Sunteți pe pagina 1din 9

assignment FOR

project MANAGEMENT
SUBMITTED BY:
Adnan temrikar
ROLL NO.49
MMS IInd A
Submitted to: PROF. amjad
kadri
ACADEMIC YEAR 2014-15

ANJUMAN -I- ISLAMS ALLANA


INSTITUTE OF MANAGEMENT
STUDIES

PETRONAS TWIN TOWER

The Petronas Towers, also known as the Petronas Twin Towers (Malay: Menara
Petronas, or Menara Berkembar Petronas), are twin skyscrapers in Kuala Lumpur,
Malaysia. According to the Council on Tall Buildings and Urban Habitat (CTBUH)'s
official definition and ranking, they were the tallest buildings in the world from 1998
to 2004 and remain the tallest twin towers in the world. The buildings are a landmark
of Kuala Lumpur, along with nearby Kuala Lumpur Tower.

History
The towers were designed by Argentine American architect Csar Pelli. They chose a
distinctive postmodern style to create a 21st-century icon for Kuala Lumpur. Planning
on the Petronas Towers started on 1 January 1992 and included rigorous tests and
simulations of wind and structural loads on the design. Seven years of construction
followed, beginning on 1 March 1993 with the excavation, which involved moving
500 truckloads of earth every night to dig down 30 metres (98 ft) below the surface.
The construction of the superstructure commenced on 1 April 1994. Interiors with
furniture were completed on 1 January 1996, the spires of Tower 1 and Tower 2 were
completed on 1 March 1996, and the first batch of Petronas personnel moved into the
building on 1 January 1997. The building was officially opened by the Prime Minister
of Malaysia's Tun Dr. Mahathir bin Mohamad on 1 August 1999. The twin towers
were built on the site of Kuala Lumpur's race track. Test boreholes found that the
original construction site effectively sat on the edge of a cliff. One half of the site was
decayed limestone while the other half was soft rock. The entire site was moved 61
metres (200 ft) to allow the buildings to sit entirely on the soft rock. Because of the
depth of the bedrock, the buildings were built on the world's deepest foundation. 104

concrete piles, ranging from 60 to 114 metres (197 to 374 ft) deep, were bored into
the ground. The concrete raft foundation, comprising 13,200 cubic metres (470,000 cu
ft) of concrete was continuously poured through a period of 54 hours for each tower.
The raft is 4.6 metres (15 ft) thick, weighs 32,500 tonnes (35,800 tons) and held the
world record for the largest concrete pour until 2007. The foundations were completed
within 12 months by Bachy Soletanche and required massive amounts of concrete. Its
engineering designs on structural framework were contributed by Haitian engineer
Domo Obiasse and colleagues Aris Battista and Princess D Battista. The Petronas
Towers' structural system is a tube in tube design, invented by Fazlur Rahman
Khan.Applying a tube-structure for extreme tall buildings is a common phenomenon.

The 88-floor towers are constructed largely of reinforced concrete, with a steel and
glass facade designed to resemble motifs found in Islamic art, a reflection of
Malaysia's Muslim religion. Another Islamic influence on the design is that the cross
section of the towers is based on a Rub el Hizb, albeit with circular sectors added to
meet office space requirements.
As a result of the Malaysian government specifying that the buildings be completed in
six years, two construction consortiums were hired to meet the deadline, one for each
tower. Tower 1, the west tower was built by a Japanese consortium led by the Hazama
Corporation (JA Jones Construction Co., MMC Engineering Services Sdn Bhd,
Ho Hup Construction Co. Bhd and Mitsubishi Corp) while Tower 2, the east tower
was built by a South Korean consortium led by the Samsung C&T Corporation
(Kukdong Engineering & Construction and Syarikat Jasatera Sdn Bhd). Early
into construction a batch of concrete failed a routine strength test causing construction
to come to a complete halt. All the completed floors were tested but it was found that
only one had used a bad batch and it was demolished. As a result of the concrete
failure, each new batch was tested before being poured. The halt in construction had
cost US$700,000 per day and led to three separate concrete plants being set up on the
site to ensure that if one produced a bad batch, the other two could continue to supply
concrete. The sky bridge contract was completed by Kukdong Engineering &
Construction. Tower 2 became the first to reach the world's tallest building at the time.
Though as a result of rushing to build this tower, tower 2 ran into problems when they
discovered the structure was leaning 25 millimetres (0.98 in) off from vertical. To
correct the lean, the next 16 floors were slanted back 20 millimetres (0.79 in) with
specialist surveyors hired to check verticality twice a day until the building's

completion
Due to the huge cost of importing steel, the towers were constructed on a cheaper
radical design of super high-strength reinforced concrete. High-strength concrete is a
material familiar to Asian contractors and twice as effective as steel in sway
reduction; however, it makes the building twice as heavy on its foundation as a
comparable steel building. Supported by 23-by-23 metre concrete cores and an outer
ring of widely spaced super columns, the towers use a sophisticated structural system
that accommodates its slender profile and provides 560,000 square metres of columnfree office space. Below the twin towers is Suria KLCC, a shopping mall, and Dewan
Filharmonik Petronas, the home of the Malaysian Philharmonic Orchestra.

FEATURES OF PETRONAS TWIN TOWERS


Entrance of Suria KLCC
Suria KLCC is a 140,000 m2 (1,500,000 sq ft) upmarket retail center at the feet of the
Petronas Towers. It features mostly foreign luxury goods and high-street labels. Its
attractions include an art gallery, a philharmonic theatre, an underwater aquarium and
also a Science center. Suria KLCC is one of the largest shopping malls in Malaysia.
KLCC Park
Spanning 17 acres (6.9 ha) below the building is the KLCC Park with jogging and
walking paths, a fountain with incorporated light show, wading pools, and a children's
playground.
Skybridge
The towers feature a double decker skybridge connecting the two towers on the 41st
and 42nd floors, which is the highest 2-story bridge in the world. It is not attached to
the main structure, but is instead designed to slide in and out of the towers to prevent
it from breaking, as the towers sway several feet in towards and away from each other
during high winds. It also provides some structural support to the towers in these
occasions. The bridge is 170 m (558 ft) above the ground and 58 m (190 ft) long,
weighing 750 tons. The same floor is also known as the podium, since visitors going
to higher levels have to change elevators here. The skybridge is open to all visitors,

but tickets are limited to about 1000 people per day, and must be obtained on a firstcome, first-served basis. Initially, the visit was free but in 2010, the tickets started
being sold by Petronas. Visitors can choose to opt for package one which is just a visit
to the skybridge or go for package two to go to the skybridge and all the way to level
86. Visitors are only allowed on the 41st floor as the 42nd floor can only be used by
the tenants of the building.
The skybridge also acts as a safety device, so that in the event of a fire or other
emergency in one tower, tenants can evacuate by crossing the skybridge to the other
tower. The total evacuation triggered by a bomb hoax on 12 September 2001 (the day
after the September 11 attacks destroyed the twin towers of the World Trade Center in
New York City) showed that the bridge would not be useful if both towers need to be
emptied simultaneously, as the capacity of the staircases was insufficient for such an
event. Plans thus call for the lifts to be used if both towers need to be evacuated, and a
successful drill following the revised plan was conducted in 2005.
There is a two hinged arch that supports the skybridge with arch legs, each 51 metres
(167 ft) long ,that are bolted to level 29 of each of the towers. After being constructed
on the ground, the sky bridge was lifted into place on the towers over a period of three
days in July 1995 but instead of being directly connected to the towers, the skybridge
can shift or slide in and out of them to counterbalance any effect from the wind.
Residing on the 41st and 42nd floors, the skybridge connects a conference room, an
executive dining room and a prayer room.
Lift system
The main bank of Otis Lifts is located in the centre of each tower. All main lifts are
double-decker with the lower deck of the lift taking passengers to even-numbered
floors and upper deck to odd-numbered floors. To reach an odd-numbered floor from
ground level, passengers must take an escalator to the upper deck of the lift.
There are 29 double-deck passenger elevators, but there are different sets that service
certain floors of the towers, specifically two sets of six of these double-deck
passenger elevators to floors 123 and 137 respectively. Another set of 5 passenger
lifts transport passengers to the 41st and 42nd floors where they can switch lifts to
reach the upper zones of the buildings, each double-deck passenger lift with the
capacity of 52 passengers or, 26 passengers per deck. There are also 6 heavy-duty
elevators for utility.
From the ground floor, there are three groups of lifts. The "short haul" group of 6 lifts

take passengers to floors between level 2/3 and level 16/17. The "mid haul" group of
six lifts take passengers to floors between level 18/19 and level 37/38. There is also a
set of shuttle lifts that take passengers directly to levels 41/42. To get to levels above
41/42, passengers must take the shuttle lifts, then change to lifts to the upper floors.
These connecting lifts are directly above the lifts that serve levels 2 to 38. The pattern
now repeats with the upper levels, one set serving levels 43/44 to 57/58 and one set
serving levels 59/60 to levels 73/74.

Apart from this main bank of lifts, there are a series of "connecting" lifts to take
people between the groups. Unlike the main lifts, these are not the double-decker
type. Two lifts are provided to take people from levels 37/38 to levels 41/42 (levels 39
and 40 are not accessible as office space). This spares someone in the lower half of
the building from having to go back to the ground floor to go to the upper half of the
building.
The lifts contain a number of safety features. It is possible to evacuate people from a
lift stuck between floors by manually driving one of the adjacent lifts next to it and
opening a panel in the wall. It is then possible for people in the stuck lift to walk
between lift cars.During an evacuation of the buildings, only the shuttle lift is allowed
to be used, as there are only doors at levels G/1 and levels 41/42; therefore should
there be a fire in the lower half of the building, this enclosed shaft would remain
unaffected. Firefighter lifts are also provided in case of emergency.
SERVICE BUILDING
The service building is to the east of the Petronas Towers and contains the chiller
plant system and the cooling towers to keep the Petronas Towers cool and
comfortable.

