307/5340FormulaFunds(HumanServicesTransit)
SR92Widening
DallasNeboRoad
Brown/MaloneSt
SR92Widening
NeboRd
E.PauldingMiddle
School
CedarcrestRoad
PA092C
SR92Widening
PA092E
SR92Widening
PA095
JohnstonSt,GriffinSt,SpringSt,andParkStPedFacility
PA101A
PauldingCountyATMSSystemExpansionPhase1
PA101B
PauldingCountyATMSSystemExpansionPhase2
SPLOSTIVFundedProjects20152017
SP1
PickettsMillCreekBridgeReplacementatDallasAcworthHwy
SP2
PossumCreekBridgeReplacementatDallasAcworthHwy
SP3
SouthMainStreetBridgeandSidewalkImprovements
SP4
BoboRoadandMt.TaborChurchRoadatSR360(MaclandRoad)
SP5
DallasAcworthHighwayatFryRd/Mt.TaborRd
IntersectionImprovements
O14
RosedaleDriveatMetromontRoad
O20
US278/SR6(JimmyCampbellParkway)atSR61(VillaRicaHwy)
E.MemorialDriveatLegionRd,SRBusiness6atLegionRd,E.
O24/25/26
MemorialDriveandSRBusiness6
O23
SR61(ConfederateAvenue)atSRBus6
O33
SR101atGoldMineRoad
O32
SR360(MaclandRoad)atSRBusiness6
O21
US278/SR6(JimmyCampbellParkway)atSR61(VillaRicaHwy)
RoadwayMaintenance
CountywideRoadwayMaintenanceLocalMatchingFunds
PedestrianImprovements
Constructionofsidewalksinthevicinityofschools,parks,andotheractivitycenters
Page 57
To
NewCuldeSac
NewCuldeSac
LostMountainRoad
JimmyCampbell
Parkway
NeboRd
SR120(Marietta
Hwy)
OldBurntHickoryRd
CobbCo.Line
GovernmentComplex
SeaboardDrive
LMIGLocalMatchingFunds
PedestrianImprovements
PauldingComprehensiveTransportationPlan
DraftFinalReport
ProjectID
Roadway/Location
From
To
TransportationFeasibilityStudies
Corridorstudiesandfeasibilitystudiesforimprovingeasttowestconnectivitywithinthecounty
PhaseIIMidRange20202030
lntersectionImprovements
O1
SR120(CharlesHardyParkway)atSRbusiness6
O2
SR92(HiramAcwothHighway)atE.PauldingDrive
O12
SR92(HiramAcworthHighway)atOldBurntHickoryRoad
O7
SR61(VillaRicaHwy)atHartRoad
O8
SR61atOldVillaRicaRoad
O9
SR61(VillaRicaHwy)atVernoyAikenRoad
O10
SR61(VillaRicaHwy)atWinndaleRoad
O13
BurntHickoryRoadatBrownsvilleExt./StoutPkwy
O15
EastPauldingDriveatBrooksRackleyRoad
O29
US278/SR6(JimmyLeeSmithParkway)atDepotDrive
O27
US278/SR6(JimmyLeeSmithParkway)atHiramPavilionSouth
O36
SR92(HiramAcworthHighway)atRosedaleDrive
O38
SR92(HiramAcworthHighway)atUS278/SR6
GeneralFundforSafetyandOperationalIntersectionImprovementsspecificlocationstobedeterminedthroughfutureanalysis
RoadwayCapacityImprovements
SR120(Charles
PA092B1
SR92
NeboRoad
HardyPkwy)
EastPaulding
OldBurntHickory
PA092C
SR92
MiddleSchool
Road
PA092E
SR92
CedarcrestRoad
CobbCountyLine
RC1
DallasAcworthHighway
EastPauldingDrive
SR92
RC6
US278/SR6
SRBus6
CobbCountyLine
RC9
SR61(VillaRicaHighway)
DallasNeboRoad
SR92
HarmonyGrove
RC19
CedarcrestRoad
CobbCountyLine
ChurchRd
WestofBrooks
RC21
EastPauldingDrive
SR120
RackleyRoad
RoadwayMaintenance
CountywideRoadwayMaintenanceLocalMatchingFunds
LMIGLocalMatchingFunds
PedestrianImprovements
Constructionofsidewalksinthevicinityofschools,parks,andotheractivitycenters
PedestrianImprovements
HumanServicesTransit
FTASection5307/5340FormulaFundsAllocation(FY20202030)
PhaseIIILongRange20312040
IntersectionImprovements
O3
SR120(BuchananHighway)atSR101
O11
Sr120(HiramSudieRoad)atDavisMillRoad
O17
US278/SR6(JimmyLeeSmithPkwy)atBillCarruthPkwy
O22
WestMemorialDriveatSRBus6(BuchananStreet)
O35
SR101atOldYorkvilleRoad
RoadwayCapacityImprovements
RC5
US278/SR6
RC13
DabbsBridgeRoad
(PA032A)
Page 58
SRBus6
SR61
SR61
US41/Cobb
PauldingComprehensiveTransportationPlan
DraftFinalReport
ProjectID
Roadway/Location
RC14
RidgeRoad(PEonly)
RC20
CedarcrestRoad
(PA036C)
NewRoadways
NC5
CedarcrestRoadtoSR61Connector(PEonly)
NC2
EastDallasBypass(PEonly)
RoadwayMaintenance
CountywideRoadwayMaintenanceLocalMatchingFunds
PedestrianImprovements
Constructionofsidewalksinthevicinityofschools,parks,andotheractivitycenters
HumanServicesTransit
FTASection53007/5340FormulaFundsAllocation(FY20312040)
From
To
DallasNeboRoad
SR92
SevenHillsExt.
SR92
CedarcrestRoad
SRBus6
SR61
SR61
LMIGLocalMatchingFunds
PedestrianImprovements
Transit/FormulaLumpSum
Source: Jacobs
Tohelprealizetherecommendationswithinthisplanintergovernmentalcooperationisessential.
Thisincludescontinuingcoordinationwithothercountydepartments,localmunicipalitiesand
neighboringcountygovernments.Coordinationwithstateandregionalagenciesisalsocriticalfor
successfulprojectdelivery.Withtransportationfundingbeinglimitedcooperativeandcoordinated
relationshipswithGDOTandtheARCshouldbefosteredandmaintained.Inaddition,jointefforts
shouldbepursuedwithneighboringjurisdictions,suchasCobbandDouglasCounties,tohelpmeet
regionaltransportationneedsandgoals.
Page 59
PauldingComprehensiveTransportationPlan
DraftFinalReport
AppendixAPublicOutreachSummary
AppendixA
A presentation of key findings from the Inventory of Existing Conditions Report and a question
and answer session; and
A participation exercise where attendees were asked to provide input on where certain types of
improvements were needed throughout the County. Each station featured a map of needs
previously identified by the Technical and Steering Committees. These maps served as
springboards to further discussion as attendees validated and supplemented the list of existing
needs.
Following the presentation, Mr. Carroll instructed participants to visit each table and provide feedback
by placing dots on the displays as described above. Consultant team members were also available at
each table to assist and take additional comments. Listed below are improvements that were either
suggested and/or confirmed by meeting attendees. For ease of review, they have been organized by
improvement type.
Capacity Improvements (Roadway Widenings)
Page 2
Note: One attendee also proposed a new bypass from SR 120 at SR 101 north to SR 61 (Cartersville
Highway), but it was largely opposed by other attendees because it traversed the Paulding Forest WMA.
Intersection Improvements
New vanpool and park and ride area at SR 120 (Charles Hardy Parkway) at US 278/SR 6 (Jimmy
Lee Smith Parkway)
New shuttle service in and around Dallas.
Note: There was also some attendees that voiced opposition to transit services of any kind in the
county.
Sidewalks
Page 3
May 2014
The intersection in Hiram of 278 and 92 has got to be the biggest traffic nightmare. There is only
one lane coming from 120 to the 278 intersection, and once you arrive there is a very short left
turn lane to get onto 278 and to the stores- cars get backed up for miles! The same holds true
along 92 coming from Douglasville, though the turn lane is not as bad. Desperately needed is a
double much longer left turn lane from 120! There is a lot of vacant land on the corner and with
Hobby Lobby opening soon, plus I see another new building going up in front of Hobby Lobby;
the traffic is only going to get a lot worse at that intersection. Take the vacant land, expand the
left turn lane to two left turning lanes! I have learned never to try to turn out of the old Kmart
area- can take forever till you can get out and only if an oncoming motorist is nice enough to let
me out.
I used to come down to Hiram to shop a lot but hate the traffic so have cut back on my trips.
Have discovered sadly to say that going to Acworth saves me time.
I recently saw an article stating that Paulding County was seeking info on traffic problems in
county. Suggest a hazard exists at the subject intersection. Left turn traffic lights need to be
added. There have been two accidents that I am aware of, the latest with injuries and I just
noticed the one sign in the intersection has been mowed down, possibly by someone trying to
avoid a near miss.
I regret that I couldn't attend the meeting on May 8th. I would like you to take a consideration
of putting a traffic light at the intersection of Merchants Drive and Coach Bobby Dodd Rd. this
intersection has become more and more busy and dangerous. A few years ago I totaled my car
while trying to turn onto this intersection. Also, Old Harris road has become a "short cut" to
Hwy 278, which adds even more traffic. Please consider adding a traffic light here.
We live on Poplar Springs Road (PSR) @ Macland Rd,(SR360) off Macland Circle. Poplar Springs
is an up and coming route of choice that connects two Arterial road, Macland Rd and 278.
Traffic on PSR has grown dramatically since the 20 years weve been here. Macland Circle is a
narrow, 15 wide cut-thru from PSR to Macland. We are excited about the completion of E
Hiram Pky, however, it will by-pass traffic directly to PSR, a two lane road to get to Macland Rd.
With Macland Rd widening by GDOT to begin within 2 years, I can see PSR will take a load of
traffic, the current 2 lanes cannot support. I see a need for Poplar Springs Rd to become a
median divided 4-lane. It was on a previous TIP but no action has occurred. Along with that
could we could correct the cur thru problem we have.
Page 4
May 2014
For each category, participants were asked to place a colored dot on the table next to those capacity
needs they felt were most needed. Within each category, meeting attendees were given a specific
number of dots (varied per station), and were able to place from one to all on any particular
improvement.
Roadway Segments with Capacity Needs
Participants were asked to review the map of county capacity needs and place any number of their four
colored dots next to their priority areas on the table. Participants placed a priority on widening US
278/SR 6 from Business 6 to Cobb County, Bakers Bridge Road from Ridge Road to Douglas County Line,
and Dallas Acworth Highway from SR 92 to East Paulding Drive. Response results can be found in Table
1.
New Roadway Connections
Participants were asked to review the map of new roadway needs and place one or both of their two
colored dots next to their priority areas on the table. Participants placed a priority on the West Dallas
Bypass, with the East Dallas Bypass and the Hiram Parallel Reliever south of Jimmy Campbell tied for a
relatively distant second place. Response results can be found in Table 2.
Multi Modal Needs
Participants were asked to review the display boards and place one dot with their answer to each
question below.
(1) Their preference on the types of bicycle and pedestrian needs that should be prioritized;
(2) Whether they would ride GRTA Xpress if service was extended to their residence and/or place of
employment;
(3) On a scale of 1 to 5, please rank the need for new local transit service in Paulding County?
(4) On a scale of 1 to 5, how important is it that the County continues to fund on-demand transit
services (Paulding Transit)?
Meeting attendees prioritized sidewalks among bike and pedestrian needs (Table 3). Attendees were
split as to whether they would utilize a GRTA Xpress Bus if it were more convenient (Table 4) but
somewhat supportive of transit and very supportive of on-demand transit services in the county (Tables
5 and 6).
Intersection Needs
Participants were asked to review the maps of intersection needs and place any number of their eight
dots next to their priority areas on the table. Participants placed a priority on the intersections at US
278/SR 6 (Jimmy Lee Smith Parkway) at SR Business 6 (Atlanta Highway), at East Memorial Drive at
Business SR 6 (Merchants Drive), and at SR 92 - US 278/SR 6 (Jimmy Lee Smith Parkway). Response
results can be found in Table 7.
Page 2
August 2014
Page 3
The intersection in Hiram of 278 and 92 has got to be the biggest traffic nightmare. There is only
one lane coming from 120 to the 278 intersection, and once you arrive there it is a very short
left turn lane to get onto 278 and to the stores- cars get backed up for miles! The same holds
true along 92 coming from Douglasville, though the turn lane is not as bad. Desperately needed
is a double much longer left turn lane from 120! There is a lot of vacant land on the corner and
with Hobby Lobby opening soon, plus I see another new building going up in front of Hobby
Lobby, the traffic is only going to get a lot worse at that intersection. Take the vacant land,
expand the left turn lane to two left turning lanes! I have learned never to try to turn out of the
old Kmart area- can take forever till you can get out and only if an oncoming motorist is nice
enough to let me out. I used to come down to Hiram to shop a lot but hate the traffic so have
cut back on my trips. Have discovered sadly to say that going to Acworth saves me time.
I recently saw an article stating that Paulding County was seeking info on traffic problems in
county. Suggest a hazard exists at the subject intersection. Left turn traffic lights need to be
added. There have been two accidents that I am aware of, the latest with injuries and I just
noticed the one sign in the intersection has been mowed down, possibly by someone trying to
avoid a near miss.
I regret that I couldn't attend the meeting. I would like you to take a consideration of putting a
traffic light at the intersection of Merchants Drive and Coach Bobby Dodd Rd. This intersection
has become more and more busy and dangerous. A few years ago I totaled my car while trying
to turn onto this intersection. Also, Old Harris Road has become a "short cut" to Hwy 278, which
adds even more traffic. Please consider adding a traffic light here.
We live on Poplar Springs Road @ Macland Rd (SR360) off Macland Circle. Poplar Springs is an
up and coming route of choice that connects two Arterial roads, Macland Rd and US 278.
Traffic on Poplar Springs has grown dramatically since the 20 years weve been here. Macland
Circle is a narrow, 15 wide cut-thru from Poplar Springs to Macland Rd.
We are excited about the completion of E Hiram Pky, however, it will by-pass traffic directly to
Poplar Springs Road, a two lane road to get to Macland Rd. With Macland Rd widening by
GDOT to begin within 2 years, I can see Poplar Springs Road will take a load of traffic, the
current 2 lanes cannot support. I see a need for Poplar Springs Rd to become a median divided
4-lane.
It was on a previous TIP but no action has occurred.
Along with that, we could
correct the cut thru problem we have.
I would like to comment that the city of Dallas desperately needs a bypass that involves better
connecting SR.61 with a loop around Dallas. Too many semi trucks have to converge into town
from all directions only to negotiate turns in front of the old courthouse and coming onto Bus.6
which aren't properly designed for big truck traffic. The traffic coming off of Dallas-Acworth Rd.
into town in the afternoons is also a big headache as I've seen it back up all the way from the
square to the post office. Sometimes I've taken a short cut through Main St. only to be blocked
August 2014
Page 4
The new end of the Bill Carruth parkway that was previously known as Cleburne Parkway traffic
light times need to be reevaluated. I work at an office on this road. The turning light allowing
people to get back onto 278 W is severely under-timed and causes a large back up in the
afternoon traffic.
Although I was very excited to see all of the projects you have planned, I would be remiss if I
didn't point out that there are many Paulding County taxpayers living in subdivisions that
haven't been paved in close to 20 years! Our surface roads in this county are poorly maintained,
full of potholes, cracks, etc., and just plain hazardous for drivers. The DOT needs to take care of
these roads first, before undertaking any other projects. I live in the Cedar Creek Subdivision off
of Hwy. 61 near the New Georgia Community, and our subdivision hasn't been paved in 18
years!! There are potholes everywhere, and most of the roads are full of cracks. Nebo Road,
Hiram Sudie Road and Ridge Road also need paving. It is important to take care of what we
already have before we try new projects.
My husband and I are the owners of a home in the Ivy Crest subdivision off Old Villa Rica Rd. For
15 years I have prayed that Old Villa Rica Rd. from Hwy 278 to Hwy 61 close to Paulding Co. High
School would be widened, improved, sidewalks added and the intersection at Hwy 61 made
much safer. I was very disappointed that it was not on your survey list of proposed
improvements. It is not a very long distance but in my opinion, it is a very dangerous stretch of
road. Please consider it for improvement.
Why is there no info on the Brushy Mtn Road paving project? It has been mentioned that some
property owners have not given the ok for the use of the right away. The right away in concern
is for the property owners on the other side of the tracks of Norfolk Southern Railway or the
north side of the tracks. This should have no effect on completing the paving of Brushy Mtn
road from the point at where new paving stop and up to the south side of the tracks of Norfolk
Southern Railway or Hwy 278 side. All property owners from Hwy 278 to the tracks of Norfolk
Southern Railway, south side have sign the necessary documents to release the use of the right
away for paving and improving our road. By all rights it should be completed for those property
owners. Please explain this injustice and why this section of the road cannot be completed. I
look forward to your response.
Please finish the projects you have already started, before starting additional projects and
spending the Money which has already been allotted for project that are at this time
incomplete, as in the paving or surfacing project of Brushy Mountain Road. Please complete the
Brushy Mountain Road Paving project.
Paulding County will be a trashed county if public transportation is brought in and established as
a tax payor subsidized alternative to autos. Bike trails are ridiculous, don't go there. Widening of
roads, traffic lights sync would be the best way to undo the congestion all over Hiram. Acworth,
Georgia and Kennesaw, Georgia know and understand how to keep traffic moving without bike
trails and tax payer funded public transportation, get with these folks, duplicate what they do
and the traffic mess in Hiram will be positively affected. Public transportation ruined every
August 2014
Page 5
Personally, I would like to see a crosswalk signal added in front of Shelton Elementary and the
Oak Glen subdivision. I live in Oak Glen and am a regular jogger. I'm constantly amazed at how
few cars stop at the crosswalk - even while I am in the middle of the road. My kids are not
school-aged yet, but I look forward to the fact that I will be able to walk them to school one day
with the exception that I am horrified at the thought that there is nothing at this crosswalk to
warn cars. Seven Hills has a flashing light. Can something like this be added to Cedarcrest Road
in front of the school?
I have completed the online priority survey. I feel that Nebo Road between Bill Carruth and
Dallas Nebo needs to be a priority, the road appears to be falling into disrepair and the patches
fail quickly.
I too agree with a request for a traffic light and turn lane improvement at Merchants Dr and the
Coach Bobby Dodd / Old Harris Rd intersection. It is a very scary and challenging drive through
that area every weekday morning.
There is a major problem with not enough speed limit signs on several roads in Paulding County.
Hwy 61 from Dallas to Villa Rica is horrible. The speed limit for most of the ride is 55. No signs
keep the speed at 45. Hwy 92 from Acworth to Douglasville is bad also. Hwy 61 has no where
near enough speed limit signs and 45 seems to be the speed. If this is checked out you will see
I'm correct.
August 2014
Votes
13
3
0
7
7
15
3
8
4
5
2
3
3
4
5
13
0
8
3
11
2
1
Roadway
Dallas Acworth Highway
Dallas Acworth
Hwy/Memorial Drive
SR Business 6/Buchanan
Street
SR Business 6/Merchants
Dr./Atlanta Hwy.
US 278/SR 6
US 278/SR 6
SR 101/113
SR 61 (Villa Rica Highway)
SR 61 (Villa Rica Highway)
SR 61 (Cartersville Highway)
SR 61 (Cartersville Highway)
SR 61 (Cartersville Highway)
Dabbs Bridge Road
Ridge Road
Nebo Road
Bakers Bridge Road
Sweetwater Church Road
Hiram Sudie Road
Cedarcrest Road
Cedarcrest Road
East Paulding Drive
Bobo Road
From
SR 92
To
E. Paulding Drive
Improvement
Widen to 4 lanes
E. Paulding Drive
SR Bus 6
Widen to 4 lanes
US 278 (W of Dallas)
Memorial Drive
Widen to 4 lanes
Memorial Drive
SR 61
Business 6
Carroll County
Douglas County Line
Hiram Sudie Road
SR Business 6
Mt. Moriah Road
Dabbs Bridge Road
SR 61
Dallas Nebo Road
Dallas Nebo Road
Ridge Road
Douglas County Line
SR 61
Seven Hills Boulevard
SR 92
SR 92
Dallas-Acworth Highway
US 278 (E of Dallas)
Business 6
Cobb County
SR 120
Ridge Road
US 278/SR 6
Old Cartersville Road
Dabbs Bridge Road
Bartow County Line
Bartow County Line
SR 92
SR 92
Douglas County Line
SR 92
SR 92
Cobb County Line
Seven Hills Boulevard
SR 120
SR 120
Widen to 4 lanes
Widen to 6 lanes
Widen to 6 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Page 6
Connection Name
W. Dallas Bypass
E. Dallas Bypass
Hiram Parallel Reliever - South of Jimmy Campbell
Hiram Parallel Reliever - North of Jimmy Campbell
Cedarcrest Rd to SR 61 Connector
Scoggins Road Extension
From
SR 61
SR 6
SR 92
SR 92
Seven Hills Blvd
US 278
To
US 278
SR 61
Metromont Road
Lake Road
SR 61
Scoggins Road
August 2014
Important
Very important
Page 7
August 2014
Page 8
Intersection Name
SR 120 (Charles Hardy Parkway) - SR Business 6 (Atlanta Highway)
SR 92 - E. Paulding Drive
SR 120 (Buchanan Highway) - SR 101
US 278/SR 6 (Jimmy Campbell Parkway) - Mount Olivet Loop
SR 61 (Cartersville Highway) - Mount Moriah Road
SR 61 (Cartersville Highway) Shady Grove Church Road
US 278/SR 6 (Jimmy Campbell Parkway) - SR 120 (Buchanan Highway)
SR 61 (Villa Rica Highway) - Old Villa Rica Road
SR 61 (Villa Rica Highway) - Vernoy Aiken Road
SR 61 (Villa Rica Highway) - Winndale Road
Hiram Sudie Road - Davis Mill Road
SR 92 - Old Burnt Hickory Road
SR 61 (Confederate Avenue) - SR Business 6 (West Memorial Drive)
Rosedale Drive - Metromont Road
US 278/SR 6 - Old Harris Road
US 278/SR 6 (Jimmy Campbell Parkway) - Cadillac Parkway
East Paulding Drive - Brooks Rackley Road
US 278/SR 6 (Jimmy Campbell Parkway) - SR 61 (Villa Rica Highway)
US 278/SR 6 (Jimmy Lee Smith Parkway) - Bill Carruth Parkway
US 278/SR 6 (Jimmy Lee Smith Parkway) - Hiram Pavilion S
US 278/SR 6 (Jimmy Lee Smith Parkway) - Hiram Pavilion N
US 278/SR 6 (Jimmy Lee Smith Parkway) - Depot Drive
Burnt Hickory Road - Brownsville Extension/Stout Parkway
SR 92 - US 278/SR 6 (Jimmy Lee Smith Parkway)
SR 92 - Paulding Commons Shopping Center
SR 61 (Villa Rica Highway) - Dallas Nebo Road
SR 360 (Macland Road) - SR Business 6 (Merchants Drive)
US 278/SR 6 (Jimmy Lee Smith Parkway) - SR Business 6 (Atlanta Highway)
Cedarcrest Road - Seven Hills Boulevard
SR 61 (Villa Rica Highway) - Hart Road
SR 101 - Old Yorkville Road
SR 101 - Holly Springs Road
SR 101 - Gold Mine Road
SR Business 6 - Coach Bobby Dodd Road
SR Business 6 - Old Harris Road
East Memorial Drive - Business SR 6 (Merchants Drive)
East Memorial Drive Legion Road
SR Business 6 (Merchants Drive) - Legion Road
West Memorial Drive - SR Business 6 (Buchanan Street)
SR 92 - Hiram Crossing Shopping Center
SR 92 - Rosedale Drive
August 2014
PauldingComprehensiveTransportationPlan
DraftFinalReport
AppendixBInventoryofExistingConditions
AppendixB
Prepared by:
January 2014
Table of Contents
1.0
2.0
3.0
Page i
1.2
1.3
2.2
2.3
ENVIRONMENTAL FACTORS........................................................................... 31
2.3.1
Natural Environment ............................................................................. 31
2.3.1
Physical Environment............................................................................. 36
3.2
TRAVEL PATTERNS......................................................................................... 52
3.2.1
Trip Origins and Destinations................................................................. 52
3.2.2
Travel Times ........................................................................................... 56
3.3
SAFETY .......................................................................................................... 58
January 2014
4.0
5.0
Page ii
3.4
3.5
3.6
TRAFFIC SIGNALIZATION................................................................................ 73
3.7
3.8
3.9
AIRPORTS...................................................................................................... 79
3.9.1
Silver Comet Field .................................................................................. 79
3.9.2
Hartsfield-Jackson Atlanta International Airport ................................... 80
3.10
3.11
3.12
3.13
4.2
January 2014
List of Figures
Figure 1: CTP Development Process ...................................................................................................2
Figure 2: Study Area ..........................................................................................................................3
Figure 3: Existing (2010) Population Density ..................................................................................... 11
Figure 4: Projected (2040) Population Density .................................................................................. 12
Figure 5: Existing (2010) Employment Density .................................................................................. 13
Figure 6: Projected Employment Density 2040 ................................................................................. 14
Figure 7: Existing Minority Population ............................................................................................. 18
Figure 8: Low-Income Population..................................................................................................... 19
Figure 9: Zero-Car Households ......................................................................................................... 20
Figure 10: Elderly Population Concentrations ................................................................................... 21
Figure 11: Existing Land Use ............................................................................................................ 24
Figure 12: Future Development Map................................................................................................ 26
Figure 13: ARCs Plan 2040 Unified Growth Policy Map..................................................................... 30
Figure 14: Impaired Waters and High Priority Watersheds ................................................................ 34
Figure 15: Hazardous Material Sites ................................................................................................. 37
Figure 16: Major Roadway Functional Classification ......................................................................... 40
Figure 17: Level of Service Description ............................................................................................. 43
Figure 18: Existing Level of Service (2015) ........................................................................................ 45
Figure 19: Projected Level of Service (2040) ..................................................................................... 46
Figure 20: Average Daily Speed AM Peak (2010) ............................................................................ 50
Figure 21: Average Daily Speed PM Peak (2010) ............................................................................ 51
Figure 22: Origins and Destination 2015 and 2040 ......................................................................... 54
Figure 23: Peak Hour Travel Times 2015 and 2040 ......................................................................... 57
Figure 24: Crash Hotspots (2010-2012) ............................................................................................. 60
Figure 25: Major Roadway Segments with Above-Average Crash Rates............................................. 61
Figure 26: Bicycle and Pedestrian Crashes (2010-2012) ..................................................................... 62
Figure 27: Bridges with Sufficiency Ratings less than 80 .................................................................... 65
Figure 28: Freight Corridors and Centers .......................................................................................... 70
Figure 29: Signalized Intersections ................................................................................................... 75
Figure 30: Pedestrian and Bicycle Facilities....................................................................................... 77
Figure 31: Major Parking Facilities ................................................................................................... 82
Figure 32: ARC Planned and Programmed Improvements ................................................................. 89
Page iii
January 2014
List of Tables
Table 1: Dallas, Georgia LCI - List of Transportation Projects ................................................................6
Table 3: Environmental Justice/Traditionally Underserved Populations ............................................ 16
Table 4: Paulding County Existing Land Use Composition .................................................................. 22
Table 5: Federal and State Protected Species Paulding County .......................................................... 35
Table 6: Inventory of Major Roadways ............................................................................................. 41
Table 7: Major Roadway LOS and Daily Volumes ............................................................................... 47
Table 8: Travel Demand between Paulding County and Other ARC Counties 2015, 2030, 2040 ......... 53
Table 9: Origins and Destinations Peak Hour Vehicle Trips 2015 and 2040 ................................... 55
Table 10: US Census Journey to Work Destinations (2006-2010) ....................................................... 55
Table 11: Travel Times between Employment Centers - 2015 and 2040 ............................................. 56
Table 12: Major Roadway Segments with Above-Average Crash Rates .............................................. 58
Table 13: Bridges Qualified for Rehabilitation ................................................................................... 64
Table 14: Locally Owned Federal Aid Route Bridge Inspections .......................................................... 66
Table 15: Locally Owned Bridge Inspections ...................................................................................... 66
Table 16: Major Roadway Heavy Truck Volumes and Percentages ..................................................... 71
Table 17: Inventory of Silver Comet Trail Crossings ........................................................................... 74
Table 18: GRTA Xpress Average Daily Ridership (2008-2013) ............................................................. 78
Table 19: ARC Planned and Programmed Improvements ................................................................... 90
Page iv
January 2014
Project Overview
The Paulding Comprehensive Transportation Plan (CTP) effort serves to update the
initial CTP completed in 2008 for unincorporated Paulding County and the Cities of
Braswell, Dallas, and Hiram through the 2040 horizon year. The plan will build upon the
initial CTP and develop short-term and long-term solutions for transportation
improvements based on the level of overall need, available funding, and stakeholder
and community input. This CTP Update will re-evaluate the previous CTP
recommendations and their current status of development and implementation. Data
from the previous CTP will be updated based on newly available information and
changes in trends. Based on the updated information, modifications may be made to
previous project recommendations and additional improvements may be proposed.
This CTP Update will address connections between land use and transportation, while
giving consideration to the ability of recommendations to support local and regional
land use plans. This CTP Update will be fully coordinated with, and will continue to serve
as, the transportation element of the Paulding County Comprehensive Plan.
The results of this CTP will be incorporated into the overall long range transportation
plan for the Atlanta region developed by the Atlanta Regional Commission (ARC),
currently called PLAN 2040, which serves as the constrained financial plan for federal,
state and local funds through the year 2040. This is important because some of the
recommendations from this update will require federal and state funding for
implementation.
1.2
Report Overview
This Inventory of Existing Conditions Report represents the initial technical step in
development of project recommendations. As reflected in Figure 1, the results of the
existing conditions analysis, in conjunction with the input received from the public
outreach program, will provide the foundation for the identification of the overall
transportation needs of Paulding County for the short-term (horizon year 2015), midterm (horizon year 2030), and long-term (horizon year 2040).
Because the end goal of the CTP Update is to develop an effective implementation
strategy for the prioritized transportation needs, factors that could impact the
implementation process, such as environmental resources and environmental justice
populations were inventoried.
Page 1
January 2014
Section 2.0 contains an assessment of the context and environment that influences
demand and potential expansion of the transportation network and mobility options
such as land use, environmental conditions and demographics.
Section 4.0 provides a summary of key findings from this baseline assessment and
how these findings will be incorporated into the needs assessment.
The study area for the CTP is presented in Figure 2 and includes the land area within the
county boundary and within the cities of Hiram, Dallas, and Braswell. This figure serves
as the map template used to display the various transportation and development
characteristics within this report. This map includes the locations of local communities
within the unincorporated county and other key points of interests.
Page 2
January 2014
Page 3
January 2014
1.3
1.3.1
Much like this update, the previous CTP presented detailed information on
transportation needs within the county to develop a set of needs-based
recommendations. It consisted of a set of recommended transportation projects
including new location projects, roadway capacity improvements, realignments,
intersection improvements, bridge improvements, transit service needs, and
bicycle/pedestrian enhancements. As an update to this document, this effort will reevaluate the previously identified goals, needs and projects to ensure previous planning
efforts are continued when appropriate and issues that have arisen since 2008 are
addressed.
This plan incorporated coordination between water infrastructure planning and
transportation planning to develop the list of recommended projects. The Paulding
County Master Sewer Study and Plan, which includes maps of anticipated future sewer
infrastructure, was consulted in this effort.
The previous CTP identified a series of Access Management Corridors recommended for
access management techniques based upon projected levels of service, planned
improvements, and environmental and geometric constraints. These corridors have
been grouped into three tiers based upon the recommended year of implementation.
The Tier II corridors, planned for 2014-2020, include segments of SR 6/US 278 and SR
120 (Charles Hardy Parkway). Tier III corridors, planned for 2021-2030, include
segments of East Paulding Drive, Bobo Road, East Memorial Drive/Dallas-Acworth
Highway, East Memorial Drive/West Memorial Drive and Buchanan Street, SR 6
Business, SR 61, SR 120, SR 120 Connector/Hiram-Sudie Road/Scoggins Road, Nebo
Road, and Bill Carruth Parkway. Tier IV corridors, planned for beyond 2030, include
segments of Macland Road, Angham Road/Main Street, Pine Valley Road, Dallas Nebo
Road, Bakers Bridge Road, Gold Mine Road, SR 101/SR 113, Sweetwater Church Road,
Brownsville Road, and Rosedale Drive.
The previous CTP also included an Access Management Toolkit as an appendix to the
report. The toolkit included detailed information on access management strategies and
techniques. It also included proposed language for an access management ordinance.
The toolkit applies access management strategies to roadways in Paulding County.
Strategies are applied broadly to functional classification type and also to specific
Page 4
January 2014
The city of Dallas conducted a LCI study for the central Dallas area in 2006. The study
area included downtown Dallas and extended to US 278 and the area surrounding the
(then-future) Paulding County Government Complex. The major focus of the study was
to guide downtown redevelopment in a way that would support the long term vitality of
the historic downtown area. The plan included a short and long-term concept plan,
which tied together a series of land use changes and transportation improvements.
The LCI plan identified a number of proposed transportation projects needed within the
study area. Table 1 lists these projects along with their status as of the five-year LCI
update completed in 2012.
1.3.3
The purpose of the Silver Comet Trail Economic Impact Analysis and Planning Study is to
assess the increasing economic impact of the trail and integrate this plan with the future
bicycle plans of local jurisdictions. Improving connectivity between the trail and nearby
cities and destinations is another major goal of the plan.
The plan identifies the need for new trail connections to several destinations within
Paulding County. This includes:
Page 5
A 0.8 mile on-road bicycle facility and sidewalk connection from the Seaboard Drive
trailhead to the Main Street Dallas commercial area to connect the trail to
downtown Dallas via Seaboard Drive and South Main Street.
A 0.7 mile segment of Old Harris Road that would include on-road bicycle facilities
and sidewalks to the Dallas Days Inn to serve out-of-town trail users.
A 2.2 mile sidepath connection along Coppermine Road and Rosedale Drive to
connect the Hiram Crossroads commercial area to the trail in the form of a loop to
help support the current businesses along the US 278 corridor, including lodging
options, and generate the potential for additional trail-serving businesses.
January 2014
Project
Type
Const.
