C311333- Amal HRSG -1 Project

Petroleum Development Oman LLC


Contract Number C311333
Amal Heat Recovery Steam Generator (HRSG)-1 Project

Section C5
Schedule of Rates

Section C5 Schedule of Rates, Schedule A Preambles


Page 1 of 13

C311333- Amal HRSG -1 Project

SECTION C5
SCHEDULE OF RATES
CONTENTS
SCHEDULE A PRICING PREAMBLES
SCHEDULE B LUMP-SUM WORK
SCHEDULE C NOT APPICABLE
SCHEDULE D ALTERATIONS & DAY-WORKS
SCHEDULE E MILESTONES
SCHEDULE F PENALTIES AND INCENTIVES

Section C5 Schedule of Rates, Schedule A Preambles


Page 2 of 13

C311333- Amal HRSG -1 Project

SECTION C5 - SCHEDULE 'A':- PRICING PREAMBLES


Schedule A Pricing Preambles.....................................................................................2
Schedule B Lump-sum Work........................................................................................2
Schedule C Not Appicable........................................................................................... 2
Schedule D Alterations & Day-works...........................................................................2
Schedule E Milestones................................................................................................ 2
Schedule F Penalties and Incentives...........................................................................2
Section C5 - Schedule 'A':- Pricing Preambles..................................................................3
Schedule 'A':- Pricing Preambles......................................................................................4
1

General Terms............................................................................................................. 4
1.1 All Inclusive Contract Price and Rates......................................................................4
1.2 Pricing of Schedules................................................................................................4
1.3 Working Hours for Site.............................................................................................5
1.4 Company Permits, Rules and Procedures.................................................................5
1.5 Company Supplied Materials...................................................................................5
1.6 Consumables........................................................................................................... 5

Lump Sum Work (Schedule 'B')...................................................................................5


2.1 Descriptions for Identification Only..........................................................................5
2.2 Addition and Omission of Work................................................................................6
2.3 Commissioning Periods............................................................................................6

Provisional and Optional Works (Schedule 'C')............................................................6

Alterations & Day-work Rates (Schedule 'D')...............................................................6


4.1 General.................................................................................................................... 6
4.2 Analogous Rates...................................................................................................... 6
4.3 Day-work Rates....................................................................................................... 6
4.4 Additional Services Procured At Day-work Basis......................................................8
4.5 Materials Procurement............................................................................................. 8
4.6 Authorisation & Payment......................................................................................... 9

Terms of Payment........................................................................................................ 9
5.1 Milestones Payments (Schedule E)........................................................................9
5.2 Payments................................................................................................................. 9
5.3 Completion of the Work (MS 10)..............................................................................9
5.4 Bonuses & Penalties.............................................................................................. 10

Contractor's Accommodation & Facilities..................................................................10


6.1 Accommodation..................................................................................................... 10

Company Provided Services......................................................................................11


7.1 Company Provided Services..................................................................................11
7.2 Logistics Service Provider (LSP).............................................................................11
7.3 Provision of Air Passenger Services.......................................................................11

Section C5 Schedule of Rates, Schedule A Preambles


Page 3 of 13

C311333- Amal HRSG -1 Project

SCHEDULE 'A':- PRICING PREAMBLES


1

GENERAL TERMS

1.1

All Inclusive Contract Price and Rates

1.1.1

Contractor shall include in the Contract Price and Rates for executing the whole of
the Work specified or reasonably inferred from the Contract.

1.1.2

The Contract Price and Rates entered shall be deemed to be the fully inclusive
cost for the Work and shall include but not be limited to: a) Direct and indirect labour, wages, overtime, bonus, transportation,
importation, exportation, messing, travelling, housing, training, holidays,
pensions, insurance, welfare, allowances, sick pay, protective clothing, safety
equipment, other payments, contributions, taxes, levies or expenses payable
in respect of labour as applicable under and in accordance with law, safety,
health, welfare.
b) Administration, agents fees, management, telephone, fax, communication
supervision costs, setting out, investigation, expenses, site and head office
overheads, control, protection, as built records and information, financing
costs, repairs.
c) Co-operation with other contractors, third parties, local establishments, Walis,
municipality, government agencies, etc.
d) Establishment costs, services, stores, industrial facilities, workshops, fences,
watching, lighting, safety, security, maintenance, latrines, messing facilities,
accommodation, electricity, air, gas, water, fuel oil, grease cleaning and
clearing up at all times.
e) Plant, machinery, equipment, fuel, lubricants, tools, temporary supports,
hoisting and lifting equipment, staging and weather protection, scaffolding,
shelters, transport, haulage.
f) Materials, consumables, water, safe storage, fixing in place, samples, testing,
cleaning, waste, handling and multiple handling, duties.
g) Other insurance, liabilities, obligations, responsibilities and risks arising out of
the General Conditions for Construction Contracts and all other documents
forming the Contract.
h) Profit and overheads.

