Status:
Checked:
Version History
Version
01
Date
01.09.2014
Description
Original
Prepared by
Vlad Aron
Reviewed by
Diana Coloja
Approved by
Purpose
ASAP
IS-U Implementation project
01.09.2014
Page 1 from 38
Alternatively, you can directly access the transaction by typing t-code in command filed and press
<Enter> or click on the check mark icon
in the top left side corner of the screen:
Procedure Steps
In the Change Order: Initial Screen" screen enter information in fields as following:
ASAP
IS-U Implementation project
01.09.2014
Page 2 from 38
Field Name
Order
Description
Order number
R/O *
R
Remarks
*R Required, O Optional
ASAP
IS-U Implementation project
01.09.2014
Page 3 from 38
Description
Description
Description
Sold-to
party
Pur. order
Sold-to party
Protocol
number
Protocol
date
Planner
group
Work center
Equipment
Maintenance
Activity Type
Functional
location
Equipment
Bsc start
Basic start
Basic fin.
Basic finish
Priority
Priority
Purchase
order date
PlannerGrp
Mn.wk.ctr
PMActType
Func. Loc.
O
O
O
O
O
*R Required, O Optional
To change information regarding address details you have the following options:
1. Customer address screen, by clicking Maintain partner address button
ASAP
IS-U Implementation project
01.09.2014
Page 4 from 38
Address data in this screen is taken from the client master data. It can be changed, but this will not
update the client master data address details
2. Object address screen by clicking Partner overview button . Information in this screen
cannot be changed, it is taken from the reference object (equipment/functional location)
ASAP
IS-U Implementation project
01.09.2014
Page 5 from 38
ASAP
IS-U Implementation project
01.09.2014
Page 6 from 38
Field Name
Country
Description
Country
R/O *
R
Remarks
*R Required, O Optional
ASAP
IS-U Implementation project
01.09.2014
Page 7 from 38
Field Name
Description
Name
Building code
Room
Floor
c/o
GIS
address
code
Building name
Street
House number
Name
Building code
Room
Floor
Entry number
GIS address code
Building name
Street
House number
R/O
*
O
R
O
O
O
O
A value is to be entered
Postal code
Postal code
City
City
Region
Region
Telephone
Telephone
Remarks
is to be entered
is to be entered
is to be entered
is to be entered
is to be entered
is to be entered
A value is to be entered
Select a value from the drop down list
A value is to be entered
Additional
address 1
Additional
address 2
District
Struct.
A value
A value
A value
A value
A value
A value
O
R
R/
O
O
Additional
address 1
Additional
address 2
District
Reg.
Grp.
A value is to be entered
*R Required, O Optional
While introducing data interrogation screens regarding address acceptance may be generated.
Click YES option to adopt data.
ASAP
IS-U Implementation project
01.09.2014
Page 8 from 38
Un.
Number
Dur.
C.Key
ActTyp
Fac
Description
*R Required, O Optional
ASAP
IS-U Implementation project
01.09.2014
Page 9 from 38
If an operation should be repeated during order processing, select the operation and click Ex.
Factor button
:
To insert a task list in the operation list click Extras option on the menu bar, then select Task List
Selection General task lists.
ASAP
IS-U Implementation project
01.09.2014
Page 10 from 38
Choose:
Yes if you want to delete the already existing operations
No if you want to keep the already existing operations
Cancel to exit the screen
In the following screen insert desired selection criteria and click Execute button to display a list of
task lists:
ASAP
IS-U Implementation project
01.09.2014
Page 11 from 38
ASAP
IS-U Implementation project
01.09.2014
Page 12 from 38
Choose:
All if you want to insert all operations
Selected if you want to insert only the selected operations
Additional operation(s) is/are inserted in the Operation tab:
ASAP
IS-U Implementation project
01.09.2014
Page 13 from 38
Click the Component field and then the match code to display the search help for materials.
Expand the selection criteria by pressing Expand button
storage location:
ASAP
IS-U Implementation project
01.09.2014
Page 14 from 38
ASAP
IS-U Implementation project
01.09.2014
Page 15 from 38
ASAP
IS-U Implementation project
01.09.2014
Page 16 from 38
Description
Quantity
Storage
location
R/O *
R
R
*R Required, O Optional
Repeat the same above steps for the required list of components.
