Documente Academic
Documente Profesional
Documente Cultură
PART I- GENERAL
RELATED DOCUMENTS
LI
A.
Drawings and general provisions of the Contract, including Conditions of Contract and
Division l Specification Sections, apply to this Section.
1.2
SUMMARY
A.
B.
1.3
This Section includes piping and specialities outside the building for the following:
I.
Sanitary sewerage
2.
3.
Division 2 Section "Excavation and fill" for excavating, trenching and backfilling.
2.
DEFINITIONS
A.
1.4
2.
PERFORMANCE REQUIREMENTS
A.
1.5
SUBMITTALS
A.
Product Data: Submit manufacturer's technical product data and installation instructions for
system materials and products.
B.
C.
2.
Manholes and other structures, including invert levels, frames, covers, and grates.
Coordination Drawings:
elevations. Include details of underground structures and connections. Show other piping
in same trench and clearances from sewerage system piping. Indicate interface and spatial
relationship between piping and proximate structures.
SANITARY SEWERAGE, TREATED SEWAGE EFFLUENT
AND GRAY WATER SYSTEM
S09077-0JD-TD-SPC-11B-ENV-02 REV 0
PEDESTRIAN TUNNELS
02530 - Page I of I I
D.
As-Built Drawings: At project close-out, submit record drawings of installed pipework and
products, in accordance with requirements of the Specification, Division I.
F.
Maintenance Data:
Submit maintenance data and parts lists for system materials and
products. Include this data, product data, Shop Drawings, and submit drawings in
maintenance manual; in accordance with requirements of the Specification, Division 1.
G.
H.
Certificate of Compliance.
Field Test Reports:
requirements.
1.6
QUALITY ASSURANCE
A.
Product Options: Drawings indicate size, profiles, and dimensional requirements of piping
and specialties and are based on the specific system selected. Other products with equal
performance characteristics may be considered.
Requirements.
B.
Regulatory Requirements:
I.
c.
1.7
Piping materials shall bear label, stamp, or other markings of specified testing agency.
B.
Protect pipe, pipe fittings, and seals from dirt and damage.
C.
Handle
pipes,
precast
concrete
manholes
and
other
structures
according
to
the
1.8
PROJECT CONDITIONS
A.
Site Information: Perform site survey, research public utility records, and verifY existing
utility locations.
B.
C.
PEDESTRIAN TUNNELS
02530- Page 2 of II
conditions and then only after arranging to provide temporary utility services according to
requirements indicated or directed:
I.
NotifY the Engineer not less than 72 hours' in advance of proposed utility
2.
Do not proceed with utility interruptions without the Engineer's written permission.
interruptions.
PART 2 - PRODUCTS
2.1
PIPING MATERIALS
A.
2.2
Refer to Part 3 "Piping Applications" Article for applications of pipe and fitting materials.
GRP pipes:
I.
2.
Pipe and fittings shall include a corrosion resistant liner, a sttuctural wall and a resin
3.
4.
5.
Pipes shall be provided with a resin rich outer layer reinforced with one layer of "C"
glass veil. The exterior layer shall have a minimum thickness of 0.2 mm. The layer
shall resin be rich and reinforced with one layer of "C" glass.
6.
The resin used for the corrosion resistant liner of the pipe and fittings shall be high
grade polyester resin (isophthalic or better) type. For the sttuctural wall and exterior
layer of the pipe a high grade isophthalic polyester resin shall be used. No dark
pigments shall be used in the pipe or fittings.
7.
All glass reinforcements except for the inner and outer surfaces of the pipe and
8.
Pipes shall be designed for a life of not Jess than 50 years. Contractor shall submit
fittings shall be of the "E" type. Surface reinforcement shall be of the "C" glass type.
calculations for initial and long term deflection with truck loads, buckling, vacuum,
pressure class, and strain in accordance with Appendix "A" of A WWA, C-950-88 or
equivalent. The maximum calculated long term deflection should not exceed 3%.
Copies of the design calculations shall be submitted to the Engineer for approval.
9.
Extra strength H30, Stiffuess: Minimum 10,000 N/m2 to 20,000 N/m2 depending on
location. Suitability of stiffness shall be verified by Contractor for the various trench
and pipe laying conditions and as recommended by the manufacturer. Pressure class
shall be 6 kg/cm2 minimum or as shown on Drawings.
10.
II.
12.
Strain corrosion resistance: Tests shall be carried out as per ASTM D 3681 or BS
5480 strain corrosion value at 50 years to equal or exceed 0.7%.
13.
