Documente Academic
Documente Profesional
Documente Cultură
LTD
(NETCO)
PIPELINE ENGINEERING
TRAINING
MANUAL
263913945.doc
TABLE OF CONTENTS
1.0
OBJECTIVES
2.0
INTRODUCTION
2.1
DEFINITIONS
2.2
2.3
PROJECT ACTIVITIES
3.0
3.1
QA/QC PROCEDURES:
3.2
DESIGN DELIVERABLES
3.3
INPUT TO PROPOSALS
4.0
4.1
4.2
PROJECT CONTROLS
4.3
PROCUREMENT
4.4
CONSTRUCTION
5.0
APPENDIX
263913945.doc
1.0
OBJECTIVE
This pipeline engineering discipline training manual is intended to provide information
about pipeline engineering and to list design deliverables produced by the discipline. It
also includes guide to the pipeline engineer on the methodology and basic
approach/work process towards producing the deliverables. Furthermore, it x-rays the
work interface with other engineering disciplines and departments in NETCO with
respect to the pipeline engineers responsibility on a project. It is however not intended
to be a design manual.
263913945.doc
2.0
INTRODUCTION
A pipeline is the means of conveying fluid from one location to another or generally
from source to user. There are three major groups of oil and gas pipelines namely:
Gathering, Transmission / Trunk and Distribution pipelines.
Gathering pipelines connect individual oil/gas sources to central treating or processing
facilities.
Transmission pipelines refer to pipelines that transport gas, crude oil or refined
products.
Flowlines are relatively small diameter pipelines that convey untreated oil/gas to a
central facility for processing.
Distribution pipelines are mostly applicable to gas transportation where they are used
in a network to convey gas from utility companies to end-users.
Pipeline engineering involves the scientific task of designing, constructing, operating
and maintaining pipeline systems. The pipeline engineer should decide on which
specific pipeline installations (materials and otherwise) are suitable for transporting the
fluid involved. In deciding this, the pipeline engineer utilizes some codes and
standards and recommended practices to ensure a safe pipeline system. Note that
pipeline involves fluid transportation off-plot (outside the plant area) in contrast to
piping which relates to the pipework in and around the plant area or facility.
This training manual presents aspects of pipeline engineering relating to the design of
a pipeline.
263913945.doc
2.1
DEFINITIONS
Pipeline
Flow Line
Condensate
Dewpoint
Hydrate
LNG
LPG
NGL
Natural Gasoline
263913945.doc
Sour Gas
Sweet Gas
Acid Gas
Multiphase Flow
Simultaneous flow of two or more fluid phases (i.e. gas, oil and
water) in the same pipeline.
Pig
Pig Trap
Pig Signaller
Sphere Pig
Scraper Pig
Inhibitor
Slug Catcher
Peak Shaving
263913945.doc
Design Life
Design factor
Ratio of the hoop stress in the pipe at the design pressure to the
yield stress of the pipe material.
MAOP
Safety factor
Laminar Flow
Flow with Reynolds number less than 2000. In this flow, the flow
patterns of fluid patterns are laminar and parallel, since any
tendency towards turbulence is counteracted by forces of
viscosity.
263913945.doc
Turbulent Flow
Absolute Pressure
Atmospheric Pressure
Gauge Pressure
SCADA
ANSI
ASME
IP
Institute of Petroleum
BS
British Standard
IGE
API
DNV
ASTM
NACE
263913945.doc
2.2
API 5L1
API 5LW
API 6D
Pipeline Valves
API 1102
API 1104
API RP 1110
API RP 1111
ASME B16.34
ASME B16.20
ASME B16.5
ASME B36.10M
BS 8010 Part 3
263913945.doc
IP (Part 6)
NACE RP0169
NACE RP0675
263913945.doc
3.0
QA/QC PROCEDURES:
A number of work procedures are applicable in the pipeline group. Project specific
procedure usually called Pipeline Discipline working procedure is prepared by the
responsible discipline engineer in a project and endorsed by the project QA/QC
personnel prior to approval by the Project Manager.
Basically, the discipline working procedure states the pipeline intended scope of works
and highlights the resources (codes/standards, software, discipline team, etc) to be
used in executing the project.
3.2
INPUT TO PROPOSALS
For any proposal, the scope of work to be undertaken is determined by the pipeline
engineer from relevant documents provided by the Client. Also, since most projects
are interdisciplinary by nature, proposal meetings are held where the pipeline engineer
interacts with other discipline personnel to further clarify his scope of work and
responsibilities.
The input to proposals by the pipeline engineer can be broken down as follows:
(i)
263913945.doc
10
number of deliverables and the extent of activities expected, the man-hour estimate is
prepared.
The methodology involved in producing man-hour estimate includes:
Step 1
Carefully study the pipeline engineering / discipline scope of activity contained in the
tender / proposal document
Step 2
List out the expected deliverables (studies, calculations, specifications, drawings, data
sheet, material requisitions, etc.)