To assign/change partners to the work order click Partner tab:
ASAP
IS-U Implementation project
01.09.2014
Page 17 from 38
Field
Name
Funct
Description
R/O *
Function
Partner
Partner
*R Required, O Optional
ASAP
IS-U Implementation project
01.09.2014
Page 18 from 38
Select the corresponding values from the drop down list or create new entries by selecting the corresponding
field and then clicking New entry button
To delete an already existing entry select the line and then click Delete Row button
ASAP
IS-U Implementation project
01.09.2014
Page 19 from 38
For work orders who are going to be used for invoicing (non-regulated services):
1. You can change also information regarding the type of service in Operations tab:
Assign an activity type to each operation that is going to be invoiced (select it from the drop dow
list).
ASAP
IS-U Implementation project
01.09.2014
Page 20 from 38
2. You can change also information regarding sales data by executing the following meniu
steps Extras -> Sales data:
In the Sales Organization Data" screen you can change the following information:
Field Name
Sales Org.
Distr.
Channel
Division
Description
Sales
Organization
Functional
location
Equipment
R/O *
R
Remarks
*R Required, O Optional
3. You can change also information regarding tested devices by clicking Enhancement tab
(this tab is active only for work order type WO48, maintenance activity type 047Install&Seal)
ASAP
IS-U Implementation project
01.09.2014
Page 21 from 38
Information regarding serial number(s) is copied from the removal work order. At this step we
should update information regarding metrological check and date of execution.
In order to close (TECO) the removal order (1st order) the install & seal order (2nd order) should be
closed (TECO) first!!!!!!
Inside 2nd work order you can find information regarding the 1 st work order in Header tab, field
Superior Order:
ASAP
IS-U Implementation project
01.09.2014
Page 22 from 38
Inside 1st work order you can find information regarding the 2 nd executing the following menu path
Extras -> Suborders -> Overview:
ASAP
IS-U Implementation project
01.09.2014
Page 23 from 38
In Set user status screen select the desired value and validate by clicking the green check mark
ASAP
IS-U Implementation project
01.09.2014
Page 24 from 38
Selected user status will also be displayed in the work order header:
ASAP
IS-U Implementation project
01.09.2014
Page 25 from 38
Click Back
Lock order
To set a lock indicator execute the following menu path Order -> Functions -> Lock -> Lock:
ASAP
IS-U Implementation project
01.09.2014
Page 26 from 38
Acces IW32 transaction again to see that the order system status is also updated:
Unlock order
To remove a lock indicator execute the following menu path Order -> Functions -> Lock ->
Unlock:
ASAP
IS-U Implementation project
01.09.2014
Page 27 from 38
Print order
To print a work order (after the work order is released) execute the following menu path Order ->
Print -> Order:
ASAP
IS-U Implementation project
01.09.2014
Page 28 from 38
Select the desired form, enter LP01 in the OutputDevice field and make sure that N (new spool request
box) is ticked.
ASAP
IS-U Implementation project
01.09.2014
tab to get to
Page 29 from 38
button.
Access IW32 transaction again to see that the order system status is also updated:
ASAP
IS-U Implementation project
01.09.2014
Page 30 from 38
Fill information regarding the date/time when the work was finished and specify if notification
related to this work order (if any) should also be closed. Press the green check mark
to leave
the screen.
The following message is displayed on the status bar at the bottom of the screen:
Access IW32 transaction again to see that the order system status is also updated:
ASAP
IS-U Implementation project
01.09.2014
Page 31 from 38
At this stage no more changes can be done inside the work order.
ASAP
IS-U Implementation project
01.09.2014
Page 32 from 38
Access IW32 transaction again to see that the order system status is also updated:
ASAP
IS-U Implementation project
01.09.2014
Page 33 from 38
Reverse closing
To reverse technically completed (CLSD) system status execute the following meniu path Order ->
Functions -> Complete -> Cancel business completion:
ASAP
IS-U Implementation project
01.09.2014
Page 34 from 38
Access IW32 transaction again to see that the order system status is also updated:
ASAP
IS-U Implementation project
01.09.2014
Page 35 from 38
To create an attachment click on Services for Object arrow button and execute below marked
steps:
ASAP
IS-U Implementation project
01.09.2014
Page 36 from 38
ASAP
IS-U Implementation project
01.09.2014
Page 37 from 38
The following message is displayed on the status bar at the bottom of the screen: