Documente Academic
Documente Profesional
Documente Cultură
Advanced Foundations
1 Piling - Introduction
What is piling?
Why so popular?
Piles can be made from steel or timber although in most housing work
piles are made from insitu or pre-cast reinforced concrete. They are
used either to transmit loads from the building through soft or
compressible ground to firmer strata below (end bearing pile), or to
distribute loads into the subsoil along the length of the pile (friction
pile). In housing, a concrete beam across the top of the piles
distributes the load from the load bearing brickwork into the piles
themselves. In framed buildings the piles usually support concrete or
steel columns.
20 or 30 years ago piling was comparatively rare for housing (other than
medium and high rise flats). Since then, several factors have led to an
increase in the use of piled foundations. These include:
building load
cost
Pier foundations, sometimes called pad and stem, are not dissimilar to
end-bearing piles in their function. However, their construction is very
different. Piling is carried out from the surface, by drilling or driving
down into the ground. When building piers, individual pits are usually
excavated and then backfilled once the piers have been constructed.
What are piers?
Pile types
driven piles which are preformed - usually steel or precast concrete (displacement)
4 Augered Piles
Continuous Flight Auger
7 Piers
Roger Bullivant Ltd provided its pre-cast house foundations package, consisting of segmental pre-cast piles, precast ground beams and suspended pre-cast floors to two major house developers on the same site in Cheddar,
Somerset. The developments were undertaken on a greenfield site which suffers from high ground water table
problems. The majority of ground levels needed to be raised by as much as 750mm across the area. It was also
anticipated that localised flooding of the site during work would be experienced. A solution to overcome all of
these difficulties was needed to enable work to proceed, as conventional foundations would be difficult and
costly to construct.
The use of segmental pre-cast piles, Tee-beam system and suspended pre-cast floors, helped overcome the poor
ground conditions. The segmental pre-cast piles provided a cost effective solution which eliminated both
excavation and spoil disposal.
Sacrificial probe piles were installed prior to final negotiations to determine the
actual pile lengths so that a fixed price package could be agreed. In total 560, 175
x 175mm square segmental pre-cast piles were installed to a maximum depth of
7m. Each pile was capable of carrying loads to 350kN and comprised 3m and 4m
segments with single T16 bar reinforcement. The piles were cropped to the required
level and either pre-cast caps or cast in-situ concrete caps positioned on top.
Approx. 2000 metres of pre-cast Tee-beams were installed, together with
2500metres of pre-cast beam joist floors.
Both projects were completed using purpose-built piling rigs, designed to undertake
work of this nature where piles ranging in size from 150 200mm are required, with
loads from 100 400 kN. The rigs use 2 3 tonne hydraulic hammers to drive in the
piles. As the gross weight of each rig is only 17 tonnes, it can be mobilised onto site
without the need for police escorts or movement orders. The size and weight of the
rig also reduces on-site problems resulting from noise and vibration.
Case Study Two
Roger Bullivant Ltd provided pre-cast concrete piling for the construction of a new
housing development in Burnham-on Sea, Somerset. The project involved
foundation piling on a section of a new development of timber-framed homes.
Three of the planned houses presented a particular challenge, as they were situated
in close proximity to a hedgerow, with the added complication of a ditch around the
perimeter where the ground was soft and wet. The plots were also very close to
existing adjacent housing which was being developed and therefore any work had to
be carefully contained.
The contractor (RB) proposed the installation of pre-cast segmented piles together
with pre-cast Tee beams. The system offers a cost-effective solution to installations
in close proximity to existing buildings or structures and, in addition, overcomes
problems of poor ground conditions without the need for soil disposal or excavation.
The area of the site was prepared to a reduced level of 650mm below floor slab
level. Investigations of the soil revealed eight distinct layers; these varied from
topsoil, firm clay, clayey and laminated silt of various types, down to fine-medium
sand. This dictated that piling would need to be to a depth of approx 17m. As the
ground compaction was good, no hardcore was needed for piling platform.
The segmental pre-cast concrete piles were installed with a top-driven hydraulic
hammer rig to depths ranging from 1 5.5 1 6.4m . The pre-cast piles were 250mm
square capable of loadings up to 600kN. The segments were each 4m with single bar
reinforcement to reduce costs and minimise wastage.
This housing development was being constructed on the site of a former sand quarry
which had been filled before the Second World War. A school was then built on the
site, incorporating underground air raid shelters constructed from very thick, highdensity concrete. The site over the disused shelters had subsequently been
developed by the addition of extra classrooms and playgrounds etc.
The exact location of the air raid shelters, the degree of fill and precise depth of
the underlying bedrock were all unknown. It had been identified that on an
adjacent piece of land, homes constructed post-war had needed to be demolished
because of major subsidence.
The developers had already completed the first six houses on one section of the
site, using vibrated concrete columns and very deep foundations. As these initial
properties had sold immediately, they were looking for an alternative solution that
would speed up the construction programme and also avoid the high cost of such
deep foundations. The solution comprised a combination of steel tubular piles and
pre-cast concrete piles both followed by pre-cast pile caps, pre-cast tee-beams and
pre-cast concrete floor slabs. The combination of both pile types enabled the
differing conditions on the site to be accommodated, with only minimal need for
spoil removal. On the section of the site where it had been identified that air raid
shelters had not existed, the ground conditions were sound and pre-cast concrete
piles 200mm to a depth of 6m were used. On the more difficult parts of the site,
170mm diameter steel piles were used, installed down to 8m and in some cases
down to 16m. The use of steel piles ensured that they could be driven through any
concrete structures forming part of the old shelters. Where any major obstructions
were identified, local excavations were carried out to assess and re-plan the piling
as required.
Installation was followed by pile cropping which ensured a sound connection
between the pile and the pre-cast cap. Over 1500metres of pre-cast reinforced
concrete tee-beams were then installed directly onto the pile caps to carry the wall
and floor loads.
This housing development is on a site formerly used as a tramway depot. The site
was bounded by two roads, a railway and a nearby underground line. Vibration was
perceived as a major constraint, as was the need to minimise traffic, and keep
noise to a minimum. Continuous helical displacement piles were used and the whole
project (nearly 500 piles) was completed in four weeks.
The piles were founded into clayed silt at depths down to 18.50 metres. The piles
had designed working loads of up to 300kN.
The first test pile was toed into boulder clay at a depth of 17.60 metres and gave a
settlement of 15mm at 1200kN. A second test pile, founded in clayed silt at a depth
of 15.50 metres provided an ultimate load of 600kN, giving a safety factor of 2.
10 Rafts
Raft foundations were sometimes used as far back as the 1920s and 1930s. This example is a house designed in
1936 - the site was a drained marsh. In the 1940s and 1950s raft foundations were quite common, particularly
beneath the thousands of prefabricated pre-cast concrete or steel buildings erected during the years following
the Second World War. Most of these houses were built on good quality farm land where the soil was generally of
modest to high bearing capacity. Rafts (or foundation slabs as they were sometimes called) were often used
because they were relatively cheap, easy to construct and did not require extensive excavation (trenches were
often dug by hand). In 1965 national Building Regulations were introduced for the first time (London still had its
own building controls), but these did not contain any 'deemed to satisfy' provisions for raft foundations (as they
did for strip foundations) - consequently each had to be engineer designed. As a result they quickly fell out of
favour.
In modern construction rafts tend to be used:
Where the soil has low load bearing capacity and varying compressibility. This might include, loose sand,
soft clays, fill, and alluvial soils (soils comprising particles suspended in water and deposited over a flood
plain or river bed).
Where pad or strip foundations would cover more than 50% of the ground area below the building.