1.2

Pricing of Schedules

1.2.1

Contractor shall be paid in accordance with the Schedule of Rates for Work
performed and services provided.

1.2.2

All Rates shall be in OMR (Omani Rial) and shall remain fixed for the duration of
the Contract.

1.2.3

Rates shall be inserted against all items in the Schedules that have a monetary
value. The value of items left un-priced shall be deemed to be included in the
Contract Price. Should the Work or obligations given in such items not be carried
out by Contractor, Company shall deduct amounts for the Work not completed
valued in accordance with the Contract.

Section C5 Schedule of Rates, Schedule A Preambles


Page 4 of 13

C311333- Amal HRSG -1 Project

1.3

Working Hours for Site

1.3.1

Contractor shall include for working normal Company hours:

Interior locations - 07.00 to 18.00, 1-hour Lunch break, seven days a week

Coastal Areas - 07.00 to 16.00, 1-hour Lunch break, Saturday to Wednesday


inclusive

1.3.2

Should Contractor require to work outside these hours then prior agreement must
be sought from Company and no additional payment will be made.

1.3.3

Contractor is to allow in the Contract Price for continuous working during all
periods where Company's existing production facilities require to be "shut-down"
or temporarily out of operation whilst the Work is executed.

1.4

Company Permits, Rules and Procedures

1.4.1

All Work executed by Contractor shall include due allowance for complying with
Company permit procedures, rules and regulations.

1.4.2

Contractor shall include for all necessary requirements for obtaining approvals
under Company's Permit to Work Procedure (PTW).

1.4.3

Where Contractor can identify cost savings resulting from a relaxation in a


particular PTW requirement, Contractor shall submit such proposals together with
an evaluation of the proposed savings to Company for approval. Any relaxation in
PTW requirements shall subject to written approval by Company and will only
apply to the stipulated areas of the Work.

1.5

Company Supplied Materials

1.5.1

Company shall provide Contractor with only those Materials specifically stated as
such in Section C4, Scope of Work. Contractor shall include in the Contract Price
for supply of all other temporary and permanent Materials required to complete
the Work. Prices for installing Company supplied Materials shall include for
making good any loss, faults or damages which occur after Contractor has taken
delivery, received or accepted them as being in good condition.

1.5.2

Company supplied Materials for certain items shall contain an allowance for
normal waste and Contractor shall be deemed to have allowed for handling these
excess quantities and returning any unused Materials to Company nominated
storage area as stated in Section C4, Scope of Work.

1.5.3

Company supplied Materials shall be handed over to Contractor at the location as


stated in Section C4, Scope of Work or other locations as directed by Company.
Contractor shall allow in his prices for handling, loading, crainage, storage,
compliance with Materials procedures, issuing of damage/deficiency reports, issue
and transporting Materials to their final location.

1.6

Consumables

1.6.1

Contractor shall provide all consumables required to complete the Work unless
specifically stated otherwise.

1.6.2

For the purposes of this Contract, consumables are considered to be, items
necessary to complete the Work, but which do not actually form part of the as
installed equipment, this shall include, but not be limited to; welding rods, fluxes,
grease, gases, incidental non-specialist lubricants, oils, refrigerants, cleaning
agents, corrosion inhibitors, solvents, rags, application equipment, disposable
protection and clothing.

2
2.1

LUMP SUM WORK (SCHEDULE 'B')


Descriptions for Identification Only

Section C5 Schedule of Rates, Schedule A Preambles


Page 5 of 13

C311333- Amal HRSG -1 Project

2.1.1

The descriptions attached to the various items are intended as brief summary of
the Work involved.
They are sufficient for identification only and not an
exhaustive list detailing every operation involved in carrying out the Work. The
descriptions have been prepared on the basis that Contractor is experienced in the
requirements of the Work to be executed and has full knowledge of the Site.

2.1.2

Notwithstanding any omission from the descriptions given in Schedule B of any


operation included within Section C4 Scope of Work and Section C6 Technical
Specification and Drawings, the cost of all operations that may be ascribed to the
Work shall be included in the Contract Price. All Work that can be reasonably
ascribed to an item description shall be deemed to be included with that item. No
liability will be accepted by Company for defective description or further
operations, other than those described, being required to complete the Work.

2.1.3

Contractor shall include in his Contract Price for excavating in whatever ground
conditions may be found. Contractor shall include a separate line item in the price
schedule for excavating entirely by hand within the confines of the Site or
wherever Company may deem mechanical excavation to be unacceptable.

2.2
2.2.1

2.3

Addition and Omission of Work


Where an addition or omission of Work can be clearly identified within the
descriptions included in Schedule B - Lump Sum Work, the amounts stated against
these descriptions shall be deemed the value of such Work. In the event that such
clear identification cannot be established then the addition or omission of such
work shall be valued in accordance with paragraph 4.0 herein.
Commissioning Periods

Section C5 Schedule of Rates, Schedule A Preambles


Page 6 of 13

C311333- Amal HRSG -1 Project

2.3.1

Contractor shall include in the Rates for maintaining on Site, during the duration of
Commissioning Work, all facilities required until Completion of the Work. This shall
include but not be limited to contract administration, trade & Site supervision,
accommodation, messing, transport and communication for all required labour to
support the Commissioning activities.

PROVISIONAL

AND

OPTIONAL WORKS (SCHEDULE 'C')

Not Applicable

ALTERATIONS & DAY-WORK RATES (SCHEDULE 'D')

4.1

General

4.1.1

The Rates contained in Schedule 'D' shall be used to evaluate modifications,


omissions and/or additions to the Work requested by Company prior to the
Completion Date. All quantities and rates, except where otherwise stated, shall be
measured in accordance with the Principles of Measurement (International) for
Works of Construction (June 1979) as published by the RICS.

4.1.2

All Rates shall apply equally to executing the Work in large or small quantities and
difficult or easy situations and no claim shall be entertained relating to the
proportions of the Work actually falling into these categories.

4.2

Analogous Rates

4.2.1

Rates shall be entered against each item listed in Schedule 'D'. Rates shall be
deemed analogous to those Rates used in pricing Works and constituent parts as
given in Schedule 'B' and subject to the requirements of item 1.1 herein.

4.2.2

If it can be demonstrated that any Rates in Schedule 'D' is not analogous to the
Rates in Schedule 'B', then Company shall have the option to adjust the given
Rates to conform to this requirement.

4.3

Day-work Rates

4.3.1

When, in the opinion of Company Work cannot be measured at Rates contained in


the Schedules of Rates for additions and deletions or at rates analogous thereto,
the value of such work shall be ascertained on the basis of the actual labour
employed and the plant and Materials used therein. These Rates will be as stated
in Schedule 'D'.

4.3.2

Labour
The rates for labour shall be comprehensive and include but not limited to:
a) Wages and all costs, payments and charges including annual and public
holidays, travelling time, expenses, fares and transport, guarantee time,
incentive and bonus payments, dirty money and danger money and other
disbursements arising from employment of labour including redundancy
payments and any requirements of the Sultanate of Oman labour Laws.
b) Charges in respect of Site and office supervision including foremen time and
extra emoluments paid to foremen and leading craftsmen and gangers, small
tools, HSEM requirements and personal protective requirement etc.
c) Site and head office overhead charges such as: rent, rates, insurance's,
electricity, gas, fuel, water, printing, stationery, postage, telephone charges,
motor car expenses etc. and repairs, renewals, maintenance and depreciation
of premises, machinery plant etc.
d) Profit

Section C5 Schedule of Rates, Schedule A Preambles


Page 7 of 13

C311333- Amal HRSG -1 Project

4.3.3

Only where Contractor is specifically instructed, in writing, by Company to work


outside normal working hours will overtime payments be certified. Overtime rates
shall only apply for hours outside the normal 10-hour day, 7-day week.

4.3.4

Working supervision shall be paid for at the hourly rate for an operative of the
applicable trade. Working foremen to be paid for at the Day-work Rate applicable
to the trade of the foreman. Foremen shall only be paid for on Day-work where
the presence of the foreman has been explicitly requested by Company.
Mechanical Plant
The Rates for mechanical plant shall be exclusive of drivers, operators and
attendants, who shall be separately charged, but shall be inclusive of all fuel,
lubricants and other consumables, servicing repairs, replacements and other
charges relating to fully operating plant. Payment for working plant shall be for
the actual hours worked only. No allowance for Stand-by Time will be paid,
unless expressly instructed by Company. Stand-by Time shall mean the time
when personnel or plant instructed by Company to be available for Work but are
not actually working.

4.3.5

4.4

Contractor shall provide for all costs and charges associated with transportation
and haulage to, from and around the Site, of Contractor Personnel and equipment
engaged in the Works. In this respect the costs of transportation, haulage and
travelling time shall be deemed to be included in the Rates. No separate payment
shall be made by Company to Contractor for transportation costs.
Additional Services Procured At Day-work Basis
Where there are no applicable Rates in the Contract for additional services to be
procured at day-work basis as a result of an Instruction, such additional services
shall be evaluated and agreed at net cost basis plus a percentage adjustment on
the net cost.
Net cost in respect of such services shall comprise of actual cost payable by
Contractor after taking into considerations of all types of discounts, commissions,
and any recoverable duties and taxes.
Any travel and accommodations required as a result of providing such additional
services shall be subject to Companys prior approval.
All Contractor handling, administration, financing, overheads and profit elements
and all other costs related to such additional services shall be deemed to be
recovered under the percentage adjustment. (Ref: Schedule D - Alterations and
Day-works under the table entitled Percentage Adjustment for Overheads for
Additional Services and Material Procurement.)
The evaluation of such additional services shall be supported by copy of the
priced contract or copy of the invoice from Subcontractors providing such
services.

4.5

Materials Procurement
Where there are no applicable Rates in the Contract for additional Materials to be
procured as a result of an Instruction, such Materials shall be evaluated at net cost
basis plus a percentage adjustment on the net cost.
Net cost in respect of such Materials shall comprise of:
(a) Actual Materials cost payable by Contractor after taking into considerations
of all types of discounts, commissions, and any recoverable duties and
taxes; and
(b) All additional costs for delivery of Materials to the first point of direct sphere
of influence of the Contractor (i.e. storage warehouse, or Site location),
including freight charges, insurance, port clearance /handling charges and
custom duties; and

Section C5 Schedule of Rates, Schedule A Preambles


Page 8 of 13

C311333- Amal HRSG -1 Project

(c) all inspection and testing required.

Section C5 Schedule of Rates, Schedule A Preambles


Page 9 of 13

C311333- Amal HRSG -1 Project

All Contractor handling, administration, financing, overheads and profit elements


and all other costs related to the procurement of such Materials shall be deemed
to be recovered under the percentage adjustment. (Ref: Schedule D - Alterations
and Day-works under the table entitled Percentage Adjustment for Overheads for
Additional Services and Material Procurement.)
The evaluation of such Materials shall be supported by copy of the priced
purchase order or copy of the invoice from the Materials Vendors.
4.6

Authorisation & Payment

4.6.1

All Dayworks must be instructed and authorised in writing and signed and
approved by Company.

4.6.2

Contractor shall prepare, on a daily basis, detailed statements of Day-works


executed. These shall be submitted to Company for approval, no later than 24hours following the completion of the days work to which it relates. Any
statements received after this duration maybe subject to assessment and
adjustment by Company.

TERMS

5.1

OF

PAYMENT

Milestones Payments (Schedule E)

5.1.1

The Work to be performed by Contractor as detailed in C4 Scope of Work has been


divided into Milestone (MS) groupings as detailed in Schedule 'E'. Only on
Completion, to the satisfaction of Company, of all Work contained within these
Milestone groupings will Company issue Contractor with a Certificate certifying
Milestone Completion. A Milestone shall only be deemed to be complete when so
certified by Company.