Step 3
Using the Engineering scope and man-hour summary form (F-5054-Pipelines), input
the information of step 2 including the associated hours. See Appendix for form
F-5054 Engineering scope and man-hour summary (Typical) for the Pipelines group.
Step 4
Pipeline LDE to check the deliverables / estimated hours against the standard
discipline default man-hour and revise as appropriate.
Step 5
Submit the LDE approved man-hour to the Proposal Manager for review/approval and
subsequent inclusion in the overall engineering man-hour summary.
(ii)
Execution plan
Arising from the project specific requirements, discipline execution plan is prepared.
This would be in accordance with the ITB and is to be submitted to the Proposal
263913945.doc
11
3.3
Expected deliverables
DESIGN DELIVERABLES
For any project involving pipeline design activities, the deliverables list depends
on the work-scope established by the Client. However the following list includes
the common deliverables produced in a pipeline design effort:
263913945.doc
Design Studies
Routing studies
Design Basis
Material Specifications (Line pipe, Bends, Valves, Risers, Pig traps, etc.)
Pipeline Hydraulics
Stability calculation
12
(a)
Drawings
Riser drawing
Design studies
In some projects, pipeline design studies are necessary in order to carry out
effective, efficient and safe design. The common areas include routing, material
selection, pigging, hydraulic study, constructability study, etc. In each study
case, experience and sound judgement are pertinent.
(b)
263913945.doc
13
Environmental impact
Permanent access
Design Basis
This is sometimes referred to as design premise, basis of design, design
memorandum etc. It contains all the information necessary for the specific
design, installation and testing of the pipeline. This includes information on the
route, pipeline operating conditions (flow, pressure, temperature etc), fluid
characteristics, design and installation requirements etc. As the name implies, it
outlines the design requirements of the entire pipeline system and serves as a
guide to the engineering design of the pipeline. Therefore, the deliverable is first
among others.
(d)
Material Specifications
These documents outline the technical requirements for the specific pipeline
items/equipment in question. The commonly prepared material specifications
include those for:
-
263913945.doc
14
Pipeline valves
(f)
Pipeline Hydraulics
Hydraulics is the study of flow of fluids under an external force. In pipeline
hydraulics, the engineer considers fluid flow conditions, whether the fluid is
compressible (gas) or incompressible (liquid). This is with the view to
determining the appropriate pipe or line size for the pipeline. This is achieved by
determining the pressure loss and any temperature changes along the pipeline
263913945.doc
15
263913945.doc
16
Stability analysis of pipelines is usually carried out where the pipeline is planned
to be installed in a swamp (high water table area) or offshore area (on the
seabed or buried). In each case, the hydrodynamic loads on the pipeline are
analyzed and the required submerged weight for stability of pipeline is
determined. Depending on the required submerged weight, concrete coating of
the pipe may be necessary.
Stress analysis
Stresses are imposed on the pipeline by internal and external factors. These
include stresses due to fluid operating conditions (pressure and temperature),
environmental and installation conditions. The stresses are analyzed under
various criteria e.g. buckling (lateral or upheaval), pipeline expansion, span
analysis, installation stress analysis, crossing (due to specific crossing
requirements) etc. In each case, the imposed stress is obtained and checked
against the code or Client allowable stress value. However, in span analysis,
the intent is to determine the allowable pipeline span length based on the
avoidance of excess stress levels (which may lead to pipeline vibrations or
oscillations). Design software like AUTOPIPE etc. can be useful.
(h)
263913945.doc
17
(j)
Drawings
Various pipeline construction drawings are produced based on the specific
project requirement. The most common drawing is the Pipeline Alignment
sheet. As the name suggests, the drawing summarizes all the relevant data
needed to define the pipeline route and the detail design of the pipeline from
one point to another. The sheet(s) covers consecutive sections of the pipeline
and are usually divided into strips containing the following information:
Plan of survey details, ground profile and construction details.
Other pipelines drawings include crossing drawings (river, rail, road, pipeline
crossing etc.), kilometer marker post, bathymetry drawings, riser detail
drawings, pig launcher/receiver drawings etc.
4.0
4.1
263913945.doc
18
PROJECT CONTROLS
Interface with project controls on a project is always present. As the project
controls section is always involved in project planning, monitoring, cost control
and cost estimation, the pipeline engineer makes necessary input to the project
controls specialist on the project. The pipeline engineers man-hour estimation
vis--vis deliverable preparation status is checked and reported on by the
project control specialist as part of project management effort. The pipeline
engineers responsibility under here include:
263913945.doc
19
4.3
PROCUREMENT
Procurement activities on a project (where applicable) involve the
acquisition/purchase of pipeline equipment/materials and services for the
project. Included in this acquisition is the checking/review of vendor or
manufacturers data. The pipeline engineers responsibilities include:
Preparation of material take-off (MTO)
Preparation of material requisitions (MRs)
Participation in the preparation of bidders list
Evaluation of technical bids/proposals
Review/approval of vendor or manufacturers drawings and data.