Year
Responsible
Party
Funding
Source
2012
Status
2009
Total
Project
Costs
$4.8 M
Downtown Parking
Structure
Parking
City, Private
City,
Private
Pedestrian
and Bicycle
2010
$4.1 M
City of Dallas
Roadway
2010
$812,500
Paulding
County
LCI,
GDOT,
Others
Paulding
County
No Longer
Relevant,
Not
Needed at
this Time
Complete
Pedestrian
2011
$1.4 M
City of Dallas
LCI
Not
Started,
Waiting
on
Hospital
Relocation
Underway
WayfindingSignage
Signage
2011
$250,000
City of Dallas
LCI
Underway
2010
$200,000
City of Dallas
LCI
Underway
Roadway
and
Pedestrian
Roadway,
Bridge,
Pedestrian,
and Bicycle
Intersection
2011
$1.2 M
City of Dallas
City of
Dallas
Not
Started
2011
$9.9M
City of Dallas
City of
Dallas
Not
Started
2011
$14.2 M
City of Dallas
Intersection
2011
$659,000
City of Dallas
Not
Started
Complete
Pedestrian
2013
$2.0 M
City of Dallas
City of
Dallas
City of
Dallas
City of
Dallas
Pedestrian
2013
$2.6 M
City of Dallas
City of
Dallas
Not
Started
GDOT
GDOT
City of Dallas
CMAQ
NotRelevant
Complete
City of Dallas
TE
Complete
GDOT
GDOT
Complete
Roadway
2030
$26 M
Widening
Sidewalks/
2007
$1 M
Pedestrian
Dallas Trailhead
Bicycle/
2010
$625,000
Pedestrian
SR 120 Bridge at Silver Comet
Bridge
2007
$532,000
Trail
Upgrade
Source: Dallas, Georgia LCI, Five Year Update Dallas, Georgia LCI
Page 6
Underway
January 2014
PLAN 2040 is a comprehensive, holistic policy document produced by the ARC to guide
the growth of the Atlanta region in a sustainable manner. Pursuant to the ARC website,
the plan serves is focused on serving people, building community, enhancing mobility,
preserving the environment, and growing the economy. There are two components of
PLAN 2040 that specifically tie into this CTP update:
Regional Transportation Plan (RTP) This is a $61 billion financially constrained plan
of transportation improvements that are meant to support the overall vision for the
region. Projects in the RTP primarily include those that are to receive federal funding
for implementation. Given that the ARC encompasses 18 counties, the CTP process
was established to gain consensus and provide local input into the overall RTP.
Therefore, the recommendations and findings that result from this Paulding CTP
update will be incorporated into the overall RTP during the next update, scheduled
in 2014. The planned and programmed improvements currently in PLAN 2040 based
on the 2007 CTP are discussed in further detail in Subsection 3.13.
Unified Growth Policy Map (UGPM) As discussed in Subsection 2.2, the UGPM was
developed by the ARC to guide future development throughout the region. Given
that local jurisdictions have authority to set their own development policies, the
UGPM is solely advisory in nature.
1.3.5
The SRTP for the ARC was undertaken in recognition that arterials are the most
challenged facilities in the Atlanta region. The primary task associated with the SRTP
relevant to the Paulding CTP effort was the identification and classification of a
prioritized regional roadway network - called the Regional Thoroughfare Network (RTN)
- for improvements and congestion management related activities. The following
Paulding County roadways are RTN facilities:
1.3.6
The Atlanta Regional Freight Mobility Plan identified and prioritized improvements and
strategies that accommodate and enhance freight mobility while mitigating their
negative impacts. The study was undertaken jointly by the ARC and GDOT in support of
the regions economic competitiveness via the facilitation of freight transportation.
Page 7
January 2014
The ASTRoMaP was developed by ARC in response to the Atlanta Regional Freight
Mobility Plan recommendation of a regional truck route network. ASTRoMaP, building
upon the RFPHN from that study, identified preferred routes and developed strategies
to support the efficient movement of goods without disproportionately impacting
existing communities, the environment or the transportation network. The RFPHM
began as a set of state routes and interstates designated for truck traffic. From this, the
final ASTRoMaP network was developed based upon evaluation criteria that included
community input, private industry input, jurisdictional input, land use concerns, and
environmental justice impacts. The network developed by this plan focused on crosstown travel and linkages among economic centers. Several roadway facilities in
Paulding County are identified in the plans truck network, as described in greater detail
in Subsection 3.5.
Page 8
January 2014
2.1
Demographic Profile
Existing and projected demographic conditions are important considerations within the
CTP planning process. A demographic assessment is needed for two primary reasons:
1) to adequately plan for projected growth; and
2) to minimize the potential for negative impacts to low-income and minority
communities, called Environmental Justice (EJ) populations, within the county that
could result from proposed transportation improvements.
2.1.1
Socioeconomic data contained within the ARC Travel Demand Model (TDM) was used to
assess projected population, household and employment growth within the county.
These data sets result from projections derived by the ARC on a regular basis that are
integrated into the model. The data used for this analysis is at a Traffic Analysis Zone
(TAZ) level of geography for the years 2010 and 2040.
Overall County Projections
Table 2 details existing and projected population, household and employment within
the county. The county is anticipated to add 153,893 residents between 2010 and 2040,
representing a 118.5 percent increase over the base year. The number of households is
expected to grow at the similarly high rate of 128.3 percent. The number of employees
is projected to increase at a higher rate, 150.1 percent, adding 30,625 jobs to the county
between 2010 and 2040. The average household size is projected to decrease slightly
from 2.81 to 2.68 persons, which is consistent with historic trends nationally and within
the region. In general, this would indicate a need to improve the county transportation
network as a whole to prepare for this growth. Understanding where this growth will
occur is critical in prioritizing transportation needs.
The countys jobs-to-housing ratio is included in Table 2. This ratio is calculated by
dividing the total number of jobs by the total number of housing units. This ratio is a
planning tool used to assess the economic base and development character of a
jurisdiction. It is also an indicator of peak hour travel trends for county residents
accessing their places of employment.
Page 9
January 2014
2010
129,003
45,957
2040
281,896
104,901
Change
153,893
58,944
Percent Change
118.5%
128.3%
Employees
Average Household Size
Jobs-to-Housing Ratio
20,425
2.81
0.44
51,077
2.69
0.49
30,625
-0.12
0.05
150.1%
-4.3%
11.4%
Based upon the American Planning Associations Jobs to Housing Balance guidance
document, the average number of workers per household is 1.5, the recommended
standard target ratio is 1.5. Given the suburban and rural character of Paulding County,
it is unlikely that a 1.5 jobs-to-housing ratio is in keeping with community desires. The
county currently exhibits a jobs-to-housing ratio of 0.44. Given that employment is
projected to grow more quickly than households or population, this ratio is projected to
improve to 0.49 in 2040. However, this ratio still suggests the county will remain a
suburban residential community, which will require the majority of workers to commute
across county lines. This development pattern contributes to high vehicle miles traveled
(VMT) and congested conditions on county arterials. A detailed analysis of commuting
patterns within the county is presented in Subsection 3.2.
Specific Area Projections
Figure 3 illustrates existing population densities, showing higher concentrations of
residents located in the eastern portion of the county, primarily east of SR 61. The
highest population densities can be found within the city of Dallas and in areas
bordering Cobb County adjacent to the SR 120 corridor. Figure 4 indicates that this
trend is expected to continue in 2040 with higher residential densities remaining in the
eastern portion of the county. An overall increase in residential densities can be seen
throughout the county, although the majority of growth is projected for areas east of SR
61. Even with the density increases projected in the eastern portion of the county, the
overall densities projected are consistent with single-family residential development.
Furthermore, there is an abundance of housing stock in the more densely-populated
areas that would suggest a significant level of new development would not be needed
to fill this unmet demand.
Most of the employment in Paulding County is associated with commercial/retail uses
and/or light industrial uses and, therefore, employment densities are relatively low
throughout the county. Existing 2010 employment densities are presented in Figure 5.
This figure shows the highest concentrations of jobs are located in the central eastern
portion of the county in the greater Dallas and Hiram areas. The projected 2040
employment densities, shown in Figure 6, illustrate that this trend is expected to
continue. Employment growth is primarily projected to occur within the eastern
portions of the county, east of SR 61.
Page 10
January 2014
Page 11
January 2014
Page 12
January 2014
Page 13
January 2014
Page 14
January 2014
Executive Order 12898, signed by President Clinton on February 16, 1994, directs
federal agencies to identify and address, as appropriate, high and adverse impacts on
Environmental Justice (EJ) populations as a result of implementing federally funded
projects, programs and/or policies. EJ populations consist of minority and low-income
persons who are defined as: minority persons, who include individuals who have
identified as Hispanic, Latino or a race other than White; and low-income persons who
are defined as those whose median household income is at or below the U.S.
Department of Health and Human Services poverty line. This analysis also identifies
concentrations of traditionally-underserved (TU) populations such as the elderly and
zero-car households. The overall purpose of this assessment is to identify potential
areas where negative impacts could result from proposed transportation projects. In
addition, identifying low-income, elderly, and zero-car populations also provides a
baseline for identifying transit needs in the county. This assessment also helps identify
the potential benefits to these populations that may result from recommended
improvements.
Data from the 2010 US Census was used to assess minority populations in the county
and the American Community Survey (ACS) for 2010 was used to analyze the lowincome population and elderly populations. The 2011 ACS was consulted to determine
zero-car households. Table 3 shows a comparison of the county percentage for EJ
populations against those for the Atlanta region. The total county populations for the EJ
groups vary given the differing data sets and sample populations (2010 US Census, 2010
ACS, 2011 ACS). While the populations for all of these groups within Paulding County are
rare lower than the regional average across the board, it is still important to identify
where these populations are concentrated. More detail regarding the specific locations
and transportation corridors where these populations reside is provided in the
subsections that follow.
Page 15
January 2014
Total
Population
142,324
134,120
Group
Population
31,807
10,967
EJ/TU
Percentage
22.3%
8.2%
Atlanta Region
EJ/TU Percentage
43.4%
13.5%
Zero-Car Households
Elderly Persons
47,691
134,875
1,090
10,220
2.3%
6.7%
6.1%
9.0%
Sources: 2010 US Census; 2010 American Community Survey; 2011 American Community Survey; Population
estimate for whom poverty status determined; Estimate for occupied housing units; Population estimate for whom
age determined.
Minority Persons
Figure 7 depicts the distribution of minority populations within the county. In 2010,
minority persons made up 22.3 percent of the county population, which was
considerably lower than the region average of 43.4 percent. The highest concentrations
of minority populations are found in the city of Dallas and in the southeastern portion of
the county bordering Douglas and Cobb Counties. Other areas with higher minority
concentrations include the greater Hiram area and the local community of Brownsville.
Roadways serving these areas include SR 92, US 278/SR6 and SR 360.
Low-Income Persons
Figure 8 depicts the distribution of low-income populations within the county.
Approximately 8.2 percent of the population is considered low-income, which is below
the average of 13.5 percent for the region. The highest concentrations of low-income
individuals can be found within the Dallas area, along the US 278/SR 6 corridor. Another
notable concentration of low-income persons is found adjacent to Hiram, along HiramSudie Road.
Zero-Car Households
In 2011, approximately 2.7 percent of the households within the county did not
maintain auto ownership. This percentage is lower than the regional average for zerocar households, which is 6.1 percent. This is consistent with the lower population
densities within the county and the fact that transit service is not currently available
throughout the County. Figure 9 displays the distribution of zero-car households within
the county. The highest concentrations of zero-car households can be found in the
greater Dallas area. This mirrors high EJ concentration areas.
Elderly Populations
Elderly persons are defined as persons aged 65 or older. According to Figure 10, larger
shares of the elderly population appear to reside in the Dallas area and in an area
immediately east of Bobo Road. Other notable concentrations of elderly population can
be found in the Yorkville area and adjacent to SR 120 (Buchanan Highway) in the
Page 16
January 2014
Page 17
While the city of Hiram has areas with EJ populations, there are few elderly and
zero-car households. This is reflective of the relatively new housing stock in
combination with the suburban development patterns in the area. While this
development pattern is not conducive to fixed route transit service, this would
indicate a need to continue if not increase the GRTA Xpress Service as well as
other travel demand management activities such as carpooling, vanpooling, and
ridesharing, for residents of the Hiram area.
January 2014
Page 18
January 2014
Page 19
January 2014
Page 20
January 2014
Page 21
January 2014
2.2
2.2.1
The following section details existing land use patterns within the county. The analysis is
based upon the ARCs most recent regional data set, LandPro 2010. This data source is
useful because it provides a common data set for the unincorporated county and the
cities of Hiram, Dallas, and Braswell. The acreages of major land use types within the
county are detailed below in Table 4.
Table 4: Paulding County Existing Land Use Composition
Land Use Type
Acreage
Percent of County
Agriculture-Forestry
97,907.68
48.6%
Single-Family Residential
53,401.20
26.5%
Park-Recreation-Conservation
36,481.88
18.1%
7,578.87
3.8%
Commercial
2,714.75
1.3%
Public-Institutional
1,737.65
0.9%
Industrial
885.10
0.4%
Transportation-Communications-Utilities
529.07
0.3%
Multi-Family Residential
399.62
0.2%
201,635.80
100%
County Total
Source: ARC LandPro 2010
Agriculture-Forestry is the most common land use in the county, comprising 48.6
percent of the total land area. This category includes agriculture, including cropland,
pasture land, areas dedicated to livestock production and equestrian facilities. It also
includes heavily forested undeveloped land. The majority of this land use type is found
in the western portions of the county, west of SR 61. Significant expanses can be found
adjacent to the Paulding Forest and Sheffield Wildlife Management Areas (WMAs).
These uses typically generate very little traffic.
The second most common land use type in the county is Single-Family Residential. This
category includes single-family residential development in a variety of forms. This
includes planned residential subdivisions, large-lot (1-2 acres) rural residential
development, and mobile home parks. These uses are found throughout the county,
but it is heavily concentrated in the eastern portions of the county, east of SR 61. The
Page 22
January 2014
Page 23
January 2014
Page 24
January 2014
The following section details land use policy framework with specific importance to
future transportation planning that influence growth in Paulding County. To assess this,
regional and local plans were reviewed; these include the Paulding County
Comprehensive Plan 2007-2027 and the ARCs Plan 2040 UGPM. A survey of historic
farms within the county has also been included in this section.
Paulding County Comprehensive Plan 2007-2027 Future Development Map
The Countys Future Development Map (shown in Figure 12) establishes a set of special
planning corridors of particular importance to transportation planning. These include
Green Corridors and Business Corridors.
Page 25
January 2014
Page 26
January 2014
January 2014
The ARC has created the UGPM to serve as a regional development guide for local
jurisdictions to accommodate growth, limit suburban sprawl and protect natural
resources. This map is a component of the recently completed Plan 2040, which was
adopted in 2011, and is much more general in terms of land use categories.
Furthermore, as a guide, it has no legal binding over how local jurisdictions plan their
Page 28
January 2014
Page 29
January 2014
Page 30
January 2014
2.3
Environmental Factors
This section describes the existing environmental conditions in Paulding County. As
projects are recommended and considered a general understanding of environmental
conditions is important in determining next steps. It is also necessary to know if there
any potential environmental concerns that would impact project implementation. The
review of environmental conditions includes the natural, physical and social
environments. The demographic and social conditions are described in Subsection 2.1.
2.3.1
Natural Environment
January 2014
Raccoon Creek A north/south creek in the northwest section of the county and
runs through the conservation area.
Sweetwater Creek An east/west creek along the southern edge of the county near
the border with Douglas County.
Mud Creek A creek that flows through the southwest corner of the county and
connects to the Tallapoosa River.
Tallapoosa River A small portion of this creek is located in the southwest corner of
Paulding County and continues into Haralson County.
The full length of Raccoon Creek, Pumpkinvine Creek, Mud Creek and the Tallapoosa
River within the county are listed on the state list of impaired waters. Impaired waters
are shown on Figure 14. Other creeks included on the list within the county include;
Cracker Creek, Gothards Creek, Lawrence Creek, Pegamore Creek, Picketts Mill Creek,
Possum Creek, Pyle Creek, Powder Springs Creek, Thomasson Creek, Ward Creek and
White Creek. The impaired waters are monitored in accordance with Section 303d of the
Clean Water Act and have controlled levels of permitted discharges in order to maintain
or improve water quality. This is important when planning for transportation
improvements because the stormwater run-off from roadways and bridges are a major
contributor to pollutants within these areas. Additional design considerations are often
required to control not only the stormwater run-off but also to control erosion and
sedimentation.
Page 32
January 2014
Page 33
January 2014
Page 34
January 2014
Common
Name
Federal Rank
State Rank
Cambarus
englishi
Tallapoosa
Crayfish
N/A
Rare
Cambarus
fasciatus
Etowah
Crayfish
N/A
Threatened
Etheostoma
etowahae
Etowah
Darter
Endangered
Endangered
Etheostoma
scotti
Cherokee
Darter
Threatened
Threatened
Etheostoma
tallapoosae
Tallapoosa
Darter
N/A
Rare
Hamiota altilis
Finelined
Pocketbook
Threatened
Threatened
Hybopsis
lineapunctata
Lined Chub
N/A
Rare
Cypripedium
acaule
Pink
Ladyslipper
N/A
Unusual
Schisandra
glabra
Bay Star-vine
N/A
Threatened
Symphyotrichu
m georgianum
Georgia Aster
Candidate
Threatened
Triphora
trianthophora
Three-birds
Orchid
N/A
Special
Concern
Habitat Description
January 2014
Physical Environment
This section discusses the existing conditions of the physical environment as related to
environmental concerns. The location of hazardous materials sites and cultural
resources are identified.
Hazardous Materials
The US Environmental Protection Agency (US EPA)regulates the discharge of hazardous
materials into the ground, water and air. The primary regulation of hazardous materials
is set under two federal laws; Resource Conservation and Recovery Act (RCRA) and
Comprehensive Environmental Response, Compensation and Liability Act (CERCLA).
CERCLA identifies Superfund sites (brownfields) that are eligible for clean-up funding.
The US EPA compiles the datasets for the different types of facilities. RCRA system
documents hazardous waste generators, transporters, treaters, storers and disposers of
hazardous waste are required to provide information on their activities to state
environmental agencies. There are four RCRA sites identified within Paulding County
and no CERCLA sites. There are several other monitoring programs for toxic and
pesticide release sites and pollutant discharge sites. US EPA Region 4 tracks facilities and
manages changes to datasets year to year. Figure 15 shows the current sites from the
RCRA inventory, TRI and other EPA Sites of Interest (pesticide and pollutant discharges)
according to US EPA Region 4. Hazardous waste sites are reviewed when considering
proposed transportation improvements to determine if there is potential to disturb
contaminated soils, which would then require remediation.
Historic Resources
Despite Paulding Countys rich history, only four resources have been listed on the
NRHP. The NRHP was established as part of the National Historic Preservation Act and is
the official national list of districts, sites, buildings, structures, and objects deemed
worthy of preservation. Two of the sites are located in Dallas, Georgia; the Paulding
County Courthouse and the Picketts Mill Battlefield Site (US Civil War). The other two
sites are in Hiram, Georgia, the Hiram Colored School and the Fannin-Cooper Farm. As
infrastructure investments are made in an area, assessments for the location of cultural
resources is typically conducted if state or federal money is used. The records of these
surveys are maintained by the State Historic Preservation Office. An online search for
cultural resources surveys was conducted using Georgia's Natural, Archaeological, and
Historic Resources GIS. The search returned almost 500 results for the county, and
includes additional properties that may be eligible for inclusion on the NRHP. As project
recommendations are made for the CTP, specific locations of resources may be
identified in relation to the recommended improvements. By identifying cultural
resources during the planning stage, efforts to avoid, minimize or mitigate impacts can
be considered and guide the next steps of project development.
Page 36
January 2014
Page 37
January 2014
Page 38
January 2014
3.1
Inventory of major facilities and the identification of the role each play in the
transportation network.
Analysis of existing and projected traffic congestion along these roadways to help
identify transportation needs.
3.1.1
Major roadway facilities within Paulding County are displayed in Figure 16. This map
illustrates the functional classification of each major roadway. Functional classification is
the process by which street and highway facilities are grouped into classes, or systems,
according to the character of traffic service that they are intended to provide. They
consist of the following:
Arterials Roads that typically carry higher volumes at higher speeds that are
characterized with more traffic and/or access devices that are intended for longer
trips.
Collectors Roads that typically connect local roads with arterials that operate at
intermediate speeds with shorter trips than those on arterials.
Local Roads All other roads not classified as an arterial or collector that provide
access to specific properties with little or no through movement.
There are no hard and fast criteria for these classifications and, therefore, they will
vary throughout the region. However, these designations are closely coordinated
through GDOT in conjunction with federal guidelines.
Page 39
January 2014
Page 40
January 2014
Page 41
Name
Functional Classification
Number of
Lanes
Center
Median
Speed Limit
(MPH)
4
4
4
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2/4
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
Yes
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Partial
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
65
45/55
55/45
55
45
45
45
45
45
45
45
45
45
35
40/45
55
55
45
45/50
45
45
45
35
40
35
35
45
45
45
55
35
45
35
45
45/55
35/45
45
40
45
January 2014
January 2014
LOS ratings for roadway segments are based upon volume to capacity (V/C) ratios. This
ratio compares the traffic volumes on a roadway with the carrying capacity of that
segment of road. V/C is the quantitative measure generated by the travel demand
model that is utilized to determine the LOS of a given roadway segment.
To assess existing and projected congestion levels on county roadways, LOS ratings have
been mapped for 2015 and 2040. The 2015 ARC TDM projections were used as existing
conditions because the data more accurately reflects short-term needs by presenting
the conditions for when those recommendations would be implemented. While this is
an existing conditions report, predicted future conditions as they pertain to roadways
provide a baseline to assess future needs. For urban counties, the ARC considers LOS
Page 43
January 2014
Page 44
January 2014
Page 45
January 2014
Page 46
January 2014
Major
Roadway
SR 92
DallasAcworth
Hwy/ E.
Memorial Dr
SR Bus 6/
Buchanan St
SR 120
(Buchanan
Hwy)
SR 120
(Charles
Hardy Pkwy)
SR 101
US 278/ SR 6
SR Bus 6/
Merchants Dr
SR 360
Number of Lanes
Modeled
Daily
Volume
2015
Daily
Volume
2030
Daily
Volume
2040
2015
AM
V/C &
LOS
2015
PM
V/C &
LOS
2030
AM
V/C &
LOS
2030
PM
V/C &
LOS
2040
AM
V/C &
LOS
2040
PM
V/C &
LOS
18,400
34,400
36,900
0.85/E
0.95/E
0.89/E
1.06/F
0.97/E
1.13/F
From
Cobb County Line
Dallas-Acworth
Hwy
Cobb County Line
SR 120
US 278/SR 6
Hiram-Sudie Rd
Hiram-Acworth
Highway
To
Hiram-Acworth Hwy
2015
2
2030
4
2040
4
2
2
2
2
4
4
4
4
4
6
4
4
4
4
6
10,900
18,300
21,100
17,100
21,700
21,700
32,900
38,800
27,400
44,600
26,600
37,200
41,500
30,400
50,000
0.5/C
0.78/D
0.8/D
0.92/E
0.94/E
0.59/C
0.93/E
0.99/E
1.02/F
1.08/F
0.46/B
0.71/D
0.75/D
0.75/D
0.78/D
0.68/C
0.91/E
0.99/E
0.9/E
0.95/E
0.58/C
0.82/D
0.84/D
0.85/E
0.89/E
0.82/D
0.97/E
1.04/F
0.95/E
1.08/F
E. Paulding Drive
9,200
12,700
14,000
0.76/D
0.98/E
1/E
1.36/F
1.2/F
1.58/F
E. Paulding Drive
SR Bus 6
11,600
15,400
17,000
0.88/E
1.02/F
1.21/F
1.2/F
1.55/F
1.36/F
Memorial Drive
US 278/SR 6
US 278/SR6
SR 120 (Conn)
2
2
2
2
2
2
11,600
6,800
16,000
8,100
18,600
10,600
0.96/E
0.48/B
1.05/F
0.58/C
1.19/F
0.51/C
1.28/F
0.58/C
1.49/F
0.64/C
1.6/F
0.73/D
SR 120 (Conn)
Cobb County Line
2
4
2
4
2
4
6,000
35,500
8,200
44,900
9,900
50,800
0.68/C
0.65/C
0.57/C
0.71/D
0.86/E
0.79/D
0.78/D
0.87/E
1.09/F
0.93/E
0.84/E
1.02/F
SR 92
SR 120
SR 120
US 278/SR 6
Carroll County Line
Polk County Line
4
2
2
4
2
2
4
2
2
31,100
15,100
5,600
37,900
19,100
7,400
42,600
21,800
8,600
0.55/C
0.72/D
0.51/C
0.64/C
0.88/E
0.6/C
0.66/C
0.91/E
0.72/D
0.72/D
1.04/F
0.83/D
0.69/C
1.01/F
0.77/D
0.78/D
1.16/F
0.9/E
SR 120
SR 61
Business 6
Cobb County
4
4
4
4
4
4
4
4
4
4
4
4
17,500
25,300
36,500
38,300
24,600
32,100
48,100
46,300
26,900
39,000
52,700
51,500
0.49/B
0.65/C
0.74/D
0.78/D
0.54/C
0.74/D
0.85/E
1.01/F
0.7/D
0.78/D
1.04/F
1.05/F
0.75/D
0.88/E
1.15/F
1.06/F
0.75/D
0.87/E
1.18/F
1.14/F
0.83/D
0.97/E
1.31/F
1.10/F
US 278/SR 6
Memorial Drive
5,900
9,400
11,900
0.7/C
0.75/D
0.97/E
1.03/F
1.15/F
1.23/F
SR 92
SR 120
2
2
4
4
4
4
22,800
15,300
30,200
19,200
33,300
21,900
0.85/E
0.64/C
0.99/E
0.77/D
0.85/E
0.56/C
0.98/E
0.75/D
0.93/E
0.64/C
1.06/F
0.81/D
Douglas County
Ridge Road
15,900
19,500
21,100
0.72/D
0.88/E
0.93/E
1.06/F
1.01/F
1.15/F
SR 61
Page 47
January 2014
Major
Roadway
Number of Lanes
Modeled
2015
AM
V/C &
LOS
2015
PM
V/C &
LOS
2030
AM
V/C &
LOS
2030
PM
V/C &
LOS
2040
AM
V/C &
LOS
2040
PM
V/C &
LOS
2040
Hiram-Sudie Road
US 278/SR 6
Old Cartersville Road
2
2
2
2
4
2
2
4
2
9,200
13,700
12,500
12,000
21,600
15,500
13,000
22,300
16,600
0.86/E
0.72/D
0.95/E
0.85/E
0.86/E
1.05/F
0.72/D
0.72/D
1.07/F
0.82/D
0.85/E
1.16/F
0.85/E
0.84/D
1.15/F
0.97/E
0.96/E
1.31/F
Mt. Moriah Rd
Dabbs Bridge Road
Bartow County Line
2
2
2
2
2
2
2
2
2
8,100
11,900
14,100
9,600
15,300
18,400
10,600
17,400
20,200
0.3/B
0.68/C
0.62/C
0.42/B
0.86/E
0.78/D
0.4/B
0.91/E
0.79/D
0.51/C
1.08/F
0.95/E
0.42/B
1.2/F
0.86/E
0.54/C
1.18/F
1.04/F
SR 61
4,700
5,700
14,400
0.72/D
0.84/D
0.92/E
1.05/F
0.81/D
1.00/F
Ridge Road
SR 61
Dallas-Nebo Road
Dallas-Nebo Road
SR 92
2
2
2
2
2
2
4,900
8,500
8,000
16,000
10,300
18,300
0.35/B
0.56/C
0.43/B
0.65/C
0.66/C
1.01/F
0.83/D
1.12/F
0.75/D
1.11/F
0.93/E
1.24/F
Nebo Road
SR 61
Dallas-Nebo Road
Dallas-Nebo Road
SR 92
2
2
2
2
2
2
4,300
6,000
5,500
9,600
7,200
12,400
0.55/C
0.56/C
0.47/B
0.6/C
0.75/D
0.95/E
0.57/C
1.06/F
0.88/E
1.09/F
0.68/C
1.2/F
Dallas-Nebo
Rd/Bakers
Bridge Rd
SR 61
Nebo Road
Nebo Road
Ridge Road
2
2
2
2
2
2
9,600
7,800
13,300
9,100
15,600
10,400
0.48/B
0.43/B
0.6/C
0.58/C
0.76/D
0.57/C
0.92/E
0.78/D
0.95/E
0.7/C
1.05/F
0.87/E
Ridge Road
Douglas County
Line
12,900
16,200
17,100
0.75/D
0.88/E
0.97/E
1.11/F
1.07/F
1.25/F
SR 92
6,700
11,000
11,800
0.73/D
0.9/E
0.82/D
0.95/E
0.91/E
1.04/F
SR 92
SR 120
2
2
2
2
2
2
6,600
3,300
6,300
5,200
6,300
6,900
0.78/D
0.25/B
0.9/E
0.33/B
0.82/D
0.38/B
0.96/E
0.51/C
0.9/E
0.47/B
1.03/F
0.66/C
SR 61
SR 92
10,800
14,200
16,800
0.75/D
0.84/E
1.04/F
1.15/F
1.19/F
1.33/F
US 278/SR 6
US 41
Dallas-Acworth
Hwy
SR 92
SR 92
4
2
4
4
4
4
19,500
9,400
23,600
14,900
28,800
16,300
0.64/C
0.54/C
0.77/D
0.67/C
0.61/C
0.54/C
0.76/D
0.68/C
0.67/C
0.57/C
0.84/E
0.75/D
12,200
14,800
16,500
0.76/D
0.9/E
0.92/E
1.04/F
1.0/F
1.17/F
Sweetwater
Church Rd
Brownsville
Rd
Scoggins Rd
Hiram-Sudie
Rd
Bill Carruth
Pkwy
Cedarcrest Rd
E. Paulding Dr
Ridge Road
Hiram-Sudie Rd
US 278/SR 6
Old Cartersville
Rd
Mt. Moriah Rd
Dabbs Bridge Rd
Daily
Volume
2040
2030
Dabbs Bridge
Rd
To
Daily
Volume
2030
2015
SR 61
From
Daily
Volume
2015
SR 120
Page 48
January 2014
To further assess existing congestion levels and travel delay an analysis of real-time
data, called NAVTEQ, has been conducted. This data was made available through the
ARC and includes average vehicular travel speeds for hourly increments throughout the
day. NAVTEQ data is developed through the consolidation of travel data from personal
GPS-enabled devices, including in-car navigation systems and smart phones.
Real-time data offers several advantages for assessing existing congestion levels over
travel demand model data. Real-time data accurately records congested travel
conditions as they occur. Model data provides a simplified interpretation of existing
conditions and has the potential to exhibit data distortions. Another advantage is that
real-time data can pinpoint congested areas within very small sections of roadway as
opposed to the larger roadway segments which comprise the model network.
Real-time travel speed data from 2010 for the AM and PM peak commuting periods is
shown in Figures 20 and 21. The differences in speeds indicate where there are specific
areas of delay along roadways and the degree to which delay occurs. Both the AM and
PM peak period maps show similarly congested conditions on many of the same
corridors as the model data. The PM peak period, however, depicts more widespread
and continuous congestion along the same roadways. An example of this is more travel
delay evident in the PM peak near major intersections along Ridge Road.
The most highly congested corridors can be found primarily in the eastern portion of the
county, particularly within the greater Dallas and Hiram areas. These include SR 92, US
278/SR 6 (through Hiram), SR 360 (Macland Road), Memorial Drive, Business
6/Merchants Drive, East Paulding Drive and Hiram-Sudie Road. SR 120 (Charles Hardy
Parkway) and Bill Carruth Parkway also feature high levels of congestion and reduced
travel speeds.
Real-time data can be particularly useful for identifying roadways with reduced travel
speeds resulting from intersection delay. Figures 20 and 21 illustrate that travel delay
can be consistently found along roadway segments near major intersections. This is
evident on many major roadway facilities including SR 92, US 278/SR 6 (through Hiram),
East Paulding Drive, SR 120 and SR 360. This data will be consulted to help identify
problem intersections in need of improvements within the upcoming Needs Assessment
phase of this study.
Page 49
January 2014
Page 50
January 2014
Page 51
January 2014
3.2
Travel Patterns
Understanding travel patterns both to and from Paulding County is critical for meeting
the travel needs of its residents and businesses. The purpose of this section is to
document the existing and projected regional travel trends based on output from the
ARC TDM. These travel patterns were derived based on more than 10,000 household
travel surveys conducted by the ARC. The two variables assessed in this analysis are:
Origins and Destinations Where are people going and how many are going there?
Travel Times How much time is it taking to access other parts of the region?
In addition to data from the TDM, journey to work data from the US Census was
consulted to provide supplementary information on travel patterns within the county.
3.2.1
Understanding the dynamic of travel to and from the county and the magnitude at
which inter-county travel occurs is important when prioritizing transportation needs.
For this analysis, there are three categories of trips taken into account:
Home Based Other (HBO) All other trips generated from a persons home
Non-Home Based (NHB) All other trips besides HBW and HBO
Table 8 presents the distribution of these three trips between Paulding County and
other portions of the region for 2015, 2030, and 2040. As shown, approximately 30
percent of HBW trips originating in Paulding County in 2015 are to jobs in Paulding
County, while a slightly higher percentage of Paulding commuters are destined for Cobb
County. Figure 22 shows the distribution of trips traveling to and from Paulding County
to other parts of the region for HBO and HBW trips. As shown, the bulk of the travel for
both HBW and HBO that leave the County are destined for Cobb County. Furthermore,
those trips destined for Fulton, Cherokee, DeKalb and other eastern portions of the
region must travel through Cobb to reach those destinations. As shown in Table 8, the
trip characteristics for NHB trips are very similar to those of HBO. In the horizon years,
the trip distribution characteristics are projected to be very similar with one exception:
the share of internal commuter trips is projected to increase through 2040. This reflects
an assumption of employment growth within Paulding. This may also be a function of
the increased travel times projected in 2040 during the peak hours, which is discussed in
the next subsection.
Table 9 shows the distribution of vehicle trips between the AM and PM peak hours in
2015 and 2040. The higher trip origins in the AM peak and higher trip destinations in the
PM peak reflect more people leaving the county in the AM and returning in the PM
peak. This trend is projected to continue through 2040.
Page 52
January 2014
Non-Home Based
Total Trips
Percentage
130,168
68%
39,532
21%
10,178
5%
3,473
2%
3,767
2%
2,860
1%
1,749
1%
630
0%
Total
Total Trips
Percentage
475,519
63%
154,023
20%
41,952
6%
27,317
4%
20,006
3%
17,600
2%
7,935
1%
4,721
1%
2030
Paulding (Internal)
Cobb
Douglas
Fulton
Bartow
Carroll
Cherokee
DeKalb
Total Trips
69,270
57,805
16,867
19,205
11,007
8,500
4,041
3,202
Percentage
36%
30%
9%
10%
6%
4%
2%
2%
Total Trips
471,200
102,832
30,852
11,289
12,105
11,975
4,907
2,053
Percentage
73%
16%
5%
2%
2%
2%
1%
0%
Total Trips
190,719
51,845
14,405
4,472
5,254
4,313
2,527
772
Percentage
69%
19%
5%
2%
2%
2%
1%
0%
Total Trips
731,190
212,482
62,124
34,966
28,366
24,788
11,474
6,027
Percentage
65%
19%
6%
3%
3%
2%
1%
1%
2040
Paulding (Internal)
Cobb
Douglas
Fulton
Bartow
Carroll
Cherokee
DeKalb
Source: ARC TDM
Total Trips
97,188
62,971
19,588
21,218
14,222
8,656
4,374
6,155
Percentage
40%
26%
8%
9%
6%
4%
2%
3%
Total Trips
574,316
116,613
34,536
13,811
12,500
15,072
5,851
2,474
Percentage
74%
15%
4%
2%
2%
2%
1%
0%
Total Trips
234,077
59,482
16,657
5,033
6,405
5,309
3,038
857
Percentage
71%
18%
5%
2%
2%
2%
1%
0%
Total Trips
905,581
239,066
70,781
40,062
33,127
29,038
13,264
9,486
Percentage
67%
18%
5%
3%
2%
2%
1%
1%
Page 53
January 2014
Page 54
2040
January 2014
2015
Origins
82,678
106,572
2015
Destinations
57,608
127,034
2040
Origins
151,927
191,161
2040
Destinations
103,951
229,999
In conjunction, the existing and projected disparity of directional flow in the AM and PM
peak hours suggests a continued need for emphasis on peak hour treatments to
roadways particularly those to Cobb County, such as US 278/SR 6, SR 120, and SR 92
to accommodate unbalanced directional flow. For example, this could include increased
signal coordination and/or reversible lanes. Furthermore, the disparity between internal
and external commuter trips suggests a continued need to promote commuter-oriented
travel demand management programs now and into the future.
In addition to TDM data, data from the US Census was analyzed to further assess travel
patterns within the county. Journey to work data was collected from the American
Community Survey for the period between 2006 to 2010. This data is shown below in
Table 10. This data represents the average number of home based work trips to
destination counties over a year period but cannot be attributed to any one year within
the five year period.
Table 10: US Census Journey to Work Destinations (2006-2010)
Destination County
Paulding (Internal)
Cobb
Douglas
Fulton
Bartow
Carroll
Cherokee
DeKalb
Gwinnett
Other
Total
Source: American Community Survey 2006-2010
Number
16,392
23,055
4,609
10,045
1,201
1,090
806
1,638
1,132
3,095
63,064
Percentage
26%
37%
7%
16%
2%
2%
1%
3%
2%
5%
100%
The census data largely tracks with the data pulled from the TDM, with some variations.
Cobb, Paulding, Fulton, and Douglas Counties are found to be the top four destination
counties within both data sets in the same order and general magnitude. However, the
ACS data shows Cobb destinations to be a higher percentage of total trips compared to
Paulding destinations (37% vs 26%), when compared to the more even split found
within the TDM (29% to 31%). The most striking difference between the data sets
involves the total number of home based work trips. The TDM projects close to twice as
many home based work trips in 2015 to the data presented within the 2006-2010 ACS.
Page 55
January 2014
Travel Times
Downtown Marietta
Town Center
2015
AM Peak from
Paulding
(min)
45-55
60-70
2015
PM Peak to
Paulding
(min)
55-65
65-75
2040
AM Peak from
Paulding
(min)
80-90
90-100
2040
PM Peak to
Paulding
(min)
100-110
110-120
Cumberland
Downtown Atlanta
70-80
75-85
80-90
80-90
110-120
120-130
130-140
150-160
Midtown Atlanta
Buckhead
80-90
90-100
85-95
95-105
125-135
125-135
155-165
150-160
Perimeter Center
95-105
100-110
130-140
155-165
As shown in Table 11, the 2015 commute times even to close activity centers in
neighboring Cobb County for Paulding County commuters are 45 minutes or above.
These travel times are a function of the typical Paulding commute taking place on
surface streets. In 2040 commute times to the major employment centers throughout
the region will increase dramatically, with most PM peak hour commute times taking
over two hours. This increase reinforces the need for peak hour treatments along some
of the key arterials such as US 278/SR 6, SR 120, and SR 92 and continued travel demand
management strategies into these major employment centers.
Page 56
January 2014
Page 57
2040
January 2014
3.3
Safety
Crashes occur most frequently at intersections, but they can also occur along segments of a
street or highway for many reasons. Understanding where and why crashes occur is useful in
measuring relative need and prioritizing projects. Crash data was analyzed using two distinct
approaches. A crash hotspot analysis was conducted to identify high crash locations, in addition
to a roadway segment analysis.
Using GIS, crash locations in close proximity to each other were grouped together to identify
crash hotspot locations. These are shown in Figure 24. This data was sourced from GDOTs
statewide crash database and is distributed by the GDOT Office of Traffic Safety and Design.
The data includes the years 2010-2012. Crash hotspots occur frequently on US 278/SR 6,
Merchants Drive, SR 120, SR 92, and SR 61. A particularly heavy concentration of hotspots can
be found in the proximity of the US 278/SR6 and SR 92 intersection in the Hiram Crossroads
area.
A segment analysis was also conducted to identify major roadway segments with crash rates
higher than the state average per 100 million vehicle miles (MVM) for their respective
functional classification type. Segments with averages above the state average have been
identified on Figure 25. Table 12 below details the average crash rates compared to the state
average for the roadway classification. The majority of above-average segments are found in
the more densely populated eastern portion of the county.
Table 12: Major Roadway Segments with Above-Average Crash Rates
Roadway
SR 92
Dallas-Acworth
Highway
Business
6/Buchanan
Street/SR 120
SR 120
SR 101
US 278/ SR 6
Page 58
From
Hiram-Acworth Hwy
Cobb County Line
Average
Crash Rate
(100 MVM)
831
308
SR 120
US 278/SR 6
Hiram-Sudie Rd
Douglas
County Line
E. Paulding Drive
756
344
1,006
884
463
463
463
463
551
463
SR Business 6
SR 120 (Conn)
346
622
463
463
SR 120 (Conn)
Polk County Line
SR 120
Polk County Line
SR 101
SR 120
Carroll County Line
SR 120
260
531
118
176
142
142
142
113
SR 120
SR 61
109
461
SR 61
Business 6
347
461
To
Functional
Classification
Statewide
Average
(100 MVM)
463
463
January 2014
Business
6/Merchants
Drive
SR 120
SR 360
SR 61
Dabbs Bridge
Road
Ridge Road
Nebo Road
Dallas-Nebo
Road
Sweetwater
Church Road
Brownsville
Road
SR 120 (Conn)
Hiram-Sudie
Road
Bill Carruth
Parkway
From
To
Business 6
US 278/SR 6
Memorial Drive
SR 92
SR 92
US 278/SR 6
SR 92
SR120
Ridge Road
Functional
Classification
National Highway System
Urban Principal Arterial
National Highway System
Urban Minor Arterial
Average
Crash Rate
(100 MVM)
Statewide
Average
(100 MVM)
1,216
461
1,562
463
420
461
757
461
337
1,130
263
463
463
187
Hiram-Sudie Road
US 278/SR 6
Old Cartersville
Road
Mt. Moriah Road
779
988
3,205
463
463
463
335
463
274
154
354
187
187
160
SR 61
Dallas-Nebo Road
SR 61
Dallas-Nebo Road
SR 61
Nebo Road
Ridge Road
Douglas County
Line
SR 92
Dallas-Nebo Road
SR 92
Dallas-Nebo Road
SR 92
Nebo Road
Ridge Road
Douglas County Line
SR 92
818
784
523
1,363
332
405
291
454
463
463
431
431
431
431
431
431
518
463
SR 120
SR 61
SR 61
SR 92
646
608
463
463
US 278/SR6
SR 92
232
463
Old Cartersville
Road
Mt. Moriah Road
Dabbs Bridge Road
SR 61
In addition to vehicular crashes, crashes involving pedestrians and bicycles were also
examined. These are displayed in Figure 26. Pedestrian crashes are found throughout
the county on major arterials, collectors and local roads. The largest cluster is found on
US 278/SR 6 in the vicinity of SR 92 in the Hiram Crossroads area, which has signalized
crosswalks but is lacking in sidewalks and has multiple curb cuts. Bicycle crashes are
relatively rare within the county with only three occurring in the three year period
between 2010 and 2012. These accidents are found in the southern portion of the
county near residential areas along Glenn Eagles Way, Bakers Bridge Road, and Laird
Road.
Page 59
January 2014
Page 60
January 2014
Page 61
January 2014
Page 62
January 2014
3.4
The following section provides an analysis of current bridge conditions relative to sufficiency
and importance to the overall roadway network. Maintaining bridges in good condition is
important for safety and to avoid delays due to road closures and weight limits. Bridges are
evaluated through a universally accepted rating formula which indicates a bridges condition
and its ability to remain in service. The result of the standardized formula is a number between
zero and 100, for which 100 represents an entirely sufficient bridge and zero represents an
entirely insufficient or deficient bridge.
The collective factors which form a sufficiency rating are collected by GDOT and submitted to
the FHWA on an annual basis. Key factors which make up a sufficiency rating include the
number of lanes relative to the roadway it carries, Average Annual Daily Traffic, structural
condition and deck condition.
Sufficiency ratings do not necessarily indicate a bridges ability to safely carry traffic loads.
Measures used to determine a bridges sufficiency also include metrics not related to the
structural integrity. These include under-clearances, the bridges location on the national
highway system, conditions of the bridge approaches, and traffic safety features, like railing
height and potential detour length should the bridge be closed. In total, there are 18 key
factors used to calculate sufficiency ratings.
The former Highway Bridge Program utilized sufficiency ratings to help prioritize bridges in
need of repair or replacement. The Highway Bridge Program was authorized by the Safe,
Accountable, Flexible, and Efficient Transportation Equity Act: A Legacy for Users (SAFTEA-LU).
Under the most recent transportation bill, Moving Ahead for Progress in the 21st Century Act
(MAP-21), this program was discontinued, although the sufficiency thresholds it establishes are
still useful for helping identify bridges in need of improvements or replacement. Under the
former program a bridge must exhibit a rating of 50 or below to qualify for federal replacement
funds. Bridges with sufficiency ratings between 50 and 80 met the minimum qualifications for
rehabilitation funding. Rehabilitation can include maintenance or repair of bridge decks,
expansion joints, bridge railings, foundations, and piers etc. Bridge rehabilitation can be a cost
efficient solution for bridges with sufficiency ratings below 50 if it can be demonstrated that the
rehabilitation will improve the bridge to an acceptable sufficiency rating.
To determine bridge sufficiency ratings within the county bridge data was collected from the
Bridge Maintenance Unit of the GDOT Office of Bridges and Structures. The data identifies nine
bridges with sufficiency ratings below 50 and 25 bridges with sufficiency ratings between 50
and 80. These bridges are described in Table 13 and located on Figure 27. Insufficient bridges
are primarily found carrying county roads, with only five found on the state route system. Four
bridges with low sufficiency ratings carry the Silver Comet Trail over underlying roadways,
which include West Avenue, Academy Drive, Metromont Road and Seaboard Drive.
Page 63
January 2014
Structure ID
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
223-5012-0
223-5045-0
223-5056-0
223-0026-0
223-5064-0
223-5068-0
223-5069-0
223-5070-0
223-5040-0
223-5071-0
223-5029-0
223-0025-0
223-5073-0
223-5074-0
223-5045-0
223-5075-0
223-5076-0
223-5011-0
223-5077-0
223-5033-0
223-5078-0
223-5030-0
223-5092-0
223-5081-0
223-5088-0
223-5082-0
223-5083-0
223-0023-0
223-5084-0
223-5085-0
223-5086-0
223-5093-0
223-5087-0
Facility Carried
Willow Springs Road
Silver Comet Trail
Silver Comet Trail
Dallas/Acworth Highway
Oberlochen Way
Woodrow Kay Road
Nebo Road
Swan Drive
Morningside Drive
Paul Harris Road
Pine Valley Road
Dallas/Acworth Highway
Laird Road
SR 120
Due West Road
SR 120
R.C. Thompson Road
Mt Olivet Road
SR 61
Bennett Road
Silver Comet Trail
Austin Bridge Road
Harmony Grove Church Rd
Bill Carruth Parkway
Seven Hills Blvd
Bill Carruth Parkway
SR 120
East Memorial Drive
Silver Comet Trail
Mill Creek Path
Hughes Road
Old Harris Road
Old Harris Road
Feature Intersected
Silver Comet Trail
West Avenue
CR 243 Academy Drive
Picketts Mill Creek
Sweetwater Creek Tributary
White Creek
Davis Mill Creek
Davis Mill Creek
Lick Log Creek
Little Pumpkinvine Creek
Sweetwater Creek
Possum Creek
Lick Log Creek
Powder Springs Creek
Picketts Mill Creek
Powder Springs Creek Tributary
McClendon Creek Tributary
Pumpkinvine Creek
Hardee Street/NS RR
Mill Creek
Metromont Road
Sweetwater Creek
Pumpkinvine Creek
Silver Comet Trail
Little Pumpkinvine Creek
Norfolk Southern RR/CK.
Lane Creek
Griffin Creek
Seaboard Avenue
Mill Creek
Lick Log Creek
Silver Comet Trail
Norfolk Southern RR
Sufficiency
Rating
15.18
15.88
28.9
28.9
36.86
47.86
47.98
49.01
49.01
56.28
56.28
57.42
59.50
60.64
60.64
61.50
64.81
64.81
69.92
69.92
70.09
70.09
73.33
74.23
74.23
75.04
76.69
76.69
77.33
77.46
78.57
78.57
79.84
Year
Constructed
1941
1963
1963
1940
1988
1988
1985
1994
1979
1995
1963
1940
1996
1997
1963
1997
1998
1969
1998
1971
1999
1979
2008
2001
2005
2001
2002
1940
2003
2002
2002
2010
2006
Page 64
January 2014
Page 65
January 2014
Facility Carried
Nebo Road
Feature Intersected
Lick Log Creek
223-0031-0
East Paulding
Drive
Braswell
Mountain
Road
East Memorial
Drive
East Memorial
Drive
Dallas-Acworth
Highway
Dallas-Acworth
Highway
Harmony
Grove Church
Road
Possum Creek
Comments
The bridge culvert is in good condition with no reported structural
defects.
The bridge culvert is in good condition.
Raccoon Creek
Griffin Creek
Lawrence Creek
Possum Creek
223-0027-0
223-0023-0
223-0024-0
223-0025-0
223-0026-0
223-5092-0
Source: GDOT
223-5008-0
223-5009-0
223-5010-0
223-5054-0
Page 66
Facility Carried
Poplar Springs
Road
Silver Comet
Trail
Feature Intersected
Rakestraw Creek
Cedarcrest
Road
Dabbs Bridge
Road
High Shoals
Road
Southern
Railroad
Westbrook Creek
Metronmont Road
Pumpkinvine Creek
Raccoon Creek
Mt. Olivet Road
Comments
This bridge culvert is in good condition. Maintenance
recommendations have been identified.
This non-highway pedestrian structure is in good condition with no
reported structural defects. Maintenance recommendations have
been identified.
This bridge culvert is in fair condition. Maintenance
recommendations have been identified.
The bridge structure is in good condition. Maintenance
recommendations have been identified.
This bridge culvert is in fair condition. Maintenance
recommendations have been identified.
This non-highway structure has been inspected for clearance
purposes only. The minimum vertical clearance is substandard and
requires posting.
January 2014
Facility Carried
Mt. Olivet
Road
Feature Intersected
Pumpkinvine Creek
223-5012-0
Willow Spring
Road
223-5014-0
Holly Springs
Road
Woodrow Kay
Road
Goldin Road
White Creek
Allgood Church
Road
McGarity Road
Tallapoosa River
Silver Comet
Trail
Silver Comet
Trail
Paul Harris
Road
Paul Harris
Road
Friendship
Church Road
Carrington
Lake
Perkins Road
West Avenue
223-5029-0
Pine Valley
Road
Sweetwater Creek
223-5030-0
Mill Creek
Road
Mill Creek
Road
Sweetwater Creek
Hughes Road
223-5068-0
223-5016-0
223-5017-0
223-5019-0
223-5056-0
223-5057-0
223-5071-0
223-5072-0
223-5025-0
223-5064-0
223-5028-0
223-5085-0
223-5068-0
Page 67
White Creek
Tallapoosa River
McClendon Creek
Academy Drive
Little Pumpkinvine
Creek
Little Pumpkinvine
Creek
Sweetwater Creek
Sweetwater Creek
Tributary
Lick Log Creek
Comments
At the present time post this structure for 19 Tons H-Truck; 19 Tons
Type 3 Truck; 26 Tons Timber Truck; 23 Tons HS-Truck and 32 Tons
Type 3S2 Truck. This structure requires posting due to insufficient
shear capacity of the concrete superstructure. A replacement
structure is required to upgrade this structure to a point where
posting is no longer required. Maintenance recommendations have
been identified to maintain current rating. At the time of the
inspection, the posting sign at the northern end of the structure was
missing. This sign is required and must be replaced.
At the present time post this structure for 08 Tons H-Truck; 09 Tons
Type 3 Truck; 13 Tons Timber Truck; 13 Tons HS-Truck and 18 Tons
Type 3S2 Truck. This structure requires posting due to the low
original design capacity of the structure. A replacement structure is
required to upgrade this structure to a point where posting is no
longer required. Maintenance recommendations have been
identified to maintain current rating.
The bridge culvert is in good condition. Maintenance
recommendations have been identified.
The corrugated metal pipe culvert is in fair condition. Maintenance
recommendations have been identified.
This bridge structure is in fair condition. Maintenance
recommendations have been identified.
This bridge structure is on good condition. Maintenance
recommendations have been identified.
This bridge structure is in good condition. Maintenance
recommendations have been identified.
This non-roadway structure is in good condition. Maintenance
recommendations have been identified.
This non-roadway structure is in good condition. Maintenance
recommendations have been identified.
The bridge structure is in fair condition. Maintenance
recommendations have been identified.
The bridge structure is in good condition. Maintenance
recommendations have been identified.
The bridge structure is in fair condition. Maintenance
recommendations have been identified.
This corrugated metal pipe culvert serves as a lake spillway and
overflow. Maintenance recommendations have been identified.
This bridge culvert is in satisfactory condition with no reported
structural deficits. Maintenance recommendations have been
identified.
At present time, Post this structure for 16 Tons H-Trucks; 18 Tons
Type 3 Truck and 25 Tons Timber Truck. This structure requires
posting due to insufficient shear capacity of the concrete
superstructure. A replacement structure is required to upgrade this
structure to a point where posting is no longer required.
Maintenance recommendations are provided to maintain this
structure at the current rating.
This bridge structure is in fair condition. Maintenance
recommendations have been identified.
This corrugated metal pipe culvert is in good condition with no
reported structural deficiencies. Maintenance recommendations
have been identified.
This corrugated metal pipe culvert is in good condition.
Maintenance recommendations have been identified.
January 2014
Facility Carried
Bennett Road
Feature Intersected
Mill Creek
223-5073-0
Laird Road
223-5036-0
Cochran Road
Mill Creek
223-5037-0
223-5040-0
Mill Creek
Lick Log Creek
223-5043-0
Old Cartersville
Road
Old Cartersville
Road
Due West Road
Lawrence Creek
Sweetwater Creek
223-5048-0
Bakers Bridge
Road
Bakers Bridge
Road
Nebo Road
223-5049-0
Nebo Road
223-5050-0
Hulsey Town
Road
Thompson
Road
Nebo Road
Bluffy Creek
223-5093-0
Old Harris
Road
223-5087-0
Old Harris
Road
Swan Drive
Norfolk Southern
Railroad
Davis Mill Creek
Bill Carruth
Parkway
West Hiram
Parkway
Silver Comet
Trail
Seaboard Drive
Seven Hills
Blvd
Double
Branches Lane
Little Pumpkinvine
Creek
Possum Creek
223-5044-0
223-5045-0
223-5094-0
223-5047-0
223-5076-0
223-5069-0
223-5070-0
223-5081-0
223-5082-0
223- 5084-0
223-5095-0
223-5088-0
223-5089-0
Page 68
Bone Creek
Picketts Mill Creek
Sweetwater Creek
Tributary
Davis Mill Creek
McClendon Creek
Tributary
Davis Mill Creek
Comments
This bridge structure is in fair condition. Maintenance
recommendations have been identified.
This bridge structure is in fair condition. Maintenance
recommendations have been identified.
This bridge culvert is in fair condition. Maintenance
recommendations have been identified.
This corrugated metal pipe culvert is in fair condition.
At present time post this structure for 14 Tons H-Truck; 14 Tons
Type 3 Truck and 17 Tons Timber Truck. This structure requires
posting due to insufficient flexural capacity of the superstructure
and insufficient lateral stability of bent #5. A replacement structure
is required to upgrade this structure to a point where posting is no
longer required. Maintenance is recommended to maintain this
structure at the current rating.
The bridge culvert is in fair condition. Maintenance
recommendations have been identified.
The bridge culvert is in fair condition. Maintenance
recommendations have been identified.
The bridge structure is in fair condition. The bridge culvert is in fair
condition. Maintenance recommendations have been identified.
The bridge structure is in good condition with no reported structural
deficiencies.
The bridge culvert is in fair condition. The bridge culvert is in fair
condition. Maintenance recommendations have been identified.
This bridge culvert is in fair condition with no reported deficiencies.
Vegetation growing in vicinity of the structure should be cut and
removed.
The bridge culvert is in good condition. Maintenance
recommendations have been identified.
This bridge culvert is in fair condition. Maintenance
recommendations have been identified.
This corrugated metal pipe culvert is in good condition.
This bridge culvert is in good condition with no reported structural
defects. Vegetation growing in vicinity of the structure should be cut
and removed.
This all concrete bridge structure is in good condition with no
reported structural deficiencies. However, the northern right
sidewalk has settled and should be repaired.
This bridge structure is in good condition.
This metal pipe culvert is in fair condition with no reported
structural defects. Maintenance recommendations have been
identified.
The bridge structure is in good condition with no reported structural
defects. Maintenance recommendations have been identified.
This bridge structure is in good condition. Maintenance
recommendations have been identified.
This non-highway pedestrian structure is in good condition with no
reported structural defects.
This corrugated metal pipe culvert is in good condition with no
reported structural deficiencies.
This bridge structure is in good condition. Maintenance
recommendations have been identified.
This bridge structure is in good condition with no reported structural
deficiencies. Maintenance recommendations have been identified.
January 2014
Facility Carried
Double
Branches Lane
Feature Intersected
Possum Creek
Comments
This all concrete bridge structure is in good condition with no
reported structural deficiencies. However, vegetation growing in the
vicinity of the structure should be cut and removed.
Source: GDOT
3.5
Page 69
January 2014
Page 70
January 2014
SR 92
From
To
Cobb County
Line
HiramAcworth
Hwy
Cobb County
Line
DallasAcworth
Hwy
Cobb County
Line
SR 120
US 278/SR 6
Dallas-Acworth
Highway/
East Memorial
Drive
Business
6/Buchanan
Street
SR 120 (West)
SR 101/113
US 278/ SR 6
Bus SR
6/Merchants
Drive
SR 120
SR 360
SR 61
Hiram-Sudie
Rd
SR 92
Daily
Truck
Volume
2030
3,600
Daily
Truck
Volume
2040
3,900
Truck
%
2015
Truck
%
2030
Truck
%
2040
11%
10%
11%
1,500
2,900
3,400
14%
13%
13%
SR 120
1,600
3,100
3,600
9%
9%
10%
US 278/SR6
Hiram-Sudie
Rd
Douglas
County Line
E. Paulding
Drive
1,600
1,400
3,200
2,500
3,700
2,900
8%
8%
8%
9%
9%
10%
1,500
2,900
3,500
7%
7%
7%
600
700
600
7%
6%
4%
E. Paulding
Drive
Memorial
Drive
Bus SR 6
500
600
600
4%
4%
4%
US 278/SR6
300
300
300
3%
2%
2%
US 278/SR 6
SR 120
(Conn)
Haralson
County Line
SR 120
300
200
300
4%
2%
3%
200
200
300
3%
2%
3%
200
200
300
4%
3%
3%
Carroll
County Line
SR 120
700
800
1,000
5%
4%
5%
400
600
700
2%
2%
3%
SR 61
Business 6
Cobb County
Line
Memorial
Drive
600
1,200
1,400
800
1,500
2,000
1,000
1,500
2,100
2%
3%
4%
2%
3%
4%
3%
3%
4%
100
200
200
2%
2%
2%
SR 92
600
900
1,000
2%
2%
2%
US 278/SR 6
SR 92
700
500
800
700
900
800
2%
2%
2%
2%
2%
2%
SR 120
Ridge Road
300
1,000
400
1,200
500
1,300
2%
6%
2%
6%
2%
6%
Hiram-Sudie
Road
US 278/SR 6
600
800
800
7%
7%
6%
600
900
800
4%
4%
4%
SR 120
(Conn)
Polk County
Line
SR 120
Polk County
Line
SR120
SR 61
Business 6
US 278/SR 6
Cobb County
Line
SR 92
Cobb County
Line
SR 92
Douglas
County Line
Ridge Road
Hiram-Sudie
Road
Page 71
Daily
Truck
Volume
2015
2,100
January 2014
From
US 278/SR 6
Dabbs Bridge
Road
Ridge Road
Old
Cartersville
Road
Mt. Moriah
Rd
Dabbs
Bridge Road
SR 61
SR 61
Nebo Road
Dallas-Nebo
Road
SR 61
Dallas-Nebo
Road/Bakers
Bridge Road
Dallas-Nebo
Road
SR 61
Nebo Road
Ridge Road
Sweetwater
Church Road
Brownsville
Road
Scoggins Rd
Hiram-Sudie
Road
Source: ARC TDM
Douglas
County Line
SR 92
SR 120
SR 61
To
Daily
Truck
Volume
2015
400
Daily
Truck
Volume
2030
600
Daily
Truck
Volume
2040
600
Truck
%
2015
Truck
%
2030
Truck
%
2040
3%
4%
4%
200
300
400
2%
3%
4%
Dabbs
Bridge Road
Bartow
County Line
Bartow
County Line
Dallas-Nebo
Road
SR 92
500
600
800
4%
4%
5%
600
700
700
4%
4%
3%
100
200
600
2%
4%
4%
100
200
200
2%
3%
2%
100
400
400
1%
3%
2%
Dallas-Nebo
Road
SR 92
100
100
200
2%
2%
3%
100
200
200
2%
2%
2%
Nebo Road
Ridge Road
Douglas
County Line
SR 92
200
400
400
200
100
400
200
200
500
2%
3%
3%
2%
1%
2%
1%
2%
3%
200
400
400
3%
4%
3%
Cobb County
Line
SR 61
SR 92
200
100
100
3%
2%
2%
0
200
100
300
100
300
0%
2%
2%
2%
1%
2%
Old
Cartersville
Road
Mt. Moriah
Rd
The analysis presented in Table 16 coincides with the ARCs ASTRoMaP corridors, which
identify SR 92, US 278/SR 6, and SR 61 as major freight corridors. The highest truck
volumes and percentages within the county are found along SR 92, and are anticipated
to grow significantly from 2015 to future years 2030 and 2040, with volumes more than
doubling on many segments. Segments of SR 92 exhibit the highest truck percentages in
the county with many in the 10-14 percent range. Typical arterials in the region carry
approximately 3-5 percent trucks.
Several segments of US 278/SR 6 also exhibit high levels of truck volumes. This is
particularly evident in the eastern portion of the county from the Cobb County line to SR
61. Truck volumes along these segments have volumes ranging from 1,200-1,400 trucks
in 2015. These volumes are anticipated to grow to 1,500-2,100 trucks in 2040.
Page 72
January 2014
3.6
Traffic Signalization
Traffic signalization is an important element to reducing travel delay, maintaining
mobility, and promoting safety along heavily-traveled corridors. As capacity
improvements become less feasible due to funding limitations, operations planning will
become a greater focus in the development of future transportation networks.
Figure 29 shows the locations of traffic signals throughout the Paulding County roadway
network. There are currently 63 signals within the county. Most of the signals are along
the US and state route highways within in the County (such as US 278/SR 6, SR 92, and
SR 120) which are also the countys most heavily-traveled roadways.
As shown in Figure 29, within developed areas such as the cities of Dallas and Hiram,
many the traffic signals along these corridors are located in close proximity to one
another. Closely-spaced traffic signals are more greatly affected by the degree of traffic
signal coordination along the travel corridor; well-timed traffic signals can process larger
amounts of traffic more smoothly, where poorly-timed traffic signals will have vehicle
queue spillback through adjacent intersections and lead to delays and driver frustration.
Increasing the number of access points (which are both side streets and driveway access
points) per mile also impacts roadway operation and the effectiveness of traffic signal
coordination. These conditions typically indicate the need for improved signal
coordination efforts and access management along developed corridors.
The Regional Traffic Operations Program (RTOP) is a GDOT initiative intended to
maximize the efficiency of a roadway through effective intelligent transportation
systems (ITS) and signalization treatments. The US 278/SR 6 corridor in Paulding County
is currently being maintained under the RTOP 2 program.
The latest federal transportation bill passed in 2012, Moving Ahead for Progress in the
21st Century (MAP-21), emphasizes operations and monitoring the performance of
roadways. This emphasis would indicate the potential for more funding to expedite the
Page 73
January 2014
3.7
Roadway
1
2
3
4
5
6
7
8
9
10
Rosedale Drive
Seaboard Avenue
Hiram-Douglasville Highway
Weddington Road
Thompson Road
Coppermine Road
Bill Carruth Parkway
11
12
13
14
15
16
17
Tucker Boulevard
18
Lane Road
19
US 278 /SR 6 (Jimmy Campbell Parkway)
20
Mt. Olivet Road
21
Willow Springs Road
22
McPherson Church Road
23
Brushy Mountain Road
Source: Jacobs
Page 74
January 2014
Page 75
January 2014
Page 76
January 2014
Page 77
January 2014
3.8
Route
2008
470
384
477
272
Source: GRTA
2009
2010
2011
2012
338
251
321
236
294
221
272
220
2013 (JanAug)
270
227
2008-2013
Change
-114
-45
Percentage
Change
-30%
-17%
While ridership of GRTA services has trended down over the past few years, there are
some demographic characteristics within Paulding County that suggests that the Xpress
service can grow in ridership once the economy rebounds. Throughout the county,
there are concentrations of populations that are low-income with automobiles. As jobs
continue to develop in the Atlanta core areas of Midtown and Downtown, it would be
reasonable to assume that the Xpress service can be a viable commute option.
Page 78
January 2014
3.9
Airports
This section focuses on Silver Comet Field and Hartsfield-Jackson Atlanta International
Airport (H-JAIA). H-JAIA has been included in this analysis due to its proximity and
importance to Paulding County in regards to air cargo and freight movement.
3.9.1
Silver Comet Field is a county-owned, regional, general and business aviation airport on
600 acres in western Paulding County. It is located on US 278/SR 6 within the Paulding
Forest WMA. The airport opened in 2010 and is the newest regional airport in Georgia,
as well as the first jet-capable airport to be built in Georgia in over thirty years. Silver
Comet Field is located 40 miles from Hartsfield-Jackson Atlanta International Airport and
30 miles from downtown Atlanta. The airport features a 23,000 square foot terminal
and a 6,000 foot runway with 7,500 feet of expansion capability.
Adjacent to the airport is the proposed Airport Technology Park, a 190-acre countyowned property suitable for aerospace and aviation company occupation. A total of 80
acres of the park feature direct runway access. The Paulding County Industrial Building
Authority is also currently constructing a 35,000 foot hangar for aircraft and corporate
offices at this site.
The County has adopted the Paulding Airport Master Overlay District to create a mixeduse zoning district which enhances and promotes economic development in the area
surrounding the airport, while maintaining flexibility in design and development
standards. The overlay boundaries are very sizable, encompassing a large area between
US 278/SR 6 and SR 120 (Buchanan Highway). Regulations within this overlay promote
high quality development through required building materials, site design standards,
and architectural guidelines. Specific land uses are prohibited in areas with the
potential for accidents and substantial noise impact areas.
Page 79
January 2014
H-JAIA is the major airport for passenger travel within the metropolitan region and is
the primary passenger airport terminal for Paulding County residents. Since 1998,
Hartsfield-Jackson has claimed the title of the worlds busiest passenger airport,
averaging more than 250,000 passengers a day. It is located approximately 40 miles
from Dallas in College Park. The airport also houses three main air cargo complexes,
and has a total of 2 million square feet of cargo handling space.
The primary roadways used to access this facility from Paulding County are US 278/SR 6
and SR 92. As a potential freight connection, this further enhances the importance of
maintaining adequate LOS and operability along these roadways.
3.10
Page 80
January 2014
GRTA Xpress As noted in Subsection 3.8, GRTA operates two routes from the
Movies 278 lot in Hiram to downtown Atlanta and midtown Atlanta. In August 2013,
these routes combined averaged approximately 400 riders per day. While not in
Paulding County, Routes 460 and 461 operate out of Douglasville and also provide a
commute option to those residents of the Brownsville area and southern Paulding
County.
Clean Air Campaign - The Clear Air Campaign runs the Georgia Commute Options
program which serves the Atlanta region, including Paulding County. This program
encourages commuters to carpool, vanpool, telework, and ride transit as part of a
regional strategy to reduce traffic and improve air quality. The program is utilized by
many major employers in the county, including WellStar Hospital, the State of
Georgia, or the Paulding County School District. The program provides cash
incentives and prizes to employees that use the service.
The Clean Air Campaign utilizes two Georgia Rideshare lots for carpooling or vanpooling
within the county. These include a lot at the First Baptist Church in downtown Dallas
and a lot adjacent to Simmon Industrial Boulevard at the Dallas Commons Shopping
Center. The First Baptist Church lot features 34 spaces and an average weekday usage
of 10 percent. The Simmon Industrial Boulevard lot features 167 spaces and an average
weekday usage of 16 percent. Information on lot sizes and usage rates have been
sourced from the ARCs 2012 Transportation Fact Book.
As noted throughout this report, both the demographics and existing and projected
travel patterns lend themselves to the feasibility of increased participation in
transportation demand management programs particularly ridesharing and/or
vanpooling.
January 2014
Page 82
January 2014
Page 83
January 2014
The following subsections describe the goals and emphasis areas of these different
programs.
Surface Transportation Program
Of the three programs, the STP program has the greatest amount of funding. ARC
estimates the projected funding available for the region at approximately $70 million
annually. Since these programs are federally-funded, a 20 percent local match is
required. Most of these funds are passed along to GDOT for improvements; however,
the ARC does have discretionary STP funds. As discretionary funds, the ARC filters these
funds through these program areas:
Page 84
Roadway Safety Program This program supplements other operations and safety
programs in the region by implementing projects that improve traffic operations and
safety along roadways and at key intersections. Potential projects include
costeffective solutions such as intersection improvements and signal upgrades. The
program objectives address congestion relief, safety, and support for economic
development.
Freight Safety Program The purpose of this program is to enhance, as quickly and
efficiently as possible, the regional freight transportation network that serves the
regional economy. Such thoroughfares include US 278/SR 6, SR 92, SR 61. The focus
of this program is on short term projects with high cost/benefit ratios that can be
implemented without excessive delays.
Last Mile Connectivity Program This program implements planning and capital
improvements for safe bicycle and pedestrian travel in the region, with an emphasis
on correcting hot spots near schools. The program is also used to provide
pedestrian connections to transit. Therefore, pedestrian facilities along US 278 to
improve access to the Xpress facility at Movies 278 would be eligible.