5.1.2

No Milestone shall be certified as complete until all outstanding related HSE and
quality audit non-conformance's have been accepted as being complete by
Company.

5.2

Payments

5.2.1

On receipt of a Company certified "Certificate of Milestone Completion",


Contractor shall invoice Company the percentage of the Contract Price stated as
being due for achievement of that Milestone in Schedule 'E'. Unless specifically
stated otherwise, in the event that no milestone is certified as being complete
during a particular month then no invoice shall be submitted. All applications for
payment shall conform to the requirements of Section C8 Procedures for
Contractors and applicable payment shall be released in accordance with Section
C3 General Conditions of Contract.

5.2.2

Unless specifically stated otherwise, Contractor shall be paid for Provisional and
Optional Work only upon their completion. Provisional and Optional Work may be
invoiced together with the next subsequent completed Milestone.

5.2.3

The invoice for payment shall detail the accumulative total percentage, applied to
the Contract Price together with the total amount of instructed and completed
Provisional and Optional Work less all previous payments. All invoices shall detail
the amounts due under each of the headings in the Schedules of Rates and for
each Variation to Contract, together with adequate supporting documentation.

5.2.4

Invoices shall only be considered for payment provided all other contractual
obligations have been fulfilled.

5.3
5.3.1

Completion of the Work (MS 10)


Contractor may only apply for payment of MS 10 'Completion of the Work' once all
Contractor's applications for additional moneys resulting from alterations, Field
Trouble Reports, Instructions and formalised by Variations to Contract, and the
consequent resultant effects have been submitted to Company for approval.

Section C5 Schedule of Rates, Schedule A Preambles


Page 10 of 13

C311333- Amal HRSG -1 Project

5.3.2

5.4

Bonuses & Penalties

5.4.1

Contractors application for payment of Completion of the Work shall constitute


notification by Contractor that this has been achieved.

Bonuses and penalties for the Work shall only be accounted for upon completion of
an applicable Milestone stage. Bonuses and penalties shall be those as detailed in
Schedule 'F'.

CONTRACTOR'S ACCOMMODATION & FACILITIES

6.1

Accommodation

6.1.1

The Contract Price shall include for the provision and maintenance of
accommodation for all Contractor Personnel. The Contract Prices shall include for
all temporary facilities being constructed and operated in full compliance with
Company regulations and standards for the duration of the Contract.

6.1.2

Contractor shall include for mobilisation, maintenance and demobilisation of all


temporary facilities on Completion of the Work.

6.1.3

Temporary Camp
The Contractor shall provide at the allocated area, temporary camp for all their
staff and Company staff for the contract duration as indicated in Section C4
General Scope of Work : 6.0 Construction, Article 6.6. The Camp shall be
constructed & maintained according to Company standards & according to the
requirement specified in C-6-35. Contractor shall be responsible for all site
preparation, development, and reinstatement.
The Contractor shall be fully responsible in line with the Company standards for
furnishing all utility services of any type within the camp plot and to support the
camp within the Scope of this Contract.
Ownership of the camp facilities shall at all times remain vested in the
Contractor.
Any site furnished to Contractor shall be restored to original
condition (cleared and cleaned), and returned to the Company in accordance
with the requirements of the Contract. The Company shall have the option to
require the Contractor to leave all piping, wiring, and permanent improvements
as-installed at the camp site.

6.1.4

'Alternative Proposal' for Use of Contractors Existing Facilities


Should Contractor already have, or acquired, suitable and fully compliant
accommodation and or industrial facilities in the location of the Work, which it is
proposed to use for this Contract, then the use of these facilities shall be
considered an 'Alternative Proposal'.
This Alternative if required shall be
instructed at time of award of the Contract.
Provision has been made to offer a saving for this 'Alternative Proposal' (Schedule
B item 1 ref no. 1.11). The price for this Alternative shall be applicable to this
Contract only, it shall not affect or have any bearing on any terms and conditions
related to other contracts.
The use of Contractors existing facilities on this Contract is subject to the
approval of Company. Such approval in no way relieves Contractor from his
obligation to provide suitable fully compliant accommodation and or industrial
facilities for the Work.