FACTS OF PETRONAS TWIN TOWERS.


1. The first designs by Cesar Pelli were rejected by the Prime Minister. Prime
Minister Mahathir felt the design was ultimately not Malaysian enough. He

wanted a building that would be identifiably Malaysian, that was of world


class standard and which Malaysians could be proud of. At first Pelli
struggled to understand what it meant to be uniquely Malaysian. Eventually
Mahathir Mohamad understood what he wanted the towers to look like: an
eight-pointed star (when seen from the top), which in Islamic culture
represents unity, harmony, stability, and rationality." However, Pelli was
worried the new design limited floor space. He solved the problem by adding
semicircles to each of the inner angles. Each tower would now have 43,600
square yards (36,455 m2) of floor space, including an additional circular
annex standing 44 stories high.
2. The original proposed design was to be 1,400 feet (427 m) high, but when Dr.
Mahathir realized, with a few adjustments, it could become the tallest building
in the world, he pushed for the height to be raised in everyway possible. Many
structural facts had to be recalculated and retested in wind tunnels. However
increased height was achieved without adding any floors, but instead adding a
small dome with an integrated pinnacle atop of the towers, reaching 1,483 feet
(452 m) and surpassing the Sears Tower.

3. . The whole complex was built on a former horse-racing track.


4. . A project this big would usually require eight years, but the Malaysian budget
only accounted for six. In order to meet the strict deadline, two construction
consortiums were hired, one for each tower, racing each other to the top.
5. . Tower One was built by a Mayjaus Joint-Venture led by Japans Hazama
Corp. and made up of JA Jones Construction Co., MMC Engineering Services
Sdn Bhd, Ho Hup Construction Co. Bhd and Mitsubishi Corp. The Tower One
foreman was Robert Pratt.
6. Tower Two was built by a SKJ Joint-Venture led by Koreas Samsung
Engineering and Construction, and comprised of Kuk Dong Engineering and
Construction Co. Ltd. and Syarikat Jasatera Sdn Bhd. The Tower Two foreman
was Jon Dunsford.
7. . Each floor had to be constructed one at a time as the two companies raced
towards the sky. In order to stay on budget each floor had to be constructed in
four days.
8. . Tower One Construction began one month before Tower two. The

Koreans/Tower two completed earlier than the Japanese/Tower 2. Tower One


was completed a few hours after tower Two.
9. . Koreans got Tower Two pretty straight. However, Tower One was an inch
(2.54 cm) off vertical. So, to correct the problem, the next 16 floors were
slanted back 0.08 of an inch (0.2 cm). International specialist surveyors were
then hired to check verticality every day and night.
10. . It took 6 years of 24 hour construction to complete the twin towers. The
building costs were US $ 1,8 billion (oil, dirty oil money!!!)
11. . It took three days to lift the Skybridge up to the 41st/42nd floor. The first
attempt was marred by a short circuit of the crane through lightning flashes
that came with the typical KL thunderstorm. So the Skybridge was left
hanging in the air until they repaired the crane and tried again the next day.
The Skybridge was designed as a Fire Escape construction, allowing
occupants to move to the other tower in case of a fire alarm
12. . There are 32000 windows with UV and solar radiation steel in both Towers.
It takes 2 months to clean them all.
13. . French Spiderman Robert Alain climbed the Twin without any equipment
twice. First time in 1997 the authorities knew about his intent and were
prepared to stop him. Yet the police noticed him only when he was half way
through his climb. They managed to catch up with the Spiderman and arrest
him only on the 60th floor. In 2007 Alain climbed Petronas again. He stopped
on the 60th floor and made a show out of surrendering to the police public
applause.
14. . Scenes from Entrapment with Sean Connery and Catherine Zena-Jones
were filmed here in 1999
15. . The main occupant of the buildings is Petronas, the national oil-company;
other include Accenture, Al Jazeera English, Carigali Hess Bloomberg,
Boeing, IBM, Khazanah Nasional Berhad, McKinsey & Co, TCS, Krawler
Networks, Microsoft, and Reuters.
16. . Though completed in 1998, the buildings were officially opened on August
28th, 1999; on the Malaysian National Day.
17. . Petronas Twin Towers were the tallest buildings in the world until 2004,
when Taipei 101 took over the title.

18. . Petronas Towers are still the tallest twin buildings in the world.
19. . There are 88 stories in Petronas Twin Towers.
20. . There are 10 double decker lifts in each tower. The double deck lifts can
carry 26 people per deck52 totaland can reach speeds of 20 feet (6.1 m)
per second.
21. . The pinnacles that top both towers stand 241 feet (73.5 m) high. They consist
of a spire, mast ball and ring ball. They are also equipped with aircraft
warning lights and window washing equipment. Each one took more than 19
weeks to make. One was made in Japan while the other was built in Korea.

S-ar putea să vă placă și