LCI studies Projects within LCI areas, such as the Dallas LCI area, to link
transportation and land use.
January 2014
Clean Vehicle & Technology Programs Purchase alternative fuel vehicles or convert
fleets to run on alternative fuels. While not necessarily a CTP issue, this fund could
be used for upgrades to County fleet vehicles if so desired.
Page 85
January 2014
Regional Trail Networks Shared-use paths that enhance mobility & access in the
region. With the presence of the Silver Comet Trail, this is an area that could be
utilized for trail connections throughout the county.
Safe Routes to Schools Enhancing safe & convenient access to elementary and
middle schools; can be projects that compliment education, outreach, and planning
efforts to enhance safe access to schools.
Transit & Station Area Access Increase the safe and convenient access to regional
transit systems, including rail, bus (local or express), and the first-mile and last-mile
connectivity to the regional transit network. While the areas surrounding the GRTA
lot in Hiram are very auto-oriented, this fund could be used to provide better
pedestrian connectivity to any new lots should the Xpress service be expanded.
Page 86
Safety Program (GDOT State Traffic Operations Office) This program is a federallyfunded program designed to reduce the number and severity of lane departure
crashes, improve pedestrian safety and improve design and operation of
intersections.
House Bill 202 - Another potential funding opportunity lies in the passage of House
Bill 202, which waives the requirement to balance funds by congressional districts
for all interstate improvements, certain freight corridor projects and projects of
regional significance. The law was intended to prepare Georgia for increased freight
flow as a result of the deepening of the Savannah River at the port.
Page 87
ARC PLAN 2040 This contains a complete list of projects for which federal funds
are to be expended for their implementation.
January 2014
Paulding County SPLOST Work Program Projects either fully funded or partially
funded through the SPLOST funds. Many of the projects within the ARC PLAN
2040 are partially funded through the SPLOST (in most cases as a local match to
federal funds).
Page 88
January 2014
Page 89
January 2014
Project
Description
From
To
Project
Status
Program
Year
Project
Sponsor
Project Description
SR 120
Railroad Bridge
Programmed
Programmed
2020
2030
SR 92 (Hiram-Acworth
Highway)
Southern Rail Line in Downtown Hiram
Dallas-Nebo Road US 278 (Jimmy Campbell
Highway)
End of Existing Airport Parkway on New Location
to a Cul-De-Sac
Paulding County Business and Technology Park
Roadway on New Location to a Cul-De-Sac
Between Brown
Nebo Road
and Malone
Streets
Nebo Road
SR 120
Programmed
2030
Programmed
Programmed
2020
2030
GDOT
Paulding
County
Paulding
County
GDOT
TBD
Programmed
2020
Programmed
2020
Programmed
2020
Paulding
County
Paulding
County
GDOT
Programmed
2020
GDOT
Programmed
2030
GDOT
Programmed
2030
GDOT
Programmed
2020
City of Dallas
Long Range
2040
Long Range
2030
Long Range
2040
Paulding
County
Paulding
County
Paulding
County
Nebo Road
SR 92 (Hiram-Douglasville
PA-092A
Highway)
SR 92 (Hiram-Acworth
PA-092B1 Highway)
SR 92 (Hiram-Acworth
SR 120
Cedarcrest Road
PA-092C
Highway)
SR 92 (Dallas-Acworth
Cedarcrest Road
Cobb County Line, North of
PA-092E
Highway)
Old Stilesboro Road
Johnston Street, Griffin Street, Spring Street, and Park Street Pedestrian
PA-095
Facilities
SR 61 (Cartersville US 41 (North Cobb
PA-032
Dabbs Bridge Road
Highway)
Parkway)
Harmony Grove
Cobb County Line
PA-036B
Cedarcrest Road
Church road
SR 92
Seven Hill Extension
PA-036C
Cedarcrest Road
Source: ARC PLAN 2040
Page 90
Pedestrian Facilities
Widen from 2 to 4 lanes
Widen from 2 to 4 lanes
Widen from 2 to 4 lanes
January 2014
4.1
Page 91
The county is anticipated to add 153,893 residents between 2010 and 2040,
representing a 118.5 percent increase. The number of households is expected to
grow at the similarly high rate of 128.3 percent. The number of employees is
projected to increase at a higher rate, 150.1 percent, adding 30,625 jobs to the
county between 2010 and 2040. In general, this would indicate a need to improve
the county transportation network as a whole to prepare for this growth.
Understanding where this growth is to occur is critical in prioritizing transportation
needs.
The county currently exhibits a jobs-to-housing ratio of 0.44. This ratio is projected
to improve to 0.49 in 2040. This ratio suggests the county will remain a suburban
residential community, which will require many workers to commute across county
lines to access jobs.
It is likely that the employment projections are somewhat understated given recent
economic development initiatives. This is particularly true for the areas near Silver
Comet Field. While commercial flights are currently being discussed at the facility,
the runway capacity in conjunction with its relatively close location (21 miles) to the
Whitaker Intermodal Facility in Austell certainly increase the potential for
employment growth in the vicinity of Silver Comet Field, along the US 278 Corridor,
and industrial parks in Dallas and along Bill Carruth Parkway. Should commercial
flights become a reality at Silver Comet Field, employment projections in Paulding
could be altered significantly.
Agriculture and Single Family Residential are the two most prevalent land uses
within Paulding County with most agricultural uses being in the western portion of
the county and residential in the eastern portion. The abundance of single-family
residential uses is relevant because these uses typically generate SOV trips during
peak hours.
January 2014
4.2
Page 92
The most prominent commercial retail corridor is the US 278/SR 6 corridor from the
Cobb County line to US 61. Commercial uses are also located in Dallas, along the SR
120 corridor, and at intersections throughout the county. Because of the amount of
ingress and egress associated with these uses, access management is usually a
priority at these locations to promote safe and efficient travel.
Both the previous CTP and the Silver Comet Trail Economic Impact Analysis and
Planning Study have recommendations for future bicycle facilities to connect to the
Silver Comet Trail and other activity centers throughout the county.
The Atlanta Regional Freight Mobility Plan identifies US 278/SR 6, a portion of which
is in Paulding County, as a potential freight corridor in need of special attention
regarding signal timing and other measures to support safe truck movement. The
plan recommends among its improvement strategies were truck-friendly lanes on US
278/SR 6 from SR 61 in Paulding County to I-85 South. The study also recommended
the improvement and modernization of signalization equipment and software along
the US 278/SR 6 corridor from SR 61 in Paulding County to I-20.
A comparison of 2015 and 2040 LOS ratings show a significant degradation of the
roadway network, particularly within the eastern half of the county. This is
particularity evident on SR 61 and other roads that provide a north-south connection
to Douglas County, and on SR 120, SR 360 and other roads that provide an east-west
connection with Cobb County. In addition, roads that serve Dallas are projected to
worsen significantly.
To further assess existing congestion levels and travel delay, an analysis of real-time
data, called NAVTEQ, has been conducted. Both the AM and PM peak period results
show similarly congested conditions on many of the same corridors as the model
data. The PM peak period, however, depicts more widespread and continuous
congestion along the same roadways. An example of this is more travel delay
evident in the PM peak near major intersections along Ridge Road.
The existing and projected disparity of directional flow in the AM and PM peak hours
suggests a continued need for emphasis on peak hour treatments to roadways
particularly those to Cobb County, such as US 278/SR 6, SR 120, and SR 92 to
accommodate unbalanced directional flow. For example, this could include
increased signal coordination and/or reversible lanes. Furthermore, the disparity
between internal and external commuter trips suggests a continued need to
promote commuter-oriented transportation demand management programs now
and into the future.
The 2015 commute times even to activity centers in neighboring Cobb County for
Paulding County commuters are relatively long. This is a function of the typical
Paulding commute taking place on surface streets rather than the interstate system.
In 2040 commute times to the major employment centers throughout the region
January 2014
Page 93
Pedestrian crash locations can be found dispersed throughout the county, with one
prominent concentration found along US 278/SR 6 in the Hiram Crossroads
commercial area. This area is in need of further study to help identify pedestrian
needs and potential safety improvements.
GDOT Bridge Inventory data from 2012 indicate three bridges with sufficiency
ratings below 50 and 14 bridges with sufficiency ratings between 50 and 80.
Insufficient bridges are primarily found carrying local or collector roads, with none
found on the state route system. Only two arterial roadways within the county, East
Memorial Drive and Dallas-Acworth Highway, contain low sufficiency rated bridges.
The highest truck volumes and percentages within the county are found along SR 92,
which has been identified as a regional north-south trucking corridor by the ARC.
Truck volumes along SR 92 are anticipated to grow significantly from 2015 to future
years 2030 and 2040, with volumes more than doubling on many segments.
Segments of SR 92 exhibit the highest truck percentages in the county with many in
the 10-14 percent range. Several segments of US 278/SR 6 also exhibit high levels of
truck volumes. This is particularly evident in the eastern portion of the county from
the Cobb County line to SR 61. Truck volumes along these segments have volumes
ranging from 1,200-1,400 trucks in 2015. These volumes are anticipated to grow
significantly to 1,500-2,100 trucks in 2040.
Most traffic signals are along the most heavily traveled roadways in the county, such
as US 278/SR 6, SR 92, and SR 120. Many signals are in close proximity to one
another. This would indicate the need for improved signal coordination and access
management along these corridors. Paulding County is currently undertaking an ITS
Master Plan scheduled for completion in March 2014. The recommendations of this
plan will be incorporated into the Needs Assessment.
The Silver Comet Trail is the major bicycle and pedestrian amenity within the county.
The trail runs approximately 17.6 miles within the county and travels through Hiram,
Dallas, and the Paulding WMA. The trail includes six trail heads, one located within
Hiram and another five located in or near Dallas. These crossings will be examined
closely within the Needs Assessment to determine where improved access and
connectivity are needed to serve surrounding developments. During the Needs
January 2014
Page 94
While ridership of GRTA services has trended down over the past few years, there
are some demographic characteristics within Paulding County that suggests that the
Xpress service can grow in ridership once the economy rebounds. Throughout the
county, there are concentrations of populations that are low-income with
automobiles. As jobs continue to develop in the Atlanta core areas of Midtown and
Downtown, it would be reasonable to assume that the Xpress service can be more a
viable commute option for Paulding citizens.
Both the demographics and existing and projected travel patterns lend themselves
to the feasibility of increased participation in transportation demand management
programs particularly ridesharing and/or vanpooling.
All but three of the 23 proposed projects in the county are programmed for some
phase of implementation within the next five years. Most of these projects are
capacity improvements to existing roadways. The most significant of these
improvements is the series of projects that constitute the widening of SR 92
throughout the entire length of Paulding County between Douglas and Cobb
Counties. The series of projects includes four separate widening projects and a
bridge project over the Southern Railroad in Hiram. Over the past few years there
have project delays associated with environmental concerns and funding shortfalls.
The progression of this project through the development phase will have a profound
influence on the short-term and long-term recommendations of this update.
January 2014
Based on the findings of this report, specific corridors will be identified for an
assessment of access management strategies.
A more detailed funding analysis and implementation history of project funding will
be conducted to gain a heighted perspective of implementation issues within
Paulding County.
Coordination with GDOT on the status of the SR 92 widening project will be sought.
As documented throughout this report, there are several mobility issues along the
roadway that would suggest the need for substantial intersection improvements
that may be included in the design of the widening. Along with representatives from
Cobb and Douglas County, Paulding County staff will be meeting with GDOT on
project status.
With the beginning of the needs assessment phase of the CTP update, the public
outreach program will be initiated. This will include:
Page 95
Interviews with key stakeholders and meetings of the Stakeholder Committee and
Technical Committee and with the general public to provide input on preliminary
needs
Launching of the project web site to provide opportunities for greater input.
January 2014
PauldingComprehensiveTransportationPlan
DraftFinalReport
AppendixCAssessmentofCurrentandFutureNeeds
AppendixC
DRAFT
AssessmentofCurrentandFutureNeedsReport
Preparedby:
December2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
TableofContents
1.0
INTRODUCTION......................................................................................................................1
1.1
PROJECTOVERVIEW.........................................................................................1
1.2
REPORTOVERVIEW...........................................................................................2
2.0
CTPVISIONANDGOALSUPDATE...........................................................................................3
3.0
STAKEHOLDERANDPUBLICINPUT........................................................................................8
3.1
PUBLICOUTREACH............................................................................................8
3.2
PUBLICLYIDENTIFIEDTRANSPORTATIONNEEDS...............................................8
4.0
NEEDSIDENTIFIEDBYTHEPREVIOUSCTP...........................................................................10
5.0
POTENTIALNEWROADWAYCONNECTIONS.......................................................................14
6.0
7.0
8.0
9.0
10.0
5.1
METHODOLOGYANDASSESSMENT................................................................14
5.2
NEWROADWAYNEEDS..................................................................................18
ROADWAYCAPACITY...........................................................................................................20
6.1
METHODOLOGYANDASSESSMENT................................................................20
6.2
ROADWAYCAPACITYNEEDS...........................................................................21
PAVEMENTCONDITIONNEEDS............................................................................................26
7.1
METHODOLOGY..............................................................................................26
7.2
ANALYSIS........................................................................................................26
7.3
PAVEMENTCONDITIONNEEDS.......................................................................27
INTERSECTIONS....................................................................................................................30
8.1
METHODOLOGYANDASSESSMENT................................................................30
8.2
INTERSECTIONSIMPROVEMENTNEEDS..........................................................30
TRANSITANDTRAVELDEMANDMANAGEMENTNEEDS....................................................33
9.1
TRANSITNEEDSIDENTIFICATIONMETHODOLOGY..........................................33
9.2
TRANSITNEEDS...............................................................................................33
9.3
TRAVELDEMANDMANAGEMENTNEEDSIDENTIFICATIONMETHODOLOGYAND
ANALYSIS........................................................................................................35
9.4
TRAVELDEMANDMANAGEMENTNEEDS........................................................35
BICYCLEANDPEDESTRIANNEEDS........................................................................................37
Page i
December2014
11.0
12.0
13.0
10.1
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
METHODOLOGYFORIDENTIFYINGBICYCLEANDPEDESTRIANNEEDS.............37
10.2
SUMMARYOFPEDESTRIANANDBICYCLENEEDS............................................39
FREIGHTNEEDS....................................................................................................................44
11.1
METHODOLOGYANDANALYSIS......................................................................44
11.2
TRUCKANDFREIGHTNEEDS...........................................................................46
SYSTEMNEEDS.....................................................................................................................49
12.1
ACCESSMANAGEMENTMETHODOLOGY........................................................49
12.2
ACCESSMANAGEMENTNEEDS.......................................................................49
12.3
BRIDGENEEDS................................................................................................52
12.4
INTELLIGENTTRANSPORTATIONSYSTEMSANDSIGNALIZATIONNEEDS
METHODOLOGYANDANALYSIS......................................................................56
12.5
SUMMARYOFINTELLIGENTTRANSPORTATIONSYSTEMSANDSIGNALIZATION
NEEDS.............................................................................................................56
FUNDINGOPTIONS...............................................................................................................58
13.1
ARCFEDERALFUNDINGPROGRAMS...............................................................58
13.2
GEORGIADEPARTMENTOFTRANSPORTATION..............................................58
13.3
STATEROADANDTOLLWAYAUTHORITY........................................................59
13.4
LOCALFUNDS.................................................................................................60
Page ii
December2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
ListofFigures
Figure1:CTPDevelopmentProcess.....................................................................................................1
Figure2:OriginsandDestination2015and2040............................................................................16
Figure3:NewRoadwayConnectionNeeds.......................................................................................19
Figure4:RoadwayCapacityNeeds....................................................................................................23
Figure5:UniverseofIntersectionOperationsNeeds.........................................................................32
Figure6:TransitandTravelDemandManagementNeeds.................................................................34
Figure7:PedestrianPlanningAreas..................................................................................................38
Figure8:PedestrianandBicycleNeeds.............................................................................................41
Figure9:FreightNeedsAreas.............................................................................................................48
Figure10:AccessManagementCorridors..........................................................................................51
Figure11:BridgeNeeds....................................................................................................................55
Figure12:SignalizedIntersections....................................................................................................57
ListofTables
Table1:GoalsandRelatedPolicyMatrix..............................................................................................4
Table2:RecommendedGoalsBasedonPolicyChanges.......................................................................6
Table4:USCensusAnnualAverageofJourneytoWorkDestinations(20062010)............................17
Table5:ProposedNewRoadwayConnections...................................................................................18
Table6:ProgrammedCapacityProjects.............................................................................................21
Table7:RoadwaySegmentswithCapacityNeeds..............................................................................24
Table8:RoadRatingDistressScoringGuide.......................................................................................26
Table9:RoadPavementRatingsin2014............................................................................................26
Table10.SelectedRoadswithPavementResurfacingNeeds..............................................................27
Table11:UniverseofIntersectionOperationsNeeds.........................................................................31
Table12:NewTransitorShuttleServiceNeeds..................................................................................33
Table13:NewParkandRideLotNeeds.............................................................................................35
Table14:VanpoolNeeds...................................................................................................................36
Table15:SidewalkSegmentNeeds....................................................................................................39
Table16:PotentialTrailheadsonSilverCometTrail...........................................................................42
Table17:MultiUseTrailNeeds.........................................................................................................43
Table18:BicycleLaneandExtendedShoulderNeeds.........................................................................43
Table19:MajorRoadwayHeavyTruckVolumesandPercentages......................................................45
Table20:AccessManagementCorridors............................................................................................49
Table21:BridgeswithReplacementandMaintenance/RehabilitationNeeds....................................54
Page iii
December2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
1.0 INTRODUCTION
1.1 ProjectOverview
ThePauldingComprehensiveTransportationPlan(CTP)updaterevisestheinitial2008
CTPforunincorporatedPauldingCountyandtheCitiesofBraswell,Dallas,andHiram
throughthe2040horizonyear.TheplanbuildsupontheinitialCTPanddevelopsshort
termandlongtermsolutionsfortransportationimprovementsbasedonthelevelof
need,availablefunding,andstakeholderandcommunityinput.Theworkflowofthe
CTPUpdateispresentedinFigure1.ThisCTPUpdatewillreevaluatethepreviousCTP
recommendationsandtheircurrentstatusofdevelopmentandimplementation.Data
fromthepreviousCTPwasupdatedbasedonrecentinformationandchangesintrends
toreassessneededtransportationimprovements.
Figure1:CTPDevelopmentProcess
ThisCTPUpdateaddressesconnectionsbetweenlanduseandtransportationby
consideringtheabilityofrecommendationstosupportlocalandregionallanduseplans.
ThisCTPUpdatewillbefullycoordinatedwith,andcontinuetoserveasthe
transportationelementof,thePauldingCountyComprehensivePlan.
TheAtlantaRegionalCommission(ARC)developedtheCTPProgramin2005to
encouragecountiesandtheirmunicipalitiestodevelopjointlongrangetransportation
plans.CTPsprovidetheARCinputintotheregionaltransportationplan(RTP).The
Page 1
December2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
adoptedPLAN2040servesasthefinanciallyconstrainedplanoftransportationprojects
forfederal,stateandlocalfundsthroughtheyear2040.Somerecommendationsfrom
thisupdatewillrequirefederalandstatefundingforimplementation,whichissecured
throughtheregionalplanningprocess.
1.2
ReportOverview
ThisreportidentifiestheneedfortransportationprojectsinPauldingCountythrough
theyear2040.Thereportisorganizedasfollows:
Section1:Introduction
Section2:VisionandgoalsidentifiedtoguidetheCTPupdate
Section3:Stakeholderoutreachandpublicengagement
Section4:Needsidentifiedbythe2008CTP
Section5:Newroadways
Section6:Roadwaycapacity
Section7:Pavementconditions
Section8:Intersectionneeds
Section9:Transitandtraveldemandmanagement
Section10:Bicycleandpedestrianfacilities
Section11:Freight
Section12:Systemwideneeds
Section13:Assessmentofpotentialfundingoptionsavailabletoaddressthe
needsidentified;fundsincludeARC,GeorgiaDepartmentofTransportation
(GDOT),StateRoadandTollwayAuthority(SRTA),andlocalfunds
Page 2
December2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
2.0 CTPVISIONANDGOALSUPDATE
ThevisionandassociatedgoalsfortheCTPprovidesaframeworkforidentifyingand
evaluatingtransportationneeds.Thegoalsfromthe2008CTPwereassessedand
revisedbasedonchangesinrelevantpoliciesatthelocal,regional,stateandfederal
levels.Then,thegoalswereincorporatedintoavisionstatement.
The2008CTPgoalsarecomparedtotransportationrelatedgoalsfromthefollowing
relevantpolicydocumentsinTable1:
PLAN2040ThecurrentARCRTP.
MovingAheadforProgressinthe21stCentury(MAP21)Thefederal
transportationbillthatsetspolicyforfederaltransportationfunding.
StatewideTransportationPlan/StatewideStrategicTransportationPlan(SWTP/SSTP)
Astatewidetransportationplanthatcombinesthelongrangetransportationplan
withastrategyfortransportationinvestmentfromabusinessperspective,prepared
bytheGeorgiaDepartmentofTransportation(GDOT).
Thefollowingconclusionsweredrawnfromthiscomparisonofgoalsandpolicy:
Noneofthepolicydocumentsreviewednameslanduseanddevelopment
connectivityasagoal;however,itisimportantthatthisplanrecognizesand
accommodatesfutureplanneddevelopmentsinitsrecommendationsgiventhe
impactfutureresidentialgrowth(anestimatedpopulationincreaseof118.5%from
2010to2040)willhaveonthetransportationnetwork.
Intergovernmentalcoordinationwasincludedamongthe2008CTPgoalsandwill
continuetobeagoalofthisCTPupdate.Understandingtheprioritiesofstateand
regionalagenciesaswellasneighboringjurisdictionscanhelpstreamlineproject
implementation.
The2008CTPdidnothaveaspecificgoalrelatingtosystemreliability.However,
thatplansupportedthegoalofpromotingTravelDemandManagementasa
componentofpromotingsystemreliability.Asavailablefundinghasdecreasedover
thelastfewyears,therehasbeenanincreasingemphasisonlowercost
improvementsasanalternativetocapacityimprovements.Therefore,apolicy
statementspecificallyprioritizingoperationalimprovementswasaddedtoequitably
prioritizelowercostimprovementsgiventhedisparitybetweenavailablefunds(e.g.,
SPLOST)andtheextensivelistoftransportationneedsidentified.
Recentpolicyhasincreasedfocusonstateofgoodrepair,ormaintenance,ofthe
existingtransportationnetwork.AfocusoftheCTPwillbetoexaminetheneedfor
assetmanagementandconsidertheassociatedmaintenancewhendeveloping
recommendedactions.Tothisend,thisneedsassessmentincludesapavement
conditionsanalysistoidentifyroadwayswiththegreatestmaintenanceneeds.
Page 3
December2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Table1:GoalsandRelatedPolicyMatrix
EmphasisArea
2008CTPGoals
Congestion
Reduction
Reducetrafficcongestionandtravel
timeswithinPauldingCounty
MultimodalTravel
Developanenhancedmultimodal
transportationnetworkincluding
bikepaths,sidewalks,andincreased
transitservicesinadditionto
roadways
LandUse/
Transportation
Connectivity
Improvedevelopmentpatterns
withinPauldingCountyby
integratingexistingandfutureland
useplanswithtransportation
improvements
Infrastructure
Condition(State
ofGoodRepair)
Notspecificallyaddressed
Assurethepreservation,
maintenanceandoperationofthe
existingmultimodaltransportation
system
Maintainthehighway
infrastructureassetsystemina
stateofgoodrepair
MajorCorridor
Prioritization
Developanintegrated
transportationnetworkthat
preservesandenhancesmobility
alongexistingandfuturemajor
corridors
Strategicallytargetroadway
capacityimprovementstoserve
regionallysignificantcorridorsand
centers
Achieveasignificantreductionin
congestionontheNational
HighwaySystem
Notspecificallyaddressed
Continuetoimplementcost
effectiveimprovementssuchas
sidewalks,multiusetrails,bicycle
lanes,androadwayoperational
upgradestoexpandtransportation
alternatives,improvesafety,and
maximizeexistingassets
Improvetheefficiencyofthe
surfacetransportationsystem
SystemReliability
Page4
PLAN2040
Assurethepreservation,
maintenanceandoperationofthe
existingmultimodaltransportation
system
Strategicallytargetroadway
capacityimprovementstoserve
regionallysignificantcorridorsand
centers
Continuetoimplementcost
effectiveimprovementssuchas
sidewalks,multiusetrails,bicycle
lanes,androadwayoperational
upgradestoexpandtransportation
alternatives,improvesafety,and
maximizeexistingassets
SWTP/SSTP
Achieveasignificantreductionin
congestionontheNationalHighway
System
Improvethemovementofpeople
andgoodsacrossandwithinthe
State
Supportaccessiblecareandactive
lifestyles
MAP21
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
EmphasisArea
2008CTPGoals
FreightMobility
andEconomic
Vitality
Notspecificallyaddressed
Innovative/
Streamlined
Financing/Project
Delivery
Developinnovativetransportation
fundingmechanismstoincrease
fundingfortransportation
improvements,whilestreamlining
projectimplementation
TravelDemand
Management
Enhancetraveldemand
managementwithinPaulding
Countybyimproving
communicationandenhancing
educationbetweenstateandlocal
agenciesandCountytransportation
systemusers
ImprovethesafetyoftheCounty's
multimodaltransportationnetwork
forallusers
Safety
Improveintergovernmental
Intergovernmental
coordinationamonggovernment
Coordination
agenciestoachieveCountygoals
Page5
PLAN2040
Maintainindustrialandfreightland
usesatstrategiclocationswith
efficientaccessandmobility
Maintainandexpandinfrastructure
tosupportairandrailtraveland
transport
MAP21
Improvethenationalfreight
network,strengthentheabilityof
ruralcommunitiestoaccess
nationalandinternationaltrade
markets,andsupportregional
economicdevelopment
Reduceprojectcosts,promotejobs
andtheeconomy,andexpeditethe
movementofpeopleandgoodsby
acceleratingprojectcompletion
througheliminatingdelaysinthe
projectdevelopmentanddelivery
process,includingreducing
regulatoryburdensandimproving
agencies'workpractices
SWTP
Continuetoimplementcost
effectiveimprovementssuchas
sidewalks,multiusetrails,bicycle
lanes,androadwayoperational
upgradestoexpandtransportation
alternatives,improvesafety,and
maximizeexistingassets
Achieveasignificantreductionin
trafficfatalitiesandseriousinjuries
onallpublicroads
Reduceinjuryandlossoflifeon
Georgiasroads
Leveragepublicprivate
partnershipsandimprove
intergovernmentalcooperationfor
successfulinfrastructure
development
ExpandGeorgiasroleasamajor
logisticshubforglobalcommerce
Createjobsandgrowbusinesses
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Onegoalfromthe2008CTPwasrevisedandfournewgoalswereaddedfortheCTP
Update.Thenewgoalswereintendedtoreflecttheshiftinpolicytoincludeconcerns
abouttheconditionofexistinginfrastructure,systemreliability,freightmobility,and
economicdevelopment.TheresultingrecommendedgoalsarepresentedinTable2.
Table2:RecommendedGoalsBasedonPolicyChanges
CurrentPolicySupport
PLAN MAP
SWTP
2040
21
EmphasisArea
2008CTPGoals
Congestion
Reduction
Toreducetrafficcongestionandtraveltimes
withinPauldingCounty
Todevelopanenhancedmultimodal
transportationnetworkincludingbikepaths,
sidewalks,andincreasedtransitservicesin
additiontoroadways
Toimprovedevelopmentpatternswithin
PauldingCountybyintegratingexistingand
futurelanduseplanswithtransportation
improvements
Multimodal
Travel
LandUse/
Transportation
Connectivity
RecommendedChange:
ResultingGoal
Leavegoalasis
Leavegoalasis
Amendgoaltoread:Tosupport
andenhanceexistingandfuture
landuseplanswith
transportationimprovements
Addgoal:Topreserveand
maintainthetransportation
infrastructuretothemaximum
extentpossible
Infrastructure
Condition
(StateofGood
Repair)
Notspecificallyaddressed
MajorCorridor
Prioritization
Todevelopanintegratedtransportation
networkthatpreservesandenhances
mobilityalongexistingandfuturemajor
corridors
System
Reliability
Notspecificallyaddressed
Freight
Mobility
Notspecificallyaddressed
Innovative/
Streamlined
Financing/Proj
ectDelivery
Todevelopinnovativetransportation
fundingmechanismstoincreasefundingfor
transportationimprovements,while
streamliningprojectimplementation
Leavegoalasis
Economic
Development
Notspecificallyaddressed
Toenhancetraveldemandmanagement
withintheCountybyimproving
TravelDemand
communicationandenhancingeducation
Management
betweenstateandlocalagenciesand
Countytransportationsystemusers
ToimprovethesafetyoftheCounty'smulti
Safety
modaltransportationnetworkforallusers
Intergovern
Toimproveintergovernmentalcoordination
mental
betweengovernmentagenciestoachieve
Coordination
Countygoals
Page6
Leavegoalasis:
Addgoal:Tofocusoncost
effectiveimprovementsto
improvesystemreliability
Addgoal:Tomaintainorenhance
thetransportationnetworkfor
goodsmovementinorderto
facilitateoverallsystem
functionalityandpromote
economicdevelopment
Addgoal:Toprioritize
transportationimprovementsin
employmentcentersandalong
majorcorridorsthroughoutthe
County
Leavegoalasis
Leavegoalasis
Leavegoalasis
December2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
BasedonthegoalsasrevisedfortheCTPUpdate,andsupportedbycurrent
transportationpolicy,thevisionforthePauldingCTPUpdateisasfollows:
To engage in a collaborative, transparent process with the purpose of enhancing multimodal
mobility throughout the County in a manner that promotes safety, economic vitality and costeffectiveness.
Page7
December2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
3.0 STAKEHOLDERANDPUBLICINPUT
3.1PublicOutreach
Anunderstandingofthepublicsmostpressingtransportationneedsisessentialtothe
assessmentofPauldingCountystransportationnetwork.Thestudygatheredinput
fromtheTechnicalCommittee,StakeholderCommittee,andthegeneralpublicto
informtheprocessanddetermineneeds.
TheTechnicalCommitteeisanadvisorygrouptotheCTPresponsibleforcontributingto
theplanfromatechnicalandprofessionalperspective.Thecommitteeiscomprisedof
representativesfromstateandregionalagenciesandneighboringjurisdictions.The
StakeholderCommitteeisresponsibleforidentifyingneedsfromtheperspectiveofa
localtransportationuser,andiscomprisedofcommunityandbusinessleadersinthe
county.Thesecommitteesmeetregularlyoverthecourseoftheupdate.Ajoint
technicalandstakeholdercommitteemeetingwasheldonApril3,2014;Committee
memberswereaskedtoidentifytransportationneedsinthecountyusingmapsthat
depictedthecountysroadways,transitfacilities,andpedestrianandbicyclefacilities.
Throughouttheneedsassessmentprocess,inputwasgatheredfromthepublicviaa
publicmeeting,survey,andevents.AtthepublicmeetingheldonMay8,2014,atthe
EventsPlaceinHiram,attendeeswereinvitedtoreviewthetransportationneedsthat
hadbeenpreviouslyidentifiedbythestakeholderandtechnicalcommittees,and
attendeeswereaskedtoconfirmtheseneedsidentifyadditionalneeds.Acommunity
survey,whichwasmadeavailableontheprojectwebsiteanddistributedthroughout
thecounty,gaugedopinionontrafficcongestionandpublictransportationinPaulding
County.AtthepublicmeetingheldonAugust14,2014attheDallasCivicCenter,
attendeeswereaskedtocompleteasurveyontheprioritizationofidentifiedneedsto
helpdeterminerecommendedprojectsforinclusioninthefinalplan.Finally,members
ofthestudyteamattendedaseriesofpublicevents,includingtheWellStarPreGrand
Opening,theChattahoocheeTechnicalCollegeStudentEvent,TouchaTruckEvent,and
thePauldingRelayforLifeEvent.Inputmapsweredisplayedattheseeventstocapture
thepublicstransportationneeds.
3.2PubliclyIdentifiedTransportationNeeds
Thefollowingneedswereidentifiedduringthepublicoutreacheffort:
Page8
Roadwaysafetyisaconcern,especiallyinareaswherethereisregularqueuing
oralotofturningtraffic.
AdditionalcapacityisneededonSR92,whichcarriesagreatdealoftrafficinthe
easternportionofthecounty
SupportforahighwaybypasstothenorthandwestoftheCityofDallas.
SupportfornewconnectionstotheSilverCometTrailandnewsidewalksnear
residentialandcommercialareasaroundthecounty.
December2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
InterestinextendingGRTAXpressBusServicefurtherintothecountywitha
newparkandridelotandinconstructingbetteraccesstoI20.
These,andmanymoreresponses,wereincludedintheevaluationandanalysisofneeds
acrossPauldingCounty.Theuseofpublicinputisdescribedinthemethodologiesfor
thevariouscategoriesinthefollowingsections.Thedetailedresultsofpublicoutreach
efforts,includingfullsurveyresults,arepresentedingreaterdetailinAppendixA.
Page9
December2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
4.0 NEEDSIDENTIFIEDBYTHEPREVIOUSCTP
The2008CTPidentifiedareaspecificneedsacrossseveralcategoriesoftransportation.
Theneedswereidentifiedbythepublicandthatstudysstakeholders.InthisUpdate
report,needsthatwereaddressedwithproposedprojectsinthe2008CTPare
referencedineachcategory.