PEDESTRIAN TUNNELS
Joints: GRP double socket couplings with rubber rings shall be to BS 2494.
Allowable angular deflection shall be toBS 5480 Table 3.
Testing on GRP pipes: The following tests shall be carried out on manufactured
pipes. Details of testing program shall be submitted to the Engineer for review and
approval prior to commencement of pipe manufacture. The manufacturer's quality
control scheme shall be to BS 5750 or ISO 9002. Guidance on quality control and
sampling shall be to BS 5480 Appendix Q. At least the following tests shall be
carried out and reported for approval.
a.
B.
b.
c.
d.
e.
f.
g.
h.
Pipe to EN 598 or equivalent and shall meet the quality standards of ISO 9002. Pipes
shall be class K9.
2.
Spigot and socket flexible joints shall be of the push-fit type with gaskets of ethylene
propylene rubber (EPDM). Spigot and socket shall provide a minimum angular
deflection of 4 degrees without leakage at the works test pressure specified. Joint
deflection at installation shall not exceed 50% of the manufacturer maximum
allowable.
3.
Spigot and socket ended pipes shall be used for straight runs and adjacent to elbows
or fittings. These joints shall be provided with rubber gaskets, and an external
thrust block is required at elbows or fittings. Anchored or self restrained joints
(locked joints) shall be used for sections adjacent to elbows in areas where space is
restricted or indicated on the Drawings or BOQ or located inside the utility tunnel.
Anchored joints are to be push-in, self anchored type able to take up the axial forces
thus allowing concrete thrust blocks to be dispensed with. The Contractor shall
submit calculations verifYing the number of restrained joints required noting that pipe
pressure testing will be made when pipes are partially backfilled or restrained in
utility tunnel.
4.
Self anchored flexible joints shall incorporate a weld on flange and tie bolts or similar
self-restrained joint system. The joints shall be suitable for a working pressure of 25
5.
6.
Pipes and fittings shall be given an external coating of zinc in accordance with EN
598 or ISO 8179 and a finishing coat of either cold applied bitumen according to
BS3416 Type II material, or hot applied bitumen toBS 4147 Type I Grade C.
8.
Pipes shall be lined internally with alumina cement mortar and shall comply with EN
598 or ISO 4 179. Fittings shall be coated internally with epoxy.
9.
polyethylene sleeving to BS 6076 and plastic adhesive tape in accordance with the
pipe manufacturer recommendations.
PEDESTRIAN TUNNELS
02530- Page 4 of 1 I
2.3
2.
Ballast:
Base Section:
thickness for walls and base riser section, and having separate base slab or base
section with integral floor.
4.
5.
Top Section: Eccentric-cone type. Top of cone of size that matches grade rings.
6.
7.
Grade Rings:
8.
Pipe Connectors: ASTM C 923M, resilient, of size required, for each pipe connecting
to base section.
B.
Heavy-Traffic
Precast
Concrete
Manholes:
ASTM C 913;
designed
according
to
ASTM C 890 for A-16, heavy-traffic, structural loading; of depth, shape, and dimensions
indicated, with provision for rubber gasketed joints.
1.
Ballast: Increase thickness of one or more precast concrete sections or add concrete
to structure, as required to prevent flotation.
2.
Gaskets: Rubber.
3.
Grade Rings: Include two o r three brick o r reinforced-concrete rings, of 150 t o 225
mm total thickness, that match 610 mm diameter frame and cover.
4.
Pipe Connectors:
ASTM C 923M,
resilient,
of
ventilated top. Suitable lifting device for covers to be provided at a rate of one for every 10
covers. Frames
For roadways: Class D400 heavy duty non-rock type for wheel loads up to 11.5 tons.
Minimum test load 400KN.
D.
2.
For sidewalks: Class B125, light duty. Minimum test load 125 KN.
3.
Manhole Cover Inserts: Manufactured, GRP form, of size to fit between manhole frame and
cover and designed to prevent stormwater inflow.
PEDESTRIAN TUNNELS
02530 -Page 5 of II
CONCRETE
A.
2.
3.
ratio.
Field formed from concrete 30 MPa minimum, with 0.45
2.5
PROTECTIVE COATINGS
A.
Internal faces of manholes and chambers shall be coated with four coats of coal tar epoxy
paint, 70% epoxy and 30% coal tar. The coating shall be applied by brush in accordance
with manufacturer's instructions. Minimum thickness shall be 1000 microns.
B.
2.
Structures below groundwater level: Waterproofing for external surfaces shall be app
modified bituminous sheet waterproofing as specified in Section 07135.