Section C5 Schedule of Rates, Schedule A Preambles


Page 11 of 13

C311333- Amal HRSG -1 Project

COMPANY PROVIDED SERVICES

7.1
7.1.1

Company Provided Services


Unless specifically stated otherwise it is Contractors responsibility to provide all
things necessary to complete the Work. However at its sole discretion Company
may provide facilities and services which could comprise any or all of the
following:

Graded level area for Contractors temporary facilities with fenced perimeter
boundary.

Provision of electrical power (connection point outside the fence boundary).

Piped water supply (connection point outside the fence boundary).

Access to sewage main (connection point outside the fence boundary).

Connect to Company telephone system.

Garbage collection from central location.

Air transportation to and from the Interior.

In the event these services are provided, and not charged for separately by
Company, then Company shall have the right to deduct from amounts due under
the Contract at the unit rates stated in Schedule 'B' or those stated below.
If Contractor is not required to mobilise or demobilise (Mob/Demob) for the
provision
of
any
of
these
facilities
then
the
unit
rates
for
mobilisation/demobilisation stated in Schedule 'B' shall be deducted from
Contractors payments.
7.1.2

Company Telephone System


Unless stated otherwise the provision of access to Companys telephone system
will be charged at the following rates:
Rental charge for each line provided for the use of the Contract - OMR 20 per
month together with installation and telephone usage charges which will be
levied at cost.

7.1.3

Electric power
Unless stated otherwise the provision of access to and supply of electrical power
from Company grid system will be charged at 20baizas per kw/hr.

7.1.4

Water Supply
Unless stated otherwise, Contractor, subject to availability, may draw water from
water supply wells if available near Site or from the Company's RO contractor.
Water drawn from these facilities will be subject to a charge of RO1.006 per m3,
all accounts shall be settled directly with Company's operating contractor.

Section C5 Schedule of Rates, Schedule A Preambles


Page 12 of 13

C311333- Amal HRSG -1 Project

7.2
7.2.1

7.3

Logistics Service Provider (LSP)


The Contract Price shall include for all costs arising from the utilisation of
Company LSP as detailed in C4 Scope of Work. This shall include but not be
limited to; administration, procurement of the LSP service, operating restrictions,
co-ordination activities notice periods etc. In the event Contractor fails to utilise
the LSP without due authorisation then Company have the right, but not the
obligation, to deduct the amount that would have been due to the LSP contractor
in the event the transportation service had been correctly requisitioned in
accordance with the Contract.
Provision of Air Passenger Services

7.3.1

When required for the performance of the Work and as required under the terms of
SP2000 HSE Specification for Road Transport (Section C9 refers) Contractor
Personnel may, subject to availability and Company approval, be allowed or
required to use Company's air passenger service.

7.3.2

Use of Companys air passenger service shall be subject to the Companys Interior
flight charges as stated below. Contractor shall include within the Rates for this
requirement, including but not limited to all charges, availability restrictions,
booking and other administration costs.

7.3.3

Names and details of all Contractor staff considered eligible and requiring the use
of Company's air passenger service must be forwarded to Company for approval.
Contractor shall notify Company of any changes to this list of eligible staff as and
when they arise. In the event of disputed numbers of flights back charged in any
one month, the monthly statement as issued by Companys air transport booking
department shall be considered adequate substantiation for Contractor.

7.3.4

Applicable Charges
For each and every occurrence that Contractor Personnel make use of Company's
air passenger service to and from the Interior or between Interior locations the
sums stated below shall be due to Company. These sums will be deducted from
amounts due to Contractor.
For Aircraft commuting between:-

US$ / one way trip per


passenger

Muscat - South Oman Interior Location

243

Muscat - North Oman Interior Location

121

North Oman
Locations

237

South

Oman

Interior

Salalah/Marmul Nimr/Salalah

81

7.3.5

Contractor may charter aircraft outside of the flight schedule (i.e. emergencies) at
current applicable charges published on Companys intranet.

7.3.6

Interior flight no-show shall mean a person who has reserved a seat on a flight but
does not report for that flight or cancel the reserved seat in accordance with
cancellation procedures. All Interior flight no-shows will be charged at the
standard flight charges given above.

Section C5 Schedule of Rates, Schedule A Preambles


Page 13 of 13