Areaandfacilityspecificroadwayneedsidentifiedbythe2008CTPinclude:
Page10
SR61
o AlternativeoptionstoSR61northfromDallas
o AlternativeoptionfromSR61NorthtoSR6withoutgoingthroughDallas
o FourlaneSR61fromSR6/US278toHiramSudieRoad
o SR61nearDallasandbottlenecks
o UpcominggrowthalongSR61Northneedstobeaddressed
o RelocationofmainlineSR61
o ImprovesafetyandcongestionalongSR61
o RelievecongestiononSR61
o SR61adjacenttoHarmonyGroveChurchRoadandthreeschoolssafety
concernsduetohighfrequencyofaccidents
SR61&SR92
o SR92andSR61needtobefourlanedthroughouttheCounty
SR92
o SR92
o SR92difficulttoenterorexitatintersectionsRosedaleandC.W.Simsat
SR92,ChurchStandMainStintersectionsinDowntownHiram
SR6&SR92
o SR6&SR92SR6/US278andSR92areprimarycorridorsthatneedtobe
addressed
SR6/US278
o ToomanylightsalongSR6fromintersectionofSR92
o RushhourtrafficalongSR6/US278inHiram
o FrontageroadalongSR6/US278
o TrafficcongestionalongSR6/US278throughHirambacksupintoCobb
CountyatFlorenceRoad
SR6
o SR6/US278throughHiramandintoCobbCounty
o Connect6(SR6)Project
o TrafficcalmingalongSR6/US278(grassmedian,trees)toimprovetraffic
o MorealternativestoSR6/US278(betterstreetnetwork)
December2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
o SR6Businesstruckuse
East/WestHiramParkway(nowBillCarruthParkway)
o WestHiramPkwyasalternatetoSR6/US278andSR92
o CompleteEastHiramParkway
o EastHiramParkwayispotentialrelieverandneedstobefinished
o TravelingfromSR92toSR6/US278
ProposedDallasBypass
o CityofDallasbypasscriticalneed
o NeedbypassforSR61
o PossiblelooparoundDallas
o SouthernbypassaroundDallas(similartoEastHiramParkway'sfunction
forHiram)
MaclandRoad
o MajorimprovementsneededalongMaclandRoadtomitigatepeakhour
congestion
o MaclandRoadhassafetyissues
o RosedaleDriveandMaclandRoad,whichcarrytrafficoverflowfrom
congestedstreets
Page11
PoplarSpringsRoad
o PoplarSprings(butdependsonstatusofSR360)
CedarcrestRoad
o CedarcrestRoadneedstobefourlaned
NeboRoad
o NeboRoadtrafficneedstobeslowed,andcongestionimprovedcarries
highervolumesthanmanycitystreets
Hiram
o FrontageroadinHiram
o PoorsignageanddirectionsinHiram
o Hiramshouldhandleitsowndevelopmentapproval(currentlyPaulding
County)
o AccessmanagementinHiram,forexample,alongSR92andSR6/US278
DowntownDallas
o DowntownDallas
o LCIProjectCompletion
o RightturnlanefromBusiness6toSR6inDowntownDallas
o ParkinginDowntownDallas
December2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
o Cityinterestedinparkingdecks,lookingtofederalgovernmentfor
additionalfunding
o PeakperiodbackupatPostOffice
o InstallnewredlightatCourthouse,becauseexistingonedoesnotwork
AccesstoInterstateHighways
o DallasAcworthHighway(OldSR381)andaccesstoI75
o ProvideaccesstoI20(i.e.,BakersBridgeRd)
o BetteraccessfromSR92toI75andI20
o Needmorelimitedaccessroads
o DirectconnectiontointerstatewouldlikeproposedMemphistoAtlanta
interstatetorunthroughPaulding
Intersections
o OldHarrisRoadatWinndaleDrive(newbridge)
o ImproveintersectionofWinndaleDriveandSR61
o NorthandSouthIndustrialDrivesatDallasAcworthHighway(leftturnlane
needed)
o IntersectionofSR61NorthandDabbsBridgeRdPM
o IntersectionofSR360/PoplarSpringsRdandEastHiramParkway
o CoordinatewithcitiesandcountiesadjacenttoPauldingforintersection
improvements
Other
o CutthroughroadssuchasLakeRoad
o C.W.Simsisbecomingatruckroute
o StraightencurvyroadssuchasHarmonyGroveChurchRd
o Needbetteraccesstofreeways(SR92,SR6/US278,SR61)
Thenonroadwayneedsidentifiedbythe2008CTPinclude:
Page12
Transit
o ParkandRidelotsandExpressCoachesattheAirportandinHiram
o BusRapidTransit,HOVlanes,andtrucklanesalongSR6/US278
o Ondemandintracountytransitforseniors,ChattahoocheeTechstudents,
andothers
o TrolleyBusfor"DowntownHistoricCirculator"tothenewcollege,senior
center,newcourthouse
o PotentialGRTAroutefromcentralPaulding(Dallas)toLockheedPlantand
back
o RubbertiretransitonSilverCometTrail
o NeedtoexpandParkandRideLotatfirestation(spacewasreducedbya
newKroger)
o ChattahoocheeTechpropertyisoptionforatransitlot
December2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
o ExpressbusdowntownthroughLCIStudy
o GRTAroutehashighridershipinPaulding,butnewcomersdonotwant
transit
Page13
Sidewalks
o BettersidewalksinDowntownDallasandHiram
o IncreasesidewalksinCityareas
o MoresidewalksneededinHiramandthroughoutCounty
Trails
o BetteraccessfromactivitycenterstoSilverCometTrail
o BikeandtrailconnectionstotheSilverCometTrail
o MoretrailheadsalongSilverCometTrail
o MoreconnectivitybetweenBenHillStricklandParkandSilverCometTrail
o BetterpedestrianconnectionsacrossSR92forBenHillStricklandPark
o Recreationneeds
o MoreconnectionsfromdevelopmentstoSilverCometTrail
o SidewalkconnectionsandpedestrianbridgesinHiram
o PotentialpedestrianbridgesalongSR6/US278andSR92
o SilverCometTrailbridge
AccessManagement
o AccessmanagementinHiram,alongSR92andSR6/US278
o NonAreaSpecific
o Betteraccessmanagementandstoplights
o Limitedaccesswithconnectivity
o Possiblenewlimitedaccessroads
o Needmorelimitedaccessroads
o Restrictedhighways
o IncreasedandimprovedaccesstoInterstates
o LimitedaccesscorridorstoconnectentireCounty
o Serviceroadswithnewcommercialdevelopmentthatexhibitaccess
managementpractices
o Needwaystoreducecongestionwithinshoppingcenters;vehiclepaths
areusedasshortcuts
o Blockorgridnetwork
Funding
o TrafficimpactfeesforCountyroads
o ARCGrantsfortransportationfunding
o LooktoConnect6StudyaspotentialfundingjustificationthroughtheARC.
o CoordinatewithcitiesandcountiesadjacenttoPauldingforintersection
improvements
December2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
5.0 POTENTIALNEWROADWAYCONNECTIONS
Constructionofnewroadwayscouldmeetthedemandfortravelbetweenlocationsnot
efficientlylinkedbytheexistingroadwaynetwork.AtthisphaseoftheCTPUpdate,
proposedroadwaysrepresenttheperceivedneedfornewconnections.Inthenext
phaseofthisstudy,thedemandfortheseroadways,alongwiththecostandfeasibility
oftheirconstruction,willbeassessedpriortoanyprojectsinclusionasa
recommendation.
5.1MethodologyandAssessment
Theneedsanalysisconsideredthedemandfornewroadwayconnectionsintermsof
existingandprojectedfuturetravelpatternsthroughoutPauldingCounty.Thestudy
firstconsideredtravelpatternsillustratedbytheoriginsanddestinationsidentifiedin
theARCTravelDemandModel.Itthenconsideredthedataregardingresidentsjourney
towork(20062010),availablefromtheUSCensusAmericanCommunitySurvey(ACS).
5.1.1
TravelPatterns
ThetravelpatternsfromtheARCTravelDemandModelwerederivedfrommorethan
10,000householdtravelsurveysconductedbytheARC.Understandingthedynamicof
traveltoandfromthecountyandthemagnitudeatwhichintercountytraveloccursis
importantwhenprioritizingtransportationneeds.Forthisanalysis,therearethree
categoriesoftripstakenintoaccount:
HomeBasedWork(HBW)Commutertripsfromapersonshometotheirplaceof
employment
HomeBasedOther(HBO)Allothertripsgeneratedfromapersonshome
NonHomeBased(NHB)Allothertrips
BasedonoutputfromtheARCTravelDemandModel,29percentofHBWtrips
originatinginPauldingCountyin2015areprojectedtobetojobswithinthecounty,and
another31percentofHBWtripsareprojectedtobetoCobbCounty(Table3).Thisis
theresultoflimitedemploymentopportunitieswithintheCountycomparedwith
greateropportunitiesinthenearestCountytotheeast.Overtime,asthenumberof
jobsinPauldingincreases,thenumberofHBWtripsthatstaywithinthecountyis
projectedtoincreasetothepointPauldingisthelargestCountyofemployment,atas
well,to40percentby2040.Thisisapositivetrendresultingfromcontinued
implementationofpoliciessupportinggoalsandemphasisareas.Nevertheless,more
thanonequarterof2040HBWtripsareprojectedtobeboundforCobbCounty.
AsshowninFigure2,thebulkoftripsforbothHBWandHBOthatleavethecountyare
destinedforCobbCounty.Furthermore,tripsdestinedforFulton,Cherokee,DeKalb,
andothereasternportionsoftheregionmusttravelthroughCobbtoreachthose
destinations.Thesepatternsindicatethatthemostdemandfornewinvestmentin
Page14
December2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
vehiculartransportation,includingnewroadwayconnectionsandadditionalcapacity,will
existprimarilyintheeasternportionofPauldingCountyorprojectsthatsupporteast/west
movement.Populationandemploymentdensitieswillsupportthatneedandoccur
primarilywithintheeasternportionofthecounty.
Table 3: Travel Demand between Paulding County and Other ARC Counties 2015, 2030, 2040
HomeBasedWork
Total
Percent
Trips
37,056
29%
39,314
31%
10,013
8%
16,698
13%
7,283
6%
6,477
5%
3,059
2%
2,798
2%
HomeBasedOther
Total
Percent
Trips
308,294
71%
75,177
17%
21,762
5%
7,146
2%
8,955
2%
8,264
2%
3,127
1%
1,293
0%
NonHomeBased
Total
Percent
Trips
130,168
68%
39,532
21%
10,178
5%
3,473
2%
3,767
2%
2,860
1%
1,749
1%
630
0%
Total
Total
Percent
Trips
475,519
63%
154,023
20%
41,952
6%
27,317
4%
20,006
3%
17,600
2%
7,935
1%
4,721
1%
HomeBasedWork
Total
Percent
Trips
69,270
36%
57,805
30%
16,867
9%
HomeBasedOther
Total
Percent
Trips
471,200
73%
102,832
16%
30,852
5%
NonHomeBased
Total
Percent
Trips
190,719
69%
51,845
19%
14,405
5%
Total
Total
Percent
Trips
731,190
65%
212,482
19%
62,124
6%
Fulton
Bartow
Carroll
Cherokee
DeKalb
19,205
11,289
12,105
11,975
4,907
2,053
HomeBasedWork
Total
Percent
Trips
97,188
40%
62,971
26%
19,588
8%
21,218
9%
14,222
6%
8,656
4%
4,374
2%
6,155
3%
2015
Paulding*
Cobb
Douglas
Fulton
Bartow
Carroll
Cherokee
DeKalb
2030
Paulding*
Cobb
Douglas
2040
Paulding*
Cobb
Douglas
Fulton
Bartow
Carroll
Cherokee
DeKalb
11,007
8,500
4,041
3,202
10%
6%
4%
2%
2%
2%
2%
2%
1%
0%
HomeBasedOther
Total
Percent
Trips
574,316
74%
116,613
15%
34,536
4%
13,811
2%
12,500
2%
15,072
2%
5,851
1%
2,474
0%
4,472
5,254
4,313
2,527
772
2%
2%
2%
1%
0%
34,966
28,366
24,788
11,474
6,027
NonHomeBased
Total
Percent
Trips
234,077
71%
59,482
18%
16,657
5%
5,033
2%
6,405
2%
5,309
2%
3,038
1%
857
0%
3%
3%
2%
1%
1%
Total
Total
Percent
Trips
905,581
67%
239,066
18%
70,781
5%
40,062
3%
33,127
2%
29,038
2%
13,264
1%
9,486
1%
*Internaltrips
Source:ARCTravelDemandModel(2040)
Note:Totalsmaynotequal100%duetorounding.
Page15
December2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Figure2:OriginsandDestination2015and2040
2015
Page16
2040
December2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
5.1.2
JourneytoWork
InadditiontoARCTravelDemandModeldata,journeytoworkdatafromthepreviously
mentionedUSCensusAmericanCommunitySurveyfor2006to2010wereanalyzedto
furtherassesstravelpatternswithinthecounty(Table4).Thisdatarepresentsthe
annualaverageofHBWtripstodestinationcountiesoverthefiveyearperiod.
Table4:USCensusAnnualAverageofJourneytoWorkDestinations(20062010)
Destination
County
Paulding*
Cobb
Douglas
Fulton
Bartow
Carroll
Cherokee
DeKalb
Gwinnett
Other
Total
Annual
Average HWB
Trips
16,392
23,055
4,609
10,045
1,201
1,090
806
1,638
1,132
3,095
63,064
Percent
26%
37%
7%
16%
2%
2%
1%
3%
2%
5%
100%
*Internaltrips
Source:AmericanCommunitySurvey20062010
TheUSCensusdatalargelyagreeswiththedatapulledfromtheARCTravelDemand
Model,withsomevariations.Cobb,Paulding,Fulton,andDouglasCountiesarefoundto
bethetopfourdestinationcountieswithinbothdatasetsinthesameorderandgeneral
magnitude.However,theACSestimatesthatmoretripsaredestinedforCobbCounty
thanPauldingCounty(37%vs.26%),whiletheARCTravelDemandModelreportsa
similarshareoftotaltripstoeachcounty(31%to29%).Themoststrikingdifference
betweenthedatasetsisthattheARCTravelDemandModelprojectsclosetotwiceas
many2015HBWtripsthatprojectedbythe20062010ACS.Thediscrepancyislikely
attributedtoprojectedresidentialgrowthin2015andtheeffectsofreducedlabor
participationresultingfromtheeconomicrecessionduringthe20062010surveyyears.
ThegrowingpercentageofcommutestakingplacewithinPauldingCountywillincrease
theneedforadditionalcapacityonalreadyheavilytravelledroads.Asexisting
roadwaysbecomecongested,driversmaybewellservedbyadditionalroadwayoptions
thatcanmeettheirconnectivityneeds.TheroadsthatconnecttheCityofDallas,SR
Business6andJimmyCampbellParkway,experienceconflictsbetweenthrough
movementandlocaltrips.Newroadwayalternativescouldhelptoseparatethrough
trafficfromlocaltrafficandaddressthislatentmobilityneed.
Page17
December2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
5.2NewRoadwayNeeds
Basedontheanticipatedtraveldemandandlackofefficientdirectconnections
betweenoriginsanddestinations,atotalofeightnewroadwayconnectionswere
identifiedasneeds.ThenewroadwayneedsarelistedinTable5andmappedinFigure
3.
Table5:ProposedNewRoadwayConnections
Connection Name
W.DallasBypass
E.DallasBypass
HiramParallelRelieverSouth
ofJimmyCampbell
HiramParallelRelieverNorth
ofJimmyCampbell
SevenHillsSR61Connector
Mt.MoriahConnector
OldCartersvilleConnector
ScogginsRoadExtension
Source:Jacobs,2008CTP
SR6/US278
SR61
2008
CTP
X
Stakeholder
Committee
Public
Input
X
SR92
MetromontRoad
SR92
LakeRoad
SevenHillsBlvd
SevenHillsBlvd
OldCartersvilleRoad
US278
SR61
Mt.MoriahRd
SR61
SR61orSR120
X
X
X
X
X
From
To
SR61
SR6/US278
Fouroftheproposednewroadwayconnectionswereincludedinthe2008CTP,theMt.
MoriahConnector,OldCartersvilleConnector,SevenHillsSR61Connector,andWest
DallasBypass.TheWestDallasBypasswasproposedinthe2008CTPtomeetamajor
connectivityneedthatwasidentified.The2008CTPcalledforafeasibilitystudyto
assesstheviabilityofabypassanddetermineifitprovidesanimprovementtotraffic
conditionsinthearea.AmoredetailedanalysisofthebypassisintheWestDallas
BypassTechnicalMemorandum.
Fourmoreconnectionswereidentifiedbythestakeholdercommitteeandpublicinput.
ThreeoftheconnectionswereidentifiedfromtheStakeholderCommittee:EastDallas
Bypass,aneastwestrelieverroadnorthofUS278/SR6(JimmyLeeSmithParkway),and
aneastwestrelieverroadsouthofUS278/SR6(JimmyLeeSmithParkway).Public
inputidentifiedafinalneedfortheScogginsRoadExtension.
Page18
December2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Figure3:NewRoadwayConnectionNeeds
Page19
December2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
6.0 ROADWAYCAPACITY
6.1MethodologyandAssessment
Roadwaysegmentsinneedofadditionalcapacitywereidentifiedthroughtheanalysisof
currentandprojectedlevelofservice(LOS)andthroughdiscussionswiththe
StakeholderCommitteeandthepublic.LOSisawidelyusedmeasureofroadway
congestion,assigninganumericassessmenttotrafficflowconditions.LOSratingsfor
roadwaysegmentsarebaseduponvolumetocapacity(V/C)ratios.Thisratiocompares
thetrafficvolumesonaroadwaywiththecarryingcapacityofthatsegmentofroad.To
assessexistingandprojectedcongestionlevelsoncountyroadways,LOSratingswere
developedfor2015,2030,and2040usingtheARCTravelDemandModel(TDM).If
2015LOSratingswerefoundtobeanEorFrating,orifsignificantdegradationwas
projectedtooccurfrom2015to2030or2040,theneedforadditionalroadwaycapacity
wasidentified.Theanalysiscomparedwhethersegmentswerealsoidentifiedbythe
2008CTP,thestakeholdercommittee,and/orthepublictogaugeoverallpriorities.
6.1.1
ImpactofProgrammedProjects
Theneedforadditionalcapacityonsomeroadwayswillbemetbyseveralwidening
projectsalreadyprogrammedwithcommittedfundingintheTransportation
ImprovementProgram(TIP).TheseprojectsarelistedinTable6.Theseprojectshave
beenincludedinthebaseTDMfortheappropriateyears,asexistingorcommitted
projects,duetotheirhighlikelihoodofconstruction.Longerrangeprojectsthatare
plannedbutnotprogrammedhavenotbeenincludedinthebaseTDMbecausetheydo
nothavesecuredfundingandasaresultfutureconstructionismoreuncertain.These
longerrangeprojectswillbeanalyzedinfuturemodelingscenarioshoweverto
determinetheimpactstheseprojectswillhaveonthetransportationnetworkandif
thereisafutureneedfortheseprojects.
Page20
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Table6:ProgrammedCapacityProjects
Corridor/Route
StateRoute92
StateRoute92
StateRoute360
StateRoute61
StateRoute92
StateRoute92
CedarcrestRoad
Termini
DouglasvilletoNebo
Road
CedarcrestRoadtoCobb
CountyLine
SR120(CharlesHardy
Parkway)toSR176(New
MaclandRoad)
DallasNeboRoadtoUS
278
NeboRoadtoSR120
(includesthebridge
wideninginHiram
GDOTPI#632921/ARC
PA027)
Approx.EastPaulding
MiddleSchooltoOld
BurntHickoryRoad
HarmonyGroveChurch
RoadtoCobbCounty
Line
ROW
Year
CST
Year
Network
GDOTPI#/ARCTIP#
Year
GDOTPI#0007691/ARCTIP#PA092A
2020
(GDOTLetScheduledforJanuary2017)
GDOTPI#0006857/ARCTIP#PA092E
2024
(GDOTLetScheduledforJune2016)
GDOTPI#0006049/ARCTIP#CO367
2020
(CobbCountyJurisdictionProject)
(GDOTLetScheduledforJuly2015)
GDOTPI#621570/ARCTIP#PA061C1
2030
(GDOTanticipateLetin2020.)
Auth
2017
2017
LR
Auth
2018
2018
LR
2018
LR
2030
GDOTPI#621720/ARCTIP#PA092B1
(GDOTLetScheduledforOctober2017)
2018
LR
2030
GDOTPI#0007692/ARCTIP#PA092C
(GDOTLetScheduledforSeptember
2019)
LR
LR
2030
NotinGDOTsWorkProgram/ARCTIP#
PA036B
DabbsBridge
Road
SR61toUS41
LR
LR
2040
CedarcrestRoad
SR92toSevenHillsBlvd
LR
LR
2040
GDOTPI#0001175/ARCTIP#PA032
(GDOTLetScheduledforFebruary2018)
NotinGDOTsWorkProgram/ARCTIP#
PA036C
LR=Actionwouldtakeplacebeyond2020;Auth=rightofwayacquisitionisunderway/completed
Source:GDOTGeotraqs,ARCTIP
6.2RoadwayCapacityNeeds
AnalysisofthesegmentsthatcurrentlyorareprojectedtoexperiencepoorLOSthrough
2040revealsasignificantneedforincreasedroadwaycapacitythroughmuchofthe
county.ConsistentwithanticipatedgrowthdescribedintheExistingConditionsReport,
themajorityofsegmentsarefoundinthemoredevelopedeasternportionofthe
county.Committeeandpublicinputconfirmedthecapacityneedsonthesesegments.
Table7detailsthelistofroadwaysegmentswithcapacityneedsidentifiedthroughthis
process,aswellasthroughinputfromtheadvisorycommitteeandthepublic,and
includesexistingandprojectedLOSandtrafficvolumes.Figure4displaysthese
segmentsonamap.
Basedontheroadwaysegmentanalysis,andexemptingroadwaysalreadyprogrammed
forwidening,thereareeighteensegmentsinneedofadditionalcapacityinthecounty.
Oftheseeighteen,eightwereidentifiedasneedingimprovementsbythe2008CTP,the
stakeholdercommittee,and/orthepublicandarecurrentlyoperatingatLOSEorF.
Theseeightroadwaysegmentsareprojectedtooperateatthislevelin2030.These
include:
Page21
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
DallasAcworthHighwayfromSR92toEastPauldingDrive(MapID#5)
DallasAcworthHighway/MemorialDrivefromEastPauldingDrivetoSR
Business6(#6)
US278/SR6fromSRBusiness6toCobbCountyLine(#10)
SR101/113fromCarrollCountyLinetoSR120(BuchananHighway)(#11)
SR61(VillaRicaHighway)fromtheDouglasCountyLinetoRidgeRoad(#13)
SR61(CartersvilleHighway)fromSRBusiness6toOldCartersvilleRoad(#15)
HiramSudieRoadfromSR61toSR92(#23)
EastPauldingDrivefromSR92toSR120(#26)
Additionalreviewduringtheprojectrecommendationsphasewilldeterminethepriority
rankingofcapacityprojects.
Page22
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Figure4:RoadwayCapacityNeeds
Page23
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Table7:RoadwaySegmentswithCapacityNeeds
Map
Key
Roadway
From
1*
SR92
CobbCounty
Line
2*
SR92
SR120
3*
SR92
US278/SR6
4*
SR92
HiramSudie
Rd
5
6
7
8
DallasAcworth
Highway
DallasAcworth
Highway/Memori
alDrive
SRBus
6/BuchananSt
SR6/Merchants
Dr./AtlantaHwy.
SR92
E.Paulding
Drive
US278(Wof
Dallas)
Memorial
Drive
9
10
US278/SR6
US278/SR6
SR61
SRBus6
11
SR101/113
Carroll
CountyLine
12*
13
14*
15
SR360(Macland
Road)
SR61(VillaRica
Highway)
SR61(VillaRica
Highway)
SR61
(Cartersville
Highway)
Page24
CobbCounty
Line
Douglas
CountyLine
DallasNebo
Road
SRBus6
To
Cedarcrest
Road/DA
Hwy
US278/SR
Bus6
HiramSudie
Road
Douglas
CountyLine
E.Paulding
Drive
Improvement
Stakeholder
Comm.
Public
Input
Widento4lanes
0.96/E
0.97/E
1.05/F
Widento4lanes
0.93/E
0.92/E
0.96/E
Widento4lanes
0.98/E
0.99/E
1.10/F
Widento6lanes
1.18/F
0.90/E
1.03/F
Widento4lanes
0.94/E
1.10/F
1.22/F
SRBus6
Widento4lanes
1.11/F
1.24/F
1.31/F
MemorialDr
Widento4lanes
0.97/E
1.17/F
1.34/F
US278(Eof
Dallas)
Widento4lanes
0.97/E
1.46/F
1.72/F
Widento6lanes
Widento6lanes
0.83/D
0.89/E
1.12/F
0.99/E
1.25/F
1.05/F
Widento4lanes
0.92/E
1.14/F
1.28/F
SR92
Widento4lanes
0.94/E
1.02/F
1.11/F
RidgeRoad
Widento4lanes
0.89/E
1.08/F
1.16/F
Widento4lanes
0.93/E
0.88/E
1.03/F
Widento4lanes
0.92/E
1.08/F
1.15/F
SRBus6
CobbCounty
SR120
(Buchanan
Hwy)
US278/SR
Bus6
Old
Cartersville
Road
2008
CTP
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Map
Key
16
17
18**
Roadway
SR61
(Cartersville
Highway)
SR61
(Cartersville
Highway)
DabbsBridge
Road
19
RidgeRoad
20
NeboRoad
21
22
23
BakersBridge
Road
Sweetwater
ChurchRoad
HiramSudie
Road
2008
CTP
Stakeholder
Comm.
Public
Input
20,700 26,400
1.04/F
1.04/F
1.08/F
3,000
11,300 20,300
0.76/D
1.19/F
1.30/F
9,600
17,500 19,700
Widento4lanes
0.96/E
1.17/F
1.31/F
Douglas
CountyLine
Widento4lanes
0.95/E
1.11/F
1.28/F
Douglas
CountyLine
SR92
Widento4lanes
0.81/D
1.23/F
1.36/F
SR61
SR92
Widento4lanes
1.00/F
1.25/F
1.40/F
From
To
Improvement
Mt.Moriah
Road
DabbsBridge
Road
Widento4lanes
0.83/D
0.99/E
1.09/F
5,000
DabbsBridge
Road
Bartow
CountyLine
Widento4lanes
0.75/D
0.96/E
SR61
Bartow
CountyLine
Widento4lanes
0.77/D
SR92
Widento4lanes
SR92
RidgeRoad
DallasNebo
Road
DallasNebo
Road
24**
CedarcrestRoad
Harmony
GroveChurch
Road
US41
Widento4lanes
0.67/C
0.68/C
0.75/D
9,400
25**
CedarcrestRoad
SR92
OakGlen
Drive
Widento4lanes
0.37/B
0.53/C
0.42/B
14,500 9,400
13,200
SR120
Widento4lanes
0.90/E
1.04/F
1.17/F
SR120
Widento4lanes
0.97/E
1.09/F
1.27/F
7,500
26
EastPaulding
Drive
27
BoboRoad
Westof
Brooks
RackleyRd
Dallas
Acworth
Highway
14,900 16,300
18,100 21,200
Page25
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
7.0 PAVEMENTCONDITIONNEEDS
7.1Methodology
Apavementevaluationandratingstudywasconductedtoevaluatepavement
conditionsofroadsinPauldingCounty.BasedonrecommendationsfromthePaulding
CountyDepartmentofTransportation,approximately560milesofthecurrent990
CountyOwnedroadmiles(1500of3040individualroads)wereevaluatedtodetermine
thecurrentconditionwithintheexistingCountystreetsystemandassistindetermining
pavementmaintenanceneeds.
Theconditionofthepavementforeachoftheroadswasratednumericallyusingvisual
surfaceobservation.Allroadswereratedbyonepersontoreducesubjectivity.Ten
distresstypeswereusedtoratethepavementcondition(Table8).Roadcondition
scoresrepresentthesumofalldistresseswhere60istheworstpossiblerating,thebest
ratingis0,and60representstheworstconditionsineverycategory.
Table8:RoadRatingDistressScoringGuide
VeryGood
Good
Fair
TransverseCracking
0
2
4
LongitudinalCracking
0
2
4
AlligatorCracking
0
3
6
Patching/Potholes
0
2
4
Rutting
0
1
2
EdgeRaveling
0
1
2
Roughness
0
1
2
Oxidation
0
1
2
Bleeding
0
1
2
MissingStone
0
1
2
Source:August2014PauldingCountyPavementEvaluationandRatingStudy
Poor
6
6
9
6
3
3
3
3
3
3
VeryPoor
8
8
12
8
4
4
4
4
4
4
Theroadwayconditionratingassumedthatallroadshavetomeetthestandardsofa
newlypavedroad.Thereforedirt,gravel,andsurfacetreatedroadswereratedpoor.
Roadswithinsubdivisionswhichonlyhadbinderplaced(andnotopping)werealso
ratedpoor.
7.2Analysis
Ratingsweresummedforeachroadbasedonthedatacollected.Roadsrankedbetween
ascoreof0to9(verygoodcondition)and55to60(notoppingcondition).SeeTable9
forasummaryoftheconditionsandneedsassociatedwiththeroadpavementratings.
Table9:RoadPavementRatingsin2014
Score
6055
5444
4334
Page26
Condition
NoTopping
VeryPoor
Poor
Needs
Rehabilitation,millingand/orfulldepthpavingneeded.
Significantpatching &isolatedrehabilitationbeforeresurfacing.
Patchingandresurfacing
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
3320
1910
90
Fair
Good
VeryGood
Resurfacing
Assumetobeingoodcondition
Assumetobeingoodcondition
Roadsrankingbetween0and19wereassumedtobeingoodconditionandnotinneed
ofimmediateattention.106roadsratedbetween55and60wereassumedtoneed
morethanresurfacing.Theseroadswerethenexcludedfromfurtherneeds
determinationanalysis.
7.3PavementConditionNeeds
Outofthe1500roadsselectedfortherating,the70roadsthatscoredbetween34and
54andthatshouldbeconsideredforfutureresurfacingarelistedinTable10.(Road
segmentterminimarkersincludeintersectingroadways,facilityendpoints,and
addressesofnearbystructures.)TheseroadsallscoredintheVeryPoororPoor
conditioncategoryandneedpatchingpriortoresurfacing.Fiftyoneofthe70pavement
resurfacingneedsroadsarelocatedwithinsubdivisions.Noneoftheroadsarecurrently
includedinthePauldingCountyDOTprojectsthatarelistedunderconstruction,under
design,orlongrangeprojectsunderdesign.
Table10.SelectedRoadswithPavementResurfacingNeeds
RatingMiles/
Subdivision*
No.
RoadName
From
To
1
2
3
4
5
6
7
8
9
10
11
BerkshireLane
BerktenCourt
CoalsonCornerRd
PatrickDr
RuffRd
TomsDr
MaryLane
TaffRd
MulberryWay
SummerGlenWay
GlenmarkLane
PlantationLane
BerkleighTrailsDr
BershireLn
HaralsonCountyLine
AtchesonRd
HaralsonCountyLine
FreyRd
HitchcockRd
BartowCountyLine
CedarCreekDr
DogwoodTrail
HollandRd
End
End
GarnerRd
173PatrickDr
GarnerRd/MarksRd
EnicePath
252MaryLane
End
111MulberryWay
107SummerGlenWay
118GlenmarkLane
PickettsRidge
166PlantationLane
12
13
WalkerCourt
TimothyDr
35WalkerCourt
14
15
16
17
18
ZionChurchRd
LimestoneLn
BethelChurchRd
HolderRd
MeadowviewLane
MindyCourt
RCThompsonRd
CobblestoneCt
RidgeRoad
E.MemorialDr
HighpointCrossing
OldYorkvilleRd
110LimestoneLn
Hwy92
End
End
NellroseLn
37MindyCourt
19
20
ParkAveW
Mt.TaborChurchRd
ParkwayCt
21
22
BensonDr
CobblestoneCt
DurhamSt
CohranStoreRoad
BuchananSt
255CobblestoneCt
Page27
0.213/BerkleighTrails*
0.061/BerkleighTrails*
0.064
0.3
0.363
0.079
0.23/LakeAvalon*
0.008
0.11/CedarCreek*
0.087/SummerGlen*
0.103/SummerGlen*
0.163/Picketts
Plantation*
0.026/BurntHickory
Estates*
1.21
0.104/FieldstoneLane*
1.651
0.41
0.165/Meadowbrook*
0.031/BurntHickory
Estates*
0.187/ParkPlace
Estates*
0.185
0.245/FieldstoneWalk*
Pavement
Condition
(score)
VeryPoor(52)
VeryPoor(52)
VeryPoor(50)
VeryPoor(50)
VeryPoor(50)
VeryPoor(50)
VeryPoor(44)
VeryPoor(44)
Poor(43)
Poor(43)
Poor(42)
Poor(42)
Poor(42)
Poor(42)
Poor(41)
Poor(40)
Poor(40)
Poor(40)
Poor(40)
Poor(40)
Poor(39)
Poor(39)
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
RatingMiles/
Subdivision*
No.
RoadName
From
To
23
24
25
KimballCt
LindaLane
NeboDr
AbbingtonLn
CleburnePkwy
NeboRd
70KimballCt
End
End
26
ParkAveE
ParkwayCt
264ParkAveE
StallionRun
DerbyRun
End
29
30
StephenCt
ThomasonRd
TimberChaseDr
TraceyLane
BuchannanHwy
MariettaHwy
41StephenCt
End
144TimberChaseDr
31
ChaddsVw
PickettsRidge
294ChaddsVw
32
33
34
35
36
37
38
39
40
41
42
43
CoveDrive
MistyRidgeTrail
SummerCreekDr
SunsetCt
BrooksRackleyRd
CrabappleTrail
CrownCt
GreenhillDr
LeadMountainRd
LegendDr
MillCreekHollow
PrinceCt
258CoveDrive
128MistyRidgeTrail
DueWestRoad
ParkAveE
EastPauldingDr
CedarCreekDr.
HighpointCrossing
HollandRd
BartowCountyLine
MaryLn
5MillCreekHollow
PrinceLn
SpringDr
MistyRidgePlace
520SummerCreekDr
97SunsetCt
HollandRoad
227CrabappleTrail
End
206GreenhillDr
DabbsBridgeRd
288LegendDr
369MillCreekHollow
End
45
46
47
SavannaCt
SettlersRidgeLane
SingletonRd
SouthernSpringsDr
CrestonCt
OldMillPoint
CarrollCountyLine
SpringMeadowsAve
End
SettlersRidgeLane
HaralsonCountyLine
83SouthernSpringsDr
48
SteepleChaseTrl
RightEnd
End
AmberTrace
BrandiDr
WilliamsRd
GarmonRd
HarbinDr
282BrandiDrive
CrestworthPlace
End
PolkCountyLine
BartowCountyLine
53
54
55
CrestworthCrossing
FloydCreekChurch
Rd
MillersDr
MonticelloCourt
NewHomeRd
131MillersDrive
SenatorsRidgeRd
NewVinsonMtn.Rd
1MillersDrive
181MonticelloCourt
CrawfordRd.
56
RidersRd
TrotterWay
End
57
58
59
60
61
62
RuffHarrisRd
SummerGlenPlace
SunsetDr
WellspringPoint
AmericanAve
EavesDr
MarshallFullerRd.
DogwoodTrail
MaclandRd
185WellspringPoint
BraswellMt.Road
BuchananHwy
Hwy61
134SummerGlenPlace
FH@299
2WellspringPoint
3563AmericanAve.