PART 3 - EXECUTION
3.1
EARTHWORK
A.
Excavating, trenching, and backfilling are specified in Division 2 Section "Excavation and
fill."
3.2
IDENTIFICATION
A.
Materials and their installation are specified in Division 2 Section "Earthwork." Arrange for
installing green warning tapes directly over piping and at outside edges of underground
structures.
I.
2.
Use detectable warning tape over nonferrous piping and over edges of underground
structures.
3.3
PIPING APPLICATIONS
A.
B.
PEDESTRIAN TUNNELS
02530 -Page 6 of II
C.
Gravity-Flow, Nonpressure Sewer Piping: GRP sewer pipe and fittings; gaskets; and
gasketed joints.
D.
Underground Piping: Use Ductile Iron spigot and socket ended pipe.
2.
Inside the technical gallery culvert piping: Use Ductile Iron pipes with locked joints.
INSTALLATION, GENERAL
3.4
A.
General Locations and Arrangements: Drawing plans and details indicate general location
and arrangement of underground sanitary sewerage piping. Location and arrangement of
piping layout take design considerations into account. Install piping as indicated, to extent
practical.
B.
Install piping beginning at low point, true to grades and alignment indicated with unbroken
continuity of invert.
sleeves, and couplings according to the manufacturer,s written instructions for using
lubricants, cements, and other installation requirements. Maintain swab or drag in line, and
pull past each joint as it is completed.
C.
Use manholes for changes in direction, unless fittings are indicated. Use fittings for branch
connections, unless direct tap into existing sewer is indicated.
D.
Install two flexible joints: the first at l diameter distance maximum from outside face of
manhole and the second at not more than l.Om away from the first joint.
E.
Install piping and connect to building's sanitary drains, of sizes and in locations indicated.
Terminate piping as indicated.
I.
F.
Tunneling: Install pipe under streets or other obstructions that cannot be disturbed by
tunneling, jacking, or a combination of both. A detailed method statement shall be submitted
for the engineer approval.
3.5
B.
General: Join and install pipe and fittings according to installations indicated.
Refer to Division 2 Section "Piped Utilities -Basic Materials and Methods" for basic piping
joint construction and installation.
c.
System Piping Joints: Make joints using system manufacturer's couplings, unless otherwise
indicated.
D.
E.
Install with top surfaces of components, except piping, flush with finished surface.
Follow manufacturer's instructions regarding placement of bedding and backfilling,
cleanliness of joint surfaces, lubricant used, correct location of components, provision of
correct gaps between end of spigot and back of socket, maximum permissible deflection of
PEDESTRIAN TUNNELS
02530 Page 7 of I I
JOmts for detachable couplings and flexible joints, provision of flexible joints for
connections to pipes built into structures.
3.6
MANHOLE INSTALLATION
A.
B.
C.
Precast Units: The Contractor shall cast in steel watertight forms at least 3 weeks before
sections are used. The Contractor shall bed lowest unit on in situ concrete base and bed and
haunch in cement mortar. The Contractor shall liberally coat joints of units with approved
bituminous material of trowelling grade prior to fixing. The Contractor shall ensure joints
are filled solid and neatly strike off surplus compound. The Contractor shall not disturb
work for 7 days thereafter. Alternatively, the Contractor shall seal joints with approved
preformed jointing strip in accordance with manufacturer's instructions and shall bed precast
concrete cover slab on top unit in cement mortar.
D.
Channels in bottom of manhole shall be smooth, semi-circular and size equal to diameter of
adjacent sewers. For straight through manholes, the Contractor shall construct channels of
half pipe sections. The Contractor shall make changes in direction of flow with smooth
curves as large as manholes permit. Changes in size and grade of channels shall be gradual
and even.
E.
Benching: The Contractor shall form in sulphate resisting concrete Class 250/20 to rise
vertically from top of channels to a height not less than soffit of outlet pipe, then slope
upwards I in I 0 to walls. Within 3 hours, the Contractor shall float with coat of sulphate
resisting cement-sand mortar I :2 and finish smooth with steel trowel.
F.
G.
H.
Step Irons: The Contractor shall cast into precast units or grout into preformed mortices.
The Contractor shall not use step irons as lifting eyes. Devices for lifting and handling shall
be provided on exterior faces.
I.
Adjustment for Level: The Contractor shall build top courses of brickwork or concrete rings
after completion of surrounding levels and adjust as necessary to give accurate and even
final levels.
J.
Covers and Gratings: The Contractor shall bed frame solidly in mortar and fix firmly using
fixing bolts and set cover in position to prevent twisting. The Contractor shall position
centrally over opening and level and square with surrounding finishes.