Vendor Liaison meetings
Inspection at Vendor / Manufacturers shop (if applicable).
263913945.doc
20
5.0
25.4 mm
1 ft
0.3048 m
1mile
1.609 km
1nautical mile
1.852 km
1 fathom
= 6ft
1.8288 m
1 in2
6.4516 cm2
1 ft2
0.0929 m2
1 in3
16.387 cm3
1 ft3
0.028317 m3
Area
Volume
Liquid Volume
1 oz
1 gal (US)
= 0.134 ft3
1 gal (Imp)
1 barrel
29.574 ml
3.785litres
4.546litres
= 42 gal (US)=
Mass
1 lbm
= 0.4536 kg
1 slug
= 1 lbf sec2/ft
1 slug
Note:
Force
Note:
1 lbf
= 4.448 N
1 lbf
= 32.174 poundals
1N
= 1 kg*m/sec2
1 ton (short)
= 907.2 kg
1 ton (long)
= 1016.0 kg
263913945.doc
0.225 lbf
21
1 lbf/ft
= 14.59N/m
1 lbf/ft
= 1.488kg/m
1 lbf/ft2
= 47.880N/m2
1 KN
= 224.8 lbf
Density
1 lbf/in3
= 27.68 g/cm3
1 lbf/ft3 (pcf)
= 16.02kg/m3
Pressure or Stress
1 psi
1 psi
= 68947 dynes/cm2
1 psi
= 0.0703 kg/cm2
1 psi
= 0.0680 atm
1 psi
= 0.0685 bar
1 psf
= 47.88 Pa
1 psf
= 4.882 kg/m2
Flow
1 gal/min
= .0631l/s
1 ft3/sec
= 101.94m3/hr
1 ft3/min
= 0.472 l/s
1 bbl/hr
= 0.159 m3/hr
1 MBPD
= 158.99 m3/day
Viscosities
Kinematic ()
1 ft2/sec
1 ft2/sec
= 92903 cs (centistokes)
Absolute ()
1 lbm/sec*ft
1 lbm/sec*ft
= 1488 cp (centipoise)
1 lbf*sec/ft2
= 47880 cp
1cp
= 0.001 Pa*s
Note: = /
263913945.doc
22
Energy
1 cal
= 4.184 J
1 Btu
= 778.2 ft*lbf
1 ft*lbf
= 1.3556 J
1 ft*lbf
= 0.324 cal
1 ft3*lbf/ in2
= 46.66 cal
1 Btu
1 Btu
= 0.2931 W*hr
1 Btu
= 0.000393 hp*hr
Notes:
1.
The SI unit for energy is the Joule (J) but calories are commonly used.
2.
The conversion factors for Btu and calories depend on the temperature. The
values given above are the main values.
Power
1 Btu/hr
= 0.2931 W
1 Btu/hr
= 0.00039846 hp (metric)
1 hp (Imp.)
1 ft lb/min
= 0.0226 W
1 ft lb/sec
= 0.324 cal/s
Note:
The SI unit for power is the Watt (W) = 1J/s; however, horsepower (SI) is
often used (735.5W). SI and Imperial systems have different hp units.
= 2.326 J/g
1 Btu/lbm
= 0.556 cal/g
= 4.186 J/g*oC
1 Btu/lbm*oF
= 4186 J/Kg*K
1 Btu/lbm*oF
= 1.0007 cal/g*oC
1 Btu/slug*oF
= 130.1 J/Kg*K
Note: Degrees Celsius and Kelvin can be used interchangeably in these formulas.
263913945.doc
23
Heat Flux
1 Btu/hr*ft2
= .0003155 W/cm2
1 Btu/hr*ft2
= .00007535 cal/s*cm2
1 Btu/hr*ft2
= .2712 cal/hr*cm2
Heat Transfer
1 Btu/hr*ft2 *oF
= .0005678 W/cm2*oC
1 Btu/hr*ft2*oF
= .0001356 cal/s*cm2*oC
1 Btu/hr*ft2 *oF
= 4882 cal/hr*m2*oC
Thermal Conductivity
1 Btu/hr*ft *oF
= 0 .0173 W/cm*0C
1 Btu/hr*t *oF
= 1.731 W/m*0C
1 Btu/hr*ft*oF
= 0.004134 cal/s*cm*0C
Speed
1 knot
= 0.514 m/s
1 mi/hr (mph)
= 1.61 km/hr
= 1.688 ft/s
Temperature
O
= (9/5)*K
= (0F - 320F)*(5/9)
= K 273.15
= Degrees Rankine
= Degrees Kelvin
R
F
C
C
F
R
263913945.doc
R 459.67
24