GoodmanRd
HarrisonLane
LakeAvalonCourt
TimothyDr
102LakeAvalonCt
End
MaryLane
27
28
44
49
50
51
52
63
64
Page28
0.061/Abington*
0.582/GreenfieldChase*
0.09/NeboGardens*
0.256/ParkPlace
Estates*
0.207/SaddleBrooke
Farms*
0.034/BurntHickory
Farms*
0.305
0.185/TimberChase*
0.284/Picketts
Plantation*
0.247/HiramCove*
0.125/MistyRidge*
0.502/SummerCreek*
0.16/ParkPlaceEstates*
1.233
0.222/CedarCreek*
0.045/Northcrest*
0.194/HollandHills*
0.099
0.274/LakeAvalon*
0.424/MillCreekStation*
0.162/BarringtonFarms*
0.122/TheMeadows@
Northcrest*
0.67/SettlersMill*
0.592
0.073/SunsetPeak*
0.242/SaddleBrooke
Farms*
0.295/BurntHickory
Estates*
0.277/BrandiValley*
1.073/TheMeadowsat
Northcrest*
Pavement
Condition
(score)
Poor(39)
Poor(39)
Poor(39)
Poor(39)
Poor(39)
Poor(38)
Poor(38)
Poor(38)
Poor(37)
Poor(37)
Poor(37)
Poor(37)
Poor(37)
Poor(36)
Poor(36)
Poor(36)
Poor(36)
Poor(36)
Poor(36)
Poor(36)
Poor(36)
Poor(36)
Poor(36)
Poor(36)
Poor(36)
Poor(36)
Poor(35)
Poor(35)
Poor(35)
0.576
Poor(35)
0.119/SettlersMill*
0.169/SenatorsRidge*
0.349
0.089/SaddleBrooke
Farms*
0.131
0.105/SummerGlen*
0.396
0.177/SettlersMill*
0.297
0.05
0.085/BurntHickory
Estates*
0.087/LakeAvalon*
Poor(35)
Poor(35)
Poor(35)
Poor(35)
Poor(35)
Poor(35)
Poor(35)
Poor(35)
Poor(34)
Poor(34)
Poor(34)
Poor(34)
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
RatingMiles/
Subdivision*
No.
RoadName
From
To
65
ParisCt
158ParisCourt
67
68
PilgrimLane
RussellDrive
SleepyHollowTrail
GailSt
HiramDouglasville
Hwy
3RussellDrive
HickoryGlenWay
End
CrockerLane
End
69
WillowbrookCt
LeftEnd
End
70
WoodwindDrive
HollySpringsRd
1212WoodwindDrive
66
0.134/DentonManor*
0.462/PilgrimsNorth*
0.31/CarringtonChase*
0.133/HickoryGlenn*
0.222/CedarCrest
Plantation*
1.159/SunsetMountain*
Pavement
Condition
(score)
Poor(34)
Poor(34)
Poor(34)
Poor(34)
Poor(34)
Poor(34)
*Subdivisionswherestudyroadsarelocated
Page29
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
8.0 INTERSECTIONS
8.1MethodologyandAssessment
Evenroadwayswithsufficientcapacitymayexperiencedelaysandbottlenecksdueto
operationalissuesatintersections.Thisneedsanalysisidentifiedintersectionsinneedof
potentialimprovementsusingdatagatheredfortheExistingConditionsReport,the
previous2008CTP,andfromcommitteeandpublicinput,asfollows:
AnalysisfromtheInventoryofExistingConditionsReportThreeareasofthe
existingconditionsanalysiswereconsideredintheintersectionanalysis:the
numberofcrashes,theleveloffreighttraffic,andtheamountofdelay.
Recommendedforimprovementinthe2008CTPAlloftheintersectionsidentified
fromtheexistingconditionsanalysiswerepreviouslyidentifiedforimprovementin
the2008CTP.Otherintersectionsidentifiedinthepreviousplanhavebeensince
improvedorareinthePauldingSPLOSTworkprogram.
CommitteeandPublicInputMostoftheinputreceivedduringthecommitteeand
publicmeetingsconfirmedtheneedsidentifiedthroughtheexistingconditions
analysis.ThisinputisnotedinTable11.
Thisanalysisfocusedonidentifyingprojectsneededtofixoperationalandsafetyissues
andcouldbecompletedinthenexttenyearswithCountyfunds.Intersection
improvementprojectswerethereforeplannedandevaluatedonanindividualbasis,not
asanetwork.
8.2IntersectionsImprovementNeeds
Threeintersectionsidentifiedasbeinginneedofimprovementwithinthe2008CTP,
whichhavenotyetbeencompleted,werealsoidentifiedbythepublicorstakeholders
forthiseffort:
SR120(BuchananHighway)SR101
SR360(MaclandRoad)SRBusiness6(MerchantsDrive)
SR101GoldMineRoad
Theseneedsshouldbeconsideredpriorities.Overall,42intersectionsneeding
improvementwereidentified(Table11).AscanbeseenfromFigure5,mostofthe
identifiedintersectionsarealongmajorroadwaysthathavealsobeenidentifiedasin
needofcapacityimprovements.Intersectionimprovementsmayimproveoperationsin
theshorttermalongthesefacilitiesuntiltheycanbewidened.Detailedanalysisofthe
identifiedintersections,alongwithpotentialimprovementsforeach,ispresentedinthe
IntersectionAnalysisTechnicalMemorandumandwillbeutilizedindeterminingthis
studysrecommendations.
Page30
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Table11:UniverseofIntersectionOperationsNeeds
No.
O1
O2
O3
O7
O8
O9
O10
O11
O12
O13
O14
O15
O16
O17
O20
O21
O22
O23
O24
O25
O26
027
O29
0
30/31
032
0
33/34
035
0
36/37
038
039
Intersection Name
SR120(CharlesHardyParkway)SRBusiness6(AtlantaHighway)
SR92EastPauldingDrive
SR120(BuchananHighway)SR101
SR61(VillaRicaHighway)HartRoad
SR61(VillaRicaHighway)OldVillaRicaRoad
SR61(VillaRicaHighway)VernoyAikenRoad
SR61(VillaRicaHighway)WinndaleRoad
SR120Conn/HiramSudieRoadDavisMillRoad
SR92(HiramAcworthHighway)OldBurntHickoryRoad
BurntHickoryRoadBrownsvilleExtension/StoutParkway
RosedaleDriveMetromontRoad
EastPauldingDriveBrooksRackleyRoad
US278/SR6(JimmyLeeSmithParkway)SRBusiness6(Atlanta
Highway)
US278/SR6(JimmyLeeSmithParkway)BillCarruthParkway
US278/SR6(JimmyCampbellParkwaySR61(VillaRicaHighway)
US278/SR6(JimmyCampbellParkway)SR120(BuchananHighway)
WestMemorialDriveSRBusiness6(BuchananStreet)
SR61(ConfederateAvenue)SRBusiness6(WestMemorialDrive)
E.MemorialDriveLegionRoad
WestMemorialDriveSR6Business(BuchananStreet)
SR61(ConfederateAvenue)SRBusiness6(WestMemorialDrive)
US278/SR6(JimmyLeeSmithParkway)HiramPavilionS
US278/SR6(JimmyLeeSmithParkway)DepotDrive
SRBusiness6OldHarrisRoadand/orBusinessSR6CoachBobby
DoddRoad
MaclandRoadSRBusiness6(MerchantsDrive)
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
SR101GoldMineRoadand/orSR101HollySpringsRoad
SR101OldYorkvilleRoad
SR92RosedaleDriveand/orHiramCrossingShoppingCenter
SR92US278/SR6(JimmyLeeSmithParkway)
SR92PauldingCommonsShoppingCenter(HobbyLobby)
2008 CTP
X
X
Stakeholder
Committee
Public Input
X
X
X
X
X
X
X
X
X
X
X
X
X
Page31
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Figure5:UniverseofIntersectionOperationsNeeds
Page32
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
9.0 TRANSITANDTRAVELDEMANDMANAGEMENTNEEDS
9.1TransitNeedsIdentificationMethodology
Transitneedswereidentifiedinfourareas:newtransitimprovements,locationsfornew
shuttleservice,locationsfornewparkandridelotsorvanpoolloading,andthe
continuationofhumanservicestransit.Theneedfornewserviceinthesefourareas
wasevaluatedintermsofinclusioninthe2008CTP,supportfortheimprovementfrom
theStakeholderCommittee,confirmationoftheneedintheexistingconditionsanalysis,
andinputregardingtheimprovementfromthegeneralpublic.
9.2TransitNeeds
IdentifiedneedsfornewservicearelistedinTable12andmappedinFigure6.The2008
CTPidentifiedaneedforcirculatorsystemsinDallasandHiram,fixedroutebusalong
US278/SR6,arterialBusRapidTransit(BRT)/HighOccupancyVehicleLanes(HOV)on
severalmajorroadways,andnewGRTAservicewithinthecountyandtolocationsin
CobbCounty.ExceptfortheneedforarterialBRT/HOVservicealongSR92/Dallas
AcworthHighway,alloftheneedsfromthepreviousCTPwerereaffirmedbyexisting
conditionsanalysis.
Table12:NewTransitorShuttleServiceNeeds
New Service
PauldingNorthwestAtlantaAirport
PauldingCountyGovernmentComplex
WellStarPauldingHospital
ChattahoocheeTechnicalInstitute
DallasCirculator
HiramCirculator
FixedRouteBusfromPaulding
NorthwestAtlantaAirportto
Dallas/HiramalongUS278/SR6
ArterialBRT/HOVSR120Charles
HardyPkwy
ArterialBRT/HOV/orTruckPreferred
LanesUS278/SR6
ArterialBRT/HOVSR92/Dallas
AcworthHwy
ExtendGRTAviaSR6toDallas
NewGRTAServicetoMarietta(CCT
Hub)viaSR120
NewGRTAServicetoCumberlandvia
SR360
X
X
Stakeholder
Committee
X
X
X
2008
CTP
Travel Trends
Public
Input
X
X
X
X
X
X
X
X
Page33
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Figure6:TransitandTravelDemandManagementNeeds
Page34
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Inaddition,theneedfornewtransitorshuttleservicetothePauldingGovernment
Complex,WellstarPauldingHospital,wasidentifiedbyexistingconditionsanalysisand
stakeholderorpublicinput.TheneedfornewGRTAservicetoMariettaviaSR120or
CumberlandviaSR360wassubstantiatedbyexistingconditionsanalysisbutnot
supportedbystakeholdersorthepublic.
Thecontinuedneedforhumanservicestransitwasidentifiedwithinthe2008CTP
completedin2008andwasconfirmedbytheStakeholderCommittee.Thiswasalso
corroboratedbythedemographicanalysis,whichidentifiedagrowingseniorpopulation
whichincreasesthedemandforthistypeofservice.
9.3
TravelDemandManagementNeedsIdentificationMethodologyand
Analysis
ThegoalofTravelDemandManagement(TDM)istoreduceoraccommodatetrafficon
existingfacilitieswithoutadditionalinvestmentsininfrastructure.TDMstrategies
includecarpoolingorencouragingtelecommuting.Thisanalysisexploredtheneedfor
investmentinparkandridelotsandvanpoollotstoaccommodateridesharinginthe
county.
Aselsewhere,theneedfornewserviceinthesefourareaswasevaluatedintermsof
inclusioninthepreviousCTP,supportfortheimprovementfromtheStakeholder
Committee,confirmationoftheneedintheexistingconditionsanalysis,andinput
regardingtheimprovementfromthegeneralpublic.(The2008CTPdidnotconsiderthe
needfornewparkandridelots.)
9.4TravelDemandManagementNeeds
TheStakeholderCommitteeidentifiedfourlocationswherenewparkandridelotsmay
beneeded:CrossroadsCommunityCenter,US278atSeaboardDrive,andUS278atSR
120.Locationswereconfirmedbytheexistingconditionsanalysis.Thenewparkand
ridelotneedsarelistedinTable13andmappedinFigure5.
Table13:NewParkandRideLotNeeds
New Park and Ride Lots
PauldingNorthwestAtlantaAirport
CrossroadsCommunityCenter
US278andSeaboardDrive
US278andSR120(CharlesHardy
Parkway)
Stakeholder
Committee
X
X
X
2008
CTP
Travel Trends
Public
Input
X
X
X
X
Page35
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
TheneedforthedevelopmentofaPauldingCountyVanpoolprogramwasidentifiedby
the2008CTPandconfirmedbyexistingconditionsanalysis.Twonewvanpoollot
locationneedswereidentifiedbythestakeholdercommitteeandconfirmedbyexisting
conditionsanalysis,atCrossroadsCommunityCenterandSR120atUS278.New
vanpoollotneedsarelistedinTable14andmappedinFigure5.
Table14:VanpoolNeeds
Vanpool Needs
CrossroadsCommunityCenter
SR120andUS278
DevelopmentofPauldingCounty
VanpoolProgram
DevelopmentofCobbPauldingCounty
VanpoolLocation
NewGeorgiaCommunity
Stakeholder
Committee
X
X
2008
CTP
Travel Trends
Public
Input
X
X
X
X
Page36
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
10.0 BICYCLEANDPEDESTRIANNEEDS
10.1 MethodologyforIdentifyingBicycleandPedestrianNeeds
Thetypesofbicycleandpedestrianfacilitiesassessedforthisanalysisare:
Sidewalksegments
Multiusetrails
Pedestriancrossingsofroadways
Trailheads(accesspointsalongtheSilverCometTrailwithparkingfacilities)
Bicyclelanes
Extendedbicycleshouldersalongroadways
10.1.1 SidewalkAnalysis
Thisanalysisinvolvedidentifyingmissingsidewalksegmentsinpedestrianpriorityareas
wheresidewalkconnectionsaremostneeded.Pedestrianpriorityareasarelocated
withinonequartermileradiiaroundmajorpedestriandestinations,suchaspark
entrances,schools,colleges,libraries,SilverCometTrailaccesspointsandtheGRTA
parkandridelot(onequartermileisconsideredacomfortablewalkingdistance).
CommercialareasidentifiedasfutureVillageCentersorCrossroadsCommunitiesonthe
FutureDevelopmentMapwerealsoconsideredtobeprioritypedestrianplanningareas.
Thereare80pedestrianpriorityplanningareasinthecounty,asshowninFigure7.
Sidewalkconnectionstolargelotruralresidentialareaswerenotidentifiedasapriority
needgiventheirlowresidentialdensities.
10.1.2 SilverCometAccessibilityAnalysis
Adetailedanalysisofpotentialenhancementsandopportunitiestoimproveoverall
accessibilitytotheSilverCometTrail,wasdocumentedintheSilverCometTrail
AccessibilityAnalysisTechnicalMemo.Theanalysishadtwocomponents:
CrossingsAccessAnalysisAnassessmentofexistingroadwaycrossingsoftheSilver
CometTrailforpotentialnewtrailheadstothefacility.Forthepurposeofthis
analysis,atrailheadisdefinedasanaccesspointwithparkingfacilities.
ExistingTrailAccessAnalysisAnassessmentofexistingaccessibilityandvisibilityof
existingtrailheadsandaccesspoints(trailconnectionswithoutparkingfacilities)to
surroundinglandusesandtheirneedandpotentialforexpansion.
Page37
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Figure7:PedestrianPlanningAreas
Page38
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
10.1.3 OtherBicycleandPedestrianNeeds
OtherbicycleandpedestrianneedswerebeyondsidewalksandaccesstotheSilver
CometTrailwasidentifiedthroughStakeholderCommitteeandpublicinput,through
theuseofmapbasedneedsidentificationexercisesatmeetingsandevents,and
throughthecommunitysurvey.Inputwascollectedregardingneedsinthefollowing
areas:pedestriancrossings,sidewalksegments,trailheadsontheSilverCometTrail,
multiusetrails,bikelanes,andextendedshoulders.
10.2 SummaryofPedestrianandBicycleNeeds
10.2.1 SidewalkSegments
Thesidewalknetworkwithinpedestrianpriorityareaswasanalyzedforgaps.Areas
withoutsidewalks,orsegmentsofthesenetworksthatweremissingsidewalks,were
inventoriedtocreatealistofneededsidewalksegments(Table15).Neededsidewalk
segments,alongwiththeremainderofthebicycleandpedestrianneedsdiscussedin
thissection,areshowninFigure8.
Atotalof46sidewalkconnectionswereidentifiedfornewconstruction.These
deficienciesaretypicallymissingsidewalksegmentsbetweenresidentialsubdivisions
andpedestriandestinations(schools,parks,libraries,etc.).Themissingsegmentsare
neededtocreateacompletesidewalknetworkinthepedestrianpriorityareas,and
wouldallowpedestrianstowalkfromonepointtoanotheroncontinuoussidewalk.
Table15:SidewalkSegmentNeeds
Map
Key
Sidewalk
Segment
From
BakersBridge
Road
BrownsvilleRoad
CedarcrestRoad
CedarcrestRoad
5
6
CedarcrestRoad
CenterStreet
SR92
FloydShelton
Elementary
HarmonyGrove
ChurchRoad
CobbCountyLine
SeaboardAvenue
ClontsRoad
WileyDrive
ColbertRd
CowboyPath
AbneyElementary
EastPauldingHome
Park
11
CrossroadsChurch
Road
DepotDrive
12
DueWestRoad
13
14
E.FosterAvenue
EastPauldingDrive
10
Page39
To
RidgeRoad
CharityDrive
SweetwaterPass
TheShoppesat
CedarcrestCommons
ArthurHillsDrive
HighcrestDrive
SR92
HalHutchens
Elementary
LegacyPointeDrive
ForestHillsDrive
WintervilleDrive
YorkvillePark
RosedaleDrive
DallasAcworth
Highway
DallasCityPark
LostMeadowsDr
US278/SR6
AutumnCreekDrive
HardeeStreet
HopeDrive
X
X
X
X
SourceofNeedsIdentification
Stakeholder
Pedestrian
Public
Committee
Analysis
Input
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Map
Key
Sidewalk
Segment
From
15
EastPauldingDrive
16
17
18
19
GravesRoad
HiramSudieRoad
HollySpringsRoad
LesterDrive
DallasAcworth
Highway
GravesRoadSpur
SR61
WoodwindDrive
DallasCityPark
20
MaclandRoad
SR92
24
MeinMitchell
Road
MetromontRoad
MulberryRock
Road
MustangDrive
25
NeboRoad
26
27
28
29
NeboRoad
OakStreet
OldVillaRicaRoad
OldVillaRicaRoad
PineShadows
Drive
21
22
23
30
GravesRoad
SouthernOaksDrive
Highway101
SR6
SR120(CharlesHardy
Pkwy)
X
X
RidgeRoad
CountryVillageDrive
US278/SR6
RosedaleDrive
DokeCochranRoad
SR61
HeritageWay
NeboElementary
School
DallasNeboRoad
SR92
SR61
SR61
DonbieDrive
PineShadowsDrive
SwanDrive
SeaboardAvenue
IvyTraceLane
StationDrive
X
X
X
X
X
X
NeboRoad
SmithFergusonRoad
NorthviewLane
WinterParkLane
AustinBridgeRoad
RidgeRunDrive
FarmStreet
SugarMillDrive
PowderSpringsStreet
X
X
X
X
X
X
X
X
SeaboardDrive
RunnellRoad
KirkDrive
EastPauldingMiddle
School
RoyalSunsetDrive
CleburneParkway
US278/SR6
PooleElementary
School
BagbyPath
PauldingMemorial
Hospital
JADobbinsMiddle
School
FourOaksDrive
PineValleyRoad
32
PineValleyRoad
33
34
35
36
37
RidgeRoad
RidgeRoad
RidgeRoad
ScogginsRoad
SeaboardAvenue
38
SouthMainStreet
39
SR101
40
SR61
TaylorFarmPark
West
TaylorFarmPark
East
DallasNeboRoad
HughesRoad
HughesRoad
SR61
TowneParkDrive
Constitution
Boulevard
CrossroadsChurch
Rd
OscarWay
41
SR92
HardyCircle
42
SR92
43
US278/SR6
Wayside
Lane/ClearCreek
Drive
WestMemorial
Drive
WilliamsLake
Road
45
46
SourceofNeedsIdentification
Stakeholder
Pedestrian
Public
Committee
Analysis
Input
Mt.TaborPark
31
44
To
OldBurntHickory
Road
DepotDrive
Source: Jacobs
Page40
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Figure8:PedestrianandBicycleNeeds
Page41
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
10.2.2 PedestrianCrossings
Theneedfortwopedestriancrossingswasidentified.Inbothcases,thereweretwo
locationsthatthepublicexpressedaninterestinwalkingbetween,buthadfoundthe
crossingofanexistingroadwayunsafe.Thefirstneedisforapedestriancrossingof
WilliamsLakeDrivethatwouldconnectsidewalksegmentsonoppositesidesofthe
roadjusteastofJADobbinsMiddleSchool.Thesecondneedisforapedestrian
connectionacrossUS278/SR6betweentheresidentialsubdivisiononClearCreekDrive
andPooleElementarySchoolonWaysideLane.However,itshouldbenotedthatanat
gradeconnectionatthislocationwouldbeunsafe.
10.2.3 NewSilverCometTrailTrailheads
Theneedforanewtrailhead,oranareawhereuserscandriveandparkalongthetrail,
existsinthoseareaswherethepublicwishestohaveaccesstotheSilverCometTrailbut
wherethereisnoaccesspointcurrentlyavailable.Thisanalysisfoundthemostneed
wasforatrailheadatMetromontRoad,butidentifiedsixlocationswherenew
trailheadsfortheSilverCometTrailmaybeneeded(Table16).Formoredetail,please
accesstheSilverCometAccessibilityAnalysisTechnicalMemorandum.
Table16:PotentialTrailheadsonSilverCometTrail
Location
IsleyStamperRoad
BillCarruthParkway(EastLoop)
MetromontRoad
ThompsonRoad/CoppermineRoad
BillCarruthParkway(WestLoop)
Source: Jacobs
X
X
10.2.4 MultiUseTrails
Newmultiusetrailsareneededinareaswherethepublicwishestowalkorbike
betweentwopoints,eitherfortransportationorrecreation,butexistingconnections
areeitherabsentorunsafeformodesotherthanautomobiles.Theneededmultiuse
trailsarelistedinTable17.Manyoftheseproposedtrailsincludeextensionsortrail
spursconnectingtotheSilverCometTrail.
Page42
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Table17:MultiUseTrailNeeds
New Trail
Location
WithinthePauldingForestWMA
WithinthePauldingForestWMA
SouthofSilverCometTrail
NorthofSilverCometTrail
BetweenPauldingNorthwestAtlanta
AirportandHulseyTownRoad
BetweenGeorgiaParkwayandPeg
ColeBridgeTrail
BetweenWeddingtonRoadand
StricklandPark
BetweenGovernmentComplexand
SeaboardTrailhead
NorthofHulseytownRoad
NearPegColeBridgeRoad
StricklandParkConnection
S.MainandUS278(Dallas)
Source: Jacobs
10.2.5 BicycleLanes
Theneedforbicyclelanesexistsinareaswherethepublicwishestobicyclebutexisting
roadwaysareunsafeforbicyclistsinmixedtraffic.Fourcorridors,MulberryRockRoad,
RidgeRoad,OldBurntHickoryRoad,andSR61(CartersvilleRoad),havebeenidentified
asinneedofbicyclelanes(Table18).TheneedforbicyclelanesalongRidgeRoadwas
initiallyidentifiedbytheadvisorycommitteeandhasbeenconfirmedthroughpublic
input.TheSR61corridorbetweenRidgeRoadandGeorgianParkwaywasidentifiedas
beinneedofanextendedshoulderratherthanbicyclelanesduetoroadwaygeometry.
TheARCsAtlantaRegionBicycleTransportationandPedestrianWalkwaysPlan
recommendspavedshoulderalongUS278fromtheCobbCountyLinetoDallasto
accommodatebicycletravelinPauldingCounty.
Table18:BicycleLaneandExtendedShoulderNeeds
Pedestrian Crossing
Location
MulberryRockRoad
RidgeRoad
SR61(CartersvilleHwy)
NearSR61
BetweenBakersBridgeRoadandSR61
BetweenMt.MoriahRoadandDabbsBridgeRoad
BetweenHarmonyGroveChurchRoadandSeven
HillsBoulevard
BetweenRidgeRoadandGeorgianParkway
CedarcrestRoad
SR61
X
X
Source: Jacobs
Page43
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
11.0 FREIGHTNEEDS
11.1 MethodologyandAnalysis
Heavydutytrucksexertagreaterimpactonthemaintenanceanddesignrequirements
ofroadwaysthansmallervehicles.Theirweightandneedforturningradiusrequire
specialaccommodationsalongroadwaysdesignatedasfreightcorridorsandotherswith
ahighpercentageoftrucktraffic.ThisanalysisoffreightneedsinPauldingCounty
considersexistingcommercialandindustrial(freightgenerating)landuses,previously
identifiedAstroMapfreightcorridors,andtruckpercentagesfromtheARCTravel
DemandModeltodeterminePauldingCountyscurrentandfuturefreightcapacityand
safetyneeds.
ThisanalysisidentifiedmultiplefreightcorridorsinPauldingCounty,severalclustersof
potentiallyfreightgeneratinglanduses,andseveralarterialcorridorscarryingagreater
thanaveragepercentageofheavytrucktraffic.Theseareasofinterestwereusedto
identifypotentialneedsintermsofheavytruckaccommodationsandconflicts.
11.1.1 FreightGeneratingLandUses
Thepresenceoffreightgeneratingcommercialandindustriallanduseswasanalyzedto
helpidentifyintersectionsandcorridorsinneedofimprovementstoaccommodate
potentialcurrentandfuturetrucktraffic.Areaswithsignificantcommercialand
industrialuseswithoutaccesstohighspeed,managedaccessroadwaysdesignedto
accommodatetrucktrafficdemonstrateaneedforfreightrelatedimprovements.
Freightgeneratinglandusesincludeindustriallanduses(primarilylightmanufacturing
andwarehousing/distributioncenters)andquarries.Twolargequarriesarelocatedin
thesouthwesternportionofthecountyoffofSR120andMulberryRockRoad.Two
largeindustrialparksarelocatedwithinthecountyanindustrialparknorthofDallas
locatedadjacenttoDallasAcworthHighwayatIndustrialBoulevardNorthandanother
eastofHiramadjacenttoRosedaleDrive.Commerciallanduseshavealsobeenincluded
inthisanalysis.LargeclustersofcommercialusescanbefoundinHiramandgreater
DallasareasalongtheUS278/SR6andMerchantsDrivecorridors.
11.1.2 AstroMapCorridors
AllARCidentifiedAstroMapfreightcorridorswereanalyzedintermsoftheirabilityto
safely,efficientlycarryheavydutytrucktraffic.InPauldingCounty,therearetwonorth
southcorridorsdesignatedontheASTRoMaP,SR92andSR61,andoneeastwest
corridor,comprisedofcombinedsegmentsofUS278/SR6andSR120(CharlesHardy
Parkway).ThesecorridorsaremappedanddiscussedingreaterdetailintheExisting
ConditionsReport.Deficienciessuchasnarrowlanes,smallturningradii,poorlymarked
andsignalizedintersections,andotherobstructionswereconsideredwhendetermining
currentandfuturefreightneedsalongthesecorridors.
Page44
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
11.1.3 TruckVolumes
Alargepercentageoftrucktripsalongaroadwaycanresultinasignificantmaintenance
impact,aswellasaneedforaccessmanagementpolicies,widelanes,andsignificant
turninglanestorage.TruckvolumesalongmajorcorridorsinPauldingCountywere
consideredinordertoidentifyallareasofmajortrucktraffic,includingthoseoutsideof
theAstroMapplan.Thisanalysisdeterminedthatthehighesttruckvolumesand
percentageswithinthecountyarefoundAstroMapdesignatedfreightcorridors,SR92,
US278/SR6,andSR61,inthatorder.TruckvolumesonPauldingCountyroadwaysare
presentedinTable19.
Table19:MajorRoadwayHeavyTruckVolumesandPercentages
Major
Roadway
SR92
From
To
CobbCounty
Line
Hiram
Acworth
Hwy
CobbCounty
Line
Dallas
Acworth
Hwy
CobbCounty
Line
SR120
US278/SR6
DallasAcworth
Highway/
MemorialDrive
Business
6/Buchanan
Street
SR120(West)
SR101/113
HiramSudie
Rd
SR92
BusSR
6/Merchants
Drive
Page45
Daily
Truck
Volume
2030
3,600
Daily
Truck
Volume
2040
3,900
Truck
%
2015
Truck
%
2030
Truck
%
2040
11%
10%
11%
1,500
2,900
3,400
14%
13%
13%
SR120
1,600
3,100
3,600
9%
9%
10%
US278/SR6
HiramSudie
Rd
Douglas
CountyLine
E.Paulding
Drive
1,600
1,400
3,200
2,500
3,700
2,900
8%
8%
8%
9%
9%
10%
1,500
2,900
3,500
7%
7%
7%
600
700
600
7%
6%
4%
E.Paulding
Drive
Memorial
Drive
BusSR6
500
600
600
4%
4%
4%
US278/SR6
300
300
300
3%
2%
2%
US278/SR6
SR120
(Conn)
Haralson
CountyLine
PolkCounty
Line
Carroll
CountyLine
SR120
300
200
300
4%
2%
3%
200
200
300
3%
2%
3%
200
200
300
4%
3%
3%
700
800
1,000
5%
4%
5%
400
600
700
2%
2%
3%
600
1,200
1,400
100
800
1,500
2,000
200
1,000
1,500
2,100
200
2%
3%
4%
2%
2%
3%
4%
2%
3%
3%
4%
2%
SR120
(Conn)
SR120
SR120
US278/SR6
Daily
Truck
Volume
2015
2,100
PolkCounty
Line
SR120
SR61
Business6
US278/SR6
SR61
Business6
CobbCounty
Memorial
Drive
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Major
Roadway
SR120
SR360
SR61
From
CobbCounty
Line
SR92
CobbCounty
Line
SR92
Douglas
CountyLine
RidgeRoad
HiramSudie
Road
US278/SR6
DabbsBridge
Road
RidgeRoad
Old
Cartersville
Road
Mt.Moriah
Rd
Dabbs
BridgeRoad
SR61
SR61
NeboRoad
DallasNebo
Road
SR61
DallasNebo
Road/Bakers
BridgeRoad
DallasNebo
Road
SR61
NeboRoad
RidgeRoad
Sweetwater
ChurchRoad
Brownsville
Road
ScogginsRoad
HiramSudie
Road
Source:ARCTDM
Douglas
CountyLine
SR92
SR120
SR61
To
Daily
Truck
Volume
2015
600
Daily
Truck
Volume
2030
900
Daily
Truck
Volume
2040
1,000
Truck
%
2015
Truck
%
2030
Truck
%
2040
2%
2%
2%
US278/SR6
SR92
700
500
800
700
900
800
2%
2%
2%
2%
2%
2%
SR120
RidgeRoad
300
1,000
400
1,200
500
1,300
2%
6%
2%
6%
2%
6%
HiramSudie
Road
US278/SR6
600
800
800
7%
7%
6%
600
900
800
4%
4%
4%
Old
Cartersville
Road
Mt.Moriah
Rd
400
600
600
3%
4%
4%
200
300
400
2%
3%
4%
500
600
800
4%
4%
5%
600
700
700
4%
4%
3%
100
200
600
2%
4%
4%
100
200
200
2%
3%
2%
100
400
400
1%
3%
2%
DallasNebo
Road
SR92
100
100
200
2%
2%
3%
100
200
200
2%
2%
2%
NeboRoad
RidgeRoad
Douglas
CountyLine
SR92
200
400
400
200
100
400
200
200
500
2%
3%
3%
2%
1%
2%
1%
2%
3%
200
400
400
3%
4%
3%
CobbCounty
Line
SR61
SR92
200
100
100
3%
2%
2%
0
200
100
300
100
300
0%
2%
2%
2%
1%
2%
SR92
Dabbs
BridgeRoad
Bartow
CountyLine
Bartow
CountyLine
DallasNebo
Road
SR92
11.2 TruckandFreightNeeds
Freightrelateditemsofinterestandareaswithpotentialheavytruckrelatedneedsare
mappedinFigure9.Theidentifiedneedsareasareprimarilylocatedwheretruckroutes
intersecttowncenters.Currently,theseareasareadequatelyequippedtodealwith
trucktraffic,buttheymayrequiremaintenanceorenhancementsastheygrow.Primary
freightcorridorssuchasSR92andSR61arealreadywellequippedtodealwithfreight
Page46
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
traffic,featuringwidelanes,ampleturninglanestorage,andwellpavedandmarked
roadways.FeaturessuchasthebridgeattheintersectionofSR92andtheSilverComet
trailpreventtruckconflictswithpedestriantraffic.
Majortruckingcorridorsareimportanttoidentifygiventheiruniqueplanning
requirements.Whilerarelyfeasible,idealroadwaydesignforlargetrucksincludelane
widthsofatleast12feet,wideturningradiiof75ftandclearzonesof10feet.Posted
speedlimitsshouldbegreaterthan45mphontruckroutestofacilitatefreightmobility.
Trafficsignalsonfreightcorridorsshouldbetimedandcoordinatedtofavorthrough
traffic.Accessmanagementpoliciesandregulationshavebeenshowntomaximize
trafficflowonthesetypesofcorridors.
DuetoPauldingCountyscontinuedresidentialgrowth,itisimportanttocontinuethe
accessmanagementandotherpolicieswhichcontributetotheeffectiveseparationof
trucksfromresidentialandtowncenters.Wheretrucksmustpassthroughdeveloping
towncenters,asinthecaseofSR92throughHiram,itisevenmorecriticaltoensure
thatthesetypesoftruckaccommodationsarebuiltandmaintained.Asfutureroadways
develop,truckfriendlybypassesmaybeconsideredinordertoallowfreighttrafficto
avoidconflictswithtowncentersinDallas,Hiram,andelsewhere.
Page47
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Figure9:FreightNeedsAreas
Page48
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
12.0 SYSTEMNEEDS
Withlimitedavailablefundingitismoreimportantthanevertoconsiderlowercost
solutionsthatprovidesystemimprovements.Smallerinvestmentsinaccess
management,signaloptimization,intersectionmodifications,andbridgerehabilitation
canimprovesafetyandoffermoreefficientoperationstorelieveormanageproblem
areas.Notallneedscanbemetbynewconstruction.Thetransportationnetwork,asit
nowexistsinPauldingCounty,wouldcontinuetoworksafelyandefficientlywith
investmentsinaccessmanagement,bridges,anditsnetworkofsignalizedintersections.
12.1 AccessManagementMethodology
Theprocessusedtoidentifyaccessmanagementcorridorsbeganwiththoseidentified
inthe2008CTP.ManyofthesecorridorswereidentifiedundertheBusinessCorridor
designationwithinthecityofDallassFutureDevelopmentMap,includingSR120
(CharlesHardyParkway),US278/SR6,SRBus6,andBillCarruthParkway.Severalother
corridorswereaddedtotheanalysis,includingSR92(likelyomittedfromtheprevious
planduetoplannedwidening)andBillCarruthParkwayExtension(whichdidnotexistin
2008).
Corridorswereanalyzedbaseduponaseriesofexistingconditionstoassesstheirlevel
ofneedforaccessmanagementstrategies.Threeexistingconditionscrashrates,
traveldelayandexisting/futurelanduseswereexamined.Onlycorridorswithhigh
crashrates,significanttraveldelayandexistingorfuturelandusesthatwouldrequire
accessmanagementwereidentifiedastargetedaccessmanagementcorridors.This
reviewreduced24potentialaccessmanagementcorridorstoeightprioritycorridors.
12.2 AccessManagementNeeds
TheeightcorridorsinneedofaccessmanagementstrategiesarelistedinTable20and
showninFigure10.Landuserecommendationsforthesecorridorsincludeimproving
bigboxretaildesign,redevelopingagingshoppingcenters,andlocatingbuilding
facadesnearthestreetwithparkingintherear.Accessmanagementrecommendations
includedrivewayconsolidationandprovidinginterparcelaccessbetween
developments.
Table20:AccessManagementCorridors
Roadway
SR120(Charles
HardyPkwy)
SR360(Macland
Rd)
SR92
BillCarruthPkwy
BillCarruthPkwy
Ext.(E.Hiram
Page49
Previous
Plan
From
To
CobbCountyLine
US278/SR6
DouglasCountyLine
US278/SR6
SR120(Charles
HardyPkwy)
CobbCountyLine
SR92
X
X
X
X
X
X
BillCarruthParkway
US278/SR6
CobbCountyLine
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Bypass)
RosedaleDr/
US278/SR6
SRBus6
SR92
CobbCountyLine
US278/SR6(Eastof
Dallas)
US278/SR6
SR120
US278/SR6(West
ofDallas)
X
X
X
X
X
X
Page50
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Figure10:AccessManagementCorridors
Page51
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
12.3 BridgeNeeds
12.3.1 MethodologyandAssessment
ThisstudycoordinatedwiththeGDOTOfficeofBridgesandStructuresandPaulding
CountytoidentifyallbridgesandculvertslocatedinPauldingCounty.Forallbridgesand
culvertsidentified,datawascollectedtoassistinthedeterminationofneedsincluding
theBridgeInventoryRatingSheet.
Sufficiencyratingswereutilizedintheidentificationofbridgesinneedofrepairor
replacement.Abridgemustexhibitaratingof50orbelowtoqualifyforfederal
replacementfunds.Allotherbridgeslisttheirrecommendedrehabilitationor
maintenancerecommendationsfromtheJanuary16,2013GDOTInspectionReport.
Thoselistedbridgeswithsufficiencyratingsof65orbelowwereidentifiedasneeding
eitherreplacementorrehabilitation.Rehabilitationcanincludemaintenanceorrepair
ofbridgedecks,expansionjoints,bridgerailings,foundations,andpiersetc.Bridge
rehabilitationcanbeacostefficientsolutionforbridgeswithsufficiencyratingsbelow
50ifitcanbedemonstratedthattherehabilitationwillimprovethebridgetoan
acceptablesufficiencyrating.
Oncealldatawascompiled,bridgeneedswerecategorizedintotwocategories:
1. Bridgesinneedofreplacement.
2. Bridgesinneedorrehabilitationormaintenance.
Someofthelistedbridgeslackasufficiencyratingbecausetheydidnothaveacomplete
NationalBridgeInventoryinspectionperformed.Sincethefullinspectionwasnot
performed,allthedataneededtocalculatethesufficiencyratingisnotincluded.These
structuresaretypicallyinprivateuseoverapublicroad.Inthosecases,GDOTchecked
clearancesandlookedforanysignificantdeficiencythatcouldcauseafailure.
12.3.2 SummaryofBridgeNeeds
AnalysisofthebridgedatainPauldingCountyidentifiedeightbridgesasbeinginneed
ofreplacementorrehabilitation(seeTable21andFigure11).Ofthese,threewere
listedaseithercurrentlyunderconstructionorunderdesign:
22350120,WillowSpringsoverSilverCometTrail
22350260,DallasAcworthHighwayatPickettsMillCreek
22350250,DallasAcworthHighwayatPossumCreek
Onebridgewasidentifiedasneedingreplacement:
Page52
22350400,MorningsideDriveatMillCreek
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
TrafficonthisbridgewaslargelyrelocatedtoBillCarruthParkwaywiththeopeningof
thenewsegmenteastofSR92.Theneedforthisreplacementmaybedeferredduetoa
majorreductionintrafficvolume.
Twobridgeswereidentifiedasinneedofrehabilitation/maintenance:
22350450,DueWestRoadatPickettsMillCreek
22350640,OberlochenWayatCarringtonLake
Finally,twobridgeswereidentifiedasinneedofreplacementof
rehabilitation/maintenance:
22350110,Mt.OlivetRoadatPumpkinvineCreek
22350290,PineValleyRoadatSweetwaterCreek
Page53
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Table21:BridgeswithReplacementandMaintenance/RehabilitationNeeds
MapID
StructureID
FacilityCarried
FeatureIntersected
22350120
WillowSpringsRoad
SilverCometTrail
22350400
MorningsideDrive
22300260
DallasAcworthHighway
Sufficiency
Rating
NotedInspectionconcern
BridgeNeeds
15.88
Buildin1941
Replacementcompleted
12914
LickLogCreek
49.01
Buildin1979
Replacement
PickettsMillCreek
49.95
Buildin1940
SettobeginCSTin201516
22350290
PineValleyRoad
SweetwaterCreek
56.28
22300250
DallasAcworthHighway
PossumCreek
57.42
22350450
DueWestRoad
PickettsMillCreek
60.64
22350640
CarringtonLake/
OberlochenWay
SweetwaterCreek
Tributary
61.50
22350110
Mt.OlivetRoad
PumpkinvineCreek
64.81
Structurepostedfor16TonsHTrucks;18Tons
Type3Truckand25TonsTimberTruck;posting
duetoinsufficientshearcapacityoftheconcrete
superstructure.Areplacementstructureis
requiredtoupgradethisstructuretoapoint
wherepostingisnolongerrequired.
Maintenancerecommendationsareprovidedto
maintainthisstructureatthecurrentrating.
Bridgestructureinfairconditionwithcorrosion
andminorsectionlossofthesteel
superstructure.
Bridgeinfaircondition;Concreteencasements
onpile#1and#2atbent3haveundermined.
Corrugatedmetalpipeculvertservesasalake
spillwayandoverflow.Maintenance
recommendationshavebeenidentified.
Atthepresenttimepostthisstructurefor19
TonsHTruck;19TonsType3Truck;26Tons
TimberTruck;23TonsHSTruckand32Tons
Type3S2Truck.Thisstructurerequiresposting
duetoinsufficientshearcapacityoftheconcrete
superstructure.Areplacementstructureis
requiredtoupgradethisstructuretoapoint
wherepostingisnolongerrequired.
Maintenancerecommendationshavebeen
identifiedt10omaintaincurrentrating.Atthe
timeoftheinspection,thepostingsignatthe
northernendofthestructurewasmissing.This
signisrequiredandmustbereplaced.
Replacement/
Maintenance/Rehabilitation
SettobeginCSTin201516
Maintenance/Rehabilitation
Maintenance/Rehabilitation
performedin2009,tobe
monitoredforfutureneeds
Replacement/
Maintenance/Rehabilitation
Page54
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Figure11:BridgeNeeds
Page55
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
12.4 IntelligentTransportationSystemsandSignalizationNeedsMethodology
andAnalysis
TrafficsignalizationandIntelligentTransportationSystems(ITS)areimportantelements
inreducingtraveldelay,maintainingmobility,andpromotingsafetyalongheavily
traveledcorridors.Ascapacityimprovementshavebecomelessfeasibleduetofunding
limitations,thereisagreaterfocusonmaintainingandimprovingthesoundoperation
ofexistingtransportationnetworks.ITSimprovestransportationsafetyandmobility
throughtheintegrationofadvancedcommunicationsintotransportationinfrastructure
andvehicles.InthecaseofPauldingCounty,ITSspecificallyappliestocommunications
amongsignalizedintersections.
Closelyspacedtrafficsignalsaremoregreatlyaffectedbythedegreeoftrafficsignal
coordinationalongthetravelcorridor;welltimedtrafficsignalscanprocesslarger
amountsoftrafficmoresmoothly,wherepoorlytimedtrafficsignalswillhavevehicle
queuespillbackthroughadjacentintersectionsandleadtodelays.Therefore,this
analysisidentifiedareaswheresignalizedintersectionswerelocatedclosetogether.The
2008CTPdidnotidentifyITSneedsorimprovements.
12.5 SummaryofIntelligentTransportationSystemsandSignalizationNeeds
Figure12showsthelocationsofalltrafficsignalsonthePauldingCountyroadway
network.Asshown,withindevelopedareassuchasthecitiesofDallasandHiram,many
ofthetrafficsignalsalongthesecorridorsarelocatedincloseproximitytooneanother.
Intheseareas,theremaybeaneedforcoordinationofsignalsusingITS.Itshouldalso
benotedthattherecommendedintersectionimprovementsresultingfromthisstudy
willincludeintersectionsinpotentialneedofsignalization.
PauldingCountywasawardedfederalgrantmoneyforanumberofITSimprovements.
Thisincludestheconstructionofatrafficcontrolcenter(TCC)andtheinstallationof
detectionandmonitoringequipment(fiberopticinterconnect,cameras,etc.)along
mostofmajorroadwaysinthecounty.Atitscompletion,theprojectwillinterconnect
46outofthe61signalswithinthecountytoanewTCCtoprovideforbettertraffic
operations.
Page56
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
Figure12:SignalizedIntersections
Page57
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
13.0 FUNDINGOPTIONS
Athoroughunderstandingofpotentialfundingsourcesisnecessaryforarealistic
transportationworkplan.Afullinventoryofpotentialsourcesandeligibilityfortheir
useisprovidedwithintheInventoryofExistingConditionsReport.Theprimarysources
fortransportationfundingarefederalfundsthroughtheARC,statefundsadministered
throughGDOT,andlocalfundsthrougheithertheSPLOSTorlocaljurisdictiongeneral
funds.
Intodaysconstrainedfiscallandscape,itwillbeessentialforPauldingCountytolook
beyonditstraditionalsourcesoffundingtoinvestintheinfrastructuredemandedbyits
transportationneeds.Thissectionpresentsanoverviewofavailablefundingprograms.
Thesepotentialfundingsourceswillbeassessedinthenextphaseofthisstudy,along
withrevenueforecaststhatwillhelpdeterminetheprojectsinthefiveyearworkplan.
13.1 ARCFederalFundingPrograms
AsthedesignatedMetropolitanPlanningOrganizationfortheAtlantaregion,theARCis
responsibleforthedistributionoffederalfundsintheregion.MAP21createdthree
distinctprogramsforfederalfunding:
SurfaceTransportationProgram(STP)Ofthethreeprograms,theSTPprogramhas
thegreatestamountoffunding.ARCestimatestheprojectedfundingavailablefor
theregionatapproximately$70millionannually.Sincetheseprogramsare
federallyfunded,a20percentlocalmatchisrequired.Mostofthesefundsare
passedalongtoGDOTforimprovements;however,theARCdoeshavediscretionary
STPfunds.
CongestionMitigationandAirQuality(CMAQ)ThepurposeofCMAQfundsisto
significantlyreduceemissionsandcongestionintheregion.Projectsmustbeableto
demonstrateameasureableemissionsorcongestionbenefitimmediatelyupon
completion.TheARCdistributesthesefundsthroughacallforprojectsthat
requiresapplicationsthatareevaluatedonacompetitivebasis.Thisprogramis
anticipatedtoreceiveapproximately$29millionannually.
TransportationAlternativesProgram(TAP)TheTAPprogramisfocusedprimarily
onexpandingmobilityoptionsfortransit,pedestrianandbicycletravelthatareof
regionalsignificance.TheARCanticipatesapproximately$7.5millionperyear
availableforthisprogram.LiketheCMAQprogram,itsolicitsapplicationsand
awardsfundingfromthisprogramonacompetitivebasis.
13.2 GeorgiaDepartmentofTransportation
GDOTalsooffersprogramsthatcouldpotentiallyfundtherecommended
improvements.Someoftheseprogramsarefederallyfundedand,assuch,maynotbe
eligibleforalocalmatchforARCprograms.TheGDOTprogramsare:
Page58
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
OperationalImprovementProgram(GDOTStateTrafficOperationsOffice)This
programisafederallyfundedprogramthatfocusesonprojectsthatprovide
operationalimprovementsforstaterouteswithminimalenvironmentalandrightof
wayimpacts.
SafetyProgram(GDOTStateTrafficOperationsOffice)Thisprogramisafederally
fundedprogramdesignedtoreducethenumberandseverityoflanedeparture
crashes,improvepedestriansafetyandimprovedesignandoperationof
intersections.
QuickResponseProgramThisprogramisstatefundedanddesignedtoaddress
quickmaintenance,safety,oroperationalconcerns.Atthepresenttime,thereis$1
millionallocatedtoeachGDOTDistricteachyear.Eachquickresponseprojecthasa
$200,000individualcap.
LocalMaintenanceandImprovementGrant(LMIG)LMIGisaprogramfundedby
GDOTforimprovementssuchasengineering,utilityadjustments,resurfacing,
addingturnlanes,etc.A30percentlocalmatchisrequiredforthesefunds.
GDOTMaintenanceProgramGDOTroutinelyperformsmaintenanceactivities
stateroadways.Primaryactivitiesincluderesurfacing,restripingandbridge
maintenance.
GATEwayGrantProgramGATE,anacronymforGeorgiaTransportation
Enhancements,isaGDOTprogramtargetedforroadsideenhancementsand
beautificationaslongastheimprovementsmeetspecificlandscapingrequirements.
Themostanapplicantcanseekunderthisprogramis$50,000.Therewerenogrants
awardedin2012duetoalackoffunds.Therefore,thisfundingsourcewouldbe
somewhatunreliableforimplementationpurposes.
HouseBill202AnotherpotentialfundingopportunityliesinthepassageofHouse
Bill202,whichwaivestherequirementtobalancefundsbycongressionaldistricts
forallinterstateimprovements,certainfreightcorridorprojectsandprojectsof
regionalsignificance.ThelawwasintendedtoprepareGeorgiaforincreasedfreight
flowasaresultofthedeepeningoftheSavannahRiverattheport.
13.3 StateRoadandTollwayAuthority
TheSRTAisresponsibleforadministratingfundsfromtheGeorgiaTransportation
InfrastructureBank(GTIB).WhileSRTAoffersbothaloanandgrantprogramfromthe
GTIBfundingpool,theGTIBloanprogramistypicallypreferredbySRTAtoprovide
transportationprojectstolocalgovernmentsthroughoutthestate.Thesefundscanbe
usedasmatchingfundsforARCfederalfunds.MuchliketheARC,SRTAsolicits
applicationsforGTIBfundingandratesthembasedon:1)mobilityimprovement;2)
matchbeingprovidedagainsttheirfunds;and3)economicdevelopmentpotential.
Page59
October2014
PauldingComprehensiveTransportationPlan
DRAFTAssessmentofCurrentandFutureNeedsReport
13.4 LocalFunds
TherearetwosourcesoflocalfundingfortransportationimprovementswithinPaulding
County,thePauldingSPLOSTProgramandthelocalgeneralfunds.Ofthesetwo,the
SPLOSTprogramisthemostutilizedespeciallyforlargerprojectsgiventhatlocal
fundsareoftenneededformoregeneralpurposessuchasparks,police,etc.The
SPLOSTisaonepercentsalestaxdesignatedtofundtransportationthatisapprovedby
voterseveryfiveyears.Ithasbeeninplacesince1987andissettoexpirein2017.Itis
expectedtobereconsideredforvoterreinstatementin2016.Ifapproved,approximate
fundingofatleast$7millionperyearshouldbeallocatedfortransportationprojects
(CityandCountyshare).
Page60
October2014
PauldingComprehensiveTransportationPlan
DraftFinalReport
AppendixDProjectCostEstimates
AppendixD
Capacity Improvements
PID
RC-1
RC-5
RC-6
RC-9
RC-13
RC-14
RC-19
RC-20
RC-21
Location
Dallas-Acworth Hwy from SR 92 to E Paulding Dr
US 278/SR 6 from SR 61 to SR Bus 6
US 278/SR 6 from SR Bus 6 to Cobb Co. Line
SR 61 from Hiram-Sudie Rd to US 278/SR 6
Dabbs Bridge Rd from SR 61 to Bartow Co. Line
Ridge Road from Dallas Nebo Rd to SR 92
Cedarcrest Rd from 7 Hills Blvd to Cobb Co. Line
Cedarcrest Rd from SR 92 to 7 Hills Blvd
E Paulding Dr from SR 92 to West of Brooks Rackley Road
Base PE
Base ROW
Base CST
Contingency
Base Total
2020 Cost
2031 Cost
$2,453,329
$11,501,500
$24,533,288
$5,547,057
$44,035,174
$55,895,174
$85,776,000
$2,244,425
$29,010,000
$22,444,250
$5,363,806
$59,062,481
$74,733,000
$112,629,000
$2,143,245
$32,625,000
$21,432,450
$5,067,724
$61,268,419
$77,524,000
$119,344,000
$1,903,480
$11,812,500
$19,034,800
$4,907,258
$37,658,038
$73,355,000
$4,376,751
$19,685,000
$43,767,512
$10,878,227
$78,707,490
$2,441,735
$12,597,500
$24,417,350
$6,056,013
$45,512,598
$57,589,000
$88,655,000
$1,926,500
$9,637,500
$19,265,000
$4,506,080
$35,335,080
$44,711,000
$68,829,000
$1,128,490
$5,912,500
$11,284,900
$2,773,689
$21,099,579
$26,698,000
$41,100,000
$1,683,813
$8,832,500
$16,838,130
$3,666,225
$31,020,668
$41,100,000
$60,425,000
Operational Improvements
Project ID
O-1
O-2
O-3
O-4
O-5
O-6
O-7
O-8
O-9
O-10
O-11
O-12
O-13
O-14
O-15
O-16
O-17
O-18
O-19
O-20
O-21
O-22
O-23
O-24
O-25
O-26
O-27
O-28
O-29
O-30
O-31
O-32
O-33
O-34
O-35
O-36
O-37
O-38
O-39
Project Location
SR 120 (Charles Hardy Parkway) - SR Business 6 (Atlanta Highway)
SR 92 (Hiram Acworth Highway) - E. Paulding Drive
SR 120 (Buchanan Highway) - SR 101
US 278/SR 6 (Jimmy Campbell Parkway) - Mount Olivet Loop
SR 61 (Cartersville Highway) - Mount Moriah Road
SR 61 (Cartersville Highway) - Shady Grove Church Road
SR 61 (Villa Rica Highway) - Hart Road
SR 61 (Villa Rica Highway) - Old Villa Rica Road
SR 61 (Villa Rica Highway) - Vernoy Aiken Road
SR 61 (Villa Rica Highway) - Winndale Road
SR 120 (Hiram Sudie Road) - Davis Mill Road
SR 92 (Hiram Acworth Highway) - Old Burnt Hickory Road
Burnt Hickory Road - Brownsville Extension/Stout Parkway
Rosedale Drive - Metromont Road
East Paulding Drive - Brooks Rackley Road
US 278/SR 6 (Jimmy Campbell Parkway) - SR Business 6 (Atlanta Highway)
US 278/SR 6 (Jimmy Campbell Parkway) - Bill Carruth Parkway/SR 120
US 278/SR 6 (Jimmy Campbell Parkway) - Cadillac Parkway
US 278/SR 6 (Jimmy Campbell Parkway) - Old Harris Road
US 278/SR 6 (Jimmy Campbell Parkway) - SR 61 (Villa Rica Highway)
US 278/SR 6 (Jimmy Campbell Parkway) - SR 120 (Buchanan Highway)
West Memorial Drive - SR Business 6 (Buchanan Street)
SR 61 (Confederate Avenue) - SR Business 6 (West Memorial Drive)
East Memorial Drive - Legion Road
SR Business 6 (Merchants Drive) - Legion Road
East Memorial Drive - SR Business 6 (Merchants Drive)
US 278/SR 6 (Jimmy Campbell Parkway) - Hiram Pavillion S
US 278/SR 6 (Jimmy Campbell Parkway) - Hiram Pavillion N
US 278/SR 6 (Jimmy Campbell Parkway) - Depot Drive
SR Business 6 - Old Harris Road
SR Business 6 - Coach Bobby Dodd Road
Macland Road - SR Business 6
SR 101 - Gold Mine Road
SR 101 - Holly Springs Road
SR 101 - Old Yorkville Road
SR 92 (Hiram Acworth Highway) - Rosedale Drive
SR 92 (Hiram Acworth Highway) - Hiram Crossing Shopping Center
SR 92 (Hiram Acworth Highway) - US 278/SR 6 (Jimmy Campbell Parkway)
SR 92 (Hiram Acworth Highway) - Paulding Commons Shopping Center
PE
ROW
CST
Contingency
Total Base Cost
2020 Cost
2031 Cost
$67,878
$212,500
$678,780
$203,634
$1,162,792
$245,073
$550,000
$2,450,730
$720,219
$3,966,022
$7,725,000
$7,725,000
$92,700
$0
$927,000
$92,700
$1,112,400
$1,407,000
$2,168,000
$20,000
$0
$200,000
$20,000
$240,000
$36,135
$75,000
$361,350
$108,405
$580,890
$37,065
$72,500
$370,650
$96,195
$576,410
$157,970
$285,000
$1,579,700
$433,910
$2,456,580
$3,109,000
$4,785,000
$190,820
$860,000
$1,908,200
$532,460
$3,491,480
$4,417,000
$6,801,000
$52,850
$72,500
$528,500
$118,550
$772,400
$978,000
$1,504,000
$424,500
$536,000
$827,000
$33,500
$22,500
$335,000
$33,500
$92,700
$0
$927,000
$92,700
$1,112,400
$1,407,000
$2,168,000
$13,542
$36,500
$135,420
$28,626
$214,088
$270,000
$417,000
$92,700
$0
$927,000
$92,700
$1,112,400
$1,407,000
$2,168,000
$10,500
$34,000
$105,000
$10,500
$160,000
$202,000
$311,000
$14,140
$34,000
$141,400
$14,140
$203,680
$258,000
$397,000
No improvement needed. SR Bus 6 southbound left turn lane (175ft) approach converted to dual left turn wit
$329,660
$687,500
$3,296,600
$828,980
$5,142,740
$13,500
$75,000
$135,000
$13,500
$237,000
$8,250
$32,500
$82,500
$8,250
$131,500
$169,695
$407,500
$1,696,950
$509,085
$2,783,230
$23,250
$85,000
$232,500
$23,250
$364,000
$92,700
$0
$927,000
$92,700
$1,112,400
$1,407,000
$2,168,000
$4,500
$17,500
$45,000
$4,500
$71,500
$91,000
$140,000
$52,355
$2,687,500
$523,550
$111,065
$3,374,470
$4,270,000
$6,573,000
Included in O-24 Intersection Improvement
Included in O-24 Intersection Improvement
$100,182
$194,364
$226,222
$77,570
$345,000
$0
$420,000
$160,000
$1,001,820
$1,943,640
$2,262,221
$775,695
$294,546
$583,092
$635,466
$226,709
$1,741,548
$2,721,096
$3,543,909
$1,239,974
$18,000
$223,380
$107,500
$465,000
$180,000
$2,233,800
$18,000
$670,140
$15,440
$72,127
$32,500
$227,500
$154,395
$721,265
$46,319
$156,880
$520,019
$2,225,000
$5,200,191
$1,501,557
$323,500
$3,592,320
$0
$248,654
$1,177,772
$0
$9,446,767
$0
$2,205,000
$3,392,000
$4,545,000
$6,997,000
$315,000
$1,491,000
$484,000
$2,293,000
$11,953,000
$18,401,000
New Alignments
PID
NC-1
NC-2
NC-3
NC-4
NC-5
Location
West Dallas Bypass SR 61 to US 278/SR 6
E. Dallas Bypass from SR Business 6 to SR 61 (Cartersville Highway)
Hiram Parallel Reliever - South of US 278/SR 6 from SR 92 to Bill Carruth Parkway
Hiram Parallel Reliever - North of US 278/SR 6 from SR 92 to Lake Road
Cedarcrest Road-SR 61 Connector
PE
$2,688,423
$6,482,045
$1,573,752
$1,506,594
$2,306,232
ROW
CST
Contingency
Base Cost Total
$8,150,000
$26,884,226
$5,555,571
$43,278,220
$26,590,000
$64,820,451
$17,364,531
$115,257,027
$21,745,000
$15,737,516
$3,947,201
$43,003,469
$5,550,000
$15,065,937
$3,756,361
$25,878,892
$26,370,000
$23,062,320
$5,938,424
$57,676,976
BicycleandPedestrianImprovements
ProjectID
BP1
BP2
BP3
BP4
BP5
BP6
BP7
BP8
BP9
BP10
BP11
BP12
BP13
BP14
BP15
BP16
BP17
BP18
BP19
BP20
BP21
BP22
BP23
BP24
BP25
BP26
BP27
BP28
BP29
BP30
BP31
BP32
BP33
BP34
BP35
BP36
BP37
BP38
BP39
BP40
BP41
BP42
BP43
BP44
BP45
BP46
BP62
BP47
BP48
BP49
BP50
BP51
BP52
BP53
BP54
BP55
BP56
BP57
BP58
BP59
BP60
BP61
ProjectLocation
BakersBridgeRoadfromRidgeRoadtoCharityDrive
BrownsvilleRoadfromSR92toSweetwaterPass
CedarcrestRoadfromFloydSheltonRoad
CedarcrestRoadfromHarmonyGroveChurchRoadtoArthurHillsDrive
CedarcrestRoadfromCobbCountyLinetoHighcrestDrive
CenterStreetfromSeaboardAvenuetoSR92
ClontsRoadfromWileyDrivetoHalHutchinsElementary
ColbertRoadfromAbneyElementarytoLegacyPointDrive
CowboyPathfromEastPauldingHomeParktoForestHillsDrive
CrossroadsChurchRoadfromWintervilleDrivetoYorkvillePark
DepotDrivefromUS278/SR6(JimmySmithParkway)toRosedaleDrive
DueWestRoadfromDallasAcworthHighwaytoAutumnCreek
EastFosterAvenuefromDallasCityParktoHardeeStreet
EastPauldingDrivefromLostMeadowsDrivetoHopeDrive
EastPauldingDrivefromDallasAcworthHighwaytoMt.TaborPark
GravesRoadfromGravesRoadSpurtoGravesRoad
HiramSudieRoadfromSR61toSouthernOaksDrive
HollySpringsRoadfromWoodwindDrivetoHighway101
LesterDrivefromDallasCityParktoSR6
MaclandRoadfromSR92toSR120(CharlesHardyParkway)
MeinMitchellRoadfromRidgeRoadtoCountryVillageDrive
MetromontRoadfromUS278/SR6toRosedaleDrive
MulberryRockRoadfromDokeCochranRoadtoSR61
MustangDrivefromHeritageWaytoDonbieDrive
NeboRoadfromNeboElementarySchooltoPineShadowsRoad
NeboRoadfromDallasNeboRoadtoSwanDrive
OakStreetfromSR92toSeaboardAvenue
OldVillaRicaRoadfromSR61toIvyTraceLane
OldVillaRicaRoadfromSR61toStationDrive
PineShadowsDrivefromNeboRoadtoSmithFergusonRoad
PineValleyRoadfromTaylorFarmParkWesttoNorthviewLane
PineValleyRoadfromTaylorFarmParkWesttoWinterParkLane
RidgeRoadfromDallasNeboRoadtoAustinBridgeRoad
RidgeRoadfromHughesRoadtoRidgeRunDrive
RidgeRoadfromHughesRoadtoFarmStreet
ScogginsRoadfromSR61toSugarMillDrive
SeaboardAvenuefromTowneParkDrivetoPowderSpringsStreet
SouthMainStreetfromConstitutionBoulevardtoSeaboardDrive
SR101fromCrossroadsChurchRoadtoRunnellRoad
SR61fromOscarWaytoKirKDrive
SR92fromHardyCircletoEastPauldingMiddleSchool
SR92fromCedarcrestRoadtoRoyalSunsetDrive
US278/SR6fromDepotDrivetoCleburneParkway
WaysideLane/ClearCreekDrivefromUS278/SR6toPooleElementarySchool
WestMemorialDrivefromBagbyPathtoPauldingMemorialHospital
WilliamsLakeRoadfromJADobbinsMiddleSchooltoFourOaksDrive
SR6/MerchantsDriveBetweenOldHarrisRoadandHenryHollandDrive
IsleyStamperRoad
EastHiramParkway
MetromontRoad
ThompsonRoad/CoppermineRoad
BillCarruthParkway
WithinthePauldingForestWMASouthofSilverCometTrail
WithinthePauldingForestWMANorthofSilverCometTrail
NorthofHulseyTownRoadBetweenSilverCometFieldandHulseyTownRoad
NearPeggyColeBridgeRoadBetweenGeorgiaParkwayandPeggyColeBridgeTrail
StricklandParkConnectionBetweenWeddingtonRoadandStricklandPark
BetweenGovernmentComplexandSeaboardTrailhead
MulberryRockRoadNearSR61
RidgeRoadBetweenBakersBridgeRoadandSR61
SR61(CartersvilleHwy)BetweenMt.MoriahRoadandDabbsBridgeRoad
CedarcrestRoadBetweenHarmonyGroveChurchRoadandSevenHillsDrive
Category
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
SidewalkSegments
NewTrailheadLocation
NewTrailheadLocation
NewTrailheadLocation
NewTrailheadLocation
NewTrailheadLocation
NewMultiUseTrail
NewMultiUseTrail
NewMultiUseTrail
NewMultiUseTrail
NewMultiUseTrail
NewMultiUseTrail
OnStreetFacility
OnStreetFacility
OnStreetFacility
OnStreetFacility
PEYR
PE
ROWYR
ROW
CSTYR
CST
Contingency
Total,YOE
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
$16,000
$12,000
$16,000
$38,000
$20,000
$21,000
$10,000
$25,000
$13,000
$14,000
$13,000
$8,000
$13,000
$91,000
$25,000
$19,000
$16,000
$57,000
$8,000
$80,000
$2,000
$30,000
$44,000
$9,000
$11,000
$15,000
$19,000
$15,000
$21,000
$8,000
$9,000
$36,000
$33,000
$9,000
$16,000
$20,000
$5,000
$15,000
$9,000
$11,000
$24,000
$15,000
$66,000
$12,000
$12,000
$19,000
$82,000
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
$184,000
$145,000
$191,000
$441,000
$237,000
$243,000
$112,000
$290,000
$158,000
$164,000
$151,000
$92,000
$158,000
$1,059,000
$290,000
$217,000
$184,000
$665,000
$92,000
$934,000
$26,000
$349,000
$513,000
$105,000
$132,000
$171,000
$224,000
$178,000
$250,000
$99,000
$105,000
$421,000
$388,000
$105,000
$191,000
$230,000
$59,000
$171,000
$105,000
$125,000
$283,000
$171,000
$770,000
$138,000
$138,000
$217,000
$962,000
$18,000
$14,000
$19,000
$44,000
$23,000
$24,000
$11,000
$29,000
$16,000
$16,000
$15,000
$9,000
$16,000
$105,000
$29,000
$21,000
$18,000
$66,000
$9,000
$92,000
$3,000
$34,000
$51,000
$10,000
$13,000
$17,000
$22,000
$18,000
$25,000
$10,000
$10,000
$42,000
$38,000
$10,000
$19,000
$23,000
$6,000
$17,000
$10,000
$12,000
$28,000
$17,000
$760,000
$14,000
$14,000
$21,000
$95,000
$218,000
$171,000
$226,000
$523,000
$280,000
$288,000
$133,000
$344,000
$187,000
$194,000
$179,000
$109,000
$187,000
$1,255,000
$344,000
$257,000
$218,000
$788,000
$109,000
$1,106,000
$31,000
$413,000
$608,000
$124,000
$156,000
$203,000
$265,000
$211,000
$296,000
$117,000
$124,000
$499,000
$459,000
$124,000
$226,000
$273,000
$70,000
$203,000
$124,000
$148,000
$335,000
$203,000
$1,596,000
$164,000
$164,000
$257,000
$1,139,000
2016
2016
2016
2016
2016
2016
2016
2016
2016
2016
$51,000
$51,000
$57,000
$9,000
$17,000
$12,000
$303,000
$1,055,000
$1,090,000
$174,000
2018
2018
2018
2018
2018
2018
2018
2018
2018
2018
$834,000
$840,000
$927,000
$146,000
$272,000
$202,000
$0
$0
$0
$0
2020
2020
2020
2020
2020
2020
2020
2020
2020
2020
$596,000
$599,000
$663,000
$102,000
$196,000
$145,000
$3,540,000
$12,337,000
$12,754,000
$2,030,000
$57,000
$57,000
$63,000
$10,000
$19,000
$14,000
$349,000
$1,217,000
$1,259,000
$200,000
$1,538,000
$1,547,000
$1,710,000
$267,000
$504,000
$373,000
$4,192,000
$14,609,000
$15,103,000
$2,404,000
PauldingComprehensiveTransportationPlan
DraftFinalReport
AppendixEProjectPrioritization
AppendixE
Multimodal Travel
Land Use
Safety
Improvement Type
Roadway Capacity
Operational Improvements
New Roadways
New Transit Service
New Park and Ride Lot
Vanpool Loading Area
New Vanpool Service
Human Service Transportation
Sidewalk Segments/Ped Crossing
New Trailheads
New Multi-Use Trails
On-Street Facilities
Access Management
Bridge Repair
Pavement Maintenance