3.7
A.
PEDESTRIAN TUNNELS
02530- Page 8 of I I
3.8
Clear interior of piping and structures of dirt and superfluous material as work progresses.
Maintain swab or drag in piping, and pull past each joint as it is completed.
I.
I n large, accessible piping, brushes and brooms may b e used for cleaning.
2.
Place plug in end of incomplete piping at the end of the day and when work stops.
3.
Flush piping between manholes and other structures to remove collected debris, if
required by the Engineer, or authorities having jurisdiction.
B.
Inspect the interior of piping to determine whether line displacement or other damage has
occurred. Inspect after approximately 600 mm of backfill is in place, and again immediately
prior to Substantial Completion. Submit separate reports for each system inspection.
C.
D.
Test new piping systems, and parts of existing systems that have been altered, extended, or
Provision of test equipment: All items for test have to be provided on site
before the test, i.e. pressure gauges, instruments, water etc.
b.
c.
Fittings and joints: Permanently anchor fittings before testing and leave all
joints exposed for checking.
d.
e.
Test sections: Limit test sections in pressure lines to not more than 500 m.
f.
Test sections: Test pressure lines between valve chambers whenever possible.
g.
h.
Closed valve: Do not test against a closed valve unless there is no acceptable
alternative.
i.
Apply pressure by manually operated test pump or, in the case of large
diameter mains, by power driven test pump, if approved.
j.
k.
Failure: Should a test fail, locate leak and replace or make good defective pipe
I.
Non-pressure lines not exceeding I 000 mm diameter are to be air tested before
backfilling and hydrostatic tested after backfilling.
n.
2.
o.
Non-pressure lines: Carry out infiltration tests where crown of pipe at high part
p.
PEDESTRIAN TUNNELS
02530
Page 9 of I I
b.
Test pressure: 1.0 m head of water above pipe soffit at highest point and not
greater than 6 m head of water at lowest point of section under test. If
maximum head is exceeded, test section in stages.
3.
c.
d.
Fill pipe slowly with water from lowest point. Do not use power-driven pump
b.
Fill absorbant pipes with water and allow to stand for at least 24 hours to allow
unless approved.
complete absorption.
c.
d.
e.
f.
pressure.
Maintain test pressure for specified test duration with pumping stopped.
Repressurize to original test pressure and record respective volumes of water
pumped.
g.
h.
i.
j.
Test pressure: Generally 1.5 times the maximum sustained pressure, minimum
15 kg/cm2.
k.
I.
4.
b.
c.
Apply pressure by approved method (i.e. hand pump) until a pressure 120 mm
head of water is indicated on a U-tube connected to the system.
d.
Pressure drop: Without further pumping, pressure is not to fall by more than
25 mm in a period of 5 minutes.
e.
Failure to pass the air test is not conclusive and if no leakage can be traced by
external application of soapy water to all sealing areas, then a hydrostatic test
is to be carried out before final rejection.
5.
Timing: Carry out test after total backfilling of length under test.
b.
c.
d.
I)
2)
e.
PEDESTRIAN TUNNELS
02530
Page 10 of I I
Timing: Cany out test after total backfilling of length under test.
Limit of length t o be tested a t one time is three full length pipes unless
otherwise approved.
c.
Apparatus: Use rubber tyred bogies which do not damage lining of pipe and an
adequate supply of electric lamps.
7.
d.
Check joints by means of feelers to ensure rubber rings are correctly located.
e.
8.
b.
c.
d.
b.
c.
below 0.5%).
d.
Stage 3: Six months after final backfill (maximum allowable deflection 4.0%).
e.
Pipes not passing the deflection tests at stage 2 or stage 3 will be removed and
replaced.
9.
Cleaning: Clean pipeline of silt and debris after backfilling pipe trenches and
completing manholes, hatch boxes etc. but before surfaces are permanently
reinstated and make ready for inspection by the Engineer's Representative.
b.
c.
Inspection: Pipelines less than 700 mm diameter and larger pipelines which
cannot be inspected from the inside, are to be inspected by passing a cylinder
of diameter 25 mm less than the internal diameter of the pipe and length not
less than the internal diameter of the pipe through each pipeline.
E.
Testing of manholes: Plug manhole inlets and outlets, fill manhole with water and allow to
stand for at least 24 hours or such longer period to allow for complete absorption. Re-top
with water. Allowable leakage over 24 hours is not to exceed I% of total volume of
manhole, otherwise make good and retest.
PEDESTRIAN TUNNELS