2015 LOS
2030 LOS
2030 V/C
X
X
X
X
X
X
X
X
X
X
Roadway Capacity
Operational Improvements
New Roadways
New Transit Service
New Park and Ride Lot
Vanpool Loading Area
New Vanpool Service
Human Service Transportation
Sidewalk Segments/Ped Crossing
New Trailheads
New Multi-Use Trails
On-Street Facilities
Access Management
Bridge Repair
Pavement Maintenance
Promotes Travel
Promotes Bicycle and
Demand Management
Ped Travel
Serves Employment
Centers
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Crash Rates
Policy Statement
Policy Statement
X
X
X
X
Policy Statement
System Preservation
Improvement Type
Promotes Transit
Ridership
Promotes State of
Good Repair
Projected 2030
Volumes
X
X
X
X
X
X
X
X
Freight Mobility
Truck Volumes
X
X
Public Comment
Env Complexity
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Policy Statement
Policy Statement
X
X
X
X
X
X
Policy Statement
Constructability
Location
US 278/SR 6 from SR 61 to SR Business 6
SR Bus 6 from Memorial Drive to US 278/SR 6 (E. of Dallas)
Dallas-Acworth Hwy/Memorial Drive from E. Paulding Drive to SR Bus 6
Dallas-Acworth Highway from SR 92 to E. Paulding Drive
SR Bus 6 from US 278/SR 6 (W. of Dallas) to Memorial Drive
SR 61 (Villa Rica Highway) from Douglas County Line to Ridge Road
SR 61 (Villa Rica Highway) from Hiram-Sudie Road to US 278/SR 6
SR 101/113 from Carroll County Line to SR 120 (Buchanon Highway)
Dabbs Bridge Road from SR 61 (Cartersville Highway) to Bartow County Line
Ridge Road from Dallas Nebo Road to SR 92
Sweetwater Church Road from Douglas County Line to SR 92
SR 61 (Cartersville Highway) from Mt. Moriah Road to Dabbs Bridge Road
Nebo Road from Dallas Nebo Road to SR 92
East Paulding Drive from SR 92 to SR 120 (Charles Hardy Parkway)
Bakers Bridge Road from Douglas County Line to Ridge Road
Cedarcrest Road from Seven Hills Boulevard to Cobb County Line
Cedarcrest Road from SR 92 to Seven Hills Boulevard
Hiram-Sudie Road from SR 61 (Villa Rica Highway) to SR 92
SR 61 (Cartersville Highway) from Dabbs Bridge Road to Bartow County Line
US 278/SR 6 from SR Business 6 to Cobb County Line
SR 61 (Cartersville Highway) from SR Business 6 to Old Cartersville Road
Improvement
Widen to 6 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
Widen to 6 lanes
Widen to 4 lanes
Overall Score
36
30
32
31
33
25
28
6
11
24
14
6
21
12
16
12
14
20
18
37
26
Operational/Intersection Improvements
ID
Location
O-37
SR 92 (Hiram Acworth Highway) - Hiram Crossing Shopping Center
O-19
US 278/SR 6 (Jimmy Campbell Parkway) - Old Harris Road
O-16
US 278/SR 6 (Jimmy Campbell Parkway) - SR Business 6 (Atlanta Highway)
O-35
SR 101 - Old Yorkville Road
O-36
SR 92 (Hiram Acworth Highway) - Rosedale Drive
O-38
SR 92 (Hiram Acworth Highway) - US 278/SR 6 (Jimmy Campbell Parkway)
O-28
US 278/SR 6 (Jimmy Campbell Parkway) - Hiram Pavillion N
O-31
SR Business 6 - Coach Bobby Dodd Road
O-1
SR 120 (Charles Hardy Parkway) - SR Business 6 (Atlanta Highway)
O-26
East Memorial Drive - SR Business 6 (Merchants Drive)
O-27
US 278/SR 6 (Jimmy Campbell Parkway) - Hiram Pavillion S
O-15
East Paulding Drive - Brooks Rackley Road
O-18
US 278/SR 6 (Jimmy Campbell Parkway) - Cadillac Parkway
O-17
US 278/SR 6 (Jimmy Campbell Parkway) - Bill Carruth Parkway/SR 120
O-22
West Memorial Drive - SR Business 6 (Buchanan Street)
O-24
East Memorial Drive - Legion Road
O-30
SR Business 6 - Old Harris Road
O-20
US 278/SR 6 (Jimmy Campbell Parkway) - SR 61 (Villa Rica Highway)
O-29
US 278/SR 6 (Jimmy Campbell Parkway) - Depot Drive
O-11
SR 120 (Hiram Sudie Road) - Davis Mill Road
O-25
SR Business 6 (Merchants Drive) - Legion Road
O-3
SR 120 (Buchanan Highway) - SR 101
O-6
SR 61 (Cartersville Highway) - Shady Grove Church Road
O-33
SR 101 - Gold Mine Road
O-13
Burnt Hickory Road - Brownsville Extension/Stout Parkway
O-9
SR 61 (Villa Rica Highway) - Vernoy Aiken Road
O-7
SR 61 (Villa Rica Highway) - Hart Road
O-23
SR 61 (Confederate Avenue) - SR Business 6 (West Memorial Drive)
O-12
SR 92 (Hiram Acworth Highway) - Old Burnt Hickory Road
O-14
Rosedale Drive - Metromont Road
O-8
SR 61 (Villa Rica Highway) - Old Villa Rica Road
O-32
Macland Road - SR Business 6
O-2
SR 92 (Hiram Acworth Highway) - E. Paulding Drive
O-10
SR 61 (Villa Rica Highway) - Winndale Road
O-21
US 278/SR 6 (Jimmy Campbell Parkway) - SR 120 (Buchanan Highway)
O-5
SR 61 (Cartersville Highway) - Mount Moriah Road
O-4
US 278/SR 6 (Jimmy Campbell Parkway) - Mount Olivet Loop
O-34
SR 101 - Holly Springs Road
Improvement
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Overall Score
25
21
22
3
26
29
22
18
28
15
22
10
21
27
8
13
17
28
25
8
18
8
7
9
11
9
14
20
16
13
13
23
23
13
17
6
14
13
New Roadways
ID
Location
NC-3
Hiram Parallel Reliever - South of US 278/SR 6 from SR 92 to Bill Carruth Parkway
NC-2
E. Dallas Bypass from SR Business 6 to SR 61 (Cartersville Highway)
NC-1
W. Dallas Bypass from SR 61 (Cartersville Highway) to US 278/SR 6
NC-5
Cedarcrest Road-SR 61 Connector
NC-4
Hiram Parallel Reliever - North of US 278/SR 6 from SR 92 to Lake Road
Improvement
New Roadway
New Roadway
New Roadway
New Roadway
New Roadway
Overall Score
26
22
23
9
26
Previous Score
36
36
33
34
31
26
26
31
22
18
32
12
21
20
13
10
16
7
13
25
14
Base PE
$2,143,245
$2,244,425
$1,467,970
$2,459,135
$2,881,720
$1,903,480
$734,455
$1,078,661
$2,441,735
$3,146,945
$2,857,570
$1,763,260
$2,264,740
$2,258,070
$1,697,810
$1,182,990
$833,815
$2,348,875
$3,126,132
$1,845,372
$2,630,626
PE
Base ROW
$32,625,000
$29,010,000
$15,412,500
$9,823,500
$34,245,000
$11,812,500
$7,920,000
$6,825,000
$12,597,500
$16,185,000
$19,242,500
$8,522,500
$9,755,000
$11,332,500
$7,995,000
$6,140,000
$4,625,000
$11,397,500
$19,685,000
$10,135,000
$16,150,000
ROW
Base CST
$21,432,450
$22,444,250
$14,679,700
$24,591,350
$28,817,200
$19,034,800
$7,344,550
$10,786,612
$24,417,350
$31,469,450
$28,575,700
$17,632,600
$22,647,400
$22,580,700
$16,978,100
$11,829,900
$8,338,150
$23,488,750
$31,261,324
$18,453,716
$26,306,264
CST
Contingency
$5,067,724
$5,363,806
$3,059,666
$5,805,901
$7,100,766
$4,907,258
$1,688,900
$2,679,828
$6,056,013
$7,848,468
$7,200,818
$3,761,890
$5,104,189
$5,550,378
$4,007,967
$2,923,729
$1,795,903
$5,668,890
$7,667,171
$4,212,805
$6,330,732
Base Total
$61,268,419
$59,062,481
$34,619,836
$42,679,886
$73,044,686
$37,658,038
$17,687,905
$21,370,101
$45,512,598
$58,649,863
$57,876,588
$31,680,250
$39,771,329
$41,721,648
$30,678,877
$22,076,619
$15,592,868
$42,904,015
$61,739,627
$34,646,893
$51,417,622
$881,660,149
Cost Rank
20
19
7
12
22
9
2
3
15
18
17
6
10
11
5
4
1
13
21
8
16
Contingency
Total Base Cost
$1,501,557
$9,446,767
$143,130
$1,250,440
$209,000
$3,245,500
$156,880
$1,177,772
$0
$0
$635,466
$3,123,909
$18,000
$323,500
$720,219
$3,966,022
$294,546
$1,396,548
$583,092
$2,721,096
Cost Rank
35
25
32
23
2
3
31
12
34
27
30
36
5
9
4
37
39
13
24
8
38
10
26
1
6
14
29
33
20
7
17
28
18
19
21
15
16
11
$520,019
$67,710
$209,000
$72,127
$2,225,000
$362,500
$737,500
$227,500
$5,200,191
$677,100
$2,090,000
$721,265
$226,222
$18,000
$245,073
$100,182
$194,364
$0
$107,500
$550,000
$0
$0
$2,262,221
$180,000
$2,450,730
$1,001,820
$1,943,640
$8,250
$13,500
$4,500
$32,500
$75,000
$17,500
$82,500
$135,000
$45,000
$8,250
$13,500
$4,500
$131,500
$237,000
$71,500
$23,250
$77,570
$13,542
$85,000
$160,000
$36,500
$232,500
$775,695
$135,420
$23,250
$226,709
$28,626
$364,000
$1,239,974
$214,088
$20,000
$88,985
$0
$142,500
$200,000
$889,850
$20,000
$226,955
$10,500
$33,500
$108,695
$52,355
$92,700
$14,140
$52,850
$124,502
$92,700
$92,700
$92,700
$37,065
$36,135
$15,440
$34,000
$22,500
$680,000
$2,687,500
$0
$34,000
$72,500
$260,000
$0
$0
$0
$72,500
$75,000
$32,500
$105,000
$335,000
$1,086,950
$523,550
$927,000
$141,400
$528,500
$1,245,015
$927,000
$927,000
$927,000
$370,650
$361,350
$154,395
$10,500
$33,500
$286,085
$111,065
$92,700
$14,140
$118,550
$373,505
$92,700
$92,700
$92,700
$96,195
$108,405
$46,319
$240,000
$1,348,290
$0
$160,000
$424,500
$2,161,730
$3,374,470
$1,112,400
$203,680
$772,400
$2,003,022
$1,112,400
$1,112,400
$1,112,400
$576,410
$580,890
$248,654
$45,453,262
PE
$1,506,594
$1,573,752
$6,482,045
$2,664,662
$6,605,737
ROW
$5,550,000
$21,745,000
$26,590,000
$11,510,000
$26,370,000
CST
$15,065,937
$15,737,516
$64,820,451
$26,646,617
$66,057,373
Contingency
$3,756,361
$3,947,201
$17,364,531
$631,628
$17,366,106
Cost Rank
1
3
5
2
6
$270,675,308
$351,928,320
$259,056,521
$26,651,554
$3,846,352
$14,955,356
Operational Improvements
Congestion and Delay
Project ID
O-1
O-2
O-3
O-4
O-5
O-6
O-7
O-8
O-9
O-10
O-11
O-12
O-13
O-14
O-15
O-16
O-17
O-18
O-19
O-20
O-21
O-22
O-23
O-24
O-25
O-26
O-27
O-28
O-29
O-30
O-31
O-32
O-33
O-34
O-35
O-36
O-37
O-38
O-39
Project Location
Land Use
Category
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Operational
Safety
2014
Delay
Score
2024 No Build
Delay
Score
Total
Delay
Score
Serves High
Growth Area
Score
Serves Paulding
Employment Area
Score
Along
Commuter
Route
Score
56.9
49.2
25.3
39.4
18.3
24.9
284
48.4
23.1
41.1
21.3
158.7
34.5
17.5
38.5
35.5
63.2
38.2
23.9
66.1
33.9
11.6
47.7
19
80.9
21.4
28.1
23.8
40
37.3
183.1
36.2
15.5
60.6
10.7
248.3
84.7
60.4
42.3
5
5
3
3
1
3
5
5
1
3
1
5
3
1
3
3
5
3
3
5
3
1
5
1
5
1
3
1
3
3
5
3
1
5
1
5
5
5
3
83.9
106.8
59.5
140.4
24.8
32.9
637.3
126.5
36.3
80.8
38.5
900
43.4
34.6
89.5
49.6
112.4
86.6
49.8
108.2
38.7
12.4
57.6
34.7
246.8
30
62.4
80.7
96.7
462.4
900
52
24
293
11.8
900
900
123.5
572.9
1
1
1
2
0
0
2
2
0
1
0
2
1
0
1
1
2
1
1
2
1
0
1
0
2
0
1
1
1
2
2
1
0
2
0
2
2
2
2
6
6
4
5
1
3
7
7
1
4
1
7
4
1
4
4
7
4
4
7
4
1
6
1
7
1
4
2
4
5
7
4
1
7
1
7
7
7
5
High
Medium
Low
Low
Low
Low
Medium
Medium
Medium
Medium
Medium
High
High
High
Medium
Medium
High
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Medium
High
High
High
Medium
Medium
Medium
Low
Low
Low
High
High
High
High
3
2
0
0
0
0
2
2
2
2
2
3
3
3
2
2
3
2
2
2
2
2
2
2
2
2
3
3
3
2
2
2
0
0
0
3
3
3
3
High
Medium
Low
Low
Low
Low
Low
Low
Low
Low
Low
Low
Low
High
Medium
High
High
High
High
High
Medium
Medium
High
High
High
High
High
High
High
High
High
High
Medium
Low
Low
High
High
High
High
3
2
0
0
0
0
0
0
0
0
0
0
0
3
2
3
3
3
3
3
2
2
3
3
3
3
3
3
3
3
3
3
2
0
0
3
3
3
3
Yes
Yes
No
No
No
No
No
No
No
No
No
Yes
No
No
No
Yes
Yes
Yes
Yes
Yes
Yes
No
No
Yes
No
Yes
Yes
Yes
Yes
Yes
No
Yes
No
No
No
Yes
Yes
Yes
Yes
1
1
0
0
0
0
0
0
0
0
0
1
0
0
0
1
1
1
1
1
1
0
0
1
0
1
1
1
1
1
0
1
0
0
0
1
1
1
1
Scoring Template
High
High
Low
Medium
Low
Low
Low
Low
Medium
Medium
Medium
Low
Low
Medium
Low
High
High
High
High
High
Low
Low
High
Low
Low
Low
High
High
High
Medium
Medium
High
Medium
Medium
Low
High
High
High
High
6
6
1
3
1
1
1
1
3
3
3
1
1
3
1
6
6
6
6
6
1
1
6
1
1
1
6
6
6
3
3
6
3
3
1
6
6
6
6
2015
Volumes
Score
2030
Volumes
Score
Total Major
Corr Score
38200
13800
9500
24700
15300
10300
16000
16000
16000
16000
16900
14200
6000
5000
7900
39400
39400
39400
39400
39400
28300
14200
14200
21200
16100
21200
36800
36800
36800
16100
16100
16100
9900
9900
9900
19000
19000
36800
18500
3
1
1
3
2
1
2
2
2
2
2
1
1
1
1
3
3
3
3
3
3
1
1
3
2
3
3
3
3
2
2
2
1
1
1
2
2
3
2
47500
28000
13900
33500
20700
12500
24300
24300
24300
24300
20700
26900
7400
6500
10300
52800
52800
52800
52800
52800
37500
18000
18000
25700
22000
25700
47300
47300
47300
22000
22000
22000
14800
14800
14800
34300
34300
47300
35200
2
1
0
1
0
0
1
1
1
1
0
1
0
0
0
2
2
2
2
2
2
0
0
1
1
1
2
2
2
1
1
1
0
0
0
2
2
2
2
5
2
1
4
2
1
3
3
3
3
2
2
1
1
1
5
5
5
5
5
5
1
1
4
3
4
5
5
5
3
3
3
1
1
1
4
4
5
4
Advisory Committee
Score
Support (Votes)
Safety
Hot Spot Analysis
High = 6
Medium = 3
Low = 1
Delay
2014 Delay
Top 1/3 = 5, Middle 1/3 = 3, Bottom 1/3 = 1
2024 Delay
Top 1/3 = 2, Middle 1/3 = 1, Bottom 1/3 = 0
Total P&C
Support Score
TOTAL
SCORE
5
6
4
0
2
1
2
0
0
1
1
4
4
2
0
0
3
0
0
9
1
2
4
3
8
15
1
3
3
0
1
6
4
5
1
2
2
12
6
2
2
2
0
1
0
1
0
0
0
0
2
2
1
0
0
1
0
0
2
0
1
2
1
2
2
0
1
1
0
0
2
2
2
0
1
1
2
2
4
4
2
2
2
2
1
0
0
1
0
2
2
2
0
1
2
0
0
4
2
1
2
1
2
3
0
2
3
0
0
4
2
2
0
2
1
4
3
28
23
8
14
6
7
14
13
9
13
8
16
11
13
10
22
27
21
21
28
17
8
20
13
18
15
22
22
25
17
18
23
9
13
3
26
25
29
25
2
2
0
2
1
2
0
0
0
1
0
0
0
1
0
1
1
0
0
2
2
0
0
0
0
1
0
1
2
0
0
2
0
0
0
1
0
2
1
Score
Public Comment
Public Comment
Land Use
Serves High Growth Area High = 3
Medium = 2
Low = 0
Serves Employment Centers
Along Commuter Routes Yes =1; No =0
Serves Paulding Emp Centers
High = 3
Medium = 2
Low = 0
5
5
1
6
2
5
1
1
0
2
0
1
1
2
1
2
2
1
1
4
6
0
1
1
0
3
1
2
3
1
1
5
1
1
1
2
1
6
2
Public Input
(Votes from 8/14
Meeting)
Major Corridors
2015 Volumes
Top 1/3 = 3, Middle 1/3 = 2, Bottom 1/3 = 1
2030 Volumes
Top 1/3 = 2, Middle 1/3 = 1, Bottom 1/3 = 0
Project Location
Category
Land Use
Safety
Freight Mobility
Constructability
Advisory
High
Existing
Projected
Total
2015
2030
Total
Public Input
TOTAL P&C
Total
Serves High
Along
Serves
TOTAL
Committee
2015
2030
2030
2040
Environmental
Total
Accident Score (2015) Score
2030 Score Major Corr Truck Score Truck Score Freight
Score
Score
Score
Score
Score
Score
Score
Score (Votes from Score SUPPORT
Score
Congestion Growth
Commuter
Paulding
LAND USE
Support
LOS
LOS
V/C
V/C
Complexity
Score
Locations
Volumes
Volumes
Score
Volumes
Volumes
Score
8/14 Meeting)
SCORE
Score
Area
Route
Employment
SCORE
(Votes)
RC-1
0.84
1.07
Yes
Yes
Low
High
13
No
31
1.07
1.09
10
Yes
Yes
Medium
Medium
7
7
2
2
17800
21000
1300
5
5
13300
16000
1100
Widen to 4 lanes
Widen to 4 lanes
RC-2
900
1200
No
32
RC-3
Widen to 4 lanes
1.35
1.62
13
Yes
No
High
High
18700
23500
100
200
Yes
33
RC-4
Widen to 4 lanes
1.08
1.24
Yes
No
High
High
11900
16300
300
500
Yes
30
RC-5
Widen to 6 lanes
1.04
1.17
Yes
Yes
High
High
No
36
0.96
Yes
Yes
High
High
7
7
2
2
1100
Widen to 6 lanes
48900
45800
5
5
800
RC-6
36200
34600
1200
1600
15
No
37
RC-7
Widen to 4 lanes
0.64
0.88
No
No
Low
Low
5800
11200
200
400
No
RC-8
0.93
0.99
Yes
Low
Medium
17600
18000
1
2
6
7
1700
No
25
5
5
1400
RC-9
RC-10
Widen to 4 lanes
Widen to 4 lanes
Widen to 4 lanes
RC-11
RC-12
1.08
1.22
Yes
No
Low
Medium
13300
15400
900
1100
No
28
1.06
1.1
Yes
No
Low
High
11000
15900
300
400
No
26
Widen to 4 lanes
0.72
0.95
No
No
Low
Low
No
0.98
1.14
No
No
Low
Low
1
4
0
1
300
11600
17200
Widen to 4 lanes
1
3
200
6500
13000
400
600
No
18
RC-13
Widen to 4 lanes
0.87
1.11
Yes
No
Low
Low
6300
9400
200
200
No
11
RC-14
Widen to 4 lanes
1.18
1.3
Yes
No
Low
High
10600
18200
100
300
No
24
RC-15
Widen to 4 lanes
1.16
1.3
11
Yes
No
Low
Medium
12700
16300
100
200
Yes
21
RC-16
Widen to 4 lanes
0.95
1.04
Yes
No
Low
Medium
10900
13800
200
200
13
Yes
16
RC-17
Widen to 4 lanes
1.20
1.34
Yes
No
Low
Low
9300
14000
200
300
No
14
RC-18
Widen to 4 lanes
1.06
1.19
Yes
No
Low
Medium
2
4
300
No
20
1
1
16000
15700
200
RC-19
1
3
RC-20
RC-21
RC-22
0.89
0.99
Yes
No
Low
Low
10400
12200
200
200
No
12
0.78
0.9
Yes
No
Medium
Low
12200
15600
200
300
11
No
14
Widen to 4 lanes
Widen to 4 lanes
0.93
1.02
Yes
No
Medium
Medium
9600
12600
100
200
Yes
12
Bobo Road from Dallas Acworth Highway to SR 120 (Charles Hardy Parkway)
Widen to 4 lanes
1.00
1.13
Yes
No
Medium
Low
10800
14300
300
200
Yes
15
Environmental Constraints
Yes = 0; No=1
Widen to 4 lanes
New Roadways
Congestion and Delay
Project ID
NC-1
NC-2
NC-3
NC-4
NC-5
NC-6
Project Location
Land Use
Safety
Freight Mobility
New Roadway
New Roadway
New Roadway
New Roadway
New Roadway
New Roadway
2015 LOS on
Parallel
Roadways
Score
2030 LOS on
Parallel
Roadways
Score
TOTAL CONGESTION
SCORE
Serves High
Growth Area
Score
Serves
Employment
Centers
Score
TOTAL LAND
USE SCORE
Crashes Along
Parallel Routes
Score
Existing (2015)
Volumes
Score
Projected 2030
Volumes
Score
TOTAL MAJOR
CORR SCORE
Score
Score
Medium
Medium
Medium
Medium
Low
Medium
2
2
2
2
1
2
High
High
Medium
Medium
Low
Medium
2
2
1
1
0
1
4
4
3
3
1
3
Medium
Medium
High
High
High
Medium
2
2
3
3
3
2
High
High
High
High
Low
Low
3
3
3
3
0
0
5
5
6
6
3
2
High
High
High
High
Low
Medium
3
3
3
3
1
2
Medium
Medium
High
High
Low
Medium
2
2
3
3
1
2
Medium
Medium
High
High
Low
Medium
1
1
2
2
0
1
3
3
5
5
1
3
Medium
Medium
High
High
Low
High
3
3
5
5
1
5
Medium
Medium
High
High
Low
High
1
1
2
2
0
2
Scoring Template
Congestion
Qualitative Assessment based on LOS
2015 V/C
High = 3; Med. = 2; Low = 1
2030 LOS
High = 2; Med. = 1; Low = 0
Land Use
Serves High Growth Area
High = 3
Medium = 2
Low = 0
High = 3
Medium = 2
Low = 0
Safety
Qualitative Hot Spot Analysis
High = 3
Medium = 2
Low = 1
4
4
7
7
1
7
6
10
1
0
2
4
Score
Score
TOTAL P&C
SUPPORT SCORE
Environmental
Complexity
Score
TOTAL
SCORE
2
2
0
0
1
1
20
10
10
8
9
4
2
1
1
1
1
0
4
3
1
1
2
1
Yes
Yes
No
No
Yes
Yes
0
0
1
1
0
0
23
22
26
26
9
18
Major Corridors
Qualitative Assessment of Volumes
2015 Volume
High = 3; Med. = 2; Low = 1
2030 Volume
High = 2; Med. = 1; Low = 0
Freight
Qualitative Assessment of Truck Volumes
2015 Volume
High = 5; Med. = 3; Low = 1
2030 Volume
High = 2; Med. = 1; Low = 0
Public Comment
Public Comment
Top 1/3 Vote Getters = 2
Middle Vote Getters = 1
Others = 0
Advisory Committee
Top 1/3 Vote Getters = 2
Middle Vote Getters = 1
Others = 0
NC-5
Old Cartersville Road/Ivey Gulledge Road from SR 61 to Seven Hills Boulevard
SR 61 North from Old Cartersville Road to Dabbs Bridge Road
NC-6
SR 61 South from Scoggins Road to US 278/SR 6
US 278/SR 6 from SR 61 to SR Business 6 (W)
Constructability
Category
Environmental Constraints
No = 1; Yes=0
BP Sidewalk PedCrossings
Multimodal Travel
Project ID
BP-1
BP-2
BP-3
BP-4
BP-5
BP-6
BP-7
BP-8
BP-9
BP-10
BP-11
BP-12
BP-13
BP-14
BP-15
BP-16
BP-17
BP-18
BP-19
BP-20
BP-21
BP-22
BP-23
BP-24
BP-25
BP-26
BP-27
BP-28
BP-29
BP-30
BP-31
BP-32
BP-33
BP-34
BP-35
BP-36
BP-37
BP-38
BP-39
BP-40
BP-41
BP-42
BP-43
BP-44
BP-45
BP-46
BP-47
BP-48
Project Location
Land Use
Major Transportation
Corridors
Safety
Category
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Sidewalk Segments
Pedestrian Crossing
SCORE
2010 Low
Income
SCORE
2010 Population
Density
SCORE
2010 Employment
Density
SCORE
Promotes Transit
Ridership
SCORE
TOTAL
MULTIMODAL
SCORE
SCORE
Connects to
Silver Comet
Trail
SCORE
TOTAL LAND
USE SCORE
Pedestrian Accident
Locations
SCORE
Functional Classification
Advisory Committee
Support (Votes)
SCORE
Public Comment
SCORE
TOTAL SCORE
Low
Low
Low
Low
Medium
Medium
Medium
Low
Medium
Medium
Medium
Low
High
Medium
Medium
Medium
Low
Medium
High
Medium
Medium
Medium
Medium
High
Low
Low
Medium
High
High
Low
Medium
Medium
Low
Low
Low
Low
Medium
High
Medium
High
Medium
Medium
Medium
Medium
High
Medium
High
Medium
1
1
1
1
3
3
3
1
3
3
3
1
5
3
3
3
1
3
5
3
3
3
3
5
1
1
3
5
5
1
3
3
1
1
1
1
3
5
3
5
3
3
3
3
5
3
5
3
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Low
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Low
Medium
Medium
Medium
Medium
Low
High
Medium
Medium
Medium
High
High
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Medium
High
Low
High
Medium
Medium
Medium
Low
High
Medium
Medium
Medium
3
3
3
3
3
3
3
3
3
1
3
3
3
3
3
3
3
1
3
3
3
3
1
5
3
3
3
5
5
3
3
3
3
3
3
3
3
5
1
5
3
3
3
1
5
3
3
3
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Medium
High
Low
Medium
High
Medium
High
High
Medium
Medium
Low
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Medium
Low
Medium
High
Medium
Medium
Low
Medium
Medium
Medium
Medium
2
2
2
2
2
2
2
2
3
0
2
3
2
3
3
2
2
0
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
0
2
3
2
2
0
2
2
2
2
Low
Low
Low
Low
Low
High
Low
Low
Medium
Low
High
Medium
Medium
Medium
Medium
Medium
High
Low
Medium
Medium
Low
High
Low
Medium
Low
Medium
High
Low
Low
Low
Low
Low
Low
Low
Low
Low
High
Medium
Low
Medium
Medium
Medium
High
Low
High
Low
Medium
Low
0
0
0
0
0
3
0
0
2
0
3
2
2
2
2
2
3
0
2
2
0
3
0
2
0
2
3
0
0
0
0
0
0
0
0
0
3
2
0
2
2
2
3
0
3
0
2
0
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
1
0
0
0
0
0
6
6
6
6
8
11
8
6
11
4
11
9
12
11
11
10
9
4
12
10
8
12
6
14
6
8
11
12
12
6
8
8
6
6
6
6
11
14
4
14
11
10
12
4
15
8
12
8
High
High
High
High
High
High
High
Medium
Medium
Medium
High
Medium
High
Medium
Medium
High
High
Medium
Medium
Medium
High
Medium
Medium
Medium
High
High
Medium
Medium
Medium
High
Medium
Medium
High
High
High
Medium
Medium
Medium
Low
High
Medium
Medium
Medium
Low
Medium
Medium
High
Medium
3
3
3
3
3
3
3
2
2
2
3
2
3
2
2
3
3
2
2
2
3
2
2
2
3
3
2
2
2
3
2
2
3
3
3
2
2
2
0
3
2
2
2
0
2
2
2
0
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
0
0
0
0
0
0
0
0
0
0
2
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
3
3
3
3
3
3
3
2
2
2
5
2
3
2
2
3
3
2
2
2
3
2
2
2
3
3
2
2
2
3
2
2
3
3
3
2
2
2
0
3
2
2
2
0
2
2
2
0
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No
Yes
No
No
No
Yes
No
0
3
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
3
0
0
3
0
0
0
3
0
1
2
2
2
2
0
0
0
0
0
0
1
0
2
2
0
2
0
0
2
0
0
1
0
1
1
0
0
0
0
1
1
2
2
2
2
0
0
2
2
2
2
3
0
2
0
2
0
0
0
0
0
0
0
0
0
0
0
3
0
1
1
1
0
0
1
1
1
0
3
1
1
0
0
0
2
1
0
1
1
0
0
0
0
0
3
0
1
0
0
0
1
2
4
7
0
0
0
0
0
0
0
0
0
0
0
3
0
1
1
1
0
0
1
1
1
0
3
1
1
0
0
0
2
1
0
1
1
0
0
0
0
0
3
0
1
0
0
0
1
2
3
3
0
Yes
No
No
Yes
Yes
No
No
No
No
No
Yes
No
No
No
No
Yes
No
Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
Yes
No
Yes
Yes
Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
1
0
0
1
1
0
0
0
0
0
1
0
0
0
0
1
0
1
0
0
0
1
0
0
0
0
0
0
0
0
1
0
1
1
1
0
0
0
0
0
0
0
0
0
0
1
0
0
1
0
0
1
1
0
0
0
0
0
4
0
1
1
1
1
0
2
1
1
0
4
1
1
0
0
0
2
1
0
2
1
1
1
1
0
0
3
0
1
0
0
0
1
2
4
3
0
11
14
11
12
14
14
11
8
13
6
20
12
16
16
16
14
14
8
15
15
11
18
10
17
10
12
13
16
15
9
13
12
12
12
12
10
13
19
6
23
15
14
20
5
21
14
22
8
Multimodal Travel
2010 Zero Car
2010 Low Income
2010 Pop. Density
2010 Emp. Density
Land Use
Serves High Growth Area
High = 3
Medium = 2
Low = 0
Safety
Pedesrtrian Crashes
Yes = 3; No = 0
Major Corridors
Functional Classification
Principal Arterial = 3
Minor Arterial = 2
Collector = 1
Local = 0
Public Support/Comment
Public Support
Yes = 1; No=0
Advisory Committee
3 or More Votes = 3
2 Votes = 2
1 Vote = 1
Not Recommended = 0
Project ID
BP-52
BP-53
BP-54
BP-55
BP-56
BP-57
Project Location
Land Use
Category
SCORE
2010 Low
Income
SCORE
Low
Low
Low
Low
Low
High
1
1
1
1
1
5
Low
Low
Low
Low
Medium
High
1
1
1
1
3
5
Multimodal Travel
2010 Zero Car
High = 5; Medium = 3; Low = 1
2010 Low Income High = 5; Medium = 3; Low = 1
2010 Pop. Density High = 5; Medium = 3; Low = 1
2010 Population
Density
Low
Low
Low
Low
Medium
Medium
SCORE
TOTAL
MULTIMODAL CORE
SCORE
Serves Community
Facilities
SCORE
Connects to
Silver Comet
Trail
SCORE
TOTAL LAND
USE SCORE
Advisory Committee
Support
SCORE
TOTAL
SCORE
1
1
1
1
2
2
3
3
3
3
6
12
No
No
No
No
Yes
Yes
0
0
0
0
1
1
No
No
No
No
Yes
Yes
0
0
0
0
1
1
No
No
Yes
No
Yes
Yes
0
0
5
0
5
5
0
0
5
0
7
7
11
7
2
0
2
4
3
3
1
0
1
2
3
3
1
0
1
2
4
4
7
1
10
11
Land Use
Serves High Growth
Yes =1;Area
No =0
Serves Community Facilities
Yes =1; No =0
Connectivity to Silver Comet Trail
Yes =5; No =0
Public Support
Public Support
Advisory Committee
Yes = 1; No=0
Top 1/3 Vote Getters = 3
Middle Vote Getters = 2
No Votes = 0
Transit TDM
Multimodal Travel
Project ID
T-1
T-2
T-3
T-4
T-5
T-6
T-7
T-8
T-9
T-10
T-11
T-12
T-13
T-14
T-15
T-16
T-17
T-18
T-19
T-20
T-21
T-22
Project Location
Land Use
Category
SCORE
2010 Low
Income
SCORE
2010 Elderly
Density
SCORE
2010 Population
Density
SCORE
2010 Employment
Density
SCORE
Promotes
Bicycle and Ped
Travel
SCORE
TOTAL MULTIMODAL
SCORE
Serves High
Growth Area
SCORE
Along
Commuter
Route
SCORE
TOTAL LAND
USE SCORE
Advisory
Committee
Support
SCORE
Public Comment
SCORE
TOTAL SCORE
Medium
High
High
High
High
Low
High
Medium
High
Low
High
Low
Low
3
5
5
5
5
1
5
3
5
1
5
1
1
Low
High
High
High
High
Medium
High
Medium
High
Low
High
Low
Low
1
5
5
5
5
3
5
3
5
1
5
1
1
High
High
High
High
High
Low
High
High
High
Medium
High
High
High
2
2
2
2
2
0
2
2
2
1
2
0
2
Medium
High
Low
Medium
High
Low
Low
High
Medium
Medium
High
Medium
Medium
2
3
1
2
3
1
1
3
2
2
3
2
2
Low
High
High
High
High
High
High
Medium
High
Low
High
Medium
Medium
1
3
3
3
3
3
3
2
3
1
3
2
2
Local/Shuttle
Local/Shuttle
Local/Shuttle
Local/Shuttle
Local/Shuttle
Local/Shuttle
Local/Shuttle
Commuter
Commuter
Commuter
Commuter
Commuter
Commuter
2
2
2
2
2
2
2
1
1
1
1
1
1
11
20
18
19
20
10
18
14
18
7
19
7
9
Low
High
Medium
Medium
High
Medium
Medium
Medium
Medium
High
Medium
Medium
Medium
0
3
2
2
3
2
2
2
2
3
2
2
2
No
Yes
Yes
Yes
No
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
0
1
1
1
0
0
1
1
1
1
1
1
1
0
4
3
3
3
2
3
3
3
4
3
3
3
0
0
3
0
1
1
0
0
0
0
4
1
0
0
0
2
0
1
1
0
0
0
0
2
1
0
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
3
1
2
2
1
1
1
1
3
2
1
12
25
24
23
25
14
22
18
22
12
25
12
13
POLICY-RELATED SOLUTIONS - PRIORITIES WILL EVOLVE THROUGH MORE EDUCATION AND COORDINATION WITH GEORGIA COMMUTE OPTIONS
POLICY-RELATED SOLUTION - CONTINUE TO MONITOR THE DEMAND FOR PAULDING TRANSIT AND SEEK ADDITIONAL FEDERAL FUNDING WHEN LOCAL MATCH IS AVAILABLE
Multimodal Travel
2010 Zero Car
2010 Low Income
2010 Elderly
2010 Pop. Density
2010 Emp. Density
Land Use
Serves High Growth Area
High = 3
Medium = 2
Low = 0
Public Comment
Public InputBased on results below: Public split on transit overall. Human services transit very popular though.
Advisory Committee
Top 1/3 Vote Getters = 2
Middle Vote Getters = 1
Others = 0
Yes = 1; No = 0
Total Possible Public Comment = 4
PUBLIC MEETING RESULTS
Would you ride GRTA Xpress Bus if
The pickup location was closer to The drop off location was closer
Yes
No
Yes
No
11
9
9
10
How important is the need for new local transit service in the county?
Very
Unimportant
Somewhat
Important
Very important
Unimporta
important
nt
4
4
1
6
6
How important is the need to continue on-demand transit services (Paulding Transit)?
Very
Unimportant
Somewhat
Important
Very important
Unimporta
important
nt
1
3
3
3
16